July 31, 2015

Wheatstone Project Update
July 31, 2015
© 2015 Chevron Corporation. All rights reserved.
1
Overall Project Progress

The Wheatstone Project is more than 65 percent complete.
Condensate
Tanks
Product Loading Jetty
LNG Trains
Materials Offloading Facility
LNG Tanks
Gas Turbine
Generators
Slug Catcher
© 2015 Chevron Corporation. All rights reserved.
2
Wheatstone Platform
Hookup and Commissioning

The 440-person accommodation vessel is connected to the platform to support
hookup and commissioning activities now underway.
Accommodation
Vessel
Wheatstone
Platform
© 2015 Chevron Corporation. All rights reserved.
3
Subsea Activities

Installation of the subsea manifolds is complete, and subsea equipment and
flow lines are now being installed on the Wheatstone and Iago gas fields.
© 2015 Chevron Corporation. All rights reserved.
4
LNG Plant Site

At the LNG plant site, equipment and modules continue to be delivered and
installed.
Train 2
Train 1
© 2015 Chevron Corporation. All rights reserved.
5
LNG Plant Site

The LNG Train 1 cold boxes have been delivered to the site. They will play a
central role in the gas liquefaction process, cooling gas to -320°F (-160°C).
© 2015 Chevron Corporation. All rights reserved.
6
LNG Plant Site

The slug catcher header and piping systems have been installed, which will
separate condensate from gas at the inlet of the plant before further gas
processing.
© 2015 Chevron Corporation. All rights reserved.
7
Marine Facilities

At the Materials Offloading Facility the breakwater is complete, and the loading
platform has been installed on the 0.75-mile (1.2-km) product-loading jetty.
Loading Platform
Product-Loading Jetty
Breakwater
© 2015 Chevron Corporation. All rights reserved.
8
Onslow Social Infrastructure

The new water tanks and booster pump are complete, and the Onslow Airport
terminal is operational.
© 2015 Chevron Corporation. All rights reserved.
9