THE GROUT LINE The Grout Line Paolo Gazzarrini Overture Third appointment with the Grout Line, and unfortunately, without material from you. As I threatened in the conclusion of the September issue I am now obliged to bother you with one of my recent papers. The Paper The paper was published at the 58th. CGS Conference held in Saskatoon in September ‘05, and I would like to thank the organizers for giving me permission to publish this paper in Geotechnical News. It is, I believe, but I will let you decide, an interesting case history of the first application in British Columbia of Jet-Grouting used for underpinning of an existing old CN tunnel. Case History of Jet-Grouting in British Columbia. Underpinning of CN Rail Tunnel in North Vancouver Paolo Gazzarrini Matt Kokan Stephen Jungaro Introduction A new re-development on North Vancouver’s waterfront east of Lonsdale is under construction. The development includes the construction of up to 1,100 residential units in low rise to high rise buildings as well as a hotel and other commercial space. The subject site, a historic ship building facility is being developed by Pinnacle International of Vancouver, B.C. One of the lots, Parcel5, is located on the Southeast corner of the intersection of Lonsdale and Esplanade. (See Figure 1 and 2) This lot presented challenging shoring problems due to the proximity of Parcel 5 to an existing rail tunnel, which has a history of previous movements and repair. Excavation and shoring was needed to facilitate the construction of an underground parkade for the future hotel and convention center to be located immediately adjacent to and below the present elevation of the historic rail tunnel, which bounds the north end of the development. The subject site is located at the southern terminus of Lonsdale Avenue, which is aligned parallel to a long post glacial bench located south of the Coast Plutonic bedrock range that forms the North Shore mountains. Previous projects in the area have identified very difficult soil and groundwater conditions in the area, particularly the presence of high artesian water pressure within sand and sand and gravel layers present in the pre-glacial deposits that underlie the site. Due to the very high degree of consolidation and high strength of these deposits, driven cut off barriers are not possible. As a result the conventional approach to excavation and shoring has been to used conventional anchored shotcrete shoring in conjunction with dewatering wells or suction well points. Unfortunately this approach has been only marginally successful as the pre-glacial deposits in the area are highly stratified. Jet-Grouting, a new technology for BC, was used to underpin the tunnel and maintain its stability during the excavation, and also to create a groundwater cut-off wall in order to prevent internal erosion (piping) of fine to medium grained sand. Geotechnical News, December 2005 47 THE GROUT LINE Figure 1. Site map Brief Description of the Technology Jet-Grouting is one of the numerous technologies used to improve the soil or soft rock. It is a technique that, utilizing special tools (Drill bits, monitor and nozzles) and Equipment (Grout Plant and Grout Pump), produces soil-cement circular columns by pumping very fluid grout mixes at very high speed (800- 900 Km/hours) at high pressures varying between 30 and 50 MPa (4,300 to 7,200 psi). Historically the technology was developed in Japan in the middle 70’s and exported into Europe, in the late 70’s and early 80’s. In Europe, specifically in northern Italy, due to the optimal soil conditions, which are particularly suitable (alluvial with sand and gravel), the technology became more and more popular. In recent years in North America the use of Jet-Grouting has become more frequent. It is more frequent to the point Figure 3. How JG works 48 Geotechnical News, December 2005 Figure 2. Final proposed development that in the last Grouting Conference in 2003 in New Orleans, a conference held every 5 years, the papers relating to Jet-G r o u tin g w ere th e mo st represented. How Jet-Grouting Works Contrary to other types of grouting, permeation, compaction or soil-mixing, Jet-Grouting uses, as mentioned before, very high speeds of grout mix achievable with very high pressures. The jet, created at the bottom of the drilling rods, erodes the original structure of the soil, and at the same time introduces a water cement mix into the soil. The result is a soil-cement column that can achieve different variable diameters and characteristics depending on: the soil, the methodology of Jet-Grouting selected and the parameters used for the jetting. After the completion of the drilling to the required depth, the jetting begins. The rods are withdrawn at a constant speed (from the bottom upwards) and rotation. See Fig. 3. Types of Jet-Grouting Three main types of Jet-Grouting are normally used: • Single-Fluid: The disaggregation of the soil and its mixing with the grout mix is done directly by the same grout mix. • Double-Fluids: The disaggregation of the soil and its mixing with the grout mix is done directly by the same grout mix and a coaxial air jetting to increase the energy. • Triple-Fluids: The disaggregation of the soil is done directly by high speed (pressure) of water and a coaxial air jetting. The mixing with the grout mix is created by a lower pressure jet of grout mix, from a nozzle below the air/water nozzles that encounters the already destroyed soil. Parameters The parameters to be considered in the Figure 4. JG applications THE GROUT LINE design phase, generally defined by the experience of the contractor, are the following: • Grout mix pressure. • Air and water pressure, in case of double and/or triple jetting. • Diameter and number of the nozzle(s). • Grout mix composition. The above three mentioned parameters are related to the consequent flow reachable. • Withdrawal speed of the rods. This parameter and the flow give us the total quantity of grout mix used for the treatment of 1 column. • Rotation speed of the rods/nozzle(s). Equipment Medium size equipment is required for the execution of Jet-Grouting. • A high pressure grout pump, typically 350HP. • A grout plant, with silo for cement, able to produce typically 9 to 12 m3 of grout mix in order to continuously feed the pump. • A drill rig specially equipped for Jet-Grouting. Usually the mast is between 15 and 18 m high to permit the execution of the columns without the need to add rods. • Compressor, in the case of the use of Double or Triple Jet-Grouting. • Accessories such as a high pressure grout hose, special swivel, special single or double or triple rods, monitor, nozzles etc. Quality Control As in all grouting projects carried out underground the control of the results is neither obvious nor direct. Thus production quality control is an essential element of the technology. The state-of-the-art of Jet-Grouting requires the installation of sophisticated sensors and computers at the pump and at the drill rig to maintain all of the parameters described above under control in real time during the drilling and jetting operations. Sensors are installed at the pump to evaluate in real time, pressure and flow; sensors are installed at the drill rig to evaluate the: depth, flow, pressure, withdraw speed and rotation. A computer on the drill rig is able to record and store all these parameters and allows for control of each phase during drilling and jetting. The data is further available and stored automatically either on computer disk, CD rom or printout. General Application of Jet-Grouting Case histories of the application of Jet-Grouting are available in the literature for numerous purposes, from a simple water cut-off wall to more complicated structural applications, such as underpinning of structures. (See Fig 4). Here is a general list: • Cut-off wall • Shoring • Shaft • General foundation of structures • Single pile with the possibility of installing reinforced steel (casing or bar) in the column • Slabs • Underpinng of structures • Tunneling (umbrella treatment). Installation of a steel element (casing or bar) is usually adopted. Depending on the application, the geometry of the jet-grouting treatment can be: • Secant (overlapped) columns, • Tangent columns, • Scattered columns, • Monodirectional columns (panels) Field Tests Usually, and as a good practice, with the scope of defining the optimal parameters of jetting, a preliminary field test is carried out before the start of the production work. Four or five columns with different parameters, based on the soil conditions and the contractor’s experience, are drilled and jetted. The columns are further excavated in order to allow for further visual inspection of the diameter reached. Unconfined Compressive Strength (UCS) and permeability tests can be carried out for a better understanding of the final result of the soil-cement columns. Advantages and disadvantages of Jet-Grouting The advantages of using Jet-Grouted columns for soil improvement are usually the following: • No vibrations to the surrounding soil during the execution of the work, and consequent reduction in risk of settlement around the structure. • Use of relatively small equipment (case histories of jetting in the basements are available). • Possibility of easily drilling through obstructions, as boulders or cobbles using pre-drilled holes. • It can be considered as a permanent soil improvement solution considering that binder is used. • Flexibility in changing the pattern of the columns or parameters during the execution of the work, and adapting the Jet-Grouting in case of unexpected soil conditions. The main disadvantage is the spoil that re-flows from the hole during the jetting of a column. This can be easily managed with special containment tanks. Jet-Grouting Application in North Vancouver The principal scope of the work was the underpinning of the tunnel to allow the excavation of the underground parking. Soil Conditions The soil conditions in the North Vancouver area are generally characterized by a near surface cap of very dense lodgement till, comprised of silty sand with gravel underlain by pre-glacial sand of the Quadra Formation. The till is well graded, very dense and therefore impermeable. It extends to a depth of about 5 to 6 meters below pre-development grades. The Quadra Formation underlies the till and contains highly stratified silts-sands and sands and gravels. In general the sands are very fine to fine, though occasional zones of medium to coarse sand and sand and gravel occur, particularly as relic channels within the deposit. Groundwater pressures increase nonlinearly with depth and high artesian pressures occur at depths in excess of 10 meters. The characteristic SPT blow count for the till is less than ¼ inch penetration for 50 Geotechnical News, December 2005 49 THE GROUT LINE Figure 5. JG design (general) blows in the till and less than ½ inch penetration for 50 blows in the Quadra Formation. Test monitoring wells drilled at the north end of Parcel 5 were flowing at the ground surface prior to commencement of excavation and the final excavation depth was in excess of 10 meters. At the Parcel 5 site, the specific case described in this paper, the pre-glacial Quadra Formation was approximately coincident with the base of the tunnel. It was know prior to construction that the base of the tunnel contained numerous voids and was flowing water and sand on a continuous basis. The shoring designer was concerned that normal well and well point de-watering would not create sufficient draw down to permit conventional underpinning to proceed and jet grouting was selected as the most reliable technology for stabilizing the soil beneath the tunnel. Design The scope of the Jet-grouting in the Photo 1. General site overview 50 Geotechnical News, December 2005 Figure 6. JG design (detail) North wall was double: a) A vertical wall was created with the aid of the reinforcing steel (# 18 bars and 2.5 foot centers with a reinforced horizontal shotcrete waler). b) An impervious cut-off was created to avoid potential loss of sand at the base of the tunnel and to create a perfect contact between the bottom of the concrete box of the tunnel and the jet-grouted columns. To achieve this contact, the jet grouting was not terminated at the bottom of the tunnel but continued 50 cm above it. The jet grout wall was extended south at the east and west ends of Parcel 5 for the purpose of providing a groundwater cut-off. The design was carried out with a required minimum diameter of the columns of 0.8 meters and a UCS at 28 days of 10 MPa. Overturning of the tunnel governed design and thus the top of the tunnel was restrained using tie backs connected to a “dead man” located on the north side of Esplanade Avenue. The calculations indicated that the tunnel could potentially undergo rotational (raking) failure if it were not restrained prior to exposing the base. The base was exposed in controlled panels (15 meters in width) to maintain passive resistance at the base of the tunnel prior to the waler being fully installed. Thus the waler was installed in Sections. The bulk of the horizontal restraint provided for the tunnel was from the single row of tie back anchors drilled through the waler. Since there was an expectation of high water flows from beneath the tunnel, the waler was constructed prior to drilling tie backs. While this slowed the process down slightly it proved to be highly beneficial as very high groundwater flows were encountered from some of the tie back holes. The tie backs consisted of TITAN 30/11 hollow core injection anchors grouted with Microsil Anchor Grout. Photo 2. Bar installation THE GROUT LINE Photo 3. Spoil TITAN anchors were used as they proved to be more economical than cased installation of conventional bar for tie backs. The performance of Microsil Anchor Grout was quite impressive. After drilling the tie backs in, using a 75 mm diameter bit, groundwater flow from the tie back sockets was very heavy, in some instances up to 100 litres/minute per 75 mm socket. The flows were very clean and no grout flow was observed after completion of the installation. A total of 183 tie backs were Photo 4. Computer at the grout plant Figure 7. Drilling log installed with no failures during testing. Microsil anchor grout has hydrophobic properties that allow it to remain stable under high groundwater flows which normal Portland cement grout is not capable of. See Fig 5 and 6 with the design of the Jet-Grouting wall and Photo 1 with a general overview of the job site during the execution of the work. Quantities and sequence of the execution of the columns 181 columns, with structural steel, in the North Wall, 18 columns in the East wall and 32 columns in the West wall were carried out totaling 2,250 meters of drilling and 1,600 meters of jet grouting. The columns at the North wall were spaced 0.75 m, the columns at the West and East wall were spaced 1m. The average depth of drilling was 9.65 meters and of Jet-grouted columns Photo 5. Computer at the drill rig Geotechnical News, December 2005 51 THE GROUT LINE Figure 8. Jetting log 6.9 meters. The working platform was approx. 3 meters above the top of the jet-grouted columns. The sequence applied, was a normal Space Split Method with Primary (P), Secondary (S) and Tertiary (T) holes. This sequence was preferred to the wet on wet sequence due to the small spacing between the columns, and to have better control of the spoil as described below. System and Parameters Used The double Jet-Grouting system was Photo 8. Excavation completed at north/west wall used in this particular application. The reason for this is twofold: firstly, to have a better control of the spoil of the jetting in o r d e r to avo id u n d e s ir e d overpressure under the tunnel and to avoid consequent uplifting, secondly, to have more energy during the Jet-Grouting and to obtain diameter columns of bigger diameter. The parameters used, after the results of a field test, in which the diameter of the columns were evaluated in 1 meter, were: Photo 6. Contact tunnel/jet-grouted columns 52 Geotechnical News, December 2005 • Grout mix composition: W/C=1 • Grout mix pressure= 40 MPa ( 5,715 psi) • Air pressure= 0.7 MPa (10 psi) • Rotation = 5 rpm The #18 bar, 6.5 meters long, was wet set into the jet grout columns using a conventional back-hoe. See photo 2. Quality control during the execution of the work 1) At the Grout Plant With the aid of a simple mud balance the grout mix composition was kept un- Photo 7. Excavation completed (80%) THE GROUT LINE Figure 9- Tunnel monitoring der control to verify the constancy of the product produced by the automatic plant. 2) Spoil Control With the same mud balance, the spoil during the jetting was frequently analyzed. The constant measurement of the density of the spoil helps in evaluating the behavior of the Jet-Grouting treatment. See photo 3. The sequence of the columns was chosen also to analyze whether reduction in the density of the spoil was detectable. The results we obtained were: Density of the Grout mix produced at the plant = 1.50 t/m3 Density (average) of the spoil in the Primary columns= 1.88 t/m3 Density (average) of the spoil in the Secondary columns= 1.87 t/m3 Density (average) of the spoil in the Tertiary columns= 1.73 t/m3 First of all we can observe that the value of the density of the spoil in all the columns was well above the density of the basic grout mix. This helps us to understand, during the execution of the work, that the mixing in-situ was effective. Additionally we can observe that between the Primary and Secondary (together) and Tertiary columns, a drastic reduction in density is evident, 1.88 vs. 1.73 t/m3. This can be explained considering that between the Primary and Secondary columns the spacing was 1.5 meters and during the execution of two adjacent columns (P and S) there was no overlap of jetting in a column already formed; the jet was acting in virgin sand. The situation is different in the case of the jetting of a Tertiary column, spaced only 0.75 meters between a P and a S. The jet was acting between two columns already formed and the reduction of density of the spoil was a clear sign of perfect overlapping of columns, as detected at the end of the work during the excavation. Parameters Data All the parameters, column by column, both for drilling and grouting, were recorded with the aid of computers installed at the drill rig and pump. See photos 4 and 5 with the computer installed at the grout plant and drill rig. See figures 7 and 8 with the printout samples for drilling and jetting. Monitoring of the tunnel Two methods were used to monitor movement of the tunnel. The base monitoring was completed using a total distance station, which provided move- ments in three dimensions. The owners of the tunnel had a requirement for near full time measurement, which was not practical for the survey method. As a result tilt beam sensors were offered, which recorded movements every two hours. These sensors have a sensitivity of better than 0.1 mm. Figure10 shows the tilt beam record as well as the survey records for one of the monitoring stations. The AC ripple on the tilt meter output has a period of 24 hours indicating that the system was capable of recording thermal expansion and contraction of the tunnel. Additionally, visual monitoring of the interior of the tunnel adjacent to where Jet-Grouting was carried out, using a camera to observe potential leakage of grout mix in the tunnel during the jetting. No movement or major leakages of grout in the tunnel were observed. Results The first visual result was observed after the excavation of the wall. The contact between the base slab of the tunnel and the Jet-Grouted columns was perfect; there was no leakage of water at the wall, as well at its bottom. The diameter of the columns was approx 1 meter in till and 1.1 meters in sand. See photos 6 ,7, 8 and 9. Some coring was carried out after the completion of the work in some columns, to analyze the characteristics of the soil/cement columns. The laboratory results obtained, were: • UCS at 56 days = 14.8 Mpa -8 • Permeability = 7.6 10 m/s Conclusions The technique of jet grouting for Underpinng was utilized for the first time in British Columbia on this very challenging project. The results were very positive confirming the technique is suitable for the local soil and groundwater conditions. It is expected that this experience could encourage the use of this technique for other difficult projects in the Lower Mainland. British Columbia is expecting rapid population growth over the next 10 years and since many of the straightforward sites have already been developed, Geotechnical News, December 2005 53 THE GROUT LINE it is likely that remaining development sites will require more sophisticated geotechnical solutions. Jet-Grouting is expected to be one of many newer techniques introduced into the lower mainland to assist in the development of these remaining challenging sites. The technique holds particular promise in environmental and reservoir applications where a highly controlled groundwater cut off solution is required. Acknowledgment We would like to thank the owner, Pinnacle International, for the authorization given to the authors for the publication o f this p aper as well as Con-Tech-Systems and Obermann KG, pumps and jet-grouting material suppliers, for the assistance supplied during the execution of the Jet-grouting work. Paolo Gazzarrini P.Eng., Sea To Sky Geotech Inc., 12 – 2242 Folkestone Way, West Vancouver, BC V7S 2X7, Tel: 604-913-1022, Fax: 604-913-0106, email: [email protected] M a tt Ko k a n , P. E n g. , Pr in c ip a l, Geopacific Consultants, 102 - 6968 Russell Avenue, Burnaby, BC V5J 4R9, Tel: 604-439-0922, Fax: 604-439-9189 Stephen Jungaro, Principal, Matcon Excavation & Shoring, 2208 Hartley Avenue, Coquitlam, BC, V3K 6X3, Tel: 604-520-5909, Fax: 604-520-5957 Conclusion I hope you enjoy the paper and I would like, again, as was done in the previous appointment, to emphasize the part related to the use of the computer and the quality control during the execution of the work. I look forward to receiving material from you! Ciao. Geotechnical Engineer C-CORE is seeking an Engineer for its geotechnical projects carried out for national and international clients. C-CORE’s geotechnical expertise includes experimental and full-scale modelling, pipeline testing, ice/seabed interaction, soil/structure interaction, and risk and numerical analysis. Its world class Centrifuge Facility is used for geotechnical centrifuge applications including cold regions and offshore work and includes an earthquake simulator. Applicants should possess an engineering degree; a post-graduate degree is desirable. Five years geotechnical experience is required and prior involvement in industry related projects would be a valuable asset. Experience in research and development would also be an asset. The successful applicant will be expected to work in a team environment, possess excellent communication skills and demonstrate initiative. This role includes assuming project management responsibilities and client reporting. If you meet these qualifications, we ask that you forward your résumé with the names of three references to the address below. Salary will commensurate with qualifications and experience. All applications will be treated confidential. Deadline for submission is January 27, 2006. C-CORE is a global engineering corporation providing innovative engineering solutions to clients in the natural resource sectors. We develop and apply advanced technologies to address production and market issues faced by natural resource sectors such as oil and gas, pipeline, mining, pulp and paper, forestry, fisheries and aquaculture. We thank all applicants for submitting a résumé; however, only those being interviewed will be contacted. Mary Booton, Executive Manager, C-CORE, Captain Robert A. Bartlett Building, Morrissey Road, St. John’s, NL, Canada, A1B 3X5, Tel: 709 737-8356, Confidential Fax: 709 737-4021, Email: [email protected], http://www.c-core.ca 54 Geotechnical News, December 2005
© Copyright 2026 Paperzz