Atlantic Coast Pipeline, LLC and Dominion Transmission, Inc. Docket Nos. CP15-554-000, CP15-554-001, & CP15-555-000 Response to Data Request Dated November 23, 2016 Question Number: 1 Question Subpart: a-b Question: 1. In comments submitted on September 7, 2016, Mr. Richard Laska alleges that the Atlantic Coast Pipeline (“ACP”) project is over-built. Mr. Laska draws this conclusion based on three sources (US Department of Energy’s Energy Information Agency and papers from two websites (www.NaturalGas.org and www.hindawi.com)) which provide a typical range between compressor stations of between 40 to 100 miles apart. As a result of this information, Mr. Laska concludes that the ACP Project has been over-built because the distance between the two proposed compressor stations is in excess of 200 miles. a. Respond to Mr. Laska’s allegations regarding the distance between the compressor stations on the ACP Project by discussing how the pipeline hydraulics dictated the location and distance of the compression facilities. As part of the response confirm that the ACP Project has taken into account the changes in elevation along the pipeline route. b. Discuss the information from the websites, quoted by Mr. Laska. Response: Subpart a Mr. Laska cites generic assertions regarding where compression is “usually situated” for a natural gas pipeline. And as noted in Mr. Laska’s comments, compression “siting is dependent on terrain,” as well as other relevant factors. The case-specific pipeline hydraulics, along with the location of its receipt and delivery points, dictate the appropriate location of compression facilities for ACP. These locations were chosen in order to minimize the total number of greenfield compressor stations that would be needed for the Project. The ACP Project design requires three compressor stations: one near the beginning of the pipeline (Marts), the second approximately 215 miles past the first station (Buckingham), and the third approximately 110 miles past the second station (Northampton). The Marts Compressor Station was placed near the beginning of the pipeline, in order to compress the lower pressure gas received from Dominion Transmission, Inc. up to the higher operating pressure in ACP. The Buckingham Compressor Station is needed to relay the gas along ACP and to be able to receive gas from the existing Transco pipeline. The Buckingham station location is where ACP intersects with the Transcontinental Gas Pipe Line (Transco), which is a large receipt location for the ACP customers. Up to 885,000 dekatherms per day (MDt/d) can be received from Transco. Transco’s pipeline pressure is lower than the proposed ACP line pressure; therefore, any volume received from Transco requires compression to enter the ACP pipeline. Because compression is needed at this location for the Transco gas, this location was chosen as the best site for the relay compression as well. If another location had been chosen for relay compression, an additional compressor station site would have been required. The Northampton Compressor Station location was selected because compression is needed to pump the gas in two directions from this point: east on AP-3 to Chesapeake (Virginia) and west on AP-2 to Pembroke (North Carolina). This station has a common suction and a split discharge, which reduces the amount of compression needed during non-peak days. If this compressor station had been proposed for further north, there would be a single discharge into the remainder of the AP-1 main line downstream. If the station had been proposed for further downstream, then two stations (one on AP-2 and one on AP-3) would have been required instead of one. Atlantic confirms that elevation was taken into account, along the length of the route, as part of the hydraulic flow studies and design in support of the Project. Subpart b The websites and papers that Mr. Laska refers to include generic statements about typical distances between compressor stations. However, the design of a particular project is very factspecific, and will vary from these general guidelines. The distance between the proposed Marts and Buckingham Compressor Stations results from analysis of the considerations described in the above response to 1.a. The appropriate location of these and the third compression facility for ACP has been determined by a variety of factors, including not only the distance between stations, but also the overall drop in elevation relevant to this project, the chosen pipeline diameter, and relative pressure requirements at specific ACP receipt and delivery points. Response Provided By: Daniel Diefenbach Manager Facility Planning & Product Development 804-771-4478 Atlantic Coast Pipeline, LLC and Dominion Transmission, Inc. Docket Nos. CP15-554-000, CP15-554-001, & CP15-555-000 Response to Data Request Dated November 23, 2016 Question Number: 2 Question Subpart: a-c Question: 2. Provide the following information for both the total 599.7 mile Atlantic Coast Pipeline as well as the 95.7 mile George Washington National Forest (GWNF) 6 alternative route: a. The number of land parcels and acres making up the permanent and temporary right-of-way necessary for the construction and operation of the pipeline. b. The number and percentage of the land parcels and acres in Question 1(a) that are within or collocated with existing rights-of-way. c. The number and percentage of the land parcels and acres in Question 1(a) for which ACP has easements. Response: Subparts a and b Land parcels crossed by the pipeline facilities along the ACP and GWNF 6 alternative route (i.e., the currently proposed route) are summarized in Tables 2-1 and 2-2, respectively. Table 2-1 Land Parcels Crossed by the Atlantic Coast Pipeline Total Collocation Number of Land Parcels Temporary Construction Impacts (acres) Permanent Operations Impacts (acres) Number of Land Parcels AP-1 1,356 5,528.1 2,910.1 AP-2 940 2,596.0 1,125.6 AP-3 436 882.8 AP-4 1 3.9 AP-5 2 2,735 Facility Project Total Percent of Total Temporary Construction Impacts (acres) Permanent Operations Impacts (acres) 109 8 374.9 208.4 139 15 310.4 148.4 506.0 246 56 297.0 181.1 2.4 0 0 0.0 0.0 12.1 5.7 0 0 0.0 0.0 9,022.9 4,549.8 494 18 982.2 537.9 Table 2-2 Land Parcels Crossed by the GWNF 6 Alternative Route Total Facility Number of Land Parcels Temporary Construction Impacts (acres) GWNF 6 Alt 254 1,601.9 Collocation Permanent Operations Impacts (acres) Number of Land Parcels 847.7 8 Percent of Total Temporary Construction Impacts (acres) Permanent Operations Impacts (acres) 3 85.5 45.7 Subpart c The response to this part of the question contains Privileged information and is filed under a separate cover. Response Provided By: Leighton McCoy Director Engineering Services 804-775-5537 Atlantic Coast Pipeline, LLC and Dominion Transmission, Inc. Docket Nos. CP15-554-000, CP15-554-001, & CP15-555-000 Response to Data Request Dated November 23, 2016 Question Number: 3 Question Subpart: N/A Question: 3. ACP states on page 7 of its application that the ACP will transport natural gas to electric generation and local distribution companies (LDCs) in Virginia and North Carolina. ACP further states that these entities will use the gas to support existing and proposed power generation facilities. On page 6 of its application, ACP states that approximately 79.2 percent of the natural gas transported by ACP would be used as fuel to generate electricity. Identify the existing and proposed power generation facilities that would be served by the ACP. Further, identify whether each facility is existing or proposed, and the anticipated in service date if the facility is proposed. Response: As stated in our Application, the Project originated from the response to the Duke Energy and Piedmont solicitation for incremental firm gas transportation service into North Carolina and Virginia Power Services Energy Corp., Inc. (VPSE’s) request for proposals for firm natural gas transportation service to serve gas-fired power generation in the Commonwealth of Virginia. In addition to serving the Power Generation market in Virginia and North Carolina, ACP was able to also address the needs of Local Distribution Companies (LDCs) in the same markets. Below is a breakdown of usage based on each shipper’s contracted capacity and the portion of the capacity expected to support power generation. LDC utilization projections are based on historic throughput. PSNC did not have a Power Generation allocation. ACP Capacity Distribution Power Generation Dominion Virginia Power Duke Energy Carolinas Duke Energy Progress 100% 100% 100% Capacity 300.00 272.25 452.75 1,025.00 PSNC Residential Commercial Industrial & Other 91.5% 8.2% 0.3% 100% Capacity 91.50 8.20 0.30 100.00 Source: SCANA Analyst Day 2014 pg. 110 Piedmont Residential Commercial Industrial Power Gen Other Source: January 2015 Investor Update pg. 5 15% 11% 23% 49% 2% 100% Capacity 24.00 17.60 36.80 78.40 3.20 160.00 VNG Residential Commercial Industrial Power Gen 20% 17% 14% 49% 100% Capacity 30.69 26.66 21.55 75.95 155.00 Source: 2014 throughput provided by K Yagelski e-mailed 7/29/15 8:56 AM Capacity for Electric Generation 1,179.35 79% Dominion Virginia Power (DVP) views ACP as an important factor to the reliable delivery of gas to its generation fleet from an overall portfolio perspective. That is, ACP will be directly connected to the two largest combined cycle units (over 2,900MW combined) in the DVP’s generation portfolio, and could also be utilized to source supply on transportation contracts that DVP maintains with other pipelines. For example, ACP will interconnect with TCO and Transco, which should allow gas to flow to numerous generation facilities within DVP’s fleet. In addition, VNG is planning to interconnect with ACP on the southern end of their system at Chesapeake, allowing additional sourcing flexibility for the delivery of gas to DVP operated generation along the VNG/JUP pipeline. A list of existing or proposed DVP generation facilities that ACP could serve is provided below. Warren County (CC) – existing Brunswick (CC) – existing Greensville (CC) – currently under construction, expected in-service date December 2018 (this unit was “proposed” at the time of the ACP FERC filing) Bear Garden (CC) – existing Bremo (other) – existing Remington (CT) – existing Possum Point (CC) – existing Bellemeade (CC) – existing Gordonsville (CC) – existing Chesterfield (CC) – existing Rosemary (CC) – existing Gravel Neck (CT) – existing Elizabeth River (CT) – existing Yorktown (other) – existing unit, availability dependent on VNG’s proposed expansion Darbytown (CT) – existing unit, availability dependent on VNG’s proposed expansion Ladysmith (CT) - existing unit, availability dependent on VNG’s proposed expansion Duke Energy will utilize ACP transportation service to meet portions of its existing and future power generation facilities. With respect to existing facilities, the ACP transportation service, through interconnects with Piedmont Natural Gas, will provide a needed and alternative fuel source for the following existing Duke Energy Progress (DEP) facilities: H.F. Lee Energy Complex, located in Goldsboro, NC totaling approximately 1,047 MW/910 MW (winter/summer) (Combined cycle) Wayne County Station, located in Goldsboro, NC totaling approximately 959 MW/ 863 MW (winter/summer) (5 combustion turbines) Sutton Energy Complex, located in Wilmington, NC totaling approximately 717 MW/622 MW (winter/summer) (Combined cycle) Smith Energy Complex, located in Hamlet, NC totaling approximately 1,227 MW/1,088 MW (winter/summer) (Combined cycle) and approximately 916 MW/780 MW (winter/summer) (5 Combustion turbines) In addition, DEP will complete an approximately 100 MW/84 MW (winter/summer) Sutton fast start/black start CT in 2017 that will be able to utilize the transportation service from ACP. With respect to proposed power generation facilities, DEP and Duke Energy Carolinas (DEC) each prepare a long range planning document called the Integrated Resource Plan (IRP), which is provided by each utility to both the North Carolina Utilities Commission and the Public Service Commission of South Carolina, and which details the generation needed for each utility to meet the forecasted electricity requirements for its customers over the next 15 years. The 2016 IRP’s are the most recent projection of how each utility’s energy portfolio will look over the next 15 years, based on current data assumptions. The 2016 IRPs identify the need for additional natural gas resources that are economic, highly efficient and reliable. The planning documents outline the following information relative to new natural gas resources. The locations of these proposed facilities have not been finalized, however, both DEC and DEP are evaluating siting locations that would provide access to ACP. Quantities of natural gas delivered on ACP would be available as a potential fuel source for these needed new electric gas generation assets. DEC: • Plan for a DEC 1,221 MW/1,123 MW (winter/summer) natural gas combined cycle in 2023. • Plan for DEC 468 MW/435 MW (winter/summer) of combustion turbine resources in 2025. DEP: • Plan for a 1,221 MW/1,123 MW (winter/summer) natural gas CC in 2022. • Plan for a potential 186 MW/161 MW (winter/summer) CT in late 2023. • Plan for 468 MW/435 MW (winter/summer) of CT capacity in 2023. • Plan for 468 MW/435 MW (winter/summer) of CT capacity in 2026. • Plan for 468 MW/435 MW (winter/summer) of CT capacity in each year from 2028 to 2030. • Plan for 936 MW/870 MW (winter/summer) of CT capacity in 2031. With the existing and proposed gas generation growth in North Carolina, the transportation service from ACP is critical to the growing gas generation needs of DEP and DEC. Response Provided By: Lyle Henry Gas Business Development Manager 804-771-4734 Atlantic Coast Pipeline, LLC and Dominion Transmission, Inc. Docket Nos. CP15-554-000, CP15-554-001, & CP15-555-000 Response to Data Request Dated November 23, 2016 Question Number: 4 Question Subpart: N/A Question: 4. State whether or not LDCs in West Virginia and Western Virginia sought service from the ACP prior to, or after ACP’s open season. Further, provide all correspondence between ACP and LDCs in West Virginia and Western Virginia regarding providing service in those areas. Response: Atlantic conducted a non-binding open season (4/16/14 – 5/9/14), and a binding open season (10/21/14 – 11/10/14) for firm transportation services. LDCs in West Virginia and Western Virginia did not express interest in capacity during either Open Season. There has not been any correspondence between ACP and any LDC in West Virginia and Western Virginia, with regard to securing ACP capacity to serve their franchise areas. Response Provided By: Lyle Henry Gas Business Development Manager 804-771-4734 Atlantic Coast Pipeline, LLC and Dominion Transmission, Inc. Docket Nos. CP15-554-000, CP15-554-001, & CP15-555-000 Response to Data Request Dated November 23, 2016 Question Number: 5 Question Subpart: a-c Question: 5. Provide the following information for both the total 37.5 mile Supply Header pipeline: a. The number of land parcels and acres making up the permanent and temporary right-of-way necessary for the construction and operation of the pipeline. b. The number and percentage of the land parcels and acres in Question 1(a) that are within or collocated with existing rights-of-way. c. The number and percentage of the land parcels and acres in Question 1(a) for which DTI has easements. Response: Subparts a and b Land parcels crossed by the pipeline facilities along the SHP are summarized in Table 5-1. Table 5-1 Land Parcels Crossed by the Supply Header Project Total Collocation Number of Land Parcels Temporary Construction Impacts (acres) Permanent Operations Impacts (acres) Number of Land Parcels TL-635 197 460.7 197.2 TL-636 33 53.2 23.3 Project Total 230 513.9 220.5 Facility Percent of Total Temporary Construction Impacts (acres) Permanent Operations Impacts (acres) 59 30 113.4 46.6 32 97 50.3 21.8 91 40 163.7 68.4 Subpart c The response to this part of the question contains Privileged information and is filed under a separate cover. Response Provided By: Leighton McCoy Director Engineering Services 804-775-5537
© Copyright 2026 Paperzz