MALAYSIA Rapid Assessment and Gap Analysis For Sustainable

MALAYSIA
Rapid Assessment and Gap Analysis
For Sustainable Energy for All (SE4ALL) Initiative
A Report by the UN Country Team Malaysia
Prepared and Edited by:
Azman Zainal Abidin (Technical Advisor), Prof Dr. Ir. KS Kannan (UNIDO) and Asfaazam Kasbani (UNDP)
Under the guidance of:
Economic Planning Unit (EPU) and Ministry of Energy, Green Technology and Water (MEGTW), Malaysia
September 2012
Disclaimer: The findings, interpretation, and conclusions expressed in this report are entirely those of the authors and should not be attributed in any
manner to the United Nations Malaysia Country Team, UNDP, UNIDO and to its affiliated organizations or to the countries they represent including
its agencies. The authors use information publicly sourced as advised and without prejudice.
1
Sustainable Energy for All (SE4ALL) Brief
UN Secretary-General Ban Ki-moon is leading a global initiative on Sustainable Energy for All to
mobilize action from all sectors of society: business, governments, investors, community groups and
academia. The United Nations is the ideal institution to convene this broad swath of actors and
forge common cause in support of three interlinked objectives:
1. Ensure Universal Assess to modern energy services
2. Double the global rate of improvement in energy efficiency (EE)
3. Double the share of renewable energy (RE) in the global energy mix
These objectives are complementary. Progress in achieving one can help with progress toward the
others. All are to be achieved by 2030, and all are necessary to achieve sustainable energy for all. The
Secretary-General’s initiative contributes to the International Year of Sustainable Energy for All in 2012,
as declared by the UN General Assembly, by providing a focus for action by all stakeholders.
OBJECTIVE
The purpose of this Rapid Assessment and Gap Analysis is to provide:
 A quick brief look of the energy situation in the country (Section 1) within the context of its
economic and social development and poverty eradication 

 A good review of where the country is in terms of the three SE4ALL goals (Section 2), and 



A good estimate of the main challenges and opportunities vis-à-vis the three goals of SE4ALL
where the major investments, policies and enabling environments will be required (Section 3) 

A sound basis and background for an Action Plan that may follow as part of the SE4ALL
activities in the country 
2
Abbreviations
AAIBE
Akaun Amanah Industri Bekalan Elektrik (AAIBE)
CEB
Central Electricity Board
DDC
District Development and Review Committee
DID
Department of Irrigation and Drainage
EC
Energy Commission (English for ST)
EE
Energy Efficiency
EIB
Energy Information Bureau
EPP
Entry Point Projects
EPU
Economic Planning Unit
FiT
Feed-in-Tariff
GDP
Gross Domestic Product
GTP
Government Transformation Programme
ICU
Implementation Coordination Unit
IPP
Independent Power Producer
ktoe
Kilo tones of oil equivalent
MDG
Millennium Development Goals
MDTCA
Ministry of Domestic Trade and Consumer Affairs
MEGTW
Ministry of Energy, Green Technology and Water
MESITA
Malaysian Electricity Supply Industries Trust
Account (English for AAIBE)
MGTC
Malaysia Green Technology Corporation
MHLG
Ministry of Housing and Local Government
MITI
Ministry of International Trade and Industry
MOA
Ministry of Agriculture
MOE
Ministry of Education
MOH
Ministry of Health
MOSTI
Ministry of Science, Technology and Innovation
MP
Malaysia Plan
MRRD
Ministry of Rural and Regional Development
NDC
National Development Council
3
NDPC
National Development Planning Council
NEB
National Energy Balance
PEMANDU
Performance Management and Delivery Unit
PLI
Poverty Line Income
PTM
Pusat Tenaga Malaysia (Malaysia Energy Center)
RBI
Rural Basic Infrastructure
RE
Renewable Energy
REPPA
Renewable Energy Power Purchase Agreement
REP-PoR
Regional Energy Programme for Poverty Reduction
SDC
State Development Committee
SEDA
Sustainable Energy Development Authority
SEPU
State Economic Planning Unit
SESB
Sabah Electricity Sdn. Bhd.
SESCO
Sarawak Electricity Company
SHS
Solar Home System
SME
Small and Medium Industries
SREP
Small Renewable Energy Projects
ST
Suruhanjaya Tenaga (Energy Commission)
TNB
Tenaga Nasional Berhad
UNCT
United Nations Country Team Malaysia
UNDP
United Nations Development Programme
UNIDO
United Nations Industrial Development
Organization
4
Table of Contents
ABBREVIATIONS ....................................................................................................................... 3
EXECUTIVE SUMMARY ............................................................................................................. 6
SECTION I: INTRODUCTION ..................................................................................................... 8
1.1 COUNTRY OVERVIEW ..........................................................................................................8
Basic socio-economic data for Malaysia .................................................................................. 8
1.2 ENERGY SITUATION.............................................................................................................9
1.2.1 Energy Supply (energy mix, export/import, electricity sector) .......................................... 9
1.2.2 Net Imports and Exports by Fuels Type .........................................................................11
1.2.3 Energy demand .............................................................................................................12
1.2.4 Energy and Economic Development ..............................................................................13
1.2.5 Energy Strategy and Relevant Targets...........................................................................14
SECTION 2: CURRENT SITUATION WITH REGARDS TO SE4ALL GOALS ............................15
2.1 ENERGY ACCESS vis-à-vis GOAL OF SE4ALL ...................................................................15
2.1.1 Overview and assessment .............................................................................................15
2.1.2 Modern energy for thermal applications (cooking, heating).............................................15
2.1.3 Access to electricity: ......................................................................................................17
2.2 ENERGY EFFICIENCY vis-à-vis GOAL OF SE4ALL ............................................................21
2.2.1 Overview and Assessment.............................................................................................21
2.2.2 Energy intensity of national economy: ............................................................................22
2.3 RENEWABLE ENERGY vis-à-vis GOAL OF SE4ALL ...........................................................24
2.3.1 Overview and Assessment.............................................................................................24
2.3.2 On-grid and off-grid renewable energy ...........................................................................25
2.4 SE4All GOALS .....................................................................................................................26
2.4.1 Energy Access ...............................................................................................................26
2.4.2 Energy Efficiency ...........................................................................................................26
2.4.3 Renewable Energy.........................................................................................................26
SECTION 3: CHALLENGES AND OPPORTUNITIES FOR ACHIEVING SE4ALL GOALS .........27
3.1 INSTITUTIONAL AND POLICY FRAMEWORK ....................................................................27
3.1.1 Energy and development ...............................................................................................27
3.1.2 Thermal energy for households......................................................................................28
3.1.3 Power sector ..................................................................................................................29
3.1.4 Modern energy for productive sectors ............................................................................29
3.1.5 National monitoring framework for SE4ALL ....................................................................29
3.2 PROGRAMS.........................................................................................................................30
3.2.1 Thermal energy..............................................................................................................30
3.2.2 Power sector ..................................................................................................................30
3.2.3 Energy efficiency programs ............................................................................................30
3.2.4 Modern energy for productive use ..................................................................................31
3.3 FINANCING ..........................................................................................................................31
3.4 PRIVATE INVESTMENT AND ENABLING BUSINESS ENVIRONMENT .............................33
3.4.1 Thermal energy for households......................................................................................33
3.4.2 Power sector ..................................................................................................................33
3.4.3 Modern energy for productive sectors ............................................................................34
3.5 GAPS AND BARRIERS ........................................................................................................35
REFERENCES...........................................................................................................................37
ANNEX 1: OTHER INITIATIVES RELATED TO SE4ALL............................................................38
5
EXECUTIVE SUMMARY
This report is prepared as part of the United Nations Country Team’s effort to support Malaysia in
embarking into SE4ALL initiatives. The Rapid Assessment and Gap Analysis report will map out
current status of SE4LL which will include sections on Current Situation and Challenges.
Malaysia has been successful in achieving the overall progress of the SE4ALL objectives. Strong and
sustained economic growth has contributed to success in meeting basic energy needs, including rural
electrification and domestic energy for cooking. While there are other factors that contributed to the national
poverty alleviation, rural electrification programme comes closest in linking the energy-poverty nexus. A study
concluded that in general, as electrification progresses, poverty tends to decrease. Starting as a security
programme for lighting villages during the emergency (prior to independence 1957), rural electrification has
graduated into an important component of rural development for uplifting the welfare of the rural population.
The programme has the potential to bring about economic empowerment of the poor via employment and
involvement in agriculture, rural industries, SMEs and energy-based entrepreneurships and also improving
education and health. However, there still remaining pocket of electrified households which will be connected
by end of 2015. At date, rural electrification has successfully penetrated 99% of the country, 100% in
Peninsular, 85% in Sabah and 90% in Sarawak. Further expansion of the rural electrification will have to focus
in Sabah and Sarawak. The lesser penetration rates in Sabah and Sarawak are mainly due to physical and
geographical constraints which entail heavy investments and also the relatively small electricity market due to
the sparsely populated rural areas. The establishment of MESITA in 1997 has successfully catalyzed the rural
electrification. Managed by MEGTW, it is an innovative trust fund where all the major IPPs in the Peninsular
Malaysia and Sabah contribute about 1% of their annual pre-tax profit for rural electrification (including
promotional activities), RE/EE projects and training. It is noted that by the year 2002, a total of USD 100 million
has been disbursed and has successfully benefited more than 250,000 households. Starting in 2010,
PEMANDU with MRRD, has started the Government Transformation Programme Rural Basic Infrastructure
initiative (RBI) which as date, has benefitted more than 50,000 households under the rural electrification
programme. On domestic energy, use of clean energy such as LPG, kerosene (for cooking and heating) is
widely available and sold in the groceries and fuel stations.
th
Energy efficiency has been in national policy, albeit broadly, since the 7 Malaysia Plan. The energy
objective of providing efficient utilization of energy serves as the guiding principle of energy efficiency
programme in building, industrial and commercial sectors. The Efficient Management Of Electrical
Energy Regulations 2008, under “Electricity Supply Act 1990” require premises which consume more
than 3,000,000kWh over a period of 6 months, to submit status reports to the Energy Commission,
Malaysia including the establishment of an energy management system. The government is currently
exploring the possibility of establishing a revised National EE Master Plan including an Act to spearhead
EE further. Under the Economic Transformation Programme, PEMANDU together with MEGTW, has
launched the SAVE programme as part of a nation-wide market transformation exercise towards the use
of energy efficient appliance. The government has started its long journey on the subsidy rationalization
programme which eventually will lead to market-based energy pricing in Malaysia.
The passing of the RE Act and the establishment of Sustainable Energy Development Authority
(SEDA) has strongly supported Government’s RE agenda. Feed-in-Tariff is currently seen as the
most feasible way to promote the use of RE sources in the national generation mix. SEDA’s role is
to administer and manage the implementation of the feed-in tariff (FiT) mechanism where the
resources focused as now are biomass, biogas, mini-hydropower and solar energy. The response
has been encouraging where almost all quotas for solar until 2014 has fully taken up. According to
the planned, Malaysia expects to connect 985MW (5.5%) of RE generation capacity by 2015.
Institutional set-up for SE4ALL has been matured and it would be natural for central agency like EPU to
continue providing direction support on the progress of the targets. MRRD shall be the lead agency for the
6
Universal Access while MEGTW shall be the focal point for EE and RE initiatives. MGTW, the
ministry responsible in the development of energy planning and implementation, acts as the
guardian for MESITA funds where it works hand-in-hand with MRRD and TNB to continue rural
electrification programme by various means. MRRD is responsible for planning and implementation
of rural infrastructures development policies, including rural electrification. TNB, as the main utility
company is responsible for generation, transmission and distribution of electricity in Peninsular
Malaysia. SESCO and SESB are responsible for the same in Sarawak and Sabah respectively.
In conclusion, Malaysia will face no major challenges implementing the three SE4ALL goals if it continues on its
chosen path. In terms of energy access, 99.4% of the country is already electrified and the remote areas shall soon
be connected with the implementation of programs that achieved 310% more electricity connections in 2010-2012
than during the previous period. Regarding EE, the government has launched many projects that will allow Malaysia
th
to achieve the SE4ALL goal by 2015. Lastly, the 10 Malaysian Plan aims to increase fivefold the share of
renewable energy sources in the energy mix (to 5.5%) by 2015. Through these efforts to promote a greener, more
efficient and more connected country, Malaysia is to achieve high-income status by 2020. Malaysia has achieved or
is on track to attaining the Millennium development goals (MDGs) at aggregate level by 2015. The primary energy
source for Malaysia comes from natural gas at 43.3% followed by crude oil at 35.5%. Malaysia is a significant net
exporter of natural gas, primarily in the form of liquefied natural gas (LNG). The National Energy policy of 1979
focuses on three different objectives to deal with the energy situation in Malaysia and it encompasses the supply,
utilization and environmental issues surrounding energy.
7
SECTION I: INTRODUCTION
1.1 COUNTRY OVERVIEW
Basic socio-economic data for Malaysia
Population:
GDP/capita:
Key economic sectors:
Poverty rate (current and
trend):
Main sources of income:
FDI:
Demographic situation:
a
28.6 million
a
b
USD 6,637 (USD 15,588.66 PPP )
Industry, Transport, Oil and Gas, Agriculture,
Banking and finance.
c
from 3.8% (2009) to 2.0%
Exports of oil and gas, manufacturing (electrical and
electronics), palm oil and rubber
d
US$ 7 billion
72.2% urban/27.8% rural, urbanization ranging
from 35% to 90% (WB, 2010)
Sources: a: EPU MIEF2011, b: World Bank, c: EPU 10MP, d: UNCTAD Report2011
Malaysia is on track to achieving a developed country status by 2020. Malaysia is projected to be able to attain
the Millennium development goals (MDGs) at aggregate level by 2015. The MDGs consist of 8 different goals
and they are to: eradicate extreme poverty and hunger; achieve universal primary education; promote gender
equality and empower women; reduce child mortality; improve maternal health; combat HIV/AIDS, malaria and
other diseases; Ensure environmental sustainability; and develop a global partnership for development.
Furthermore efforts have been carried out to raise the living standards of low-income households through
greater interagency coordination and improvements in application processes.
Malaysia has experienced three decades of impressive economic and social progress, enabling it to provide
for the health and education of its people, to eradicate poverty in large measure, to build excellent
infrastructure and to become a major global exporter. The changing global landscape, financial and economic
pressures, free movements of human capital, environmental issues and profits affecting Malaysia’s progress
towards Vision 2020. Towards this end, both the New Economic Model and the Tenth Malaysia Plan, which
emphasize inclusive growth, aspire to provide equal opportunities to all Malaysians. Apart from eradicating
poverty, priority will be on increasing the coverage of basic infrastructure such as roads, electricity (universal
assess) and water supplies, and communication networks. Health-care access, coverage and quality will
continue to be improved. In meeting its voluntary commitment of reducing greenhouse gases and to ensure
the sustainability of the environment (including conservation and sustainable use of natural resources),
emphasis will be placed on using renewable energy and on increasing energy efficiency through new
guidelines, standards, laws and incentives, which in directly support the SE4ALL objectives.
8
1.2 ENERGY SITUATION
1.2.1 Energy Supply (energy mix, export/import, electricity sector)
Primary Energy Sources
ktoe
Hydropower
Coal and
Coke
Crude Oil
Natural Gas*
Petroleum
Products &
Others
Source: NEB 2009
The primary energy source for Malaysia comes from natural gas at 41% followed by crude oil at 40.1%
(2009). Its total primary energy supply registered at 74,582 ktoe, a decline of 1.2 percent compared to
72,384 ktoe during the previous year. The decrease was led by lower primary production of natural gas
and crude oil in 2009. This was anticipated also by decreasing imports of total energy due to unattractive
energy demand during the period. Malaysia has one of the most extensive natural gas pipeline networks
in Asia, owing to the multi-phased peninsular Gas Utilization (PGU) project that was completed in 1998.
Natural gas in Malaysia is mainly utilized for electricity generation through natural gas fired power plants,
petrochemical and large industrial uses, and motor vehicles.
Upstream industries
The country’s crude oil and condensate reserves amounted to 5.517 billion barrels in 2009. The average
production of domestic crude oil and condensate increased from 681,000 barrels per day (bpd) in 2000
to 658,800 bpd in 2009. Based on this production level, which is in line with the National Depletion
Policy, the reserves are projected to last for 15 years (ADB). Nearly all of Malaysia's oil comes from
offshore fields. The continental shelf is divided into 3 producing basins: the Malay basin offshore
peninsular Malaysia in the west and the Sarawak and Sabah basins in the east. Most of the country’s oil
reserves are located in the Malay basin and tend to be of high quality. Malaysia’s benchmark crude oil,
Tapis Blend, is of the light and sweet variety with an API gravity of 44° and sulfur content of 0.08 percent
by weight. More than half of total Malaysian oil production currently comes from the Tapis field in the
offshore Malay basin. Malaysian oil production has been gradually decreasing since reaching a peak of
862,000 bbl/d in 2004 due to its maturing reservoirs. Malaysia consumes the majority of its oil production
and domestic consumption has been rising as production has been falling. The government is focused
on opening up new investment opportunities by enhancing output from existing fields and developing
new fields in deep water areas offshore Sarawak and Sabah.
9
Gross natural gas production however has been rising steadily, reaching 2.7 Tcf in 2010, while domestic
natural gas consumption has also increased steadily, reaching 1.1 Tcf in 2010, 42 percent of production.
Downstream Industries
Malaysia had about 538,580 barrels per calendar day (b/cd) of refining capacity at seven facilities as of
January 2011. PETRONAS went into refining and distribution in 1983 where it initiated the construction of
refineries at Malacca and at Kerteh in order to reduce its dependence on Royal Dutch/Shell's two refineries at
Port Dickson and Esso's refinery in Sarawak. Malaysia invested heavily in refining activities during the last two
decades and is now able to meet most of its demand for petroleum products domestically, after relying on the
refining industry in Singapore for many years. Petronas operates three refineries (259,000 b/cd total capacity),
while Shell operates two (170,000 b/cd total capacity), ExxonMobil operates one (86,000 b/cd), and Kemanan
Bitumen Co. operates another (23,750 b/cd). Kemanan Bitumen refinery largely produces bitumen from heavy
crudes. The Sabah Oil and Gas Terminal, under construction in Kimanis, Sabah, is expected to be completed
by the end of 2013. It will receive crude from offshore fields, process and distribute the products via a planned
310-mile pipeline linking Sabah with Bintulu, Sarawak. The terminal will have a processing capacity of 300,000
bbl/d of crude and condensate. By 1990, 252 service stations carried the PETRONAS brand, all but twenty
(20) on a franchise basis, and another fifty (50) were planned. Some were set up on grounds of social benefit
rather than of strict commercial calculation.
Electricity sector
Biomass
2%
Diesel
5%
Others
0%
Hydro
8%
Oil
1%
Hydro
5%
Coal
40%
Oil
Diesel
1%
1%
Other
2%
Coal
28%
Gas
56%
Gas
52%
Installed Capacity (2010)
Biomass
1%
Others
0%
Generation Mix (2010)
Source: NEB 2009
As of 2010, installed capacity amounted to 27,179 MW while the generation mix stands at 125,045
GWj where maximum demand was at 15,072 MW.
The Malaysian electricity sector has evolved tremendously for the past 60 years. The national utility (Tenaga
National Berhad) is currently involved in the generation, transmission and distribution of electricity business. In
Peninsular Malaysia, the Company is a major contributor to the total industry capacity through six thermal stations
and three major hydroelectric schemes. It also manages and operates the National Grid which links TNB power
stations and IPPs to the distribution network in the peninsula. The grid is connected to Thailand’s transmission
system in the north and Singapore’s transmission system in the south. In East Malaysia, TNB, through 80%-owned
subsidiary Sabah Electricity Sdn. Bhd. (SESB), manages the Sabah Grid and aims to provide electricity to 95% of
the state’s population by year 2013. TNB’s distribution network is managed through a comprehensive distribution
system, customer service centres and call management centres. Over the years, TNB has diversified from its core
business into the manufacture of transformers, high voltage switchgears and cables; the provision of professional
consultancy services; and architectural, civil, electrical engineering works and services, repair and maintenance. In
2005, TNB embarked on a 20-Year Strategic Plan which entails greater focus on green initiatives such as the
development of renewable sources of fuel, and more effective demand side management via energy efficiency.
These efforts complement the Government’s
10
carbon reduction agenda while also creating a foundation for sustainable energy for the future. Set
up as the Central Electricity Board of the Federation of Malaya in 1949, TNB has powered national
development efforts for more than 60 years by providing reliable and efficient electricity services.
1.2.2 Net Imports and Exports by Fuels Type
10,000
9,000
25,000
8,000
7,000
20,000
6,000
5,000
15,000
4,000
3,000
10,000
2,000
5,000
1,000
0
Coal &
Coke
0
Crude Oil Petroleum Natural
Products
Gas
LNG
Energy Imports in ktoe (2009)
Pet. Products
Coal & Coke
Energy Exports in ktoe (2009)
Source: NEB 2009
Coal remains the highest imported fuel mainly for coal-fired power plants. The Liquefied Natural Gas
(LNG) and the crude oil are the largest exported. The majority of Malaysia’s oil exports go to markets in
Japan, Thailand, South Korea and Singapore. The LNG and natural gas products are mostly exported
to Japan, South Korea, and Taiwan. Malaysia is a significant net exporter of natural gas, primarily in
the form of liquefied natural gas (LNG). It was recorded in 2005 that Malaysia exported just over 1 Tcf
(trillion cubic feet) of LNG, mostly to Japan, South Korea, and Taiwan. In 2010, Malaysia exported
234,000 bbl/d of crude oil, down slightly from the 236,000 bbl/d exported in 2009. This was about 35
percent of Malaysia’s crude oil production. The Tapis blend is Malaysia’s major exported crude oil
because its high quality and low sulfur content commands premium prices. In 2010, Malaysia imported
205,000 bbl/d of lower-cost crude oil for processing at its oil refineries.
The production and export of Liquefied Natural Gas (LNG), however, has increased from 23,606 ktoe in 2009 from
22,277 ktoe in 2008 level. Malaysia was the third largest exporter of LNG in the world after Qatar and Indonesia in
2010, exporting over 1 Tcf of LNG, which accounted for 10 percent of total world LNG exports.
Japan, South Korea, Taiwan, and China have supply contracts with Malaysia, and are the largest purchasers.
LNG is primarily transported by Malaysia International Shipping Corporation (MISC), which owns and
operates 27 LNG tankers, the single largest LNG tanker fleet in the world by volume of LNG carried. MISC is
62-percent owned by Petronas. The Bintulu LNG complex on Sarawak is the main hub for Malaysia's natural
gas industry. Petronas owns majority interests in Bintulu's three LNG processing plants, which are supplied by
offshore natural gas fields. The Bintulu facility is the largest LNG complex in the world, with 8 production
trains and a total liquefaction capacity of 1.7 Tcf per year following the debottlenecking completed at end2010, which raised overall capacity by 0.6 Tcf per year. Japanese financing has been critical to the
development of Malaysia's LNG facilities. Also in Bintulu is Shell’s gas to liquids (GTL) project which has a
production capacity of 14,700 bbl/d. Construction began on Petronas’ Sabah Oil and Gas Terminal (SOGT) in
Kimanis, Sabah in 2011 and is expected to be completed by the end of 2013. It will have a handling capacity
of 1.3 Bcf/d of natural gas per day from the Gumusat-Kakap, Malikai, and Knabalu offshore fields. It will upply
gas for domestic use in Sabah, largely for a new electric power plant slated for completion in 2014. A reported
11
500,000 cubic feet per day will be piped to the Bintulu complex to be exported as LNG. The
Sabah-Sarawak Gas Pipeline project is part of this development.
1.2.3 Energy demand
Final Energy Demand in ktoe (1999 vs 2009)
Source: NEB 2009
Energy demands in the transport sector have been increasing swiftly in Malaysia due to improvements in
transportation. The rapid industrialization of the country in recent years has led to high economic growth,
which in turn has led to population growth and an accelerated ownership of motorized vehicles. The total
number of vehicles in the country have increased from about 5 million in 1991 to 19 million in 2009,
thereby registering an average annual growth rate of about 8% during this period. The growth in the
number of vehicles in the country has been faster than the growth in population.
Based on the National Energy Balance, Industrial sector is the main user of electricity in Malaysia with its
share of 44.9 percent from total consumption in 2009. The electricity consumption from the industrial sector
increased by 0.9 percent to register at 3,719 ktoe (43,220 GWh) compared to the previous year. The
consumption of electricity in the commercial sector also increased to reach 2,743 ktoe (31,857 GWh), boosted
by tourism activities following the expansion of new routes by airlines and various tourism promotional
activities organised during the year. The electricity consumption in the residential sector recorded an increase
of 7.4 percent to register at 1,792 ktoe (20,822 GWh). The electricity consumption from the rail transport
sector, however, decreased from 15 ktoe (173 GWh) in 2008 to 12 ktoe (163 GWh) in 2009.
12
1.2.4 Energy and Economic Development
Share of energy sector in GDP
Source: ETP 2011
In 2009, the combined oil, gas and energy sectors represented 19 % of GDP equivalent to RM127
billion (USD 41 billion) while in 2015, it is expected that 11.1% of GDP equivalent to RM81.9 billion
(USD 26.42 billion). In total, the national oil company, Petronas, provides about 40% of the
revenue for federal budget in taxes, dividends and royalties.
Electricity and Economic Growth
120,000
600,000
100,000
500,000
80,000
400,000
60,000
300,000
40,000
200,000
20,000
100,000
Electricity
Consumption
(GWh)
GDP (RM mil)
0
0
Source: NEB 2009
The last 20 years have seen the growth of electricity in tandem with the growth of country’s GDP.
Industrial, commercial and residential sectors are the main users of electricity use and will continue to be
the critical sectors based on the current trend of increasing middle-income families as well the opening
up of new townships and construction of new commercial and residential buildings. The total electricity
consumption recorded a growth of 3.8% compared to the previous year to register at 8,286 ktoe (96,307
GWh). It is clear that the demand for electricity has seen a large increase the past 20 years or so. With
Malaysia’s urban population to reach 78% in 2030 from 63 % 2002, combined with high per capita GDP
growth of 3.4% per annum over the outlook period, it will lead to a change in lifestyle, where energy
consumption will be based mostly on commercial energy sources in the form of electricity (EPU 10MP).
13
1.2.5 Energy Strategy and Relevant Targets
Since independence in 1957, Malaysia has always strive in ensuring universal access to basic
infrastructure (roads, electricity, treated water and basic sanitation). During the 10 Malaysia plan
period, electricity supply coverage will be expanded through the grid extension and alternative
systems such as mini hydro and solar hybrid. Coverage of electricity supply is expected to reach
almost 100% in Peninsular Malaysia and 99% in Sabah and Sarawak by 2015.
Malaysia’s concerns on energy security for economic development started during the 1970s oil crisis. The
National Energy policy of 1979 was prepared and focuses on three different objectives: the supply, utilization
and environmental issues surrounding energy. The supply objective aims to ensure adequate, secure and
cost-effective supply of energy; the utilization objective aims to promote efficient utilisation of this energy and
discourage wasteful and non-productive patterns of energy consumption; and finally the environmental
objective aims to ensure factors pertaining to environmental protection are not neglected in production and
utilization of energy. In 1981, the Four-Fuel diversification policy was introduced, which strives to reduce the
over-dependence on a single fuel source; and to focus on four main sources of fuel, i.e. oil, hydropower,
natural gas and coal. To strengthen further, the Fifth-fuel policy was introduced in 2000 which focuses on
incorporating renewable energy as next available fuel for power generation; and expanding fuel sources to
comprise, hydropower, natural gas, coal and renewable energy. Other related policies includes 1974
Petroleum Development Act (establishment of Petronas), 1975 National Petroleum Policy, 1980 National
Depletion Policy, 1990 Electricity Supply Act, 1993 Gas Supply Acts, 1994 Electricity Regulations, 1997 Gas
Supply Regulation and the 2001 Energy Commission Act.
In 2010, the Renewable Energy Action plan was formulated to intensify the development of gridconnected renewable energy, particularly biomass, as the 'fifth fuel' resource under the country’s
Fuel Diversification and Fifth-fuel Policies. REAP provides potential targets for RE in Malaysia
where more than 6,500 MW can potentially be generated from solar PV: 1,340 MW by 2030 from
biomass; 410 MW by 2028 from biogas; 490 MW from mini-hydro by 2020 and about 360 MW by
2022 from Solid waste. Arising from the needs of a dedicated regulation on RE, the RE Act and the
Sustainable Energy Development Authority (SEDA) Act were successfully gazetted in 2010 which
leads to the official starting of the Feed-in-Tariff mechanism for RE projects in December 2011. It is
expected that that renewable energy to reach 985 MW (5.5%) by 2015 and 2,080 MW by 2020.
The New Energy Policy (2011-2015) emphasizes energy security and economic efficiency as well
as environmental and social considerations. The Policy will focus on five strategic pillars: initiatives
to secure and manage reliable energy supply; measures to encourage energy efficiency (EE);
adoption of market-based energy pricing; stronger governance and managing change.
EE initiatives will gain momentum with the finalization of the National Energy Efficiency Master Plan
expected to be in 2012, setting of minimum energy performance standards for appliances and
development of green technologies. These measures will encourage industries and consumers to
use energy productively and minimize waste to be more competitive in the global market.
14
SECTION 2: CURRENT SITUATION WITH REGARDS TO SE4ALL GOALS
2.1 ENERGY ACCESS vis-à-vis GOAL OF SE4ALL
2.1.1 Overview and assessment
Rural electrification rate and availability of clean domestic energy (for cooking mainly) will be used in the
context of preparing this Rapid report. As at date, rural electrification has successfully penetrated 99% of
the country, 99.5% in Peninsular Malaysia, 77% in Sabah and 76% in Sarawak. Fossil fuel such as LPG
and kerosene for cooking is available in the market and widely sold in the groceries, supermarkets and
selected gasoline stations. Nevertheless, fuel wood is still being used in some area especially in remote
Peninsular and in highlands of Sabah and Sarawak, where it can be found easily and without cost.
Malaysia has still a large number of small villages and islands, mainly in Sabah and Sarawak that lack 24-hour
electricity, and the probability of connecting them to high voltage gridlines in the near future is poor due to
geographical issues and many other logistical constraints. No exact record on the remaining gaps to cover but
it is estimated nearly 300,000 households are still without 24-hour electricity as per DOS statistic in 2005,
mainly in Sabah and Sarawak. Nevertheless, the government has embarked on several initiatives to find
sustainable ways to cater for the electricity demands of these poor rural villages. Solar home system (SHS) (of
150W less) has been installed in various remote locations since 1990 where a total installed capacity as date
is nearly 2MW in capacity. Solar diesel PV hybrids have been initiated by TNB-Energy Services since the year
2001 in Pekan, Pahang including several islands in Peninsular Malaysia.
Approach to providing 24-hour electricity supply is similar to providing clean and treated water, the
process of adding new power connections across Malaysia involves connecting to grid-based electricity
or implementing solar hybrid systems. The type of new connection hinges upon population density and
the remoteness of a location. The preferred mode of supplying electricity would be to connect to the
electricity grid. However, in rural areas which are very far from any transmission infrastructure, or in
instances where connections to the main grid are very expensive, technologies such as solar hybrid
power generation or micro hydro-electricity are introduced. In the year under review, these alternative
approaches helped ensure the provision of electricity to more villages in rural areas.
Malaysia has matured institutional set-up in the energy industries, covering the oil and gas sector to the
electricity segment. The Economic Planning Unit (EPU) has the overarching responsibility towards energy
policy and planning, both for conventional and non-conventional sources of energy, and poverty reduction in
Malaysia. The Ministry of Rural and Regional Development (MRRD) and the Ministry of Energy, Green
Technology and Water (MEGTW), work in close coordination for the rural electrification programme. In
addition the MEGTW works in tandem with the Energy Commission (EC) and the Sustainable Energy
Development Authority (SEDA) to coordinate national programmes in energy efficiency and renewable energy.
2.1.2 Modern energy for thermal applications (cooking, heating)
Availability/quality of supply including status of domestic supply chain:
Domestic energy for cooking comes in the form of Liquefied Petroleum Gas (LPG) is sold openly and is
available in many shops in the rural area. Fossil fuel such as gasoline (for transportation) and kerosene
(use for cooking and lighting) is widely sold and can be bought easily even in the un/semi-electrified
places (such as in deep rural in the state of Sabah and Sarawak). On the other hand, traditional fuels
(especially wood) are also popular and still being used considering its abundance in the area.
15
LPG in Malaysia is widely used in households for heating appliances such as ovens and stoves It is also used
in industries such as iron and steel industry, aerosol propellant industry, glass and ceramic manufacture,
copper tubing and cable manufacture. For cooking, it comes in three cylinder sizes which are the 12, 14 and
50 kg cylinders. The 12, 14 and 50 kg cylinders are painted according to the manufacturers’ specification
(yellow for Shell, Green for Petronas and Blue for Esso). In 2009, LPG accounted for 2.9% of the total
production of oil refinery, 10.4% of the total demand and 6% of the final consumption for petroleum products.
Affordability
Gasoline and LPG are under government’s controlled items and sold with subsidized price. In 2012,
the price is as below
RM 1.90 (USD 0.61)/L for RON 95;
RM 2.10 (USD 0.677/L for RON 97;
RM 1.80 (USD 0.58) /L for Diesel;
RM 1.90 (USD 0.61) /kg for LPG
Use of subsidy allows energy prices to be managed within the affordability level of the majority
Malaysians. Average monthly household expenditure of, as below, shows that the cost of total
energy is below 5% of the average monthly income.
Average Monthly and Share of Household Expenditure for Urban and Rural, 2004/05
Expenditure group
Urban
Urban share of Rural share of
Total (RM)
Rural (RM)
(RM)
expenditure (%)
expenditure (%)
Housing, Water, 429.57
522.3
247.4
22.86
19.01
Electricity
Electricity
59.33
71.38
35.62
3.12
2.74
Gas
9.27
8.84
10.13
0.39
0.78
Liquid Fuels
0.19
0.08
0.4
0.004
0.03
Other Fuels
0.44
0.15
1.01
0.01
0.08
(Source: DOS)
Pattern of Household Expenditure on Fuels in 2005
Share of households without access to modern cooking/heating is estimated to be 0.5% mainly
using forest products. Population without electricity is estimated to be 200,000 as of 2011.
16
Subsidies:
Continuing from the above Affordability section, below is the detail subsidy structure:
Fuel type
RON95
Diesel
LPG (for 14kg unit)
Consumer price/L
(RM)
1.90
1.80
26.60
Price without subsidy/L
(RM)
2.93
2.66
48.02
Share of subsidy in
retail price
35%
32%
45%
Domestic energy has generally enjoys 30 to 40% subsidy from the government in ensuring the sold price
are within the reach of the mass. These energy subsidies may be direct cash transfers to producers,
consumers, or related bodies, as well as indirect support mechanisms, such as tax exemptions and
rebates, price controls, trade restrictions, and limits on market access. The subsidies makes the fuel
more affordable as it ensures adequate domestic supply by supporting indigenous fuel production in
order to reduce import dependency, or supporting overseas activities of national energy companies.
2.1.3 Access to electricity:
Physical access:
Grid connection: 99.7 % of population in Malaysia
Urban/rural areas: 99.5% in Peninsular Malaysia, 77% in Sabah and 76% in Sarawak in 2009
Target group: The remote areas in Peninsular Malaysia, islands and the states of Sabah and Sarawak.
Generally, major populated areas are connected to efficient grid systems as below.
Source: Energy Commission
Rural Electrification Programme
Since the 1950s, rural electrification has been promoted as part of rural development programme to bring
about security and physical development to the rural areas in the then Malaya. Rural electrification of
villages, implemented through the then Central Electricity Board was initially supplied using diesel
generators, mainly for security reasons in the fight against communist insurgencies. Rural electrification
has since been incorporated as part of rural development programme and received allocation under its
Five Year Development Plans, beginning from the First Malaya Plan (1960-1965) and later in the First
Malaysia Plan (1966-1970) up to the present Tenth Malaysia Plan (2010 - 2015).
The rural electrification programme is aimed at providing electricity supply to homes and villages, which are beyond
the operational areas of the local authorities, including the ‘orang asli’ in Peninsular and the indigenous groups of
Sabah and Sarawak by means of extending the grid lines, provision of generator sets and use of alternative energy
such as SHSs and solar-hybrid system. Rural electrification forms part of efforts to
17
provide social amenities to enhance the quality of life and living standards among the rural communities.
Priorities for rural electrification programme will be to provided transmission lines best to 33kV lines, low
voltage line to the villages and to upgrade infrastructure of 12 hours to 24 hours electricity supply.
Since 1970s, rural electrification has been incorporated in the New Economic Policy (NEP) framework for
eradicating poverty and increasing the quality of life in the rural areas, especially of the rural poor.
Increasing use of electricity is expected to increase productivity and incomes in the agriculture, industry
and commercial sectors and also affect the modernization and attitudinal change in the rural sector.
Qualifying Criteria for different types of Electrification Programme
Extension of Grid
Lines
 Priority will be
given to villages
which have high
population and
available public
amenities such as
schools, clinics and
religious centres.
 Average cost for
the project is
estimated around
RM25,000 (USD
8,065) per house
Generator Set
SHS
Solar-Hybrid system
 Easy assess to the
site via roads or
rivers
 Nearest grid lines
are more than
10km away
 Will not be
receiving any grid
line extension in
the next 5 years
 Average cost for
the project is
estimated to be
around RM15,000
(USD 4,839) per
house
 No proper road
leading to the area
 Will not be
receiving any grid
line extension in
the next 5 years
 Public amenities
will be given
priority
 No potential for
mini/micro hydro
system
 For housing unit,
maximum output is
100-150W capacity
 Nearest 11kV
overhead line is
more than 10 km
 No plan for grid
connection in the
next 3 years
 Depending on
locations where
project cost is
cheaper than grid
extension
 Clustered housing
units with at least
20 homes will be
given priority.
 Maximum output
shall be 50kW
capacity
Source: MRRD / MESITA
Current Approach to Rural Electrification Programme under PEMANDU NKRA Rural Basic Initiatives :
Rural development continues to be a fundamental component of the national agenda. Since Independence,
the government, via the many Malaya and Malaysia Plans, as above, has rolled out development initiatives for
roads, water, electricity and housing to ensure that the fruits of modernisation benefit all. In 2010, the Rural
Basic Infrastructure (RBI) NKRA was conceived to accelerate these efforts by delivering unprecedented big
and quick wins to rural communities. In 2011, the MRRD and the various implementing agencies were once
again tasked with spearheading RBI efforts. They continued to build upon the good momentum achieved in
the previous year and the rural landscape was further transformed for the better. Their efforts centred on
ensuring improved accessibility via new and upgraded roads, providing a clean, constant water supply and an
uninterrupted electricity supply, as well as building and refurbishing homes for rural communities. In 2010 and
2011 alone, a total of 54,222 houses have been benefitted under this programme. In 2012, it is targeted to
achieve 39,442 houses with allocated budget of RM 1 billion (USD 323 million).
18
Availability and reliability of supply:
Breakdown on Electricity (Gross Generation, Consumption, Installed Capacity, Peak Demand
and Reserve Margin) for Malaysia
Region
Peninsular
Malaysia
Sarawak
Sabah
Total
Electricity Gross
Generation
GWh
%
95,120
90.0
Electricity Consumption
GWh
87,950
6,068
4,518
105,706
4,539
3,818
96,307
5.7
4.3
100.0
%
91.3
Installed
Capacity
MW
22,173
Peak
Demand
MW
14,245
Reserve
Margin
%
55.7
4.7
4.0
100.0
1,220
984
24,377
996
719
22.5
36.9
Source: NEB 2009
Historically, though were very isolated cases, Malaysia had been impacted by several blackouts in the past.
The first major blackout was in 1992 when lightning struck a transmission facility causing rolling failure in the
transmission and distribution system. Another blackout occurred in 1996, which occurred due to the tripping of
a transmission line near the Sultan Ismail power station in Paka, Terengganu. Another outage happened in
2003 in the southern area of peninsular Malaysia due to a power outing. Finally the latest outage was in 2005
and was due to a fault in the main cable transmission line grid near Serendah, Selangor. For the past 10
years, Malaysia’s grid supply has been good and un-interrupted and going into average interruption data,
according to System Average Interruption Duration Index (SAIDI) report, Malaysia has improved quality of
supply compared to the previous years where in Peninsular it has recorded 4% in Peninsular and decreased
76% in Sabah between 2009 and 2010. Malaysia generally has a stable and consistent power supply.
Affordability:
Tariffs (as of April 2012)
Power companies
Tenaga Nasional Bhd (TNB)
Sabah Electricity Sdn Bhd
(SESB)
Syarikat SESCO Bhd (Sarawak)
Tariffs (in USD/kWh)
Domestic
Commercial (low voltage)
6.97 (1-200 kWh)
12.57 (1-200 kWh)
5.59 (1-100 k Wh)
10.56 (1-200 kWh)
Industrial (low voltage)
11.03 (1-200 kWh)
10.23 (for all kWh)
10.88 (1-100 kWh)
12.79 (1-100 kWh)
12.79 (1-100 kWh)
(Source: TNB, SESB, SESCO)
The charge of tariffs imposed on the domestic use is much lower to the ones imposed on the commercial or
industrial scales making it affordable of the household expenditure scale. The government also continues the
the Lifeline Band which is at 200kWh/month. The Lifeline Band ensures domestic consumers in the 1 to
200kWh per month band to be secluded from the recent electricity tariff increase since 1997. Around 3.3
million households will continue to enjoy the subsidised rate of 21.8 sen/kWh ( USD .07/kWh) . This number of
households safely encompasses all 200,000 poor households (i.e. income less than RM750 per month).
Share of utility bills in household incomes:
As of 2005, the urban and rural shares of electricity expenditure were respectively of 3.12% and
2.74% of household income. Table in the 2.1.2 Affordability section shall be referred.
Subsidies:
A subsidy of 30 % to 40 % is given on average of kWh use.
Sustainability
In 2010, the Electricity Commission Report (ST) highlighted that Peninsular Malaysia could face a
power shortage by 2015 if the generation capacity did not grow. This was based on a demand
growth trend of between 5% and 8% every year that could result in the electricity reserve margin
dropping below 20% by 2015, from the current healthy level of around 55.7%, if supply growth do
not keep pace. The government is currently exploring various alternatives for new planting up.
19
Share of renewable energy sources (RES) in power mix:
Share of sustainable biomass and other RES:
Type of RE
Biomass
Solid waste
Biogas
Mini hydro
Solar PV
Others (wind)
Capacity of generated energy connected to the grid
(MW)
30
5.5
2
2
1
23.5
64
As for 2010, RES accounted for less than 1% of total generated electricity.
20
2.2 ENERGY EFFICIENCY vis-à-vis GOAL OF SE4ALL
2.2.1 Overview and Assessment
th
Energy efficiency (EE) measures (including demand side management) have been ongoing since the 7
Malaysia Plan period (1996-2000) and in 10 Malaysia Plan, it has been intensified to harness energy
savings potential and reduce Malaysia’s carbon emissions and dependence on fossil fuels. Intrinsic
barriers to energy efficiency that pose challenges in capturing this opportunity are being addressed. EE
covers the efficiency of power generation, transmission and distribution of electricity as well as various
end uses of energy such as in the industrial, commercial and residential. In other words it can be divided
into supply and demand side perspectives. In the recent 10th Malaysia Plan (2011-2015), the key
emphasis is on the short-term goals vested in National Green Technology Policy (2009), these include
promotion of EE for power producer, establishment of EE targets and standards.
The Efficient Management Of Electrical Energy Regulations which was launched in 2008, under
“Electricity Supply Act 1990” require premises which consume more than 3,000,000kWh over a
period of 6 months, to submit status reports to the “Energy Commission”, Malaysia including the
establishment of an energy management system. The government is currently exploring the
possibility of establishing a revised National EE Master Plan including an Act to spearhead EE
further. PEMANDU together with MEGTW, has launched the SAVE programme as part of a nationwide market transformation exercise towards the use of energy efficient appliance.
There are a number of completed and ongoing projects which will support national EE programme such
as the DANIDA Capacity building in integrated resources planning at government and related agencies,
DANIDA’s Center on Training on EE & RE (CETREE) Capacity building project, MEGTW Low Energy
Office (LEO) at Putrajaya; TNB’s Demand Side Management, Green township, JICA’s Low Carbon
Society (LCS) in Iskandar Development Region, UNDP /GEF Malaysia Industrial Energy Efficiency
Improvement Project and the UNDP/GEF Building Sector Energy Efficiency Project (BSEEP).
SAVE or Sustainability Achieved via Energy Efficiency, is a program spearheaded by the Ministry of
Energy, Green Technology and Water to improve energy efficiency in Malaysia. It is launched in 2011 as
a quick start programme to encourage residential users to change into energy efficient appliances when
making new purchases. It is to create a culture of efficient energy usage among general public and
business entities. This initiative targets the final end user through the retailers of electronic appliances
and it is targeted to provide national savings up to 7,300 GWh of energy saved by the year 2020. It is
also to accelerate the transformation of the consumer appliances market to increase the share of Energy
Efficient (EE) models and to phase out inefficient models from the local market so as to reduce the price
premium for EE products. 100,000 rebate vouchers for 5-Star rated refrigerators and 65,000 vouchers for
5-Star rated air conditioners have been allocated to states across Malaysia. Rebates will be awarded on
a first-come, first-served basis to qualified domestic consumers who purchase 5-Star rated refrigerators,
air conditioners or chillers during the rebate offer period through participating retailers. As date, over
more than 4,000 retail outlets nationwide are registered with KeTTHA under the SAVE Rebate Program,
with 12 different brands to choose from. The rebate program starts on July 7, 2011 and will last until all
rebates are taken at the end of 2012. To date, about 12.4 per cent and 7.1 per cent of market share of
five-star rated energy efficient refrigerators and air conditioners respectively have been recorded through
the initiatives being implemented, with total energy saving accumulation of 66.3 GWh.
Under the PEMANDU Energy, Oil and Gas cluster, EPP9, Malaysia will focus on five
relevant levers to improve EE which are,
1. to lead by example on energy-efficiency practices and philosophy,
2. to stimulate sales of energy-efficient appliances,
3. the Government will work with TNB to make co-generation economically viable,
21
4. to regulate better insulated buildings and
5. to stimulate the sale of energy-efficient vehicles.
In March 2011, it was announced that Faber Group Berhad will spearhead the pilot project for the
Energy Performance Management System (EPMS) for government entities. Faber has commenced
and completed energy audits at five hospitals in the northern states of Peninsular Malaysia. To
stimulate the use of fuel efficient cars, the import duty on all hybrid cars has been exempted,
bringing the cost of hybrid models such as the Toyota Prius and Honda Insight to more competitive
levels. Sales of hybrid cars are expected to achieve record highs in 2011. This exemption was
extended to the end of 2013 in the recent Budget 2012 announcement. The implementation of
Energy Performance Contracting (EPC) in 120 top energy- using government buildings will be
further explored for implementation in all government buildings and private properties.
2.2.2 Energy intensity of national economy:
(Source: 2010 MDG report)
2.2.3 Industrial Energy Intensity
Industrial Energy Intensity stands at 78 toe/RM million in 2009 (NEB 2009)
Under the Malaysian Industrial Energy Efficiency Improvement Project (MIEEIP) from 2000-2007 which was
funded by United Nations Development Program (UNDP), Global Environmental Facility (GEF), private sector
and Government of Malaysia, eight industrial sectors, cement, ceramic, food, glass, iron & steel, pulp & paper,
rubber and wood has been identified to have the potential to promote and improve energy efficiency.
Electrical Energy- use Equipment has been produced to give a the guidelines to encourage industries to
adopt energy efficiency practices and improving their energy utilization for a commonly used equipment
such as fans, motors, pumps, chillers, transformers and air-compressors. A standard general energy
audit guideline, the Industrial Energy Audit Guidelines shall be used as a reference material by energy
consulting firms in their audit services to industries. There are 54 energy audits in the eight industrial sub
sectors under MIEEIP. The project has highlighted a number of important issues and some significant
lessons have been learnt. The experiences and the outcomes in the form of industry involvement and the
demonstration models will provide exemplars for further steps in energy efficiency throughout Malaysia.
2.2.4 Residential Energy Consumption
Residential Energy Consumption is at 3042 ktoe in 2012 (NEB 2009).
EE appliances which participated in the voluntary rating programme are Refrigerators, Domestic
Electric Fans, Ballast for Fluorescent Lamps, Electric Lamps, Air Conditioners (Split Unit),
Televisions, High Efficiency Motors and Insulation Materials. Out of these eight appliances only four
(4) appliances have participated in the voluntary ‘star labelling’ programme (as below) which are
televisions, refrigerators, Domestic Electric Fans and Air Conditioners (Split Unit).
22
Sample of a Malaysian voluntary labelling programme
2.2.5 Potential cumulative energy savings by 2015
The 10 Malaysia Plan estimated that there would be a potential cumulative energy saving of 4,000
ktoe by 2015.
As explained, the national energy efficiency master plan will be drawn up and measures such as
phasing out incandescent light bulbs and requiring more devices to have EE labelling will be
introduced. In addition, there will be a ratings system for green townships, led by Putrajaya and
Cyberjaya, along with minimum energy performance standards for equipment and machinery.
23
2.3 RENEWABLE ENERGY vis-à-vis GOAL OF SE4ALL
2.3.1 Overview and Assessment
Policy on renewable energy (RE) has been mainstreamed and recognised as early in the year 2000. The advent of
the Fifth fuel policy has further reinforced Malaysia’s position in developing the RE industries. It was initially targeted
to contribute 5% of the country’s electricity demand by year 2005 and the Small Renewable Energy Program (SREP)
was launched in May 2001 under the initiative of the Special Committee on Renewable Energy (SCORE) aimed to
support the government’s strategy in intensifying the development utilization of RE, where by 2005, equal to between
500 and 600 megawatt (MW) of installed capacity to be made available. The policy has been reinforced by fiscal
incentives, such as investment tax allowances and accelerated capital allowance which encourages the connection
of small renewable power generation plants to the national grid.
The buy-back tariff started with a fixed price from RM 0.17/kWh (USD 0.055 /kWh), RM 0.19/kWh
(USD 0.062 /kWh) and finally RM 0.21/kWh (USD 0.067 /kWh). However, despite the efforts, RE
pricing was seen still unattractive to compete with the level playing field with the fossil-fuel tariff and
a need to restructure the RE industries was needed.
On 2nd April 2010, the Cabinet approved the National Renewable Energy Policy and Action Plan that
would be the cornerstone for a more aggressive deployment of RE in the country. The policy and
objectives of the National Renewable Energy Policy and Action Plan are to enhance the utilisation of
indigenous RE resources to contribute towards national electricity supply security and sustainable
socioeconomic development. Finally, in 2011, Malaysia’s Parliment gazzeted the Renewable Energy Act
(RE Act) and the Sustainable Energy Development Authority (SEDA) to spearhead the RE in Malaysia.
Its key role is to administer and manage the implementation of the feed-in tariff (FiT) mechanism where
the resources focused as of now are biomass, biogas, mini-hydropower and solar energy. Applications
for the FiT opened on 1 December 2011, with quota for solar photovoltaic cells of 150MW, biomass
(including solid waste) of 240MW, biogas (including landfill) of 90MW and small hydro of 150MW offered
to any interested party through an open online application system. The quota allocation for solar
photovoltaic up until 2014 was almost fully applied for within 24 hours of its launch, whilst applications for
quota allocation for biomass, biogas and small hydro have been similarly encouraging.
Installed Capacity (MW) of Plants in Progress
Biogas
Small Hydro
Biomass (SolidWaste
)
Biomass
Individual
Non-individual (≤500kW)
Non-individual (>500kW)
HousingDeveloper
2012
2013
2014
8.36
4
0
5.38
2.8
0
9.2
28.3
42.05
8.9
0
0
33
48.5
6
6.53
2.86
0
2.37
3.28
0.79
61.02
58.5
30.53
0
0
0
134.75
148.25
79.37
Cumulative
12.36
8.18
79.55
8.9
87.5
9.39
6.45
150.05
0
362.37
Biogas (
Landfill /Sewage)
Year
Total
Source: SEDA’s Website September 2012
Currently, electricity generation from RE sources is very costly and not competitive with large scale plants
using conventional fossil fuel sources. The higher cost per unit has made investment in RE not attractive to
investors and electricity utility. The objective of FiT is to spur RE growth in Malaysia. FiT will be used to
subsidise the difference between the premium tariff rate and the current selling price of a unit of electricity from
RE developers to TNB under the SREP programme (i.e. at a maximum price of 21 sen/kWh).
24
2.3.2 On-grid and off-grid renewable energy
Category
Gridconnected
(MW)
Off-grid (MW)
Total
Mini-hydro
Biomass & biogas
Solar PV
Wind
Total
23.8
32
1
-
56.8
23.8
447
479
6.1
0.2
0.2
7.1
453.3
510.1
On-grid and off-grid RE in MW, Source: Energy Commission 2010
RE Operational Capacity
(source: SEDA’s website August 2012)
As RE Act has recently started in December 2011, progress on RE projects with FiT is relatively new and
many still in planning and commissioning stage. As date, 43.90 MW capacity has been in operation.
Use of renewable energy sources (RES) for thermal applications (cooking/heating)
As date, there is no official record on Malaysia’s rural using RE for cooking and heating.
Use of RES for productive activities
As date, there is no official record on Malaysia’s industries using RE for cooking and heating. However, there
were research projects undertaken by the National University of Malaysia (UKM) and Malaysia Research and
Development on Agriculture Industries (MARDI) on the use of solar drying for agriculture products.
25
2.4 SE4All GOALS
2.4.1 Energy Access
Malaysia is committed to ensuring universal access to modern energy services and providing 100%
electricity to the rural area. Under the Government Transformation Programme, universal access is
targeted to be achieved 2015. Targets for additional houses to be supplied with electricity are about
6,000 houses in Peninsular Malaysia, 59,000 houses in Sabah and 76,000 houses in Sarawak.
2.4.2 Energy Efficiency
The National Energy Efficiency Master Plan, 2010 is a holistic implementation roadmap to drive
efficiency measures across sectors with a target to achieve cumulative energy savings of 4,000 kilo
ton of oil equivalent (ktoe) by 2015 according to the 10 Malaysia Plan.
2.4.3 Renewable Energy
The share of renewable energy sources in the electricity sector will be increased from less than one percent
today to 5.5% in 2015 (985 MW). The doubling of rate on the use of RE at the national context (based on
business-as-usual scenario and upon the successful introduction of FiT) may happen middle of 2013.
RE Generation Capacity Targets under FiT (MW)
Year
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2025
2030
Biogas Biomass
20
110
35
150
50
200
75
260
100
330
125
410
155
500
185
600
215
700
240
800
350
1,190
410
1,340
Solid
Waste
20
50
90
140
200
240
280
310
340
360
380
390
26
Hydro
60
110
170
230
290
350
400
440
470
490
490
490
Solar
PV
9
20
33
48
65
84
105
129
157
190
455
1,370
TOTAL
219
365
543
753
985
1,209
1,440
1,664
1,882
2,080
2,865
4,000
SECTION 3: CHALLENGES AND OPPORTUNITIES FOR ACHIEVING SE4ALL
GOALS
3.1 INSTITUTIONAL AND POLICY FRAMEWORK
3.1.1 Energy and development
Energy in national development and poverty reduction strategies and plans
Energy is an important factor to Malaysia’s economic growth, constituting about 20 per cent of the
nation’s Gross Domestic Product (GDP). The Government plans to increase diversification of the
energy industry, step up exploration for new oil and gas resources, enhance production from known
reserves, and encourage the use of alternative energy sources such as solar, hydro-electric and
even nuclear. The energy sector’s contributions to our GNI are expected to rise from RM110 billion
in 2009 to RM241 billion in 2020. Hence, the energy sector needs to be more efficient and resilient
to be able to deliver adequate and reliable energy supply to support our country’s rapid growth
against a backdrop of depleting energy resources as well as escalating and volatile energy prices.
GDP (RM Million)
Trend: GDP vs Electricity Consumption
600,000
1
500,000
1
400,000
8
300,000
6
200,000
4
100,000
2
0
There is a strong correlationship between the rate of electrification and the reduction of poverty level in
Malaysia, although it will only due to rural electrification factor alone. Strong poverty alleviation programme
especially in the beginning of 1970s together with extensive completion of rural basic infrastructure (roads,
water, sanitation, schools and clinics) including rural education have contributed to the success of the poverty
eradication programme. The rise of electricity consumption is in tandem with the growth of GDP.
Energy governance:
Energy policy in Malaysia is set and overseen by the Economic Planning Unit (EPU), with close coordination
with the line ministries (MEGTW, on electricity matters) and agencies (i.e. Energy Commission and SEDA).
MEGTW regulates the non-oil and electricity sector (and gas energy and security sectors) while EC regulates
the energy supply activities and enforces energy supply laws. SEDA, is a newly set up statutory body formed
under the Sustainable Energy Development Authority Act 2011 whose role is to administer and manage the
implementation of the feed-in tariff mechanism mandated under the Renewable Energy Act 2011. Malaysia
Green Technology Corporation (MGTC) from time to time provides promotion, policy research and awareness
support to MEGTW related to green technology including RE and EE initiatives.
27
EPU
- formulates overall policy on rural development
- incorporates impacts of infrastructure
development to social and economic growth
PEMANDU / ICU /
State EPUs
Oversee
implementation
MEGTW
- guardian of the MESITA fund
- energy policy
EC:
MOE
- rural school
electrification
MOH
- rural clinic
electrification
Regulates electricity
MRRD
industry
SEDA:
Administrator of RE Act
MGTC:
Energy R&D on EE /RE
receives information on rural
development programme
including rural electrification
(basic infrastructure)
PWD / TNB
PWD / TNB
PWD / TNB
- project
- project
- project
SubContractors
SubContractors
SubContractors
- installations /
- installations /
- installations /
Linkages of Electricity Institutions related to Rural Electrification Projects
With respect to oil and gas industries, Petroliam National Berhad (PETRONAS), holds exclusive
ownership rights to all oil and gas exploration and production projects in Malaysia, for all licensing
procedures, and is subject to only the Prime Minister, who also controls appointments to the company
board. The company holds stakes in the majority of oil and gas blocks in Malaysia. It is the single largest
contributor of Malaysian government revenues, (over 40 percent in 2010), by way of taxes and dividends.
Malaysia's oil and gas policy has historically focused on maintaining the reserve base to ensure long
term supply security while providing affordable fuel to its population. In July 2010, the government
introduced subsidy reductions for gasoline, diesel, and liquid petroleum gas (LPG) with the aim of
gradually decreasing fuel subsidies to reduce expenditures. Further cuts in fuel subsidies are planned.
Generally, Malaysia plans for adoption of market-based energy pricing, in line with overall strategy to
rationalize subsidies where energy subsidies will be reduced, with the goal of achieving market pricing by
2015. Gas prices for the power and non-power sectors will be reviewed every six months to gradually
reflect market prices. A decoupling approach for energy pricing will be undertaken to explicitly itemize
subsidy value in consumer energy bills and eventually delink subsidy from energy use. For low-income
households and other groups for which the social safety net is required, different forms of assistance will
be provided. Malaysia also belives in the stronger governance of the energy sector where the goal to
raise productivity and efficiency. In this regard, the gas supply industry will be further liberalized to
facilitate the entry of new suppliers and third-party access arrangements. The electricity supply industry
will also be restructured to instil greater market discipline.
3.1.2 Thermal energy for households
LPG industry in Malaysia is currently dominated by state owned Petronas followed by Shell and
Esso among others while piped gas supply is regulated by the EC.
28
3.1.3 Power sector
MEGTW is the responsible ministry and the utility are provided by the utility companies (TNB in
Peninsular Malaysia, SESB in Sabah and SESCO in Sarawak.
3.1.4 Modern energy for productive sectors
RE is poised to be connected with up to 5.5% of total generation mix by 2015. MEGTW is responsible on
the execution of the RE Act policy while SEDA is to administer the FiT mechanism under the RE Act.
3.1.5 National monitoring framework for SE4ALL
Proposed indicators to measure and monitor achievement of national SE4ALL goals
Energy access indicators:
- Country rural electrification rate
- Share of households with access to electricity/energy for cooking & heating
- Impacts of electricity to rural
people EE indicators:
-
Average electricity consumption of households
Primary and final energy intensity by sector
Efficiency of total electricity generation
GDP / unit of Energy Used
Energy Used per capita
RE indicators:
- Share of renewables in gross electricity consumption
- Share of renewables in electricity generating capacity
- Share of households using modern energy for heating/cooking
Data requirements, gaps and associated capacity development needs
Related to 3.5
29
3.2 PROGRAMS
3.2.1 Thermal energy
Programme
LPG for cooking has been widely used. As date, there is no program on the use of thermal energy
from RE for domestic cooking and heating. Use of charcoal from biomass briquette is negligible.
For industrial usage, efforts are already on going on the use of RE sources from industrial byproducts (i.e. wood chips, MDF waste, saw dust, empty fruit bunch) mainly for producing steam (low
pressure/ high pressure) for manufacturing processes.
Sustainability
Research and development and pilot projects on briquette / pellet production especially from
biomass palm oil waste (EFB/blended) and rice husk has already in existence. Commercial
production has yet to be fully taken off. The processing cost is estimated at RM 150 per tonne and
the selling price for export market at RM 600 to RM 700 per tonne.
3.2.2 Power sector
Physical access (electrification)
As at date, rural electrification has successfully penetrated 99% of the country, 99.5% in Peninsular
Malaysia, 77% in Sabah and 76% in Sarawak (10 Malaysia Plan)
Reliability (grid maintenance/upgrade)
The utility companies (TNB, SESB, SESCO) has ongoing programme on ensuring continuous supply of power.
Sustainability (investment in renewable energy, on-grid and off grid, and energy efficiency)
The advent of RE Act has allowed the use of RE sources for power generation. Refer 2.3 for details.
3.2.3 Energy efficiency programs
Sector
Residential
Township
Initiatives
 Phasing out of incandescent light bulbs by 2014 to reduce carbon dioxide
emissions by an estimated 732,000 tons and reducing energy usage by 1,074 GW
a year.
 Increasing energy performance labeling from four (air conditioner, refrigerator,
television and fan) to ten electrical appliances (six additional appliances - rice
cooker, electric kettle, washing machine, microwave, clothes dryer and
dishwasher).
 Labeling appliances enables consumers to make informed decisions as they
purchase energy efficient products.
 Robust tariff structures (“the more you use, the more you pay principle”) to
encourage energy saving and avoid wastages.
 Encourages use of passive designs at home
 Introduction of guidelines for green townships and rating scales based on carbon
footprint baseline and promoting such townships starting with Putrajaya and
Cyberjaya.
30

Industrial
Buildings
Transport
Implementation of the newly formulated Low Carbon City Framework (LCCF) to
encourage less GHG emissions especially from energy usage
 Promotes energy efficient / multi modal public transport system
 Increasing the use of energy efficient machineries and equipment such as high
efficiency motors, pumps and variable speed drive controls.
 Encourages energy benchmarking among subsectors of industries
 Encourages the setting up of Energy Management Team to look into energy
consumption and measures and Energy Manager
 Encourages the use of ISO 5000 energy Management System
 Mandatory reporting of the energy usage and its management plan for electricity
users of 500,000kWh / year
 Introduction of Minimum Energy Performance Standards for selected appliances
to restrict the manufacture, import and sale of inefficient appliances to
consumers.
 Promotes the use of rating tools such as the Green Building Index (GBI), LEEDS
and CIDB Pass
Promotes
the Life-Cycle analysis (“cradle-to-cradle”) for building construction

industries under Carbon Common Metric (CCM)
 Effective public transportation system
 Use of Bus Rapid Transit in Iskandar Development Region (pilot phase)
Source: EPU 10MP
3.2.4 Modern energy for productive use
Sector
Community
Livelihood
Initiatives, currently ongoing
 Use of micro-hydro system for electricity generation
 Use of solar hybrid for electricity generation
 Solar home system (per household) for rural area
 Use of grid-connected solar PV system
Agriculture
 Use of solar drying in processing agriculture products (pilot stage)
 Use of micro-hydro system for pumps ( irrigation)
Energy Supply
 On-grid: Introduction of feed-in-Tariff for wide spread electricity generation from
RE sources (biomass, biogas, PV, mini-hydro)
 Off-grid: promotes the use of hybrid-diesel, micro-hydro and wind
Industries
 Use of biomass/biogas for in-house electricity generation use
 Use of biomass/biogas for use in the manufacturing processes (heating)
Education
 Use of solar PV for rural schools for ICT and communication
Transport
 Initiated Electric Vehicle piloting in Putrajaya, Cyberjaya and Bukit Bintang. It is
planned that charging station will be of hybrid solar/RE type in the near future
(including smart-grid connectability)
3.3 FINANCING
Government’s allocation: Financing for basic infrastructure (water, roads and rural electrification)
comes from the government development budget.
Feed-in Tariff (FiT): Financing for Feed-in Tariff (FiT) is currently based on of 1% of electricity usage
for consumers who are using more than 300kWh per month. It is estimated the amount to be RM 1
billion per year to be placed under the Renewable Energy Fund, to be administered by SEDA.
31
Fiscal and Financial Incentives: Since 2001, in order to promote EE and RE, companies
implementing RE & EE measures in their premises may be granted investment tax allowance,
accelerated capital allowance, import duty exemption and sales tax exemption.
Green Technology Financing Scheme (GTFS): In the budget speech for 2010, Dato’ Seri Najib Tun Abdul
Razak, the Prime Minister of Malaysia announced the establishment of Green Technology Financing Scheme
amounting to RM1.5 billion as an effort to improve the supply and utilization of Green Technology. The
scheme could benefit companies who are producers and users of green technology. In operationalizing it, the
Government will bear 2% of the total interest/profit rate. In addition, the Government will provide a guarantee
of 60% on the financing amount via Credit Guarantee Corporation Malaysia Berhad (CGC), with the remaining
40% financing risk to be borne by participating financial institutions (PFIs).
The Prime Minister also appointed MGTC as the conduit for the Green Technology Financing Scheme (GTFS)
application. The scheme is expected to provide benefits to more than 140 companies of which the application
will be open starting from 1st January 2010. It is also a mechanism that helps finance any technology that is
suitable for the identified project criteria provided it is a proven technology. GTFS requires that projects must
be located within Malaysia, utilising local and/or imported technology. Private companies that could benefit
from this financing scheme are “PRODUCER” or “USER” of green technology products or systems, as follows
FEATURES
USER OF GREEN TECHNOLOGY
PRODUCER OF GREEN TECHNOLOGY
Financing size
Maximum: RM50 million per company Maximum: RM10 million per
Financing tenure
Up to 15 years
Eligibility criteria
Legally registered Malaysian -owned Legally registered Malaysian companies (at least 51%) in all economic owned companies (at least 70%) in
all economic sectors
sectors
Participating financial
institutions (PFIs)
All commercial and Islamic banks.
GFIs: Bank Pembangunan, SME bank, Agrobank, Bank Rakyat, EXIM
bank and Bank Simpanan Nasional
company Up to 10 years
(source: MGTC)
Malaysia Electricity Supply Industry Trust Account (MESITA): MESITA was formally established on 1 January
1997 under a Trust Deed issued by the Ministry of Finance. The decision to establish MESITA was made by
the Malaysian Cabinet on 11 December 1996 which required all Independent Power Producers (IPPs) to fulfil
their national obligation towards the development of electricity supply industry in the country. To reflect their
role in the comprehensive contribution to electricity supply industry, the concept of social obligation which was
used in the initial establishment of MESITA was later changed to national obligation after discussions were
held between MEWC, TNB and the IPPs. The Independent Power Producers (IPPs) which sell electricity to the
Peninsular Grid make contributions annually to the Trust Account. The rate agreed by the contributors is
pegged at one percent (1%) of the total audited annual turnover of the previous year. This rate will remain until
2005 and thereafter a review of the rate will be done. The accumulated income of MESITA for the year 1998 to
2002 was RM 365,454,420.94 (USD 117,888,522.8 millions). All the IPPs contributed 1% of their annual
turnover from their audited accounts. Throughout its existence, MESITA managed to play a catalytic role in
carrying out the development programme of the electricity supply industry on a sustainable basis. Prior to the
existence of MESITA, all programme were implemented on a piece-meal and ad-hoc basis by agencies in the
electricity sector. These applications were localized and confine to their respective organizations and were not
industry-focused. The rural electrification project under the MESITA fund from 1998 to 2010 recorded
expenses of RM148,089,209.19 (USD 48 million) to upgrade and provide infrastructure for rural electrification
programme. As a result, a total of 41,218 houses are connected to the grid and 7,652 houses are connected to
the solar hybrid system especially for indigenous communities in Peninsular Malaysia.
The type of projects allowed under the MESITA Trust Deed are as
follows: 1. Rural electrification programme;
32
2. Research and development (R&D) programme for the electricity industry including
R&D on the development of new and renewable sources of energy;
3. Training and educational programme for human resource development in the electricity sector;
4. Energy efficiency (EE) programme; and the promotion and development of the
electricity supply industry;
5. The promotion and development of the electricity supply industry.
3.4 PRIVATE INVESTMENT AND ENABLING BUSINESS ENVIRONMENT
3.4.1 Thermal energy for households
Private sector actors involved in supply chain (energy supply companies, technology providers, financiers)
LPG for cooking is readily available in local sundries and is sold by public companies and private entrepreneurs.
Barriers to private investment in modern energy supplies and technologies for cooking and
other thermal applications
None significant as date
3.4.2 Power sector
Private sector actors involved in supply chain
Tenaga Nasional Bhd. (TNB) is the largest electricity utility company in Malaysia with a total installed
generation capacity of ore than 15,000 MW.
Syarikat SESCO Bhd
(formerly Sarawak Electricity Supply Corporation, SESCO) is the privatized
organization responsible for the generation, transmission and distribution of
electricity for the Sarawak state in Malaysia.
Sabah Electricity Sdn. Bhd SESB) is a company that generates, transmits and distributes electricity mainly
in Sabah and Federal Territory of Labuan. SESB is a subsidiary of TNB.
Independent
Power Responsible of about 70.78% (19,237 MW) of electricity generation in
producers (IPP)
Malaysia representing 17 different companies.
RE Developers
No official record but it estimated that there are more than 100 companies
who are currently expressed interest in participating in SREP and FiT.
Barriers to private investment in new on-grid and off-grid power generation capacity (especially for
RES), grid extension/maintenance, demand-side management (DSM) and energy efficiency
Type
Institutional
barriers
Data
Information
barriers
Description
Lack of institutional support especially on
the use of renewable energy (either for
thermal or off-grid electricity) in the rural
area.
Impacts
Lack of functioning institutional network on
RE could be overcome by encouraging joint
effort between government agencies (federal
and state) and private institutions in order to
explore the technical and commercial viability
of energy generation from renewable
resources and enhancing capacity building of
key players such as government decisionmakers, industries and utilities on RE
implementation. RE
/ Insufficient/limited data availability on the Impacts of rural electrification on small and
use of energy in the rural area
medium enterprises (and to poverty
alleviation) in rural areas have not been
extensively documented. Neither does the
33

Financial and
Incentive
barriers

Level playing field: Due to higher
commitments
accorded
to
development or expansion plans,
renewable energy is given a lower
priority by Malaysian enterprises.
There is a clear need for refocusing
the energy fuel mix in the country’s
energy equation to give importance
to renewable energy.
present framework of datum identifies these
enterprises by their location i.e., rural or
urban.
 The subsidy for conventional fuel source
should be gradually eliminated and/or
transferred to RE resources to promote
RE installations.
Special funds for energy delivery in  In agro-based industries, loans can be
rural: set up by the government to
utilized for purchase of farm equipments
promote small
and medium
and machineries, which utilize efficient
enterprises (i.e SMIDEC’s funds) do
electricity. Fish processing and agronot target entrepreneurs involved in
processing industries in rural areas are
energy service delivery such as
potential or actual beneficiaries of rural
enterprises in solar energy business.
electrification. Reliable supply
of
There is, at present, lack of incentive
electricity in rural areas enables
to these enterprises to operate in
fishermen in coastal areas to keep their
rural areas. There are a number of
daily catch in freezers. Provision of
enterprises in rural area, which
electricity enables cottage industries to
utilize energy, particularly electricity
work long hours and improve their
for lighting and motive power. Rice
productivity and income.
Female
mills, oil mills, weaving enterprises,
members of the community who work in
batik and crafts in rural areas
these enterprises also benefit from the
benefit from the use of electricity.
increased income and output due to the
Provision of electricity enables these
provision of electricity services.
enterprises to work long hours.
3.4.3 Modern energy for productive sectors
Similar to the above 3.4.2
34
3.5 GAPS AND BARRIERS
Section on gaps and barriers on Thermal energy for household, Power sector and Modern
energy for productive sectors will be summarized as below.
Barriers
Institutional
SE4ALL Objectives
EE
Universal Access
RE
No major issues noted in
the grid-connected
No major issues noted in the
electricity. MEGTW is the
electricity sector.
focal point for the
MEGTW is the focal point for
development of RE
the development of EE
policies with SEDA as the
policies supported by EC and
administrator of the FiT
SEDA.
mechanism.
No major issues noted.
MRRD remains as the
focal point for the rural
basic infrastructure
programme. EPU, ICU
and PEMANDU oversee
Energy use in transport
the implementation
remains as a challenge as
progress including rural
there is clearly an absence of
energy planning.
a dedicated agency in
charged on it.
Regulatory
No major issues noted.
Technical
No major issues noted.
The remaining gridextension remains a
challenge due to the
limited number of final
connections / houses
Awareness /
Promotion
No major issues noted
Use of RE (such as
biofuel) in transport
remains as a challenge
due to unseen economic
benefits (vs fossil fuel) as
per the current oil price.
Lack of a dedicated
regulatory mechanism on EE
hampers efficient energy
utilization in industrial,
residential, commercial and
No major issues noted.
the transportation sectors. It
is noted that
Efficient Management Of
Electrical Energy Regulations
2008 has been in operation
since 2008
No major issues noted.
Innovative ideas such as
No major issues noted. EE is
pooling FiT and new RE
looked mainly at sectoral
sources (which are not
level (buildings, energy
part of the current FiT
supply, energy demand,
scheme) such as wind
industrial and transportation
and geothermal are not
sectors)
currently not the national
priority.
Public awareness on the use
of energy (electrical and
domestic energy) is low due
to cheap and abundant
No major issues noted.
supply. The government is
fully aware and is currently
considering subsidy
rationalization in stragerred
35
Financing
basis. Use of public transport
has been in increasing trend
due to the improved
infrastructure.
Financing for EE projects
remains a challenge due to
No major issues noted as
limited successful cases on EE
both fuel for domestic
project financing. The
energy (LPG) and
government is currently
transport are marketsupporting Energy
based.
Performance Contracting in
selected hospitals.
36
Financing for RE projects
remains a challenge due
to limited successful
cases on RE project
financing. Cost of
technology is still
considered high.
REFERENCES
1. 10 Malaysia Plan, EPU 2010
2.
Economic Planning Unit, Economic Monitor, website September 2012
3.
4.
5.
6.
7.
ETP Energy, Oil and Gas, PEMANDU 2011
GTP Annual Reports, PEMANDU 2011
IEA Report / website September 2012
MDG Report, EPU and UN Country Team, 2010
National Energy Balance 2009
8.
PRODUCTION OF PALM-BASED BIOMASS BRIQUETTES. MPOB, 2006
9. Suruhanjaya Tenaga Statistics 2010
10. UNDP Human Development Report, 2011
11. World Bank Country Data, website September 2012
37
FINAL Draft: 19 Sep 2012
INTERNAL USE & FOR CONSULTATION ONLY
Annex 1: Other Initiatives related to SE4ALL
No
Project Name
Period
Related to SE
Objective
Implemented
by
Activities
Universal
Access
Pipeline projects
1
Third National
Communication
20132016
2
Green Technology
Application for the
development of the
Low Carbon Cities
(GTALCC)
20142019
3
4
5
GHG Bi-Annual
Update Reporting
(BUR)
Solar Thermal for
Industrial and Heating
application



Develop GHG Inventory
Formulate mitigation measures
UNDP and
Recommend adaptation actions
NRE
Build capacities of public and private sectors

(industries, residential and commercial
developers)
 Promote widespread use of EE and RE principles
in the cities
UNDP, GEF  Build capacities of town/city planners in adopting
and MEGTW
green technologies to mitigate GHG (technical,
financing and awareness)
 Develop guidelines and standards
20132015
UNDP and
NRE
20152018
UNIDO and
MIGHT
Low Emission Capacity 2013Building Project (LECB) 2015
UNDP and
NRE
Updates of GHG Inventory

Promote the Use of solar thermal for industrial
use
 Develop standard and guidelines
 Build stakeholder’s capacities in understanding
solar thermal technology
Build national capacity in the development of Low
Emission Development Strategies (LEDS), Nationally
Appropriate Mitigation Actions (NAMA) and
Measurements, Reporting and Verification (MRV)
38
EE
No
Project Name
Period
Related to SE
Objective
Implemented
by
Activities
Universal
Access
On-going Projects
Reducing Emission
2011from Deforestation
2013
6
and Land Degradation
plus (REDD+)
2011Economics of Climate 2013
7
Change Study
8
9
10
11
12
Roadmap on
2012Reduction of 40%
2013
Carbon Intensity in
Malaysia
Development of
2012
National Carbon
Disclosure Programme
(NCDP) Framework
Study
2010
Building Sector Energy
–
Efficiency Project
2015
(BSEEP)
UNDP and
NRE
UNDP and
EPU
NRE and
UNITEN
UNDP and
NRE

Develop necessary costing for CC mitigation and
adaptation measures
Harmonize necessary modelling tools for policy

makers
Finalize and streamline national mitigation actions in
relation to PM’s pledge in Copenhagen of 40% carbon
intensity reduction


UNDP, GEF
and PWD



2012 - UNIDO, GEF
Industrial Energy
2017 and SMIDEC
Efficiency for
Manufacturing Sector
(IEEMS)
Green Township (and 2010
Low Carbon Cities
–
Framework (LCCF)) 2015
Formulating REDD+ National Strategies
Increase readiness phase for Malaysia
MEGTW





Formulate necessary framework for voluntary
emission reduction programme in Malaysia
Invite private sectors to support national CC
initiatives
Focus on EE for new and existing buildings
Develop rating tools and standards
Build capacity of public and private developers
on building EE design
Promote the use of ISO50000 Energy
Management System
Build capacity of SME in managing energy usage
Develop guidelines and standards for industrial
equipment
Develop voluntary guidelines for cities in
reducing GHG emission
Focus on passive and active measures including
EE
39
No
Project Name
Period
Related to SE
Objective
Implemented
by
Activities
Universal
Access
13
Green Building Index Since
(GBI)
2007
14
Green PASS for
buildings
15
Low Carbon Society
(LCS)
green initiatives such as 3R and composting
Professionals Certification of buildings and township according to
(led by PAM) industry-certified GBI rating tools
CIDB and JKR Certification framework of Malaysia’s buildings and
township according to UNEP’s Carbon Common Metric

JICA, EPU,
UTM and

Iskandar
Development

Region
Completed Projects (from year 2000 onwards)
Malaysian Industrial 2000 - UNDP, GEF
Energy Efficiency
2007 and MEGTW
Improvement project
(MIEEIP)
16
Develop pilot research projects on low carbon
society for Iskandar region
Utilize scenario planning and modelling
approach to low carbon cities
Build capacity of policy makers in prioritizing EE
and RE measures




17
Biomass power
2003generation and co2008
generation for utilizing
waste from Palm Oil
Mills (BIOGEN)
UNDP, GEF
and MEGTW



Build capacities of public and private sectors
(industrial sectors) in understanding EE
Develop necessary policies and rating tools on
EE
Demonstrate the techno-economic benefits of
EE in the industrial sector
Create awareness on the use of efficient
energy in the industrial sectors
Demonstrate the feasibility of utilizing
biomass and biogas from Palm oil Mills for
energy generation
Formulate necessary policies of gridconnected energy generation
Create awareness on the use of biomass and
biogas in the palm oil industry
EE
40
No
Project Name
Period
Related to SE
Objective
Implemented
by
Activities
Universal
Access
Building Integrated
Photovoltaic project
(BIPV)
20052011
UNDP, GEF 
and MEGTW

18


19
20
DANIDA Energy
2003Efficiency / Demand- 2006
Side Management
Programme
DANIDA,
Energy
Commission
DANIDA programme
on development of
Solid Waste
Management
framework in
Malaysia
DANIDA,
MHLG





Develop framework on the use of gridconnected solar PV for power generation
Initiate the regulatoty framework for the
establishment of the Feed-in-Tariff mechanism
for RE
Create sustainable financing for RE generation
Encourage FDI for solar manufacturing plants in
Malaysia
Develop framework on EE and demand-side
management for industrial products and building
sectors
Build capacity of public office in formulating and
regulating necessary policies on EE
Develop framework and policies on solid waste
management (SWM) in Malaysia
Build capacity of public office and private
sectors in dealing with SWM issues
Communicate with state actors on managing
domestic waste
EE
41