MALAYSIA Rapid Assessment and Gap Analysis For Sustainable Energy for All (SE4ALL) Initiative A Report by the UN Country Team Malaysia Prepared and Edited by: Azman Zainal Abidin (Technical Advisor), Prof Dr. Ir. KS Kannan (UNIDO) and Asfaazam Kasbani (UNDP) Under the guidance of: Economic Planning Unit (EPU) and Ministry of Energy, Green Technology and Water (MEGTW), Malaysia September 2012 Disclaimer: The findings, interpretation, and conclusions expressed in this report are entirely those of the authors and should not be attributed in any manner to the United Nations Malaysia Country Team, UNDP, UNIDO and to its affiliated organizations or to the countries they represent including its agencies. The authors use information publicly sourced as advised and without prejudice. 1 Sustainable Energy for All (SE4ALL) Brief UN Secretary-General Ban Ki-moon is leading a global initiative on Sustainable Energy for All to mobilize action from all sectors of society: business, governments, investors, community groups and academia. The United Nations is the ideal institution to convene this broad swath of actors and forge common cause in support of three interlinked objectives: 1. Ensure Universal Assess to modern energy services 2. Double the global rate of improvement in energy efficiency (EE) 3. Double the share of renewable energy (RE) in the global energy mix These objectives are complementary. Progress in achieving one can help with progress toward the others. All are to be achieved by 2030, and all are necessary to achieve sustainable energy for all. The Secretary-General’s initiative contributes to the International Year of Sustainable Energy for All in 2012, as declared by the UN General Assembly, by providing a focus for action by all stakeholders. OBJECTIVE The purpose of this Rapid Assessment and Gap Analysis is to provide: A quick brief look of the energy situation in the country (Section 1) within the context of its economic and social development and poverty eradication A good review of where the country is in terms of the three SE4ALL goals (Section 2), and A good estimate of the main challenges and opportunities vis-à-vis the three goals of SE4ALL where the major investments, policies and enabling environments will be required (Section 3) A sound basis and background for an Action Plan that may follow as part of the SE4ALL activities in the country 2 Abbreviations AAIBE Akaun Amanah Industri Bekalan Elektrik (AAIBE) CEB Central Electricity Board DDC District Development and Review Committee DID Department of Irrigation and Drainage EC Energy Commission (English for ST) EE Energy Efficiency EIB Energy Information Bureau EPP Entry Point Projects EPU Economic Planning Unit FiT Feed-in-Tariff GDP Gross Domestic Product GTP Government Transformation Programme ICU Implementation Coordination Unit IPP Independent Power Producer ktoe Kilo tones of oil equivalent MDG Millennium Development Goals MDTCA Ministry of Domestic Trade and Consumer Affairs MEGTW Ministry of Energy, Green Technology and Water MESITA Malaysian Electricity Supply Industries Trust Account (English for AAIBE) MGTC Malaysia Green Technology Corporation MHLG Ministry of Housing and Local Government MITI Ministry of International Trade and Industry MOA Ministry of Agriculture MOE Ministry of Education MOH Ministry of Health MOSTI Ministry of Science, Technology and Innovation MP Malaysia Plan MRRD Ministry of Rural and Regional Development NDC National Development Council 3 NDPC National Development Planning Council NEB National Energy Balance PEMANDU Performance Management and Delivery Unit PLI Poverty Line Income PTM Pusat Tenaga Malaysia (Malaysia Energy Center) RBI Rural Basic Infrastructure RE Renewable Energy REPPA Renewable Energy Power Purchase Agreement REP-PoR Regional Energy Programme for Poverty Reduction SDC State Development Committee SEDA Sustainable Energy Development Authority SEPU State Economic Planning Unit SESB Sabah Electricity Sdn. Bhd. SESCO Sarawak Electricity Company SHS Solar Home System SME Small and Medium Industries SREP Small Renewable Energy Projects ST Suruhanjaya Tenaga (Energy Commission) TNB Tenaga Nasional Berhad UNCT United Nations Country Team Malaysia UNDP United Nations Development Programme UNIDO United Nations Industrial Development Organization 4 Table of Contents ABBREVIATIONS ....................................................................................................................... 3 EXECUTIVE SUMMARY ............................................................................................................. 6 SECTION I: INTRODUCTION ..................................................................................................... 8 1.1 COUNTRY OVERVIEW ..........................................................................................................8 Basic socio-economic data for Malaysia .................................................................................. 8 1.2 ENERGY SITUATION.............................................................................................................9 1.2.1 Energy Supply (energy mix, export/import, electricity sector) .......................................... 9 1.2.2 Net Imports and Exports by Fuels Type .........................................................................11 1.2.3 Energy demand .............................................................................................................12 1.2.4 Energy and Economic Development ..............................................................................13 1.2.5 Energy Strategy and Relevant Targets...........................................................................14 SECTION 2: CURRENT SITUATION WITH REGARDS TO SE4ALL GOALS ............................15 2.1 ENERGY ACCESS vis-à-vis GOAL OF SE4ALL ...................................................................15 2.1.1 Overview and assessment .............................................................................................15 2.1.2 Modern energy for thermal applications (cooking, heating).............................................15 2.1.3 Access to electricity: ......................................................................................................17 2.2 ENERGY EFFICIENCY vis-à-vis GOAL OF SE4ALL ............................................................21 2.2.1 Overview and Assessment.............................................................................................21 2.2.2 Energy intensity of national economy: ............................................................................22 2.3 RENEWABLE ENERGY vis-à-vis GOAL OF SE4ALL ...........................................................24 2.3.1 Overview and Assessment.............................................................................................24 2.3.2 On-grid and off-grid renewable energy ...........................................................................25 2.4 SE4All GOALS .....................................................................................................................26 2.4.1 Energy Access ...............................................................................................................26 2.4.2 Energy Efficiency ...........................................................................................................26 2.4.3 Renewable Energy.........................................................................................................26 SECTION 3: CHALLENGES AND OPPORTUNITIES FOR ACHIEVING SE4ALL GOALS .........27 3.1 INSTITUTIONAL AND POLICY FRAMEWORK ....................................................................27 3.1.1 Energy and development ...............................................................................................27 3.1.2 Thermal energy for households......................................................................................28 3.1.3 Power sector ..................................................................................................................29 3.1.4 Modern energy for productive sectors ............................................................................29 3.1.5 National monitoring framework for SE4ALL ....................................................................29 3.2 PROGRAMS.........................................................................................................................30 3.2.1 Thermal energy..............................................................................................................30 3.2.2 Power sector ..................................................................................................................30 3.2.3 Energy efficiency programs ............................................................................................30 3.2.4 Modern energy for productive use ..................................................................................31 3.3 FINANCING ..........................................................................................................................31 3.4 PRIVATE INVESTMENT AND ENABLING BUSINESS ENVIRONMENT .............................33 3.4.1 Thermal energy for households......................................................................................33 3.4.2 Power sector ..................................................................................................................33 3.4.3 Modern energy for productive sectors ............................................................................34 3.5 GAPS AND BARRIERS ........................................................................................................35 REFERENCES...........................................................................................................................37 ANNEX 1: OTHER INITIATIVES RELATED TO SE4ALL............................................................38 5 EXECUTIVE SUMMARY This report is prepared as part of the United Nations Country Team’s effort to support Malaysia in embarking into SE4ALL initiatives. The Rapid Assessment and Gap Analysis report will map out current status of SE4LL which will include sections on Current Situation and Challenges. Malaysia has been successful in achieving the overall progress of the SE4ALL objectives. Strong and sustained economic growth has contributed to success in meeting basic energy needs, including rural electrification and domestic energy for cooking. While there are other factors that contributed to the national poverty alleviation, rural electrification programme comes closest in linking the energy-poverty nexus. A study concluded that in general, as electrification progresses, poverty tends to decrease. Starting as a security programme for lighting villages during the emergency (prior to independence 1957), rural electrification has graduated into an important component of rural development for uplifting the welfare of the rural population. The programme has the potential to bring about economic empowerment of the poor via employment and involvement in agriculture, rural industries, SMEs and energy-based entrepreneurships and also improving education and health. However, there still remaining pocket of electrified households which will be connected by end of 2015. At date, rural electrification has successfully penetrated 99% of the country, 100% in Peninsular, 85% in Sabah and 90% in Sarawak. Further expansion of the rural electrification will have to focus in Sabah and Sarawak. The lesser penetration rates in Sabah and Sarawak are mainly due to physical and geographical constraints which entail heavy investments and also the relatively small electricity market due to the sparsely populated rural areas. The establishment of MESITA in 1997 has successfully catalyzed the rural electrification. Managed by MEGTW, it is an innovative trust fund where all the major IPPs in the Peninsular Malaysia and Sabah contribute about 1% of their annual pre-tax profit for rural electrification (including promotional activities), RE/EE projects and training. It is noted that by the year 2002, a total of USD 100 million has been disbursed and has successfully benefited more than 250,000 households. Starting in 2010, PEMANDU with MRRD, has started the Government Transformation Programme Rural Basic Infrastructure initiative (RBI) which as date, has benefitted more than 50,000 households under the rural electrification programme. On domestic energy, use of clean energy such as LPG, kerosene (for cooking and heating) is widely available and sold in the groceries and fuel stations. th Energy efficiency has been in national policy, albeit broadly, since the 7 Malaysia Plan. The energy objective of providing efficient utilization of energy serves as the guiding principle of energy efficiency programme in building, industrial and commercial sectors. The Efficient Management Of Electrical Energy Regulations 2008, under “Electricity Supply Act 1990” require premises which consume more than 3,000,000kWh over a period of 6 months, to submit status reports to the Energy Commission, Malaysia including the establishment of an energy management system. The government is currently exploring the possibility of establishing a revised National EE Master Plan including an Act to spearhead EE further. Under the Economic Transformation Programme, PEMANDU together with MEGTW, has launched the SAVE programme as part of a nation-wide market transformation exercise towards the use of energy efficient appliance. The government has started its long journey on the subsidy rationalization programme which eventually will lead to market-based energy pricing in Malaysia. The passing of the RE Act and the establishment of Sustainable Energy Development Authority (SEDA) has strongly supported Government’s RE agenda. Feed-in-Tariff is currently seen as the most feasible way to promote the use of RE sources in the national generation mix. SEDA’s role is to administer and manage the implementation of the feed-in tariff (FiT) mechanism where the resources focused as now are biomass, biogas, mini-hydropower and solar energy. The response has been encouraging where almost all quotas for solar until 2014 has fully taken up. According to the planned, Malaysia expects to connect 985MW (5.5%) of RE generation capacity by 2015. Institutional set-up for SE4ALL has been matured and it would be natural for central agency like EPU to continue providing direction support on the progress of the targets. MRRD shall be the lead agency for the 6 Universal Access while MEGTW shall be the focal point for EE and RE initiatives. MGTW, the ministry responsible in the development of energy planning and implementation, acts as the guardian for MESITA funds where it works hand-in-hand with MRRD and TNB to continue rural electrification programme by various means. MRRD is responsible for planning and implementation of rural infrastructures development policies, including rural electrification. TNB, as the main utility company is responsible for generation, transmission and distribution of electricity in Peninsular Malaysia. SESCO and SESB are responsible for the same in Sarawak and Sabah respectively. In conclusion, Malaysia will face no major challenges implementing the three SE4ALL goals if it continues on its chosen path. In terms of energy access, 99.4% of the country is already electrified and the remote areas shall soon be connected with the implementation of programs that achieved 310% more electricity connections in 2010-2012 than during the previous period. Regarding EE, the government has launched many projects that will allow Malaysia th to achieve the SE4ALL goal by 2015. Lastly, the 10 Malaysian Plan aims to increase fivefold the share of renewable energy sources in the energy mix (to 5.5%) by 2015. Through these efforts to promote a greener, more efficient and more connected country, Malaysia is to achieve high-income status by 2020. Malaysia has achieved or is on track to attaining the Millennium development goals (MDGs) at aggregate level by 2015. The primary energy source for Malaysia comes from natural gas at 43.3% followed by crude oil at 35.5%. Malaysia is a significant net exporter of natural gas, primarily in the form of liquefied natural gas (LNG). The National Energy policy of 1979 focuses on three different objectives to deal with the energy situation in Malaysia and it encompasses the supply, utilization and environmental issues surrounding energy. 7 SECTION I: INTRODUCTION 1.1 COUNTRY OVERVIEW Basic socio-economic data for Malaysia Population: GDP/capita: Key economic sectors: Poverty rate (current and trend): Main sources of income: FDI: Demographic situation: a 28.6 million a b USD 6,637 (USD 15,588.66 PPP ) Industry, Transport, Oil and Gas, Agriculture, Banking and finance. c from 3.8% (2009) to 2.0% Exports of oil and gas, manufacturing (electrical and electronics), palm oil and rubber d US$ 7 billion 72.2% urban/27.8% rural, urbanization ranging from 35% to 90% (WB, 2010) Sources: a: EPU MIEF2011, b: World Bank, c: EPU 10MP, d: UNCTAD Report2011 Malaysia is on track to achieving a developed country status by 2020. Malaysia is projected to be able to attain the Millennium development goals (MDGs) at aggregate level by 2015. The MDGs consist of 8 different goals and they are to: eradicate extreme poverty and hunger; achieve universal primary education; promote gender equality and empower women; reduce child mortality; improve maternal health; combat HIV/AIDS, malaria and other diseases; Ensure environmental sustainability; and develop a global partnership for development. Furthermore efforts have been carried out to raise the living standards of low-income households through greater interagency coordination and improvements in application processes. Malaysia has experienced three decades of impressive economic and social progress, enabling it to provide for the health and education of its people, to eradicate poverty in large measure, to build excellent infrastructure and to become a major global exporter. The changing global landscape, financial and economic pressures, free movements of human capital, environmental issues and profits affecting Malaysia’s progress towards Vision 2020. Towards this end, both the New Economic Model and the Tenth Malaysia Plan, which emphasize inclusive growth, aspire to provide equal opportunities to all Malaysians. Apart from eradicating poverty, priority will be on increasing the coverage of basic infrastructure such as roads, electricity (universal assess) and water supplies, and communication networks. Health-care access, coverage and quality will continue to be improved. In meeting its voluntary commitment of reducing greenhouse gases and to ensure the sustainability of the environment (including conservation and sustainable use of natural resources), emphasis will be placed on using renewable energy and on increasing energy efficiency through new guidelines, standards, laws and incentives, which in directly support the SE4ALL objectives. 8 1.2 ENERGY SITUATION 1.2.1 Energy Supply (energy mix, export/import, electricity sector) Primary Energy Sources ktoe Hydropower Coal and Coke Crude Oil Natural Gas* Petroleum Products & Others Source: NEB 2009 The primary energy source for Malaysia comes from natural gas at 41% followed by crude oil at 40.1% (2009). Its total primary energy supply registered at 74,582 ktoe, a decline of 1.2 percent compared to 72,384 ktoe during the previous year. The decrease was led by lower primary production of natural gas and crude oil in 2009. This was anticipated also by decreasing imports of total energy due to unattractive energy demand during the period. Malaysia has one of the most extensive natural gas pipeline networks in Asia, owing to the multi-phased peninsular Gas Utilization (PGU) project that was completed in 1998. Natural gas in Malaysia is mainly utilized for electricity generation through natural gas fired power plants, petrochemical and large industrial uses, and motor vehicles. Upstream industries The country’s crude oil and condensate reserves amounted to 5.517 billion barrels in 2009. The average production of domestic crude oil and condensate increased from 681,000 barrels per day (bpd) in 2000 to 658,800 bpd in 2009. Based on this production level, which is in line with the National Depletion Policy, the reserves are projected to last for 15 years (ADB). Nearly all of Malaysia's oil comes from offshore fields. The continental shelf is divided into 3 producing basins: the Malay basin offshore peninsular Malaysia in the west and the Sarawak and Sabah basins in the east. Most of the country’s oil reserves are located in the Malay basin and tend to be of high quality. Malaysia’s benchmark crude oil, Tapis Blend, is of the light and sweet variety with an API gravity of 44° and sulfur content of 0.08 percent by weight. More than half of total Malaysian oil production currently comes from the Tapis field in the offshore Malay basin. Malaysian oil production has been gradually decreasing since reaching a peak of 862,000 bbl/d in 2004 due to its maturing reservoirs. Malaysia consumes the majority of its oil production and domestic consumption has been rising as production has been falling. The government is focused on opening up new investment opportunities by enhancing output from existing fields and developing new fields in deep water areas offshore Sarawak and Sabah. 9 Gross natural gas production however has been rising steadily, reaching 2.7 Tcf in 2010, while domestic natural gas consumption has also increased steadily, reaching 1.1 Tcf in 2010, 42 percent of production. Downstream Industries Malaysia had about 538,580 barrels per calendar day (b/cd) of refining capacity at seven facilities as of January 2011. PETRONAS went into refining and distribution in 1983 where it initiated the construction of refineries at Malacca and at Kerteh in order to reduce its dependence on Royal Dutch/Shell's two refineries at Port Dickson and Esso's refinery in Sarawak. Malaysia invested heavily in refining activities during the last two decades and is now able to meet most of its demand for petroleum products domestically, after relying on the refining industry in Singapore for many years. Petronas operates three refineries (259,000 b/cd total capacity), while Shell operates two (170,000 b/cd total capacity), ExxonMobil operates one (86,000 b/cd), and Kemanan Bitumen Co. operates another (23,750 b/cd). Kemanan Bitumen refinery largely produces bitumen from heavy crudes. The Sabah Oil and Gas Terminal, under construction in Kimanis, Sabah, is expected to be completed by the end of 2013. It will receive crude from offshore fields, process and distribute the products via a planned 310-mile pipeline linking Sabah with Bintulu, Sarawak. The terminal will have a processing capacity of 300,000 bbl/d of crude and condensate. By 1990, 252 service stations carried the PETRONAS brand, all but twenty (20) on a franchise basis, and another fifty (50) were planned. Some were set up on grounds of social benefit rather than of strict commercial calculation. Electricity sector Biomass 2% Diesel 5% Others 0% Hydro 8% Oil 1% Hydro 5% Coal 40% Oil Diesel 1% 1% Other 2% Coal 28% Gas 56% Gas 52% Installed Capacity (2010) Biomass 1% Others 0% Generation Mix (2010) Source: NEB 2009 As of 2010, installed capacity amounted to 27,179 MW while the generation mix stands at 125,045 GWj where maximum demand was at 15,072 MW. The Malaysian electricity sector has evolved tremendously for the past 60 years. The national utility (Tenaga National Berhad) is currently involved in the generation, transmission and distribution of electricity business. In Peninsular Malaysia, the Company is a major contributor to the total industry capacity through six thermal stations and three major hydroelectric schemes. It also manages and operates the National Grid which links TNB power stations and IPPs to the distribution network in the peninsula. The grid is connected to Thailand’s transmission system in the north and Singapore’s transmission system in the south. In East Malaysia, TNB, through 80%-owned subsidiary Sabah Electricity Sdn. Bhd. (SESB), manages the Sabah Grid and aims to provide electricity to 95% of the state’s population by year 2013. TNB’s distribution network is managed through a comprehensive distribution system, customer service centres and call management centres. Over the years, TNB has diversified from its core business into the manufacture of transformers, high voltage switchgears and cables; the provision of professional consultancy services; and architectural, civil, electrical engineering works and services, repair and maintenance. In 2005, TNB embarked on a 20-Year Strategic Plan which entails greater focus on green initiatives such as the development of renewable sources of fuel, and more effective demand side management via energy efficiency. These efforts complement the Government’s 10 carbon reduction agenda while also creating a foundation for sustainable energy for the future. Set up as the Central Electricity Board of the Federation of Malaya in 1949, TNB has powered national development efforts for more than 60 years by providing reliable and efficient electricity services. 1.2.2 Net Imports and Exports by Fuels Type 10,000 9,000 25,000 8,000 7,000 20,000 6,000 5,000 15,000 4,000 3,000 10,000 2,000 5,000 1,000 0 Coal & Coke 0 Crude Oil Petroleum Natural Products Gas LNG Energy Imports in ktoe (2009) Pet. Products Coal & Coke Energy Exports in ktoe (2009) Source: NEB 2009 Coal remains the highest imported fuel mainly for coal-fired power plants. The Liquefied Natural Gas (LNG) and the crude oil are the largest exported. The majority of Malaysia’s oil exports go to markets in Japan, Thailand, South Korea and Singapore. The LNG and natural gas products are mostly exported to Japan, South Korea, and Taiwan. Malaysia is a significant net exporter of natural gas, primarily in the form of liquefied natural gas (LNG). It was recorded in 2005 that Malaysia exported just over 1 Tcf (trillion cubic feet) of LNG, mostly to Japan, South Korea, and Taiwan. In 2010, Malaysia exported 234,000 bbl/d of crude oil, down slightly from the 236,000 bbl/d exported in 2009. This was about 35 percent of Malaysia’s crude oil production. The Tapis blend is Malaysia’s major exported crude oil because its high quality and low sulfur content commands premium prices. In 2010, Malaysia imported 205,000 bbl/d of lower-cost crude oil for processing at its oil refineries. The production and export of Liquefied Natural Gas (LNG), however, has increased from 23,606 ktoe in 2009 from 22,277 ktoe in 2008 level. Malaysia was the third largest exporter of LNG in the world after Qatar and Indonesia in 2010, exporting over 1 Tcf of LNG, which accounted for 10 percent of total world LNG exports. Japan, South Korea, Taiwan, and China have supply contracts with Malaysia, and are the largest purchasers. LNG is primarily transported by Malaysia International Shipping Corporation (MISC), which owns and operates 27 LNG tankers, the single largest LNG tanker fleet in the world by volume of LNG carried. MISC is 62-percent owned by Petronas. The Bintulu LNG complex on Sarawak is the main hub for Malaysia's natural gas industry. Petronas owns majority interests in Bintulu's three LNG processing plants, which are supplied by offshore natural gas fields. The Bintulu facility is the largest LNG complex in the world, with 8 production trains and a total liquefaction capacity of 1.7 Tcf per year following the debottlenecking completed at end2010, which raised overall capacity by 0.6 Tcf per year. Japanese financing has been critical to the development of Malaysia's LNG facilities. Also in Bintulu is Shell’s gas to liquids (GTL) project which has a production capacity of 14,700 bbl/d. Construction began on Petronas’ Sabah Oil and Gas Terminal (SOGT) in Kimanis, Sabah in 2011 and is expected to be completed by the end of 2013. It will have a handling capacity of 1.3 Bcf/d of natural gas per day from the Gumusat-Kakap, Malikai, and Knabalu offshore fields. It will upply gas for domestic use in Sabah, largely for a new electric power plant slated for completion in 2014. A reported 11 500,000 cubic feet per day will be piped to the Bintulu complex to be exported as LNG. The Sabah-Sarawak Gas Pipeline project is part of this development. 1.2.3 Energy demand Final Energy Demand in ktoe (1999 vs 2009) Source: NEB 2009 Energy demands in the transport sector have been increasing swiftly in Malaysia due to improvements in transportation. The rapid industrialization of the country in recent years has led to high economic growth, which in turn has led to population growth and an accelerated ownership of motorized vehicles. The total number of vehicles in the country have increased from about 5 million in 1991 to 19 million in 2009, thereby registering an average annual growth rate of about 8% during this period. The growth in the number of vehicles in the country has been faster than the growth in population. Based on the National Energy Balance, Industrial sector is the main user of electricity in Malaysia with its share of 44.9 percent from total consumption in 2009. The electricity consumption from the industrial sector increased by 0.9 percent to register at 3,719 ktoe (43,220 GWh) compared to the previous year. The consumption of electricity in the commercial sector also increased to reach 2,743 ktoe (31,857 GWh), boosted by tourism activities following the expansion of new routes by airlines and various tourism promotional activities organised during the year. The electricity consumption in the residential sector recorded an increase of 7.4 percent to register at 1,792 ktoe (20,822 GWh). The electricity consumption from the rail transport sector, however, decreased from 15 ktoe (173 GWh) in 2008 to 12 ktoe (163 GWh) in 2009. 12 1.2.4 Energy and Economic Development Share of energy sector in GDP Source: ETP 2011 In 2009, the combined oil, gas and energy sectors represented 19 % of GDP equivalent to RM127 billion (USD 41 billion) while in 2015, it is expected that 11.1% of GDP equivalent to RM81.9 billion (USD 26.42 billion). In total, the national oil company, Petronas, provides about 40% of the revenue for federal budget in taxes, dividends and royalties. Electricity and Economic Growth 120,000 600,000 100,000 500,000 80,000 400,000 60,000 300,000 40,000 200,000 20,000 100,000 Electricity Consumption (GWh) GDP (RM mil) 0 0 Source: NEB 2009 The last 20 years have seen the growth of electricity in tandem with the growth of country’s GDP. Industrial, commercial and residential sectors are the main users of electricity use and will continue to be the critical sectors based on the current trend of increasing middle-income families as well the opening up of new townships and construction of new commercial and residential buildings. The total electricity consumption recorded a growth of 3.8% compared to the previous year to register at 8,286 ktoe (96,307 GWh). It is clear that the demand for electricity has seen a large increase the past 20 years or so. With Malaysia’s urban population to reach 78% in 2030 from 63 % 2002, combined with high per capita GDP growth of 3.4% per annum over the outlook period, it will lead to a change in lifestyle, where energy consumption will be based mostly on commercial energy sources in the form of electricity (EPU 10MP). 13 1.2.5 Energy Strategy and Relevant Targets Since independence in 1957, Malaysia has always strive in ensuring universal access to basic infrastructure (roads, electricity, treated water and basic sanitation). During the 10 Malaysia plan period, electricity supply coverage will be expanded through the grid extension and alternative systems such as mini hydro and solar hybrid. Coverage of electricity supply is expected to reach almost 100% in Peninsular Malaysia and 99% in Sabah and Sarawak by 2015. Malaysia’s concerns on energy security for economic development started during the 1970s oil crisis. The National Energy policy of 1979 was prepared and focuses on three different objectives: the supply, utilization and environmental issues surrounding energy. The supply objective aims to ensure adequate, secure and cost-effective supply of energy; the utilization objective aims to promote efficient utilisation of this energy and discourage wasteful and non-productive patterns of energy consumption; and finally the environmental objective aims to ensure factors pertaining to environmental protection are not neglected in production and utilization of energy. In 1981, the Four-Fuel diversification policy was introduced, which strives to reduce the over-dependence on a single fuel source; and to focus on four main sources of fuel, i.e. oil, hydropower, natural gas and coal. To strengthen further, the Fifth-fuel policy was introduced in 2000 which focuses on incorporating renewable energy as next available fuel for power generation; and expanding fuel sources to comprise, hydropower, natural gas, coal and renewable energy. Other related policies includes 1974 Petroleum Development Act (establishment of Petronas), 1975 National Petroleum Policy, 1980 National Depletion Policy, 1990 Electricity Supply Act, 1993 Gas Supply Acts, 1994 Electricity Regulations, 1997 Gas Supply Regulation and the 2001 Energy Commission Act. In 2010, the Renewable Energy Action plan was formulated to intensify the development of gridconnected renewable energy, particularly biomass, as the 'fifth fuel' resource under the country’s Fuel Diversification and Fifth-fuel Policies. REAP provides potential targets for RE in Malaysia where more than 6,500 MW can potentially be generated from solar PV: 1,340 MW by 2030 from biomass; 410 MW by 2028 from biogas; 490 MW from mini-hydro by 2020 and about 360 MW by 2022 from Solid waste. Arising from the needs of a dedicated regulation on RE, the RE Act and the Sustainable Energy Development Authority (SEDA) Act were successfully gazetted in 2010 which leads to the official starting of the Feed-in-Tariff mechanism for RE projects in December 2011. It is expected that that renewable energy to reach 985 MW (5.5%) by 2015 and 2,080 MW by 2020. The New Energy Policy (2011-2015) emphasizes energy security and economic efficiency as well as environmental and social considerations. The Policy will focus on five strategic pillars: initiatives to secure and manage reliable energy supply; measures to encourage energy efficiency (EE); adoption of market-based energy pricing; stronger governance and managing change. EE initiatives will gain momentum with the finalization of the National Energy Efficiency Master Plan expected to be in 2012, setting of minimum energy performance standards for appliances and development of green technologies. These measures will encourage industries and consumers to use energy productively and minimize waste to be more competitive in the global market. 14 SECTION 2: CURRENT SITUATION WITH REGARDS TO SE4ALL GOALS 2.1 ENERGY ACCESS vis-à-vis GOAL OF SE4ALL 2.1.1 Overview and assessment Rural electrification rate and availability of clean domestic energy (for cooking mainly) will be used in the context of preparing this Rapid report. As at date, rural electrification has successfully penetrated 99% of the country, 99.5% in Peninsular Malaysia, 77% in Sabah and 76% in Sarawak. Fossil fuel such as LPG and kerosene for cooking is available in the market and widely sold in the groceries, supermarkets and selected gasoline stations. Nevertheless, fuel wood is still being used in some area especially in remote Peninsular and in highlands of Sabah and Sarawak, where it can be found easily and without cost. Malaysia has still a large number of small villages and islands, mainly in Sabah and Sarawak that lack 24-hour electricity, and the probability of connecting them to high voltage gridlines in the near future is poor due to geographical issues and many other logistical constraints. No exact record on the remaining gaps to cover but it is estimated nearly 300,000 households are still without 24-hour electricity as per DOS statistic in 2005, mainly in Sabah and Sarawak. Nevertheless, the government has embarked on several initiatives to find sustainable ways to cater for the electricity demands of these poor rural villages. Solar home system (SHS) (of 150W less) has been installed in various remote locations since 1990 where a total installed capacity as date is nearly 2MW in capacity. Solar diesel PV hybrids have been initiated by TNB-Energy Services since the year 2001 in Pekan, Pahang including several islands in Peninsular Malaysia. Approach to providing 24-hour electricity supply is similar to providing clean and treated water, the process of adding new power connections across Malaysia involves connecting to grid-based electricity or implementing solar hybrid systems. The type of new connection hinges upon population density and the remoteness of a location. The preferred mode of supplying electricity would be to connect to the electricity grid. However, in rural areas which are very far from any transmission infrastructure, or in instances where connections to the main grid are very expensive, technologies such as solar hybrid power generation or micro hydro-electricity are introduced. In the year under review, these alternative approaches helped ensure the provision of electricity to more villages in rural areas. Malaysia has matured institutional set-up in the energy industries, covering the oil and gas sector to the electricity segment. The Economic Planning Unit (EPU) has the overarching responsibility towards energy policy and planning, both for conventional and non-conventional sources of energy, and poverty reduction in Malaysia. The Ministry of Rural and Regional Development (MRRD) and the Ministry of Energy, Green Technology and Water (MEGTW), work in close coordination for the rural electrification programme. In addition the MEGTW works in tandem with the Energy Commission (EC) and the Sustainable Energy Development Authority (SEDA) to coordinate national programmes in energy efficiency and renewable energy. 2.1.2 Modern energy for thermal applications (cooking, heating) Availability/quality of supply including status of domestic supply chain: Domestic energy for cooking comes in the form of Liquefied Petroleum Gas (LPG) is sold openly and is available in many shops in the rural area. Fossil fuel such as gasoline (for transportation) and kerosene (use for cooking and lighting) is widely sold and can be bought easily even in the un/semi-electrified places (such as in deep rural in the state of Sabah and Sarawak). On the other hand, traditional fuels (especially wood) are also popular and still being used considering its abundance in the area. 15 LPG in Malaysia is widely used in households for heating appliances such as ovens and stoves It is also used in industries such as iron and steel industry, aerosol propellant industry, glass and ceramic manufacture, copper tubing and cable manufacture. For cooking, it comes in three cylinder sizes which are the 12, 14 and 50 kg cylinders. The 12, 14 and 50 kg cylinders are painted according to the manufacturers’ specification (yellow for Shell, Green for Petronas and Blue for Esso). In 2009, LPG accounted for 2.9% of the total production of oil refinery, 10.4% of the total demand and 6% of the final consumption for petroleum products. Affordability Gasoline and LPG are under government’s controlled items and sold with subsidized price. In 2012, the price is as below RM 1.90 (USD 0.61)/L for RON 95; RM 2.10 (USD 0.677/L for RON 97; RM 1.80 (USD 0.58) /L for Diesel; RM 1.90 (USD 0.61) /kg for LPG Use of subsidy allows energy prices to be managed within the affordability level of the majority Malaysians. Average monthly household expenditure of, as below, shows that the cost of total energy is below 5% of the average monthly income. Average Monthly and Share of Household Expenditure for Urban and Rural, 2004/05 Expenditure group Urban Urban share of Rural share of Total (RM) Rural (RM) (RM) expenditure (%) expenditure (%) Housing, Water, 429.57 522.3 247.4 22.86 19.01 Electricity Electricity 59.33 71.38 35.62 3.12 2.74 Gas 9.27 8.84 10.13 0.39 0.78 Liquid Fuels 0.19 0.08 0.4 0.004 0.03 Other Fuels 0.44 0.15 1.01 0.01 0.08 (Source: DOS) Pattern of Household Expenditure on Fuels in 2005 Share of households without access to modern cooking/heating is estimated to be 0.5% mainly using forest products. Population without electricity is estimated to be 200,000 as of 2011. 16 Subsidies: Continuing from the above Affordability section, below is the detail subsidy structure: Fuel type RON95 Diesel LPG (for 14kg unit) Consumer price/L (RM) 1.90 1.80 26.60 Price without subsidy/L (RM) 2.93 2.66 48.02 Share of subsidy in retail price 35% 32% 45% Domestic energy has generally enjoys 30 to 40% subsidy from the government in ensuring the sold price are within the reach of the mass. These energy subsidies may be direct cash transfers to producers, consumers, or related bodies, as well as indirect support mechanisms, such as tax exemptions and rebates, price controls, trade restrictions, and limits on market access. The subsidies makes the fuel more affordable as it ensures adequate domestic supply by supporting indigenous fuel production in order to reduce import dependency, or supporting overseas activities of national energy companies. 2.1.3 Access to electricity: Physical access: Grid connection: 99.7 % of population in Malaysia Urban/rural areas: 99.5% in Peninsular Malaysia, 77% in Sabah and 76% in Sarawak in 2009 Target group: The remote areas in Peninsular Malaysia, islands and the states of Sabah and Sarawak. Generally, major populated areas are connected to efficient grid systems as below. Source: Energy Commission Rural Electrification Programme Since the 1950s, rural electrification has been promoted as part of rural development programme to bring about security and physical development to the rural areas in the then Malaya. Rural electrification of villages, implemented through the then Central Electricity Board was initially supplied using diesel generators, mainly for security reasons in the fight against communist insurgencies. Rural electrification has since been incorporated as part of rural development programme and received allocation under its Five Year Development Plans, beginning from the First Malaya Plan (1960-1965) and later in the First Malaysia Plan (1966-1970) up to the present Tenth Malaysia Plan (2010 - 2015). The rural electrification programme is aimed at providing electricity supply to homes and villages, which are beyond the operational areas of the local authorities, including the ‘orang asli’ in Peninsular and the indigenous groups of Sabah and Sarawak by means of extending the grid lines, provision of generator sets and use of alternative energy such as SHSs and solar-hybrid system. Rural electrification forms part of efforts to 17 provide social amenities to enhance the quality of life and living standards among the rural communities. Priorities for rural electrification programme will be to provided transmission lines best to 33kV lines, low voltage line to the villages and to upgrade infrastructure of 12 hours to 24 hours electricity supply. Since 1970s, rural electrification has been incorporated in the New Economic Policy (NEP) framework for eradicating poverty and increasing the quality of life in the rural areas, especially of the rural poor. Increasing use of electricity is expected to increase productivity and incomes in the agriculture, industry and commercial sectors and also affect the modernization and attitudinal change in the rural sector. Qualifying Criteria for different types of Electrification Programme Extension of Grid Lines Priority will be given to villages which have high population and available public amenities such as schools, clinics and religious centres. Average cost for the project is estimated around RM25,000 (USD 8,065) per house Generator Set SHS Solar-Hybrid system Easy assess to the site via roads or rivers Nearest grid lines are more than 10km away Will not be receiving any grid line extension in the next 5 years Average cost for the project is estimated to be around RM15,000 (USD 4,839) per house No proper road leading to the area Will not be receiving any grid line extension in the next 5 years Public amenities will be given priority No potential for mini/micro hydro system For housing unit, maximum output is 100-150W capacity Nearest 11kV overhead line is more than 10 km No plan for grid connection in the next 3 years Depending on locations where project cost is cheaper than grid extension Clustered housing units with at least 20 homes will be given priority. Maximum output shall be 50kW capacity Source: MRRD / MESITA Current Approach to Rural Electrification Programme under PEMANDU NKRA Rural Basic Initiatives : Rural development continues to be a fundamental component of the national agenda. Since Independence, the government, via the many Malaya and Malaysia Plans, as above, has rolled out development initiatives for roads, water, electricity and housing to ensure that the fruits of modernisation benefit all. In 2010, the Rural Basic Infrastructure (RBI) NKRA was conceived to accelerate these efforts by delivering unprecedented big and quick wins to rural communities. In 2011, the MRRD and the various implementing agencies were once again tasked with spearheading RBI efforts. They continued to build upon the good momentum achieved in the previous year and the rural landscape was further transformed for the better. Their efforts centred on ensuring improved accessibility via new and upgraded roads, providing a clean, constant water supply and an uninterrupted electricity supply, as well as building and refurbishing homes for rural communities. In 2010 and 2011 alone, a total of 54,222 houses have been benefitted under this programme. In 2012, it is targeted to achieve 39,442 houses with allocated budget of RM 1 billion (USD 323 million). 18 Availability and reliability of supply: Breakdown on Electricity (Gross Generation, Consumption, Installed Capacity, Peak Demand and Reserve Margin) for Malaysia Region Peninsular Malaysia Sarawak Sabah Total Electricity Gross Generation GWh % 95,120 90.0 Electricity Consumption GWh 87,950 6,068 4,518 105,706 4,539 3,818 96,307 5.7 4.3 100.0 % 91.3 Installed Capacity MW 22,173 Peak Demand MW 14,245 Reserve Margin % 55.7 4.7 4.0 100.0 1,220 984 24,377 996 719 22.5 36.9 Source: NEB 2009 Historically, though were very isolated cases, Malaysia had been impacted by several blackouts in the past. The first major blackout was in 1992 when lightning struck a transmission facility causing rolling failure in the transmission and distribution system. Another blackout occurred in 1996, which occurred due to the tripping of a transmission line near the Sultan Ismail power station in Paka, Terengganu. Another outage happened in 2003 in the southern area of peninsular Malaysia due to a power outing. Finally the latest outage was in 2005 and was due to a fault in the main cable transmission line grid near Serendah, Selangor. For the past 10 years, Malaysia’s grid supply has been good and un-interrupted and going into average interruption data, according to System Average Interruption Duration Index (SAIDI) report, Malaysia has improved quality of supply compared to the previous years where in Peninsular it has recorded 4% in Peninsular and decreased 76% in Sabah between 2009 and 2010. Malaysia generally has a stable and consistent power supply. Affordability: Tariffs (as of April 2012) Power companies Tenaga Nasional Bhd (TNB) Sabah Electricity Sdn Bhd (SESB) Syarikat SESCO Bhd (Sarawak) Tariffs (in USD/kWh) Domestic Commercial (low voltage) 6.97 (1-200 kWh) 12.57 (1-200 kWh) 5.59 (1-100 k Wh) 10.56 (1-200 kWh) Industrial (low voltage) 11.03 (1-200 kWh) 10.23 (for all kWh) 10.88 (1-100 kWh) 12.79 (1-100 kWh) 12.79 (1-100 kWh) (Source: TNB, SESB, SESCO) The charge of tariffs imposed on the domestic use is much lower to the ones imposed on the commercial or industrial scales making it affordable of the household expenditure scale. The government also continues the the Lifeline Band which is at 200kWh/month. The Lifeline Band ensures domestic consumers in the 1 to 200kWh per month band to be secluded from the recent electricity tariff increase since 1997. Around 3.3 million households will continue to enjoy the subsidised rate of 21.8 sen/kWh ( USD .07/kWh) . This number of households safely encompasses all 200,000 poor households (i.e. income less than RM750 per month). Share of utility bills in household incomes: As of 2005, the urban and rural shares of electricity expenditure were respectively of 3.12% and 2.74% of household income. Table in the 2.1.2 Affordability section shall be referred. Subsidies: A subsidy of 30 % to 40 % is given on average of kWh use. Sustainability In 2010, the Electricity Commission Report (ST) highlighted that Peninsular Malaysia could face a power shortage by 2015 if the generation capacity did not grow. This was based on a demand growth trend of between 5% and 8% every year that could result in the electricity reserve margin dropping below 20% by 2015, from the current healthy level of around 55.7%, if supply growth do not keep pace. The government is currently exploring various alternatives for new planting up. 19 Share of renewable energy sources (RES) in power mix: Share of sustainable biomass and other RES: Type of RE Biomass Solid waste Biogas Mini hydro Solar PV Others (wind) Capacity of generated energy connected to the grid (MW) 30 5.5 2 2 1 23.5 64 As for 2010, RES accounted for less than 1% of total generated electricity. 20 2.2 ENERGY EFFICIENCY vis-à-vis GOAL OF SE4ALL 2.2.1 Overview and Assessment th Energy efficiency (EE) measures (including demand side management) have been ongoing since the 7 Malaysia Plan period (1996-2000) and in 10 Malaysia Plan, it has been intensified to harness energy savings potential and reduce Malaysia’s carbon emissions and dependence on fossil fuels. Intrinsic barriers to energy efficiency that pose challenges in capturing this opportunity are being addressed. EE covers the efficiency of power generation, transmission and distribution of electricity as well as various end uses of energy such as in the industrial, commercial and residential. In other words it can be divided into supply and demand side perspectives. In the recent 10th Malaysia Plan (2011-2015), the key emphasis is on the short-term goals vested in National Green Technology Policy (2009), these include promotion of EE for power producer, establishment of EE targets and standards. The Efficient Management Of Electrical Energy Regulations which was launched in 2008, under “Electricity Supply Act 1990” require premises which consume more than 3,000,000kWh over a period of 6 months, to submit status reports to the “Energy Commission”, Malaysia including the establishment of an energy management system. The government is currently exploring the possibility of establishing a revised National EE Master Plan including an Act to spearhead EE further. PEMANDU together with MEGTW, has launched the SAVE programme as part of a nationwide market transformation exercise towards the use of energy efficient appliance. There are a number of completed and ongoing projects which will support national EE programme such as the DANIDA Capacity building in integrated resources planning at government and related agencies, DANIDA’s Center on Training on EE & RE (CETREE) Capacity building project, MEGTW Low Energy Office (LEO) at Putrajaya; TNB’s Demand Side Management, Green township, JICA’s Low Carbon Society (LCS) in Iskandar Development Region, UNDP /GEF Malaysia Industrial Energy Efficiency Improvement Project and the UNDP/GEF Building Sector Energy Efficiency Project (BSEEP). SAVE or Sustainability Achieved via Energy Efficiency, is a program spearheaded by the Ministry of Energy, Green Technology and Water to improve energy efficiency in Malaysia. It is launched in 2011 as a quick start programme to encourage residential users to change into energy efficient appliances when making new purchases. It is to create a culture of efficient energy usage among general public and business entities. This initiative targets the final end user through the retailers of electronic appliances and it is targeted to provide national savings up to 7,300 GWh of energy saved by the year 2020. It is also to accelerate the transformation of the consumer appliances market to increase the share of Energy Efficient (EE) models and to phase out inefficient models from the local market so as to reduce the price premium for EE products. 100,000 rebate vouchers for 5-Star rated refrigerators and 65,000 vouchers for 5-Star rated air conditioners have been allocated to states across Malaysia. Rebates will be awarded on a first-come, first-served basis to qualified domestic consumers who purchase 5-Star rated refrigerators, air conditioners or chillers during the rebate offer period through participating retailers. As date, over more than 4,000 retail outlets nationwide are registered with KeTTHA under the SAVE Rebate Program, with 12 different brands to choose from. The rebate program starts on July 7, 2011 and will last until all rebates are taken at the end of 2012. To date, about 12.4 per cent and 7.1 per cent of market share of five-star rated energy efficient refrigerators and air conditioners respectively have been recorded through the initiatives being implemented, with total energy saving accumulation of 66.3 GWh. Under the PEMANDU Energy, Oil and Gas cluster, EPP9, Malaysia will focus on five relevant levers to improve EE which are, 1. to lead by example on energy-efficiency practices and philosophy, 2. to stimulate sales of energy-efficient appliances, 3. the Government will work with TNB to make co-generation economically viable, 21 4. to regulate better insulated buildings and 5. to stimulate the sale of energy-efficient vehicles. In March 2011, it was announced that Faber Group Berhad will spearhead the pilot project for the Energy Performance Management System (EPMS) for government entities. Faber has commenced and completed energy audits at five hospitals in the northern states of Peninsular Malaysia. To stimulate the use of fuel efficient cars, the import duty on all hybrid cars has been exempted, bringing the cost of hybrid models such as the Toyota Prius and Honda Insight to more competitive levels. Sales of hybrid cars are expected to achieve record highs in 2011. This exemption was extended to the end of 2013 in the recent Budget 2012 announcement. The implementation of Energy Performance Contracting (EPC) in 120 top energy- using government buildings will be further explored for implementation in all government buildings and private properties. 2.2.2 Energy intensity of national economy: (Source: 2010 MDG report) 2.2.3 Industrial Energy Intensity Industrial Energy Intensity stands at 78 toe/RM million in 2009 (NEB 2009) Under the Malaysian Industrial Energy Efficiency Improvement Project (MIEEIP) from 2000-2007 which was funded by United Nations Development Program (UNDP), Global Environmental Facility (GEF), private sector and Government of Malaysia, eight industrial sectors, cement, ceramic, food, glass, iron & steel, pulp & paper, rubber and wood has been identified to have the potential to promote and improve energy efficiency. Electrical Energy- use Equipment has been produced to give a the guidelines to encourage industries to adopt energy efficiency practices and improving their energy utilization for a commonly used equipment such as fans, motors, pumps, chillers, transformers and air-compressors. A standard general energy audit guideline, the Industrial Energy Audit Guidelines shall be used as a reference material by energy consulting firms in their audit services to industries. There are 54 energy audits in the eight industrial sub sectors under MIEEIP. The project has highlighted a number of important issues and some significant lessons have been learnt. The experiences and the outcomes in the form of industry involvement and the demonstration models will provide exemplars for further steps in energy efficiency throughout Malaysia. 2.2.4 Residential Energy Consumption Residential Energy Consumption is at 3042 ktoe in 2012 (NEB 2009). EE appliances which participated in the voluntary rating programme are Refrigerators, Domestic Electric Fans, Ballast for Fluorescent Lamps, Electric Lamps, Air Conditioners (Split Unit), Televisions, High Efficiency Motors and Insulation Materials. Out of these eight appliances only four (4) appliances have participated in the voluntary ‘star labelling’ programme (as below) which are televisions, refrigerators, Domestic Electric Fans and Air Conditioners (Split Unit). 22 Sample of a Malaysian voluntary labelling programme 2.2.5 Potential cumulative energy savings by 2015 The 10 Malaysia Plan estimated that there would be a potential cumulative energy saving of 4,000 ktoe by 2015. As explained, the national energy efficiency master plan will be drawn up and measures such as phasing out incandescent light bulbs and requiring more devices to have EE labelling will be introduced. In addition, there will be a ratings system for green townships, led by Putrajaya and Cyberjaya, along with minimum energy performance standards for equipment and machinery. 23 2.3 RENEWABLE ENERGY vis-à-vis GOAL OF SE4ALL 2.3.1 Overview and Assessment Policy on renewable energy (RE) has been mainstreamed and recognised as early in the year 2000. The advent of the Fifth fuel policy has further reinforced Malaysia’s position in developing the RE industries. It was initially targeted to contribute 5% of the country’s electricity demand by year 2005 and the Small Renewable Energy Program (SREP) was launched in May 2001 under the initiative of the Special Committee on Renewable Energy (SCORE) aimed to support the government’s strategy in intensifying the development utilization of RE, where by 2005, equal to between 500 and 600 megawatt (MW) of installed capacity to be made available. The policy has been reinforced by fiscal incentives, such as investment tax allowances and accelerated capital allowance which encourages the connection of small renewable power generation plants to the national grid. The buy-back tariff started with a fixed price from RM 0.17/kWh (USD 0.055 /kWh), RM 0.19/kWh (USD 0.062 /kWh) and finally RM 0.21/kWh (USD 0.067 /kWh). However, despite the efforts, RE pricing was seen still unattractive to compete with the level playing field with the fossil-fuel tariff and a need to restructure the RE industries was needed. On 2nd April 2010, the Cabinet approved the National Renewable Energy Policy and Action Plan that would be the cornerstone for a more aggressive deployment of RE in the country. The policy and objectives of the National Renewable Energy Policy and Action Plan are to enhance the utilisation of indigenous RE resources to contribute towards national electricity supply security and sustainable socioeconomic development. Finally, in 2011, Malaysia’s Parliment gazzeted the Renewable Energy Act (RE Act) and the Sustainable Energy Development Authority (SEDA) to spearhead the RE in Malaysia. Its key role is to administer and manage the implementation of the feed-in tariff (FiT) mechanism where the resources focused as of now are biomass, biogas, mini-hydropower and solar energy. Applications for the FiT opened on 1 December 2011, with quota for solar photovoltaic cells of 150MW, biomass (including solid waste) of 240MW, biogas (including landfill) of 90MW and small hydro of 150MW offered to any interested party through an open online application system. The quota allocation for solar photovoltaic up until 2014 was almost fully applied for within 24 hours of its launch, whilst applications for quota allocation for biomass, biogas and small hydro have been similarly encouraging. Installed Capacity (MW) of Plants in Progress Biogas Small Hydro Biomass (SolidWaste ) Biomass Individual Non-individual (≤500kW) Non-individual (>500kW) HousingDeveloper 2012 2013 2014 8.36 4 0 5.38 2.8 0 9.2 28.3 42.05 8.9 0 0 33 48.5 6 6.53 2.86 0 2.37 3.28 0.79 61.02 58.5 30.53 0 0 0 134.75 148.25 79.37 Cumulative 12.36 8.18 79.55 8.9 87.5 9.39 6.45 150.05 0 362.37 Biogas ( Landfill /Sewage) Year Total Source: SEDA’s Website September 2012 Currently, electricity generation from RE sources is very costly and not competitive with large scale plants using conventional fossil fuel sources. The higher cost per unit has made investment in RE not attractive to investors and electricity utility. The objective of FiT is to spur RE growth in Malaysia. FiT will be used to subsidise the difference between the premium tariff rate and the current selling price of a unit of electricity from RE developers to TNB under the SREP programme (i.e. at a maximum price of 21 sen/kWh). 24 2.3.2 On-grid and off-grid renewable energy Category Gridconnected (MW) Off-grid (MW) Total Mini-hydro Biomass & biogas Solar PV Wind Total 23.8 32 1 - 56.8 23.8 447 479 6.1 0.2 0.2 7.1 453.3 510.1 On-grid and off-grid RE in MW, Source: Energy Commission 2010 RE Operational Capacity (source: SEDA’s website August 2012) As RE Act has recently started in December 2011, progress on RE projects with FiT is relatively new and many still in planning and commissioning stage. As date, 43.90 MW capacity has been in operation. Use of renewable energy sources (RES) for thermal applications (cooking/heating) As date, there is no official record on Malaysia’s rural using RE for cooking and heating. Use of RES for productive activities As date, there is no official record on Malaysia’s industries using RE for cooking and heating. However, there were research projects undertaken by the National University of Malaysia (UKM) and Malaysia Research and Development on Agriculture Industries (MARDI) on the use of solar drying for agriculture products. 25 2.4 SE4All GOALS 2.4.1 Energy Access Malaysia is committed to ensuring universal access to modern energy services and providing 100% electricity to the rural area. Under the Government Transformation Programme, universal access is targeted to be achieved 2015. Targets for additional houses to be supplied with electricity are about 6,000 houses in Peninsular Malaysia, 59,000 houses in Sabah and 76,000 houses in Sarawak. 2.4.2 Energy Efficiency The National Energy Efficiency Master Plan, 2010 is a holistic implementation roadmap to drive efficiency measures across sectors with a target to achieve cumulative energy savings of 4,000 kilo ton of oil equivalent (ktoe) by 2015 according to the 10 Malaysia Plan. 2.4.3 Renewable Energy The share of renewable energy sources in the electricity sector will be increased from less than one percent today to 5.5% in 2015 (985 MW). The doubling of rate on the use of RE at the national context (based on business-as-usual scenario and upon the successful introduction of FiT) may happen middle of 2013. RE Generation Capacity Targets under FiT (MW) Year 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2025 2030 Biogas Biomass 20 110 35 150 50 200 75 260 100 330 125 410 155 500 185 600 215 700 240 800 350 1,190 410 1,340 Solid Waste 20 50 90 140 200 240 280 310 340 360 380 390 26 Hydro 60 110 170 230 290 350 400 440 470 490 490 490 Solar PV 9 20 33 48 65 84 105 129 157 190 455 1,370 TOTAL 219 365 543 753 985 1,209 1,440 1,664 1,882 2,080 2,865 4,000 SECTION 3: CHALLENGES AND OPPORTUNITIES FOR ACHIEVING SE4ALL GOALS 3.1 INSTITUTIONAL AND POLICY FRAMEWORK 3.1.1 Energy and development Energy in national development and poverty reduction strategies and plans Energy is an important factor to Malaysia’s economic growth, constituting about 20 per cent of the nation’s Gross Domestic Product (GDP). The Government plans to increase diversification of the energy industry, step up exploration for new oil and gas resources, enhance production from known reserves, and encourage the use of alternative energy sources such as solar, hydro-electric and even nuclear. The energy sector’s contributions to our GNI are expected to rise from RM110 billion in 2009 to RM241 billion in 2020. Hence, the energy sector needs to be more efficient and resilient to be able to deliver adequate and reliable energy supply to support our country’s rapid growth against a backdrop of depleting energy resources as well as escalating and volatile energy prices. GDP (RM Million) Trend: GDP vs Electricity Consumption 600,000 1 500,000 1 400,000 8 300,000 6 200,000 4 100,000 2 0 There is a strong correlationship between the rate of electrification and the reduction of poverty level in Malaysia, although it will only due to rural electrification factor alone. Strong poverty alleviation programme especially in the beginning of 1970s together with extensive completion of rural basic infrastructure (roads, water, sanitation, schools and clinics) including rural education have contributed to the success of the poverty eradication programme. The rise of electricity consumption is in tandem with the growth of GDP. Energy governance: Energy policy in Malaysia is set and overseen by the Economic Planning Unit (EPU), with close coordination with the line ministries (MEGTW, on electricity matters) and agencies (i.e. Energy Commission and SEDA). MEGTW regulates the non-oil and electricity sector (and gas energy and security sectors) while EC regulates the energy supply activities and enforces energy supply laws. SEDA, is a newly set up statutory body formed under the Sustainable Energy Development Authority Act 2011 whose role is to administer and manage the implementation of the feed-in tariff mechanism mandated under the Renewable Energy Act 2011. Malaysia Green Technology Corporation (MGTC) from time to time provides promotion, policy research and awareness support to MEGTW related to green technology including RE and EE initiatives. 27 EPU - formulates overall policy on rural development - incorporates impacts of infrastructure development to social and economic growth PEMANDU / ICU / State EPUs Oversee implementation MEGTW - guardian of the MESITA fund - energy policy EC: MOE - rural school electrification MOH - rural clinic electrification Regulates electricity MRRD industry SEDA: Administrator of RE Act MGTC: Energy R&D on EE /RE receives information on rural development programme including rural electrification (basic infrastructure) PWD / TNB PWD / TNB PWD / TNB - project - project - project SubContractors SubContractors SubContractors - installations / - installations / - installations / Linkages of Electricity Institutions related to Rural Electrification Projects With respect to oil and gas industries, Petroliam National Berhad (PETRONAS), holds exclusive ownership rights to all oil and gas exploration and production projects in Malaysia, for all licensing procedures, and is subject to only the Prime Minister, who also controls appointments to the company board. The company holds stakes in the majority of oil and gas blocks in Malaysia. It is the single largest contributor of Malaysian government revenues, (over 40 percent in 2010), by way of taxes and dividends. Malaysia's oil and gas policy has historically focused on maintaining the reserve base to ensure long term supply security while providing affordable fuel to its population. In July 2010, the government introduced subsidy reductions for gasoline, diesel, and liquid petroleum gas (LPG) with the aim of gradually decreasing fuel subsidies to reduce expenditures. Further cuts in fuel subsidies are planned. Generally, Malaysia plans for adoption of market-based energy pricing, in line with overall strategy to rationalize subsidies where energy subsidies will be reduced, with the goal of achieving market pricing by 2015. Gas prices for the power and non-power sectors will be reviewed every six months to gradually reflect market prices. A decoupling approach for energy pricing will be undertaken to explicitly itemize subsidy value in consumer energy bills and eventually delink subsidy from energy use. For low-income households and other groups for which the social safety net is required, different forms of assistance will be provided. Malaysia also belives in the stronger governance of the energy sector where the goal to raise productivity and efficiency. In this regard, the gas supply industry will be further liberalized to facilitate the entry of new suppliers and third-party access arrangements. The electricity supply industry will also be restructured to instil greater market discipline. 3.1.2 Thermal energy for households LPG industry in Malaysia is currently dominated by state owned Petronas followed by Shell and Esso among others while piped gas supply is regulated by the EC. 28 3.1.3 Power sector MEGTW is the responsible ministry and the utility are provided by the utility companies (TNB in Peninsular Malaysia, SESB in Sabah and SESCO in Sarawak. 3.1.4 Modern energy for productive sectors RE is poised to be connected with up to 5.5% of total generation mix by 2015. MEGTW is responsible on the execution of the RE Act policy while SEDA is to administer the FiT mechanism under the RE Act. 3.1.5 National monitoring framework for SE4ALL Proposed indicators to measure and monitor achievement of national SE4ALL goals Energy access indicators: - Country rural electrification rate - Share of households with access to electricity/energy for cooking & heating - Impacts of electricity to rural people EE indicators: - Average electricity consumption of households Primary and final energy intensity by sector Efficiency of total electricity generation GDP / unit of Energy Used Energy Used per capita RE indicators: - Share of renewables in gross electricity consumption - Share of renewables in electricity generating capacity - Share of households using modern energy for heating/cooking Data requirements, gaps and associated capacity development needs Related to 3.5 29 3.2 PROGRAMS 3.2.1 Thermal energy Programme LPG for cooking has been widely used. As date, there is no program on the use of thermal energy from RE for domestic cooking and heating. Use of charcoal from biomass briquette is negligible. For industrial usage, efforts are already on going on the use of RE sources from industrial byproducts (i.e. wood chips, MDF waste, saw dust, empty fruit bunch) mainly for producing steam (low pressure/ high pressure) for manufacturing processes. Sustainability Research and development and pilot projects on briquette / pellet production especially from biomass palm oil waste (EFB/blended) and rice husk has already in existence. Commercial production has yet to be fully taken off. The processing cost is estimated at RM 150 per tonne and the selling price for export market at RM 600 to RM 700 per tonne. 3.2.2 Power sector Physical access (electrification) As at date, rural electrification has successfully penetrated 99% of the country, 99.5% in Peninsular Malaysia, 77% in Sabah and 76% in Sarawak (10 Malaysia Plan) Reliability (grid maintenance/upgrade) The utility companies (TNB, SESB, SESCO) has ongoing programme on ensuring continuous supply of power. Sustainability (investment in renewable energy, on-grid and off grid, and energy efficiency) The advent of RE Act has allowed the use of RE sources for power generation. Refer 2.3 for details. 3.2.3 Energy efficiency programs Sector Residential Township Initiatives Phasing out of incandescent light bulbs by 2014 to reduce carbon dioxide emissions by an estimated 732,000 tons and reducing energy usage by 1,074 GW a year. Increasing energy performance labeling from four (air conditioner, refrigerator, television and fan) to ten electrical appliances (six additional appliances - rice cooker, electric kettle, washing machine, microwave, clothes dryer and dishwasher). Labeling appliances enables consumers to make informed decisions as they purchase energy efficient products. Robust tariff structures (“the more you use, the more you pay principle”) to encourage energy saving and avoid wastages. Encourages use of passive designs at home Introduction of guidelines for green townships and rating scales based on carbon footprint baseline and promoting such townships starting with Putrajaya and Cyberjaya. 30 Industrial Buildings Transport Implementation of the newly formulated Low Carbon City Framework (LCCF) to encourage less GHG emissions especially from energy usage Promotes energy efficient / multi modal public transport system Increasing the use of energy efficient machineries and equipment such as high efficiency motors, pumps and variable speed drive controls. Encourages energy benchmarking among subsectors of industries Encourages the setting up of Energy Management Team to look into energy consumption and measures and Energy Manager Encourages the use of ISO 5000 energy Management System Mandatory reporting of the energy usage and its management plan for electricity users of 500,000kWh / year Introduction of Minimum Energy Performance Standards for selected appliances to restrict the manufacture, import and sale of inefficient appliances to consumers. Promotes the use of rating tools such as the Green Building Index (GBI), LEEDS and CIDB Pass Promotes the Life-Cycle analysis (“cradle-to-cradle”) for building construction industries under Carbon Common Metric (CCM) Effective public transportation system Use of Bus Rapid Transit in Iskandar Development Region (pilot phase) Source: EPU 10MP 3.2.4 Modern energy for productive use Sector Community Livelihood Initiatives, currently ongoing Use of micro-hydro system for electricity generation Use of solar hybrid for electricity generation Solar home system (per household) for rural area Use of grid-connected solar PV system Agriculture Use of solar drying in processing agriculture products (pilot stage) Use of micro-hydro system for pumps ( irrigation) Energy Supply On-grid: Introduction of feed-in-Tariff for wide spread electricity generation from RE sources (biomass, biogas, PV, mini-hydro) Off-grid: promotes the use of hybrid-diesel, micro-hydro and wind Industries Use of biomass/biogas for in-house electricity generation use Use of biomass/biogas for use in the manufacturing processes (heating) Education Use of solar PV for rural schools for ICT and communication Transport Initiated Electric Vehicle piloting in Putrajaya, Cyberjaya and Bukit Bintang. It is planned that charging station will be of hybrid solar/RE type in the near future (including smart-grid connectability) 3.3 FINANCING Government’s allocation: Financing for basic infrastructure (water, roads and rural electrification) comes from the government development budget. Feed-in Tariff (FiT): Financing for Feed-in Tariff (FiT) is currently based on of 1% of electricity usage for consumers who are using more than 300kWh per month. It is estimated the amount to be RM 1 billion per year to be placed under the Renewable Energy Fund, to be administered by SEDA. 31 Fiscal and Financial Incentives: Since 2001, in order to promote EE and RE, companies implementing RE & EE measures in their premises may be granted investment tax allowance, accelerated capital allowance, import duty exemption and sales tax exemption. Green Technology Financing Scheme (GTFS): In the budget speech for 2010, Dato’ Seri Najib Tun Abdul Razak, the Prime Minister of Malaysia announced the establishment of Green Technology Financing Scheme amounting to RM1.5 billion as an effort to improve the supply and utilization of Green Technology. The scheme could benefit companies who are producers and users of green technology. In operationalizing it, the Government will bear 2% of the total interest/profit rate. In addition, the Government will provide a guarantee of 60% on the financing amount via Credit Guarantee Corporation Malaysia Berhad (CGC), with the remaining 40% financing risk to be borne by participating financial institutions (PFIs). The Prime Minister also appointed MGTC as the conduit for the Green Technology Financing Scheme (GTFS) application. The scheme is expected to provide benefits to more than 140 companies of which the application will be open starting from 1st January 2010. It is also a mechanism that helps finance any technology that is suitable for the identified project criteria provided it is a proven technology. GTFS requires that projects must be located within Malaysia, utilising local and/or imported technology. Private companies that could benefit from this financing scheme are “PRODUCER” or “USER” of green technology products or systems, as follows FEATURES USER OF GREEN TECHNOLOGY PRODUCER OF GREEN TECHNOLOGY Financing size Maximum: RM50 million per company Maximum: RM10 million per Financing tenure Up to 15 years Eligibility criteria Legally registered Malaysian -owned Legally registered Malaysian companies (at least 51%) in all economic owned companies (at least 70%) in all economic sectors sectors Participating financial institutions (PFIs) All commercial and Islamic banks. GFIs: Bank Pembangunan, SME bank, Agrobank, Bank Rakyat, EXIM bank and Bank Simpanan Nasional company Up to 10 years (source: MGTC) Malaysia Electricity Supply Industry Trust Account (MESITA): MESITA was formally established on 1 January 1997 under a Trust Deed issued by the Ministry of Finance. The decision to establish MESITA was made by the Malaysian Cabinet on 11 December 1996 which required all Independent Power Producers (IPPs) to fulfil their national obligation towards the development of electricity supply industry in the country. To reflect their role in the comprehensive contribution to electricity supply industry, the concept of social obligation which was used in the initial establishment of MESITA was later changed to national obligation after discussions were held between MEWC, TNB and the IPPs. The Independent Power Producers (IPPs) which sell electricity to the Peninsular Grid make contributions annually to the Trust Account. The rate agreed by the contributors is pegged at one percent (1%) of the total audited annual turnover of the previous year. This rate will remain until 2005 and thereafter a review of the rate will be done. The accumulated income of MESITA for the year 1998 to 2002 was RM 365,454,420.94 (USD 117,888,522.8 millions). All the IPPs contributed 1% of their annual turnover from their audited accounts. Throughout its existence, MESITA managed to play a catalytic role in carrying out the development programme of the electricity supply industry on a sustainable basis. Prior to the existence of MESITA, all programme were implemented on a piece-meal and ad-hoc basis by agencies in the electricity sector. These applications were localized and confine to their respective organizations and were not industry-focused. The rural electrification project under the MESITA fund from 1998 to 2010 recorded expenses of RM148,089,209.19 (USD 48 million) to upgrade and provide infrastructure for rural electrification programme. As a result, a total of 41,218 houses are connected to the grid and 7,652 houses are connected to the solar hybrid system especially for indigenous communities in Peninsular Malaysia. The type of projects allowed under the MESITA Trust Deed are as follows: 1. Rural electrification programme; 32 2. Research and development (R&D) programme for the electricity industry including R&D on the development of new and renewable sources of energy; 3. Training and educational programme for human resource development in the electricity sector; 4. Energy efficiency (EE) programme; and the promotion and development of the electricity supply industry; 5. The promotion and development of the electricity supply industry. 3.4 PRIVATE INVESTMENT AND ENABLING BUSINESS ENVIRONMENT 3.4.1 Thermal energy for households Private sector actors involved in supply chain (energy supply companies, technology providers, financiers) LPG for cooking is readily available in local sundries and is sold by public companies and private entrepreneurs. Barriers to private investment in modern energy supplies and technologies for cooking and other thermal applications None significant as date 3.4.2 Power sector Private sector actors involved in supply chain Tenaga Nasional Bhd. (TNB) is the largest electricity utility company in Malaysia with a total installed generation capacity of ore than 15,000 MW. Syarikat SESCO Bhd (formerly Sarawak Electricity Supply Corporation, SESCO) is the privatized organization responsible for the generation, transmission and distribution of electricity for the Sarawak state in Malaysia. Sabah Electricity Sdn. Bhd SESB) is a company that generates, transmits and distributes electricity mainly in Sabah and Federal Territory of Labuan. SESB is a subsidiary of TNB. Independent Power Responsible of about 70.78% (19,237 MW) of electricity generation in producers (IPP) Malaysia representing 17 different companies. RE Developers No official record but it estimated that there are more than 100 companies who are currently expressed interest in participating in SREP and FiT. Barriers to private investment in new on-grid and off-grid power generation capacity (especially for RES), grid extension/maintenance, demand-side management (DSM) and energy efficiency Type Institutional barriers Data Information barriers Description Lack of institutional support especially on the use of renewable energy (either for thermal or off-grid electricity) in the rural area. Impacts Lack of functioning institutional network on RE could be overcome by encouraging joint effort between government agencies (federal and state) and private institutions in order to explore the technical and commercial viability of energy generation from renewable resources and enhancing capacity building of key players such as government decisionmakers, industries and utilities on RE implementation. RE / Insufficient/limited data availability on the Impacts of rural electrification on small and use of energy in the rural area medium enterprises (and to poverty alleviation) in rural areas have not been extensively documented. Neither does the 33 Financial and Incentive barriers Level playing field: Due to higher commitments accorded to development or expansion plans, renewable energy is given a lower priority by Malaysian enterprises. There is a clear need for refocusing the energy fuel mix in the country’s energy equation to give importance to renewable energy. present framework of datum identifies these enterprises by their location i.e., rural or urban. The subsidy for conventional fuel source should be gradually eliminated and/or transferred to RE resources to promote RE installations. Special funds for energy delivery in In agro-based industries, loans can be rural: set up by the government to utilized for purchase of farm equipments promote small and medium and machineries, which utilize efficient enterprises (i.e SMIDEC’s funds) do electricity. Fish processing and agronot target entrepreneurs involved in processing industries in rural areas are energy service delivery such as potential or actual beneficiaries of rural enterprises in solar energy business. electrification. Reliable supply of There is, at present, lack of incentive electricity in rural areas enables to these enterprises to operate in fishermen in coastal areas to keep their rural areas. There are a number of daily catch in freezers. Provision of enterprises in rural area, which electricity enables cottage industries to utilize energy, particularly electricity work long hours and improve their for lighting and motive power. Rice productivity and income. Female mills, oil mills, weaving enterprises, members of the community who work in batik and crafts in rural areas these enterprises also benefit from the benefit from the use of electricity. increased income and output due to the Provision of electricity enables these provision of electricity services. enterprises to work long hours. 3.4.3 Modern energy for productive sectors Similar to the above 3.4.2 34 3.5 GAPS AND BARRIERS Section on gaps and barriers on Thermal energy for household, Power sector and Modern energy for productive sectors will be summarized as below. Barriers Institutional SE4ALL Objectives EE Universal Access RE No major issues noted in the grid-connected No major issues noted in the electricity. MEGTW is the electricity sector. focal point for the MEGTW is the focal point for development of RE the development of EE policies with SEDA as the policies supported by EC and administrator of the FiT SEDA. mechanism. No major issues noted. MRRD remains as the focal point for the rural basic infrastructure programme. EPU, ICU and PEMANDU oversee Energy use in transport the implementation remains as a challenge as progress including rural there is clearly an absence of energy planning. a dedicated agency in charged on it. Regulatory No major issues noted. Technical No major issues noted. The remaining gridextension remains a challenge due to the limited number of final connections / houses Awareness / Promotion No major issues noted Use of RE (such as biofuel) in transport remains as a challenge due to unseen economic benefits (vs fossil fuel) as per the current oil price. Lack of a dedicated regulatory mechanism on EE hampers efficient energy utilization in industrial, residential, commercial and No major issues noted. the transportation sectors. It is noted that Efficient Management Of Electrical Energy Regulations 2008 has been in operation since 2008 No major issues noted. Innovative ideas such as No major issues noted. EE is pooling FiT and new RE looked mainly at sectoral sources (which are not level (buildings, energy part of the current FiT supply, energy demand, scheme) such as wind industrial and transportation and geothermal are not sectors) currently not the national priority. Public awareness on the use of energy (electrical and domestic energy) is low due to cheap and abundant No major issues noted. supply. The government is fully aware and is currently considering subsidy rationalization in stragerred 35 Financing basis. Use of public transport has been in increasing trend due to the improved infrastructure. Financing for EE projects remains a challenge due to No major issues noted as limited successful cases on EE both fuel for domestic project financing. The energy (LPG) and government is currently transport are marketsupporting Energy based. Performance Contracting in selected hospitals. 36 Financing for RE projects remains a challenge due to limited successful cases on RE project financing. Cost of technology is still considered high. REFERENCES 1. 10 Malaysia Plan, EPU 2010 2. Economic Planning Unit, Economic Monitor, website September 2012 3. 4. 5. 6. 7. ETP Energy, Oil and Gas, PEMANDU 2011 GTP Annual Reports, PEMANDU 2011 IEA Report / website September 2012 MDG Report, EPU and UN Country Team, 2010 National Energy Balance 2009 8. PRODUCTION OF PALM-BASED BIOMASS BRIQUETTES. MPOB, 2006 9. Suruhanjaya Tenaga Statistics 2010 10. UNDP Human Development Report, 2011 11. World Bank Country Data, website September 2012 37 FINAL Draft: 19 Sep 2012 INTERNAL USE & FOR CONSULTATION ONLY Annex 1: Other Initiatives related to SE4ALL No Project Name Period Related to SE Objective Implemented by Activities Universal Access Pipeline projects 1 Third National Communication 20132016 2 Green Technology Application for the development of the Low Carbon Cities (GTALCC) 20142019 3 4 5 GHG Bi-Annual Update Reporting (BUR) Solar Thermal for Industrial and Heating application Develop GHG Inventory Formulate mitigation measures UNDP and Recommend adaptation actions NRE Build capacities of public and private sectors (industries, residential and commercial developers) Promote widespread use of EE and RE principles in the cities UNDP, GEF Build capacities of town/city planners in adopting and MEGTW green technologies to mitigate GHG (technical, financing and awareness) Develop guidelines and standards 20132015 UNDP and NRE 20152018 UNIDO and MIGHT Low Emission Capacity 2013Building Project (LECB) 2015 UNDP and NRE Updates of GHG Inventory Promote the Use of solar thermal for industrial use Develop standard and guidelines Build stakeholder’s capacities in understanding solar thermal technology Build national capacity in the development of Low Emission Development Strategies (LEDS), Nationally Appropriate Mitigation Actions (NAMA) and Measurements, Reporting and Verification (MRV) 38 EE No Project Name Period Related to SE Objective Implemented by Activities Universal Access On-going Projects Reducing Emission 2011from Deforestation 2013 6 and Land Degradation plus (REDD+) 2011Economics of Climate 2013 7 Change Study 8 9 10 11 12 Roadmap on 2012Reduction of 40% 2013 Carbon Intensity in Malaysia Development of 2012 National Carbon Disclosure Programme (NCDP) Framework Study 2010 Building Sector Energy – Efficiency Project 2015 (BSEEP) UNDP and NRE UNDP and EPU NRE and UNITEN UNDP and NRE Develop necessary costing for CC mitigation and adaptation measures Harmonize necessary modelling tools for policy makers Finalize and streamline national mitigation actions in relation to PM’s pledge in Copenhagen of 40% carbon intensity reduction UNDP, GEF and PWD 2012 - UNIDO, GEF Industrial Energy 2017 and SMIDEC Efficiency for Manufacturing Sector (IEEMS) Green Township (and 2010 Low Carbon Cities – Framework (LCCF)) 2015 Formulating REDD+ National Strategies Increase readiness phase for Malaysia MEGTW Formulate necessary framework for voluntary emission reduction programme in Malaysia Invite private sectors to support national CC initiatives Focus on EE for new and existing buildings Develop rating tools and standards Build capacity of public and private developers on building EE design Promote the use of ISO50000 Energy Management System Build capacity of SME in managing energy usage Develop guidelines and standards for industrial equipment Develop voluntary guidelines for cities in reducing GHG emission Focus on passive and active measures including EE 39 No Project Name Period Related to SE Objective Implemented by Activities Universal Access 13 Green Building Index Since (GBI) 2007 14 Green PASS for buildings 15 Low Carbon Society (LCS) green initiatives such as 3R and composting Professionals Certification of buildings and township according to (led by PAM) industry-certified GBI rating tools CIDB and JKR Certification framework of Malaysia’s buildings and township according to UNEP’s Carbon Common Metric JICA, EPU, UTM and Iskandar Development Region Completed Projects (from year 2000 onwards) Malaysian Industrial 2000 - UNDP, GEF Energy Efficiency 2007 and MEGTW Improvement project (MIEEIP) 16 Develop pilot research projects on low carbon society for Iskandar region Utilize scenario planning and modelling approach to low carbon cities Build capacity of policy makers in prioritizing EE and RE measures 17 Biomass power 2003generation and co2008 generation for utilizing waste from Palm Oil Mills (BIOGEN) UNDP, GEF and MEGTW Build capacities of public and private sectors (industrial sectors) in understanding EE Develop necessary policies and rating tools on EE Demonstrate the techno-economic benefits of EE in the industrial sector Create awareness on the use of efficient energy in the industrial sectors Demonstrate the feasibility of utilizing biomass and biogas from Palm oil Mills for energy generation Formulate necessary policies of gridconnected energy generation Create awareness on the use of biomass and biogas in the palm oil industry EE 40 No Project Name Period Related to SE Objective Implemented by Activities Universal Access Building Integrated Photovoltaic project (BIPV) 20052011 UNDP, GEF and MEGTW 18 19 20 DANIDA Energy 2003Efficiency / Demand- 2006 Side Management Programme DANIDA, Energy Commission DANIDA programme on development of Solid Waste Management framework in Malaysia DANIDA, MHLG Develop framework on the use of gridconnected solar PV for power generation Initiate the regulatoty framework for the establishment of the Feed-in-Tariff mechanism for RE Create sustainable financing for RE generation Encourage FDI for solar manufacturing plants in Malaysia Develop framework on EE and demand-side management for industrial products and building sectors Build capacity of public office in formulating and regulating necessary policies on EE Develop framework and policies on solid waste management (SWM) in Malaysia Build capacity of public office and private sectors in dealing with SWM issues Communicate with state actors on managing domestic waste EE 41
© Copyright 2026 Paperzz