CITY OF ANAHEIM Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area SEPTEMBER 2010 VOLUME 1 Table of Contents VOLUME 1 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Executive Summary............................................................................................................... 1 1.1 General ................................................................................................................................ 1 1.2 Drainage Basin 5 ................................................................................................................ 1 1.3 Drainage Basin 10 .............................................................................................................. 2 1.4 Drainage Basin 11 .............................................................................................................. 2 1.5 Drainage Basin 13 .............................................................................................................. 2 1.6 Drainage Basin 15 .............................................................................................................. 3 1.7 Capital Improvement Plan ............................................................................................... 3 1.8 Storm Drain Impact and Improvement Fee................................................................... 5 1.9 Potential Locations for Detention/Infiltration Basins in City Parks.......................... 5 Introduction ............................................................................................................................ 9 2.1 Purpose ............................................................................................................................... 9 2.2 Background ........................................................................................................................ 9 Technical Criteria ................................................................................................................ 10 3.1 Hydrologic Analysis ....................................................................................................... 10 3.2 Hydraulics Analysis........................................................................................................ 10 3.3 Downstream Boundaries................................................................................................ 11 Drainage Basin 5 .................................................................................................................. 12 4.1 Hydrologic Analysis ....................................................................................................... 12 4.2 Analysis of Existing Improvements.............................................................................. 12 4.3 Proposed Improvements ................................................................................................ 13 4.4 Cost Estimates.................................................................................................................. 13 Drainage Basin 10 ................................................................................................................ 15 5.1 Hydrologic Analysis ....................................................................................................... 15 5.2 Analysis of Existing Improvements.............................................................................. 15 5.3 Proposed Improvements ................................................................................................ 16 5.4 Cost Estimates.................................................................................................................. 16 Drainage Basin 11 ................................................................................................................ 21 6.1 Hydrologic Analysis ....................................................................................................... 21 6.2 Analysis of Existing Improvements.............................................................................. 22 6.3 Proposed Improvements ................................................................................................ 23 6.4 Cost Estimates.................................................................................................................. 23 Drainage Basin 13 ................................................................................................................ 26 7.1 Hydrologic Analysis ....................................................................................................... 26 7.2 Analysis of Existing Improvements.............................................................................. 26 7.3 Proposed Improvements ................................................................................................ 27 7.4 Cost Estimates.................................................................................................................. 27 Drainage Basin 15 ................................................................................................................ 29 8.1 Hydrologic Analysis ....................................................................................................... 29 8.2 Analysis of Existing Improvements.............................................................................. 30 8.3 Proposed Improvements ................................................................................................ 31 8.4 Cost Estimates.................................................................................................................. 31 Capital Improvement Plan................................................................................................. 35 Storm Drain Impact and Improvement Fee .................................................................... 37 Potential Locations for Detention/Infiltration Basins in City Parks ......................... 38 I List of Figures Figure 1 Study Area ................................................................................................................. 6 Figure 2 Drainage Areas .......................................................................................................... 7 Figure 3 Proposed Improvements ............................................................................................ 8 Figure 4 Drainage Basin 5 ..................................................................................................... 14 Figure 5 Drainage Basin 10 ................................................................................................... 19 Figure 6 Drainage Basin 10 Alternative Proposed Improvements ........................................ 20 Figure 7 Drainage Basin 11 ................................................................................................... 25 Figure 8 Drainage Basin 13 ................................................................................................... 28 Figure 9 Drainage Basin 15 ................................................................................................... 33 Figure 10 Drainage Basin 15 Alternative Proposed Improvements ...................................... 34 List of Tables Table ES-1 – Priority 1 Cost Estimate ...................................................................................... 4 Table ES-2 – Priority 2 Cost Estimate ...................................................................................... 4 Table ES-3 – Priority 3 Cost Estimate ...................................................................................... 5 Table ES - 4 Potential Locations for Detention/Infiltration Basins within City Parks ............. 5 Table 1 – Basin 5 Summary of Hydrology ............................................................................. 12 Table 2 – Basin 5 Cost Estimate ............................................................................................. 13 Table 3 – Basin 10 Summary of Hydrology ........................................................................... 15 Table 4 – Basin 10 Cost Estimate ........................................................................................... 16 Table 5 – Basin 10 Alternative Cost Estimate ........................................................................ 18 Table 6 - Basin 11 Summary of Hydrology ............................................................................ 22 Table 7 - Basin 11 Cost Estimate............................................................................................ 24 Table 8 - Basin 13 Summary of Hydrology ............................................................................ 26 Table 9 - Basin 13 Cost Estimate............................................................................................ 27 Table 10 - Basin 15 Summary of Hydrology .......................................................................... 30 Table 11 - Basin 15 Cost Estimate.......................................................................................... 31 Table 12 - Basin 15 Alternative Cost Estimate....................................................................... 32 Table 13 – Priority 1 Cost Estimate ........................................................................................ 35 Table 14 – Priority 2 Cost Estimate ........................................................................................ 36 Table 15 – Priority 3 Cost Estimate ........................................................................................ 36 Table 16 - Potential Locations for Detention/Infiltration Basins within City Parks.............. 38 Appendices Appendix A Cost Estimates VOLUME 2 (Bound Separately) Appendix B Hydrology Maps Appendix C Hydrology Calculations Appendix D Existing Hydraulic Calculations II Appendix E Appendix F Proposed Hydraulic Calculations Street Flow Calculations III 1. Executive Summary 1.1 General The City of Anaheim Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area (FCTA) covers that portion of the City of Anaheim ultimately tributary to Orange County Flood Control District (OCFCD) regional facility Fullerton Creek Channel (A03). The purpose of the Master Plan is to provide comprehensive long-range planning for the implementation and development of drainage facility improvements in the area, determine the cost of implementing the facilities, and discuss funding priorities of the improvements. This Master Plan is based on the criteria outlined in the City’s Drainage Manual for Public and Private Drainage Facilities, dated August, 2005. In 1973, the City published a Master Plan of Drainage for the City of Anaheim. That report divided the City into 42 Drainage Districts based generally on local storm drainage facilities and the City limits at that time. In 1983, two additional Drainage Districts were added for a total of 44 Drainage Districts. Since that time the City limits have changed to include more tributary area and the City has changed its drainage classification system to watersheds which are tributary to the County of Orange’s regional drainage facilities. The City of Anaheim is divided into seven major watershed tributary areas; Santa Ana River, Carbon Creek Channel, East Garden Grove-Wintersburg Channel, Anaheim Barber City Channel, Fullerton Creek Channel, Stanton Channel, and Moody Creek Channel. Each of these watersheds include several of the Districts from the 1973 Master Plan. The FCTA includes Drainage District’s 5, 10, 11, 13, and 15 from the 1973 Master Plan. These areas are identified as Drainage Basins instead of Districts for this Master Plan and are shown on Figure 1. The boundaries of some of the basins have been modified from the 1973 Master Plan boundaries. Figure 1 shows the new boundaries, and all references to areas in this Master Plan are based on the new boundaries. Each Drainage Basin is further divided into one or more Drainage Areas as shown in Figure 2. 1.2 Drainage Basin 5 Drainage Basin 5 drains approximately 360 acres, and is generally bounded by the 91 freeway on the north, the I-5 freeway on the east, a few hundred feet south of La Palma Avenue to the south, and Dale Avenue on the west. Generally, water flows over land to streets and then through pipes from the southeast to the northwest, and ties into Caltrans facilities at the City limits with the City of Buena Park. As shown in Figure 2, Drainage Basin 5 consists of 1 Drainage Area. There are two storm drains in area 5-1. The main storm drain system in Magnolia Avenue and La Palma Avenue can convey 70 percent of the 10-year flow. The second storm drain in Knollwood Circle which ties in to the first storm drain is adequate to convey the 10-year storm event. However, the City’s flooded width criteria during a 10, 25 and 100-year storm event are not satisfied in most locations. An extension to the existing facilities in La Palma Avenue, and parallel relief storm drains in La Palma Avenue and Magnolia Avenue are recommended to satisfy both the City’s requirement of conveying the 10-year storm event 1 and the flooded width criteria. The estimated cost for constructing the improvements is $13,774,000 (2010 dollars). 1.3 Drainage Basin 10 Drainage Basin 10 drains approximately 175 acres, and is generally bounded by the 91 freeway on the north, Brookhurst Street on the east, La Palma Avenue on the south, and the I-5 freeway on the west. Generally, water flows in streets from east to west before entering a catch basin which ties into the Houston Channel Lateral at the City Limits. The Houston Channel Lateral drains into Houston Channel, which is tributary to Fullerton Creek Channel. As shown in Figure 2, Drainage Basin 10 consists of 4 Drainage Areas. There are no existing storm drain facilities within Drainage Basin 10. The City’s flooded width criteria during a 10, 25 and 100-year storm event are met for streets in Areas 10-3 and 10-4. However, they are not satisfied in several locations in Areas 10-1 and 10-2. Construction of new facilities in Houston Avenue, Coronet Avenue, and Falmouth Avenue are recommended to satisfy both the City’s requirement of conveying the 10-year storm event and the flooded width criteria. The estimated cost for constructing the improvements is $8,191,000 (2010 dollars). 1.4 Drainage Basin 11 Drainage Basin 11 drains approximately 430 acres, and is generally bounded by the 91 freeway on the north, Euclid Street on the east, Catalpa Avenue to the south, and Brookhurst Street on the west. Generally, water flows over land to streets and then through pipes from south to north and from east to west. The east to west flow ties into Caltrans facilities along the I-5 freeway at Brookhurst Street. The south to north flow drains into a Caltrans facility along the 91 freeway. The Caltrans facilities drain into Houston Channel (A03S02), which is tributary to Fullerton Creek Channel. As shown in Figure 2, Drainage Basin 11 consists of 8 Drainage Areas. There is only one existing storm drain system in Basin 11. This system drains Area 11-3 in Coronet Avenue and has a capacity of 70 percent of the 10-year flow. The City’s flooded width criteria during a 10, 25 and 100-year storm event are met for streets in Areas 11-4 through 11-8. However, the City’s flooded width criteria during a 10, 25 and 100-year storm event are not satisfied in many locations in Areas 11-1, 11-2 and 11-3. New storm drain facilities along La Palma Avenue in Area 11-1 and Brookhurst Street in Area 11-2 and a parallel storm drain along Coronet Avenue in Area 11-3 are recommended to satisfy the City’s requirement of conveying the 10-year storm event as well as the City’s flooded width criteria. The estimated cost for the improvements is $17,424,000 (2010 dollars). 1.5 Drainage Basin 13 Drainage Basin 13 drains approximately 125 acres, and is generally bounded by the 91 freeway on the north, Harbor Boulevard on the east, La Palma Avenue on the south, and Euclid Street on the west. Generally, water flows over land to streets from east to west and then from south to north through an existing storm drain system along Euclid Avenue that ties into a Caltrans facility along the 91 freeway. The Caltrans facility drains into Houston Channel, which is tributary to Fullerton Creek Channel. As shown in Figure 2, Drainage Basin 13 consists of 1 Drainage Area. 2 The existing storm drain system in Area 13-1 can convey the 10-year storm event except for the double 10.5-foot by 2-foot reinforced concrete box (RCB) along Euclid Street. The RCB has a capacity of 80 percent of the 10-year flow. The City’s flooded width criteria during a 10, 25 and 100-year storm event are not satisfied in Chevy Chase Drive and Romneya Avenue. Extensions to the existing facilities are recommended to satisfy the City’s flooded width criteria in these locations and a parallel storm drain in Euclid Street is also recommended. The estimated cost for constructing the improvements is $4,602,000 (2010 dollars). 1.6 Drainage Basin 15 Drainage Basin 15 drains approximately 225 acres, and is generally bounded by Fullerton Creek Channel and the city limits to the north, Raymond Avenue on the east, the 91 freeway on the south, and Lemon Street on the west. The majority of flow drains to a storm drain in Orangethorpe Avenue and Lemon Street which outlets to Fullerton Creek Channel to the north. A few small areas drain north to A03S05 which outlets to Fullerton Creek Channel. As shown in Figure 2, Drainage Basin 15 consists of 6 Drainage Areas. The existing storm drains analyzed in Basin 15 are adequately sized to carry the 10-year storm event except for the storm drain in Area 15-1. This system can convey 90 percent of the 10-year flow. The storm drains in Area 15-4 and 15-6 can convey the 100-year flow and 10-year flows, respectively. Runoff from Areas 15-2, 15-3 and 15-5 flow over land and in streets directly into either Fullerton Creek Channel or A03S05, which is tributary to Fullerton Creek Channel. The City’s flooded width criteria during a 10, 25 and 100-year storm event are not satisfied in some locations. Extensions to the existing facilities, and parallel storm drains along Orangethorpe Avenue and Lemon Street are recommended to satisfy both the City’s requirement of conveying the 10-year storm event as well as the flooded width criteria. The estimated cost for constructing these improvements is $4,938,000 (2010 dollars). 1.7 Capital Improvement Plan The goal of the Capital Improvement Plan is to identify an organized system for implementing the proposed improvements as financing becomes available. A total of 20 projects totaling $48.9 million (2010 dollars) have been identified as part of this Master Plan. These projects range from small extensions of existing storm drains to large storm drain systems in arterial highways. A priority ranking was developed to identify the most important projects that should be constructed first. This ranking was based on the level to which the existing system meets the City’s flood protection goals. Three categories of improvements were identified as outlined below. Priority 1 - Proposed new storm drain in an arterial highway or local street to achieve 10, 25, and 100-year flood protection levels. Priority 2 - Proposed parallel or replacement storm drain in an arterial highway or local street to achieve 10, 25, and 100-year flood protection levels. Priority 3 - Proposed new storm drain in a local street where 100-year protection levels are met without the storm drain, however, the storm drain is required to achieve flood protection levels for the 10-year storm. 3 Figure 3 outlines the proposed improvements by priority. Table ES-1 outlines those projects designated as Priority 1. There are a total of 7 projects totaling $20.9 million (2010 dollars). Table ES-1 – Priority 1 Cost Estimate Area Storm Drain ID 10-1 SD 10-1_01 (P) 10-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Houston Avenue New 60-inch RCP 2,320 $4,335,000 SD 10-1_02 (P) Coronet Avenue New 48-inch RCP 1,080 $1,544,000 11-1 SD 11-1_01 (P) La Palma Avenue Replacement 60-inch RCP /54-inch /60-inch RCP/ New 42-inch RCP 4,155 $6,588,000 11-1 SD 11-1_02 (P) Dogwood Avenue New 48-inch RCP 1,155 $1,647,000 $8,235,000 11-2 SD 11-2_01 (P) Brookhurst Street New 54-inch/60-inch RCP 2,385 $3,817,000 $3,817,000 15-1 SD 15-1_01 (P) Orangethorpe Avenue Extension 42-inch RCP 625 $782,000 15-4 SD 15-4_01 (P) Orangethorpe Park/Orangethorpe Avenue Extension 42-inch RCP 1,740 $2,168,000 $2,168,000 $20,881,000 $20,881,000 TOTAL Area Total $5,879,000 $782,000 Table ES-2 below outlines those projects designated as Priority 2. There are a total of 7 projects totaling $19.8 million (2010 dollars). Table ES-2 – Priority 2 Cost Estimate Area Storm Drain ID Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) 5-1 SD 5-1_03 (P) La Palma Avenue Parallel Relief Drain 42inch/48-inch/54-inch RCP 2,990 $ 4,423,000 5-1 SD 5-1_02 (P) Magnolia Avenue Parallel Relief Drain 54inch RCP 2,770 $ 4,577,000 5-1 SD 5-1_01 (P) Magnolia Avenue to Dale Avenue Parallel Relief Drain 54inch RCP 2,550 $ 4,227,000 11-3 SD 11-3_01 (P) Coronet Avenue Parallel 72-inch RCP/ 60inch RCP 2,265 $4,307,000 13-1 SD 13-1_01 (P) Euclid Street Parallel 36-inch RCP 315 $325,000 $325,000 15-1 SD 15-1_02 (P) Orangethorpe Avenue Parallel 36-inch RCP 585 $633,000 $633,000 15-1 SD 15-1_03 (P) Lemon Street Parallel 36-inch RCP 1,250 $1,355,000 $1,355,000 $19,847,000 $19,847,000 TOTAL Area Total $13,227,000 $4,307,000 Table ES-3 below outlines those projects designated as Priority 3. There are a total of 6 projects totaling $8.2 million (2010 dollars). 4 Table ES-3 – Priority 3 Cost Estimate Area Storm Drain ID 5-1 SD 5-1_04 (P) 10-1 Street Type of Facility Length (feet) Sequoia Avenue Extension 33-inch RCP 540 SD 10-1_03 (P) Coronet Avenue New 42-inch RCP 1,015 $1,279,000 $1,279,000 10-2 SD 10-2_01 (P) Falmouth Avenue New 36-inch RCP 980 $1,033,000 $1,033,000 11-1 SD 11-1_03 (P) Dogwood & Mohican Avenue New 42-inch RCP 875 $1,065,000 $1,065,000 13-1 SD 13-1_02 (P) Chevy Chase Drive Replacement 42-inch RCP/ New 42-inch RCP 2,245 $2,820,000 13-1 SD 13-1_03 (P) Romneya Drive Extension 36-inch RCP 1,355 $1,457,000 4,277,000 $8,201,000 $8,201,000 TOTAL Estimated Cost (2010 Dollars) $ 547,000 Area Total $ 547,000 1.8 Storm Drain Impact and Improvement Fee To finance storm drain improvements and to mitigate the flooding and storm drainage impacts caused by new development and/or by additions and expansions to existing development the City of Anaheim City Council previously adopted an ordinance and storm drain impact fees for certain areas with the City. None of these fees are applicable to the Fullerton Creek Tributary Area. A future study will be conducted to identify financing mechanisms for constructing the improvements. These could include such options as Impact Fees, Assessment Districts or other financing mechanisms. 1.9 Potential Locations for Detention/Infiltration Basins in City Parks An analysis of potential locations for detention and infiltration basins in City parks was made. These detention/infiltration basins could potentially reduce the size or need for downstream storm drain facilities. The analysis was made by looking at the location of each park within the study area and determining if an existing or proposed storm drain facility was located nearby. If a storm drain facility was located nearby, then the potential to reduce downstream storm drain facilities was made. If the basin could reduce downstream facilities, then the location was identified as a potential location for a detention or infiltration basin. The results of the analysis are summarized in Table ES-4. Detailed analysis will need to be performed to determine the size and effectiveness of basins at these potential locations. Table ES- 4 Potential Locations for Detention/Infiltration Basins within City Parks Park Name Street by Park MP Basin SD Nearby 5 - MANZANITA PARK Canary St. FC – 13-1 Proposed 10 - JOHN MARSHALL FC - 11-1, PARK La Palma Ave 11-2 Proposed 1 Notes: Could reduce proposed storm drain for street flooding Is SD Deficient Possible D/S of Location Park for Basin Yes Yes1 Yes Yes1 5 Legend Anaheim City Limits Street Right of Way Basin 5 Basin 10 Basin 11 Basin 13 FREEDOM AVE LIBERTY AVE GEMINI PL LEMON ST HARBOR BLVD 1) OLIVE ST rbo nC r ee k( B0 WALNUT ST DR GILBUC K SE NE CA LIDO LN 5 Ca PATT ST KEMP ST ANAHEIM BLVD HOMER ST SWAN ST VILLAGE WAY MAYFAIR AVE WEST ST RALEIGH ST RIVIERA ST RAVENNA ST CITR ON ROBIN ST LOMBARD DR WAY RRY CHE LIDO ST LOMITA ST ARBOR ST CROWN ST ST LOARA ST FAIRHAVEN ST EUCLID ST IDW AY EUCL FANN ST ECHO ST NUTWOOD ST EMERALD ST LAGUNA ST MOHAWK AVE MOHICAN AVE IROQUOIS AVE ONONDAGA AVE CHIPPEWA AVE RT BA YP O MULLER ST DAHLIA DR PRIMROSE ST AGATE ST HERMOSA DR SU WICHITA ST FAIRVIEW ST FERN ST GARDEN ST CAROL DR BERNIECE DR ALADDIN DR EMPIRE ST VALLEY ST CAMELLIA ST BIRCHER ST BROOKHURST ST LOARA ST RF MAPLE ST LOTUS ST HOLLY ST HOLLY ST VALLEY ST VENTURA ST SIESTA ST KATHRYN DR VENTURA ST MONTEREY ST LINDSAY ST ARCHER ST PL BAKER ST HACIENDA ST FLORETTE ST GILBERT ST TOPO ST GAIN ST HAMPTON ST VE TH A WO R E LLS Y ST EMIL ST T ST E ST GAIN ST ALAMO ST ALAMO ST HAMPTON ST MAGNOLIA AVE MONTEREY ST ROANNE ST GENEVA ST MODENA ST HANOVER ST HARCOURT ST AURORA ST LA REINA ST LA PERLA ST NANCITA ST FELICIDAD ST ARON ST ST ST DINA STINSON ST VINE E ST C LAU ST Z EYN NTIN LVD EL S DICK OR B E CLEM T ON S ST TROJAN ST MORAGA ST WAY HICKORY DR H EM LO C K GUAVA AVE COLORADO ST CIR WAY SYRACUSE ST ST T GER LPHIA ST LE M E NA E LM RO S ADE AY ADW BRO S TER ME L ST K OA E KRO PHIL OAK R ST NTE HE L S ST PINE DOYLE DR ST LINCOLN AVE ST COLGATE ST VINE T ES S RTR C Y CH A CITT E OLIV DALE AVE ST ST LN T ST S ESS CE N B HAR H ST T VICKI LN E ROS BUSH ST VINE IS ST MAV T E ST INA S T IN PAUL S EKA TOP Y EMIL T KENDOR DR Feet AFTON T ES S RTR J AN S ST 5 BENWOOD DR 2,000 ST ST ON S R CY P CE 1,000 1 inch equals 2,000 feet LE M T A S ERT CHA SAB DINA T LPHIA INA S A DE E LM ± 0 T TH S NOR PHIL ST ALB R ES OHIO N A ST IS ST SANTA A NA S TEDMAR AVE LN T ST ALEXIS AVE Y FA INDIA ELM AVE TER CL A U T MABLE ST BROADWAY E ST ST PINE Y S ST WA A NS H ST Y J RE S WA E A DIAMOND ST VE LINCOLN AVE ST PAMPAS LN WILH ENTIN NE T ON S PEARL ST HIR CE N CL E M PI CITR T ST EMBASSY ST WAY Raymond Basin LA PALMA AVE ZEYN T T ON S EL S ST S NS S ORE CAM IR LN BALSAM AV E JULIANNA AVE S DR MILL LE M DICK NA S HE L E JA A ST ERT A LB SY K PAR H ST DR WES TEDMAR AVE LS EER O ILLIN ELM PL WI ) S ST 01 JANS BIRCHMONT DR PINE EMBASSY AVE WEDG EWOO D RE S 1P Z DR (B 0 ST Dr ai n TER PENHALL WAY 5 WIN St or m PION 5 AVE LEN M EL ST HIAWATHA AVE 5 DR MALL AVE im PARK AVE CRESCENT AVE GEFA ORAN 91 COMMERCIAL ST JULIANA ST WAY KEN WAY JADE DISCOVERY LN 91 VICTOR AVE NORTH ST N WA RO TRANSIT AVE DIANE WAY he DR LIDO PL Carbon Creek (B01) na GE R DR CATALINA AVE W es tA RED CLA E DWY December 9, 2009 M DR AM R ALAMEDA AVE CATALPA DR DR DR \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps HY AC BE MARIAN AVE ek ( Crescent Basin BROWNWOOD AVE AVE BROADWAY GRAMERCY AVE CRESCENT AVE B0 1 ) CATALPA AVE CATHERINE DR DR ACADEMY AVE PL 5 CATALPA AVE FRANCES DR NT TOLA AVE 5 RE SD N G LE EN LN LODGE AVE LANCER re on C LINCOLN AVE LEVEL FIR AVE D MO MHP DOGWOOD AVE ST Ca r b GLEN AVE WE ON CT 11 MALBORO AVE PALMA AVE GREENACRE AVE GLENCREST AVE 13 ME R VALDINA AVE ARLINGTON AVE SUM GLENOAKS AVE FALMOUTH AVE 91 CANARY ST CHEVY CHASE DR ROMNEYA DR AY TW EN YALE AVE MORO PL WAY 91 R DR L CENTE MEDICA NET AV E SC TYLER AVE RAINBOW AVE CORO E CR BRUCE AVE CATALPA AVE MA GREENBRIER AVE ER GROTON ST FALMOUTH AVE AVE WAY BAYLOR AVE CA M FULTON ST GRAYSON AVE VIA PA L SEQUOIA HOLLY SIESTA ST ALAMO ST ST 10 5 LA TAMARACK 91 CORONET AVE EUCLID ST 91 CORONET AVE MORAGA ST R D D 2) 91 GILB ERT FERNDALE ST DEVONSHIRE RD ELMIRA ST BRAEBURN ST CIR LA N D O O W 3S 0 ORANGEFAIR MALL T ST 5 WOODLAND DR (A 0 15 DURST ST EA S BLUEBELL DR ne l DR KNOLLWOOD Cha n AETNA ST MAGNOLIA AVE DALE AVE t on MARINER PHLOX DR R HOUSTON AVE PARKSIDE LN CARNATION DR KE PARLDALE LN Hou s AVE ORANGETHORPE AVE CIR 5 BA PECKHAM ST ORANGETHORPE AVE A03S05 RAYMOND AVE 03) LEMON VIA ne l (A WALNUT VIA SPRUCE VIA CYPRESS VIA C h an AMERIC AN r eek LEMON ST rton C ST Fulle ORANGETHORPE PARK Basin 15 TH SOU ST Figure 1 Study Area Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area Legend Drainage Basin 5-1 Drainage Area Anaheim City Limits 15-2 FREEDOM AVE LIBERTY AVE ORANGETHORPE AVE GEMINI PL (B OLIVE ST Ca rb on Cr ee k HOMER ST SWAN ST PATT ST 01 ) RALEIGH ST RIVIERA ST VILLAGE WAY KEMP ST CIR WALNUT ST LOARA ST SONYA ST RAVENNA ST CITR ON D 42 N ROBIN ST WAY CHE RRY LIDO ST LAGUNA ST LIDO LN EUCLID ST LOMITA ST ARBOR ST DRESDEN CROWN ST HERMOSA DR MOHICAN AVE W AY EUCLI D FLORETTE ST HACIENDA ST BROADVIEW ST ECHO ST EMERALD ST NUTWOOD ST FAIRHAVEN ST MANOR ST RT CRESCENT WAY BA YP O MULLER ST DAHLIA DR AGATE ST MAYFAIR AVE DR MOHAWK AVE IROQUOIS AVE ONONDAGA AVE WICHITA ST FAIRVIEW ST HOLLY ST GARDEN ST CAROL DR BERNIECE DR ALADDIN DR EMPIRE ST LOMBARD DR HO US LEN LI G HOLLY ST HT CHIPPEWA AVE VALLEY ST VALLEY ST BROOKHURST ST BIRCHER ST KATHRYN DR SIESTA ST MONTEREY ST VENTURA ST LINDSAY ST ARCHER ST FANN ST MAPLE ST COLUMBINE ST SIESTA ST VENTURA ST MONTEREY ST ALAMO ST MORAGA ST DORIA ST GILBERT ST PL BAKER ST TOPO ST MONUMENT ST HAMPTON ST ARON ALAMO ST HAMPTON ST HARCOURT ST 1) k( B0 ee Cr n rb o Ca STINSON ST MAPLE ST LOTUS PL CATALPA AVE LOTUS ST GROTON ST FULTON ST SIESTA ST MONTEREY ST ALAMO ST GILBERT ST FERNDALE ST ROANNE ST GENEVA ST MODENA ST HANOVER ST FELICIDAD ST MAGNOLIA AVE AURORA ST NANCITA ST LA PERLA ST LA REINA ST COLORADO ST DEVONSHIRE RD ELMIRA ST CIR KNOLLWOOD WAY K GUAVA AVE HICKORY DR H EM LO C BRAEBURN ST DALE AVE WAY SYRACUSE ST CIR GAIN ST E ST Y ST EMIL ST TROJAN ST ST VE TH A WOR TH S S OU T ST R ST ISON Z EYN ELLS VINE ATCH NA TA A T T NTIN T T ST 5 NA S EL S DICK H E LE S ST PINE H ST JANS R ES E CLEM ST ST DOYLE DR ST COLGATE ST VINE E ST RO S INA S SA N EGE ME L DALE AVE ST ITTY T CC ES S RTR K RO T HIA S DELP ON S EL ST D CLAU AY AD W M ST A PHIL ST LE M BRO A EC ST BUSH ST CHA S ST OAK R ST NTE E ROS LN ST S ST E OLIV Y EMIL E RTR ST ST IS ST ST CHA 2,000 VINE MAV E ST T LPHIA BLVD T RE S 1,000 AFTON ST TER CEN OHIO T OIS E AV TEDMAR AVE NA S ILLIN LN INDIA Y FA IN PAUL INA S A DE ST ON S E ST E ST MO R CY P ± 0 1 inch equals 2,000 feet T SAB PHIL DINA LE M ENTIN ST PINE S ST A NS H ST Y J RE S WA BLVD T N SE CL A U HEIM ANA CL E M BO R S NS A S YC Raymond Basin S EKA TOP Y ST EMIL T T HA R JA DIAMOND ST ST TER CE N DR ST EL S NA S ZEYN DICK HE L E S ST AVE R ALEXIS AVE T A S ERT CE TE ELM AVE ALB PEARL ST 5 MABLE ST H ST BALSAM AV E Feet S MILL ST ST 1) LINCOLN AV E PAMPAS LN JANS P0 ST 01 l (1 2x WI 7 RC L S B) H IR E ON S (B WEDG EWOO D era OHIO Dr ai n Lat DR EER PION T TA S R E B AL CITR orm ek WAY KEN WAY JADE PARK AVE ST T NOR H ST RE S St RN E PINE ST im Cre E LA V T ST TEDMAR AVE LIDO PL ES ELM PL he ) H AVE 5 on JULIANA ST W ES na Ca rb VICTOR AVE DR C VICTORIA AVE M EL W es tA DIANE WAY HIAWATHA AVE 01 k (B CRESCENT AVE ALAMEDA AVE BROWNWOOD AVE e Cre bon Car GE AN M DR AM R 5 Crescent Basin CATALINA AVE CATALPA DR CATALPA AVE 11-5 RED CLA DR M MARIAN AVE 5 CATHERINE DR N A UTUM DR TRANSIT AVE Broadway Storm Drain (B01P08) CATALPA AVE FRANCES DR N WA RO MALL AVE 11-1 5 December 9, 2009 HY AC BE AVE LEVEL CHAIN AVE LA PALMA AVE DR N G LE R ER D DWY MHP ST AVE GLEN DR \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps NEIGHBORS AVE LODGE AVE Z DR GREENACRE AVE LINCOLN AVE PL MALBORO AVE 11-3 DR E R O H S Y A B LN LEN VALDINA AVE 11-8 11-7 11-6 11-4 AV E 13-1 R TER GLENOAKS AVE ON CT O RB HA S NUG 91 COMMERCIAL ST WIN GREENBRIER AVE ER NET AV E GLEN AVE UOIA ARLINGTON AVE T ST 10-3 CORO IR LN 91 CANARY ST LANCER VICKI LN GRAYSON AVE SEQ 91 CHEVY CHASE DR FALMOUTH AVE 5 BRUCE AVE YALE AVE ACADEMY AVE 11-2 A WAY KENDOR DR 10-2 CRESCENT AVE CA M TOLA AVE 10-1 GEFA ORAN 91 91 91 NET AVE CORO M HOLLY TYLER AVE 91 5 RAINBOW AVE TAMARACK BAYLOR AVE SA VE 2) CORONET AV E L PA VIA OD E 3S 0 DISCOVERY LN OOD BELLFLOWER DR RH WOODLAND DR (A 0 DURST ST E AS BLUEBELL DR 10-4 5-1 ne l 15-5 BRIARW PHLOX DR Cha n ORANGEFAIR MALL MORAGA ST R CARNATION DR AVE t on AETNA ST KE HOUSTON AVE PARKSIDE LN LEMON ST BA Hou s 15-6 15-4 15-1 PICADILLYWAY PARLDALE LN 15-3 ORANGETHORPE AVE PECKHAM ST 5 A03S05 RAYMOND AVE 03) LEMON VIA ne l (A WALNUT VIA SPRUCE VIA C h an AMERIC AN r eek LEMON ST rton C ST Fulle ORANGETHORPE PARK Street Right of Way ST Figure 2 Drainage Areas Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area Legend Anaheim City Limits Street Right of Way Proposed Storm Drains Priority 1 Priority 2 Priority 3 Existing Storm Drains ) ) 30 Anaheim (Pipe size in inches) RAYMOND AVE HARBOR BLVD 36 LEMON ST 60 36 51 ORANGETHORPE PARK SD 15-4_01 (P) 42" 48 1) k( B0 30 KEMP ST 66 51 18 ree nC HOMER ST SWAN ST 54 6'3" X )) ( ! ) 24 IR C 18 48 NE CA 24 21 24 18 () )! ) ( ! ) ) ! ( ) ) ! ) ( ( !! ( 18 ( ! ) )! () ) ( ! )) ) ( ! )! ( ) ( ! ) ( ! 75 75 )) ( ! ) ) ( ! ) ) !) ( ( ! ! ( ( ! ) ) ) ) ) ( ! )! () ) )! ( ( ! ) ( )! () ! ( ! 30 RALEIGH ST 24 VILLAGE WAY 18 36 WALNUT ST SE 42 3'3" RIVIERA ST 24 30 RAVENNA ST CITR ON LOMBARD DR LIDO ST LAGUNA ST 33 REDONDO EUCLID ST MAYFAIR AVE DRESDEN 48 51 FAIRHAVEN ST MANOR ST PARKWOOD ST FANN ST LIDO LN MOHICAN AVE CHIPPEWA AVE FLORETTE ST HACIENDA ST BROADVIEW ST 36 21 NUTWOOD ST ECHO ST EMERALD ST 69 42 CRESCENT WAY MULLER ST DAHLIA DR CAROL DR BERNIECE DR ALADDIN DR EMPIRE ST 72 36 33 FAIRVIEW ST GARDEN ST VALLEY ST 30 SIESTA ST 51 LOARA ST RF 27 HOLLY ST SU 24 MAPLE ST LOTUS ST SD 13-1_01 (P) 36" 72" SD 11-2_01 (P) 60" 60" 54" GROTON ST FULTON ST SIESTA ST ALAMO ST VENTURA ST 27 36 PRIMROSE ST AGATE ST M AM rb o FERN ST MORAGA ST 48 GILBERT ST 48 ee Cr 36 30 GENEVA ST ROANNE ST MODENA ST HAMPTON ST CAMBRIA ST HARCOURT ST HANOVER ST 54 57 1) k( B0 COLORADO ST LA REINA ST COLGATE ST SYRACUSE ST FELICIDAD ST NANCITA ST LA PERLA ST AURORA ST GUAVA AVE HICKORY DR n R CAMELLIA ST ) 36 48 48 1 24 8 2 75 4 75 75 ) ) ( ! T 24 ( ! 188 1 ( ! ( )) ! ( ( )! ! )) ) 24 78 !) ( )! ( ER S WAT 42 GAIN ST 21 BE AC HY PL BAKER ST ) ) ) ( )! Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area ST NA TA A SA N ) ! ( ) ) () ! ( ( ! )! 30 24 MAGNOLIA AVE E ST Ca ( ! )) ( ! )) ! ( ( !! ( ) R ST STINSON ST 30 24 () ) )! ()) ( ! ! 30 30 ) )! ( ( ! 30 48 54 36 TROJAN ST !) ( ) ST N ST DOYLE DR ) ) ( ! )) EGE K RO LLIP 39 ( ! ) ( ! ( ! )) E OLIV LEM O ) () ! ) ) ) ST 72 69 ST PINE ) ( ! ) ) ( ! ( ! ) () ! Y ST EMIL 57 ) ! ( ) ) ) Z EYN ) ! )! ( ( ) ) 30 18 ST 18 )) ! (( ! ) T INA S )) ( ! )) ( ! ) ) ( ! ) ) 24 ! ( ) E LM 36 D CLAU 6 36 3 ) ROS ME L 49" E 15 Figure 3 Proposed Improvements ( ! ) ! ( ( ! ) !) )( ( !! ( 48 ) ! ( ) ) ST 42 !) ) ( ) ( ! ) 30 39 Feet 1 inch equals 2,000 feet sn i e l1 a u q ch fe ,0 2 t 63 63 48 ( ! ( ! 30 D 42N ( ! ) () ! !) ( ) ( ! 2,000 !) ( )) ) ) ( ! ( ! ) () )! ( ! () )! 24 18 36 )! ( 54 12 ( ! ) 57 57 ( ! ) 18 ( ! ( ! ( ! ) ( ! ) () ! ) ) ! ( ! ( ( ! ) ) ) ) !) ( 18 78 78 24 () )! ) ( ! () ! ) ! ( ( (! ! ) 1,000 ) ) ( ) ! ) ! ) ( ( (! ! ) ) ) ) ) () )! 90 ) 6 () )! ( ! ) )) ( ! ( ! ) ( ! E ST ENTIN T CLEMICKEL S D T NA S H E LE DALE AVE 0 27 18 42 18 42 18 45 57 ) ! ( ( ! ) AY ADW S ST VICKI LN ! ( ) ) D ST E ST B U S H EA ROS -H O ST VINE "L 42 VINE ST IS ST Y ST EMIL KENDOR DR ) X MAV E ST 33 ST ) )) 33 90 93 93 () ) ! ( )! ( ! ) ( ! () ! ) ( ! !! ( ( ) ± ) ) ) 30 ) ) )! ( ( !) ) )) !) ( ) ) ( ! ) ) ) !) ) ( ( (! ! ) T KA S ) !) ( 33 ST 93 ) ) IN PAUL A ST DINA ) ! ( ) ( ! E TOP SABIN ( ! ) ) 33 ! ( ) 39 LPHIA AD E PHIL ) () ! ) )) ) ( ! ST ( ! ) ) ( ! ( ! 33 32" X ) ( ! ) ( ! 93 H ST R ES 5 BENWOOD DR ) ) !) ( 12 ) ( ! ( ) ( )! ! BR O ST ( ! ) S DR C LA U ! ( ) JANS ) ) ( ! ! ( 42 ( ) ! ) () )! 36 ( ! ) ) ) ( ! ) ( !! ( ) ) )) ( ! T 27 ( ! 27 18 247 2 24 42 N Y L FA ( ! TEDMAR AVE ( ! ) ( ! ALEXIS AVE 48 ) ( ! ST ) )) ( ! ZEYN ) ) ! ) ( ) ) T ON S E ST ENTIN )! () LE M 18 ) ) ( ) ! 24 ! ( ) MILL () ! ) ) S RES CYP 3 ) 24 36ELM AVE ) ) )! ( ) 42 ) ( )! ) ) ) )) ) ) () )! ) 93 ( )) )! )) ! ( ( ! ) ) ( ! ) () ) )! ( ! ) 2' 7' x 1 )) ) T T RE S A M O A DE L E S SY C 93 9 ) 24 ) ) Proposed Pipeline ID Drainage Area_Line No. (Proposed) 30 Raymond Basin ) )! ( ) A ST ERT ALB 30 ( ! DIAMOND ST CL E M ) ( ! T ) ! ( EL S 36 ) ) ( ! ) 24 BALSAMAV 48 E ) DICK ) ) ) ( ( ! ! ! ( )) ) 36 ( ! T 42 ) ) ( ! ) Basin 15 SD 5-1_01 (P) ) ) Basin 13 91 JULIANNA AVE ) ) ) OHIO E ELM AV TEDMAR AVE ) ! ( 27 18 ) ) ( (! ! ) ( ! PEARL ST ) NA S 54 ) )) ( ! ) ) )) ( ! ) ( ! 24 ) 42 )! () ( ! ) 36 18 ELM AVE 18 !) ( ) ! ( ) (! ! ( ) RC WI B) LS HIR E AVE )! ( )) Y ) ) K WA PAR ) ( ! !) ( NA S INDIA 78 ! ( ) )) ( ) ! ST ( ! 2x7 MABLE ST ) ( ! ) ) ( ) ! ) ( ! !) ( ) )) ! ( ! (( ! ) ) ) ( ! !) ( ( ! LINCOLN AV E PAMPAS LN R ) ( ) ! ST ) ! ) ( ) 12 () ! ) OHIO ( ! 4 DR ( ! 30 ) ( ) ! ( ! OR ANGEFALN IR Basin 11 ( ! ( ) ! ST ) !) ( ) ) ( ! ) ) ST PINE 27 Y S ST WA A NS Y J NE T WA PI HS S RES NS JA ST ) ) ) ( ! ) H ST ) ) ) l (1 ( ! 30 OD ) ) ( ! ) S ST ) 10' X 6' 10' X 6' ) ( (! ! ( ! (! ! ( ) N WAY)!( KED JA E ST ERTA ALB ) ) ) ( ! 33 ) () ! ( ! D EER PION GEW O ) JANS ( ! ) ) ) ( ! ) ( ! PINE ) ( ! ( ! 36 2' T 7' X 1 TH S NOR WAY RO W AN 2 27 !) ( T NE S ) ) ST DR 90 ( ! ) ( ! ) ! ( ) ( ! OIS December 9, 2009 MARIAN AVE ) ) ) ILLIN ( ) ! ) )) ) ( ! ) ( ! ( ! PARK AVE ( ! ) )! ( 42 57 ( ! ek ) ) ER LA V E AV ( ) ! ) Broadway Storm Drain (B01P08) ) ) Cre WE D ) ) WESTMONT DR ) ) ) ) on ) ) L BEVERLY DR 5.0' x 3.0' ater a 01 ) ) ) () ! )) ( ! ) 5 ) ! ( R ) ) ( ! ) () ! ) ( ! ) Ca rb ) ) ( )! () ! ) )) ) ( ! )) ) )! ( 1P M TE ) )! () 93 ( ! ( ! ) ( ! (B 0 )! () ) ) ( ! ) !) ( ) 16 ' ) DR ) ) LIDO PL TU ) A)U 5 \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps ( ( ! ! ) ) ) ) () ! k( 1 B0 ) ) ( ! () ! ) ( ! N DR ES H ( ! ) ( ! HIAWATHA!( AVE !) ( ) ) () ! ( ! 66 Dr ain 7. 25 'X C MALL AVE ) !) ( ) ) ( ) ! ) 24 18 ) ) ) ! ( ) () ! ) ) TRANSIT AVE () )! 96 93 ) DIANE WAY ) ) )) ( ! ) orm ) ) ) ) )) ( ! ) ( )! ( ! RO N ) CATALINA AVE St ee Cr on ) )) ) 42 ) 18 im ) ( ) ! 33 LEVEL AVE CHAIN AVE ALAMEDA AVE he ) ! ( AN ) ) na rb Ca ) ) ! ( M ( ! ) ( ! ) ( ) )! W es tA ! ( ) BROWNWOOD AVE ) ) ( ! () ! 60 96 ) )) ( ! ( ! 36 ) ) ) )! () ) ! ( 5 AVE TOLA ) ) ) ) ( ! LINCOLN AVE GREENLEAF AVE CRESCENT AVE CATALPA DR CATALPA AVE Crescent Basin ) ) ) ) ! ( R E D ED G ) CLAR ) ( ! 30 18 30 ) RE S ) ) FRANCES DR FRANCIS DR DR CATHERINE ) 30 24 ) ( ! 21 2' X 6' ( ! 42 ) ) 5 36 SD 11-1_03 (P) 42" ( ! ) ! ( ) ( ! COMMERCIAL ST ) ( ! ) ( ! ! (( ! ( ! ( ! ( ! IT 12.0' C 2.0' 1 7.0' x ! ( ) ) ) ( ! ) ) )! ()) ! ( ) ! ( ) ) ( ! ) JULIANA ST 7.0' X 24 ) ) !) ) ( ) ) ) ) ! ) ( ) ) )! ( MHP ) ) ) ) ( ! ( ! )! ( ) ST YALE AVE ) ) ( ! ( ) ! )) ( ! )) )! () YER D W DR ) ! ( ) ! ( ) )! ) ( 57 27" X 42" ELLIP TYLER AVE !) )) ( ( ! () )! BRUCE AVE ( ! 45 DR DR ) 18 18 SD 11-1_02 (P) 48" GLENOAKS AVE ) 30 ( ) ! ) ME RO CTN!() FIR AVE ) !) ( GLENCREST AVE ) 33" DOGWOOD AVE ) ) ) () ! ) ) ) ( !! ( ) SD 11-1_01 (P) 42" N GLE VICTOR AVE Z DR BAYLOR AVE 36 54" DOGWOOD AVE VALDINA AVE ( ! )! () ! ( ) ROMNEYA DR ( ! ST GLEN AVE LANCER )) ) CA ) ) GLENOAKS AVE ) ! ( ) ( ! ) !) ( ( ! 66 ) ) ()) ! 54 ( ! LEN ) ) ) ) ) )) ( ! ) ) ( ) ! ) ) !) ( 36" LN ) TER HOLLY 42 36 ) () ! ) ) )! () ) ! () ) ) T ST )) Y WA )) ) ( ! )! ( 39 W ES ) W GREENBRIER AVE SD 5-1_04 (P 5 ) AD O LN ) ) ) )) ) ) SH SD 13-1_03 (P) !) ( ( )! 91 54 ( ! ( ( ! ! (! ) ) ( ! 36 24 ) WIN TAMARACK 60" Replacement E ) ( ! )) ()) ! ) ) ) ) 42 !) ( ( ! ) MALBORO AVE 36 ) )) ) HOLLY ST ) RAINBOW AVE !) )( ) ( ! ( ! ) ) ( ! ( ! Basin 10 " 27 ) (! () )! ) ) ( ! ( ! ) ) ! ( )) ( ! SD 11-1_01 (P) 60" ) ) 42 SEQUOIA AV 63 ) ) ) ( ! ) ( ) ! ( ! ) ) ( ! ) ) ) ) ) ( ! 9!( 1 CANARY ST 42" (P) SD 13-1_02 ) ) ! ( ) ) HELE SD 5-1_03 (P) ) ( ( ! ! ) ) 01 (P) CORONET AVE ) ! ( ( ! ) ( ! DURST ST 42 ) (! ! ( ) ) ) ) 45 ( )! ()) ) ) ) ! ()) ! ) ) )! !) ( ( ! ) ) ) ) (( ) ! ) ) ) ) ) LINDSAY ST ) ( ! lle l ( ! ) ) ( ! ( ! ) ) 27 ) ) ) ) ) ) SD 11-3 _ LN DISCOVERY ) ( ) ! ) 51 ) ! ( )) BROOKHURST ST ) ) 5 ( ! 42" 24 ) ( ! ) 42" Parallel AVE (PFALMOUTH ) 3 6" ) Basin 5 ) ( ! 42 ) ! ( ) 54" Parallel 48" Parallel GRAYSON AVE _01 ) ! )) ( ar a ) ( ! SD 15-1_01 (P) 42" T ST !) ( LA PALMA AVE HOLLYOAK ST ALAMO ST MINOT ST 36 36" 36" KATHRYN DR RAN CHIT O ST 42 SD 102 )) Drainage Basin EA S ) MORAGA ST GILBERT ST ) ) WOODLA ND DR ) () ! ) ! ( ) MONTEREY ST ( ! AETNA ST ( ! ) () )! Buena Park ( ! ( ! Lateral ) ( ! 24 ) 60 "P 91 CHEVY CHASE DR 30 36 WAY BELLFLOWER DR ) 91 3.0' 48 BLUEBELL DR ) )) ) 91 ) DR PHLOX DR ( ! 60 KNOLLWOOD CIR ) ) ET AVE CORON X 5.5' 54 CARNATION DR 91 CORO N ET AVE SD 10-1_03 (P) 42" SD 1 0-1_0 2 (P ) 48" 24 Parallel SD 5-1_02 (P) 54" ) ) DEVONSHIRE RD AVESD 10-1_01 (P) 60" 60HOUSTON " ( ! PARKSIDE LN ) ( ( ! ! 02 ) 36 ( )! R AVE 39 69 ELMIRA ST ) 3S KE 48 DALE AVE 54" Parallel A0 ( ! 36 SD 5-1_01 (P) ) 5 ( ! BRAEBURN ST ( ! ( ! BA FERNDALE ST 6'x4' RCB ( ! ) 60 6'x6' RCB ne l( ( !! ( ) SD 15-1_02 (P) 36" Parallel !) ( ( ! ( ) ! ( )! ) BIRCHER ST ) ) ( ! FREEDOM AVE !) ( ORANGETHORPE AVE 48 27 ORANGETHORPE AVE Ho ust on Ch an 91 PECKHAM ST ) A03S05 Private 48 03) rbo ne l (A Ca C h an OLIVE ST r eek Caltrans 33 ) rton C 72 ) 66 Fulle ) SD 15-1_03 (P) 36" Parallel County ( ! ) ( ! ) )) 2. Introduction 2.1 Purpose The City of Anaheim Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area (FCTA) covers that portion of the City of Anaheim ultimately tributary to Orange County Flood Control District (OCFCD) regional facility Fullerton Creek Channel (A03). The purpose of the Master Plan is to provide comprehensive long-range planning for the implementation and development of drainage facility improvements in the area, determine the cost of implementing the facilities, and discuss funding priorities of the improvements. This Master Plan is based on the criteria outlined in the City’s Drainage Manual for Public and Private Drainage Facilities, dated August, 2005. 2.2 Background In 1973, the City published a Master Plan of Drainage for the City of Anaheim. That report divided the City into 42 Drainage Districts based generally on local storm drainage facilities and the City limits at that time. In 1983, two additional Drainage Districts were added for a total of 44 Drainage Districts. Since that time the City limits have changed to include more tributary area and the City has changed its drainage classification system to watersheds which relate to the County of Orange’s regional drainage facilities. The City of Anaheim is divided into seven major watershed tributary areas; Santa Ana River, Carbon Creek Channel, East Garden Grove-Wintersburg Channel, Anaheim Barber City Channel, Fullerton Creek Channel, Stanton Channel, and Moody Creek Channel. Each of these watersheds include several of the Districts from the 1973 Master Plan. The FCTA includes Drainage District’s 5, 10, 11, 13, and 15 from the 1973 Master Plan. These areas are identified as Drainage Basins instead of Districts for this Master Plan and are shown on Figure 1. The boundaries of some of the basins have been modified from the 1973 Master Plan boundaries. Figure 1 shows the new boundaries, and all references to areas in this Master Plan are based on the new boundaries. As shown on Figure 1, Drainage Basins 5, 10, 11, and 13 are generally bounded by the 91 freeway to the north; West Street to the east; a few hundred feet south of La Palma Avenue to the south; and Dale Avenue to the west. Most of the flow from these Drainage Basins drain to Houston Channel which is tributary to Fullerton Creek Channel. Basin 5 drains to a Caltrans Facility tributary to Fullerton Creek Channel. Drainage Basin 15 is generally bounded by Fullerton Creek Channel and the northerly city limits to the north; Raymond Avenue to the east; the 91 freeway to the south; and Lemon Street to the west (See Figure 1). The majority of flows from Drainage Basin 15 drain to a storm drain in Orangethorpe Avenue and Lemon Street which outlets to Fullerton Creek Channel to the north. A few small areas drain to A03S05 which outlets to Fullerton Creek Channel. 9 3. Technical Criteria 3.1 Hydrologic Analysis The hydrologic analysis for the City of Anaheim Master Plan of Storm Drainage for FCTA was performed in accordance with the City of Anaheim Department of Public Works Storm Drainage Manual for Public and Private Storm Drainage Facilities, dated August of 2005. The City of Anaheim has adopted the 1986 Orange County Hydrology Manual (and the subsequent Addendum No. 1 to the Hydrology Manual, issued in 1995), except for the modifications outlined in Division 1 of the City’s Manual. The modification affecting hydrology includes the requirement that the analysis of all storm events be based on the “high confidence level” storm frequency event. This criterion was used for the Master Plan. The methods, data, and criteria integrated and incorporated are consistent with accepted methods of analyzing storm water runoff throughout Orange County as outlined in the Orange County Hydrology Manual. GIS Facility Maps and AutoCad drawings were obtained from the City, which contained streets and existing facilities for the FCTA. Drainage Basins were delineated based on the 1973 drainage maps. A field review was then conducted, and the drainage patterns were further refined. Land use data was obtained from the City of Anaheim’s October 2008 General Plan and soils information was obtained from the 1986 Orange County Hydrology Manual. Land use, soils information and subarea information was input into the Advanced Engineering Software Computer Program RATOC which is based on the 1986 Orange County Hydrology Manual. 3.2 Hydraulics Analysis Storm drains and street flooded width analyses were performed in accordance with the City of Anaheim Department of Public Works Storm Drainage manual, dated August of 2005. The existing drainage systems were analyzed using computer analysis techniques that consisted of the storm drain analysis program, Water Surface and Pressure Gradient Hydraulic Analysis System (WSPG), originally written for use by the Los Angeles County Flood Control District. WSPG is a hydraulics program that can be used to determine the capacity of a storm drain system. The computational procedure is based on solving Bernoulli’s equation for the total energy at each section and Manning’s formula for friction loss between the sections in a reach. Confluences are analyzed using pressure and momentum theory. The program uses basic mathematical and hydraulic principles to calculate such data as cross sectional area, wetted perimeter, normal depth, critical depth, pressure, and momentum. The proposed storm drains were sized using the WSPG program and FlowMaster. Relevant storm drain information such as pipe sizes and invert elevations were obtained from storm drain improvement as-built drawings. 10 The hydraulic analysis performed assumed that the streets would be free and clear of any major obstructions and that the storm drains would be adequately maintained so that blockage would not occur. Street capacity analyses assumed that all streets conformed to the City of Anaheim’s typical street sections. Street widths were determined from street plans and as-built drawings. Based on the technical criteria outlined in this chapter, preliminary sizes of the Master Plan facilities were determined. The hydraulic control for calculations typically assumed that the water surface elevation was one foot below the ground surface. For lateral storm drains, the hydraulic control was taken from the water surface elevation of the major storm drain at the point of confluence between the drains. 3.3 Downstream Boundaries The FCTA is bordered on the north by the 91 freeway and the Houston and Fullerton Creek Channels, which coincide with the City Limits. This study evaluates the capacity of each facility up to the City limits. The approach for the proposed hydraulics at the boundary of the City limit is to recognize the adjacent agency’s downstream capacities. The drainage facilities along the 91 freeway are Caltrans facilities. As-built drawings were obtained for Caltrans facilities and used to determine the downstream control. The Houston and Fullerton Creek Channel are OCFCD regional facilities. Hydraulic reports for the Houston and Fullerton Creek Channels were obtained to determine the downstream control. In this study, when existing downstream facilities are determined to be unable to convey the flow from the City of Anaheim’s master plan storm drain at the City limits, excess flow at the City boundary is proposed to be resurfaced onto the street through equalizers. 11 4. Drainage Basin 5 Drainage Basin 5 drains approximately 360 acres, and is generally bounded by the 91 freeway on the north, the I-5 freeway on the east, a few hundred feet south of La Palma Avenue to the south, and Dale Avenue on the west. As shown in Figure 4, drainage basins are further divided into drainage areas depending on the existing flow patterns and storm drain outlets. Since the entire basin drains into the same system, Basin 5 consists of only one drainage area, Area 5-1. Generally, storm water flows from the southeast to the northwest to a storm drain in La Palma Avenue. The storm drain turns north on Magnolia Avenue to the Interstate 5 freeway and parallels the 5 freeway where it then ties into a Caltrans facility at the City limits with the City of Buena Park. 4.1 Hydrologic Analysis The hydrologic analysis for Drainage Basin 5 was performed in accordance with the hydrologic criteria outlined in Chapter 3 and is included in Appendix C. The hydrology map for Basin 5 is included in Appendix B. The following table highlights the flow rates at the key drainage nodes for Area 5-1 in Basin 5. The table shows associated drainage areas and flows for 10-, 25-, and 100-year storm events. Table 1 – Basin 5 Summary of Hydrology Area Node 5-1 508 5-1 5-1 Location Drainage Area (ac) 10-Year Flow (cfs) 25-Year Flow (cfs) 100-Year Flow (cfs) La Palma Ave and Magnolia Ave 118 125 160 220 509 Magnolia Ave and Woodland Dr 143 155 195 265 513 Dale Ave at 160 ft South of 91 Frwy Onramp 356 380 480 665 4.2 Analysis of Existing Improvements Storm water in Area 5-1 is conveyed through two storm drains. One drain begins approximately 1000 feet west of the I-5 freeway in La Palma Avenue. The drain flows west, then turns north in Magnolia Avenue, where it continues to the I-5 freeway. The drain turns northwest, and follows the I-5 freeway to the 91 freeway. Then the drain turns west and flows in an alley towards Dale Avenue. Approximately 500 feet east of Dale Avenue, the drain joins an existing Caltrans facility that continues west to Dale Avenue. At the junction with the Caltrans facility, a parallel storm drain branches off and continues west to Dale Avenue. At Dale Avenue, the parallel storm drain joins the Caltrans facility. At this point, the drain enters the City of Buena Park. This drain captures runoff from the eastern and central region of Area 5-1. This drain varies in size from 33-inch to 78-inch reinforced concrete pipe (RCP), and can convey a maximum of 145 cubic feet per second (cfs), which is nearly equivalent to a 10-year storm event. The existing hydraulic calculations for Area 5-1 are included in Appendix D. 12 The second storm drain begins approximately 1000 feet north of La Palma Avenue in Knollwood Circle. The drain flows north for approximately 1200 feet, then turns west for approximately 200 feet, then enters the City of Buena Park and ties into a Caltrans facility along the 91 Freeway. This pipe varies from a 48-inch to 54-inch RCP, and can convey a maximum of 80 cfs which is equivalent to a 10-year storm event. This drain captures runoff from the western portion of Area 5-1. 4.3 Proposed Improvements In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains, and also to satisfy the flooded width criteria, the following improvements are recommended and shown in Figure 4. The hydraulic calculations are included in Appendix E and the street flow calculations are in Appendix F. In order to satisfy the City’s 10-yr storm event and flooded width criteria, the storm drain in Sequoia Avenue must be extended 540 feet east. This extension is proposed to be a 33-inch RCP. In addition, a parallel relief drain varying in size from 42 to 54-inch RCP is recommended to relieve some of the flow in the La Palma Avenue and Magnolia Avenue drain. This proposed relief drain is intended to relieve a maximum of 65 cfs from the existing facilities, taking flow from the area south of La Palma Avenue and will extend to Dale Avenue for a total of 8,315 feet. 4.4 Cost Estimates The estimated costs summarized in Table 2 include costs for construction, engineering, design, surveying, and construction management. Pipe costs are per linear foot of pipe and have been increased to include excavation, shoring, bedding, backfill, compaction, removal of excess material, and trench resurfacing. The detailed cost estimates for Basin 5 are included in Appendix A. Since the construction of the recommended facilities will be spread out over a number of years, the total cost of master plan implementation will be subject to future construction cost increases. Therefore, it is recommended that the funding programs established for implementation of the Master Plan of Storm Drainage make provisions for the increased cost of deferred construction. Inflation factors should be applied to reflect a specific year’s total cost over the 2010 total costs. Summarized in Table 2 are the construction cost estimates by project location for Area 5-1 in Basin 5. Table 2 – Basin 5 Cost Estimate Area Storm Drain ID 5-1 SD 5-1_04 (P) 5-1 Type of Facility Length (feet) Sequoia Avenue Extension 33-inch RCP 540 SD 5-1_03 (P) La Palma Avenue Parallel Relief Drain 42inch/48-inch/54-inch RCP 2,990 $ 4,423,000 5-1 SD 5-1_02 (P) Magnolia Avenue Parallel Relief Drain 54inch RCP 2,770 $ 4,577,000 5-1 SD 5-1_01 (P) Magnolia Avenue to Dale Avenue Parallel Relief Drain 54inch RCP 2,550 $ 4,227,000 TOTAL FOR BASIN 5 Street Estimated Cost (2010 Dollars) $ 547,000 $13,774,000 13 ) ) ) Legend Anaheim City Limits 5-1 Drainage Area Street Right of Way ) ORANGETHORPE AVE ) ) Priority 1 Priority 2 Priority 3 ) Existing Storm Drains BAKER AVE 91 30 ) ) ) ) \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps RUSSELL PL December 9, 2009 CORNELL AVE 18 STANLEY AVE ) RUSSELL AVE ) ( ! 18 ) () ! () ! LN 4' X 5' E US HO HT LIG RE D R FA LM OU TH AV ) E ED R ) ) ( ! ) ) ( ! ( ! ) ( ) ! ) 24 SHO ) ( ! ) ANA KEYSTONE ST 0 FAIRVIEW ST E AV IVY LN BROOKHURST ST R FI ( ! CRESCENT AVE 48 ) ) ! ( bon ek C re 1) (B 0 AF A V E ) GRAMERCY AVE West Anaheim Storm Drain (B01P01) ) NL E Carbon Creek (B01) ) ! ( ! ( ) Car ) Feet 1 inch equals 1,000 feet Figure 4 Drainage Basin 5 ) ( ! 36 ) VALLEY ST ) ! ( ( ! ) GRE E 30 ) ) ) ) ) 1,000 GLENOAKS AVE ) ) ALAMO ST MORAGA ST !) ( 500 CATALPA AVE 39 36 ) GENEVA ST ) ! ( ) CRE AVE ± !) ( ) HE I M LOTUS ST OR SURF DR 27 FULTON ST GROTON ST SIESTA ST MONTEREY ST ) ) FERN ST SIESTA ST MONTEREY ST MORAGA ST VENTURA ST VENTURA ST REISER CT DORIA ST MORO LN GILBERT ST ROANNE ST 36 ) ! ( ( ! ) GREENA ) HAMPTON ST ) ) ) ) ) ) HE CA SA HANOVER ST ) BAYLOR CIR ) ) )! ( ! ) ( ) ) ALAMEDA AVE ( ! ( ! LAFAYE TTE DR) ( ! ALAMEDA AVE ) BROWNWOOD AVE CATALINA AVE ) MULLER ST LA REINA ST COLORADO ST ) ) () ! BAYLOR AVE SYRACUSE ST STANLEY PL ) ) 54 KENDOR DR PEPPER CIR ) STOCKTON AVE BAYLOR AVE CORNELL PL DRACAENA DR ) GLEN AVE ) MHP BEL AIR ST JOSHUA CIR ) ( ! OS A HERM ) ( ! CAMERON CT VALDINA AVE ) ) 33" ) H YS BA DOGWOOD AVE SD 5-1_04 (P C ASA MAHOGANY CIR ) CEDAR DR ) ) ) ) 57 ) ) ) ) MAGNOLIA AVE ) ) ) COLGATE ST CRESCENT AVE ) DUKE PL ALONA PL RM OS A ) ( ! ) HARCOURT ST ) ) ) ) ) ) ) ) MH P GLENCREST AVE ) ) ) ) MODENA ST GRAMERCY AVE HOLLY WAY ) ) ( ! ) MORO PL ) ( ! ) ) ) ) VE YA NANCITA ST GREENACRE AVE ) ) ) !! ( ( ) HANSEN ST ( ! LA PALMA AVE ) ) GE D R CORON ET AVE ) ) ) ( ! C LIPPER ) LN )! () ) SEQUOIA AV E RC CAMBRIA ST GREENLEAF AVE ) ) ) ( ! ME AURORA ST ) ) ) ( ! ) 36 ) 42 A GR LA REINA ST ) HAMPTON ST ) ) ( ! ) 42 ) HARON ST HOME PL HANOVER ST FELICIDAD ST LA PERLA ST HICKORY DR DALE AVE GUAVA AVE ) ) Crescent Basin ) SEQUOIA AVE Y HEMLOCK WA GREENLEAF AVE ) GLENOAKS AVE ) ) ! ( ( ! ) W AVE VALDINA AVE GLENHAVEN AVE 42" Parallel ) ( ( ! ! 45 33 O RAINB GREENBRIER AVE ) ( ! ALAMO ST ) ) ) 30 ) ! ( ) MORAGA ST 48" Parallel 54 ) ) 24 ) ( ! ) COMPASS LN VIA PALMA ( ! ANC HOR A ) GRAYSON AVE () ! ) ( ) )! ( ! Proposed Pipeline ID Drainage Area_Line No. (Proposed) SD 5-1_01 (P) ) ROMNEYA DR GRAYSON AVE E ) ) ) FALMOUTH AVE 54" Parallel ) SIERRA PL HUNTINGTON AVE 36 SD 5-1_03 (P) ) AV E CLOVER AVE 5 ) 42 ) ! ( SHADOW LN MINOT ST ) WOODLAND DR ) DE S E ) GARDEN ST ( ! ! ( ) ) CLOVER AVE ALAMO ST ) ) ( ! ) HOLLYOAK ST AETNA ST RH O LA PALMA AVE HAZELNUT ST ) T ( ! ) NEPTUNE) DR ) ) ) ALE S F E R ND 60 FELICIDAD CIR ) DEVONSHIRE RD BRAEBURN ST PL ) W OO DL A ND DR ) ARLINGTON AVE 4 GILBERT ST 8 ) AL E IRENE PL BELLFLOWER DR ) ND CO V ET A R ON WINDROS Anaheim (Pipe size in inches) County Caltrans Private Lateral Buena Park 24 BLUEBELL DR TAMARACK WAY PEONY CIR 48 PAVONIA CIR PHLOX DR TEAKWOOD CIR BEGONIA CIR PYRACANTHA CIR ) AV O ) 60 LANTANA DR LAVENDER CIR LOTUS CIR LILAC CIR ( ! ) ) ) CORONET AVE MARINER WAY CARNATION DR ( ! ELMIRA ST ) ) rallel SD 5-1_02 (P) 54" Pa 54 VE ALE A KNOLLWOOD CIR ( ! 4' X 7' D AVON ) ( ! 91 HOUSTON AVE ( ! SHOAL DR 91 PARKSIDE LN HOLLY ST 03S 02) HOLLY ST WAY CLEMSON l (A COLUMBINE PL ( ! ) PARLDALE LN BRITAIN MAPLE ST 69 ann e COLUMBINE ST ) Ch MAPLE ST ( ! on WAKE FOREST DR ( ! ( ! ) ust JASMINE PL 6'x4' RCB 78 PEPPER TREE DR 48 Ho LY WAY LOTUS PL ( ! 54" Parallel IL PICAD JASMINE ST 6'x6' RCB SD 5-1_01 (P) BUCKINGHAM ST ) ( ! CATALPA AVE ) ) ( ! BROOKHURST RD ) Proposed Storm Drains PECKHAM ST ) ) MAGNOLIA AVE ) CORPORATE WAY Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area 5. Drainage Basin 10 Drainage Basin 10 drains approximately 175 acres, and is generally bounded by the 91 freeway on the north, the Brookhurst Street on the east, La Palma Avenue on the south, and the I-5 freeway on the west. As shown in Figure 5, drainage basins are further divided into drainage areas depending on the existing flow patterns and storm drain outlets. Basin 10 consists of Area 10-1, 10-2, 10-3, and 10-4. Storm water in Area 10-1 generally flows east to west and ties into Houston Channel Lateral at the City Limits with the City of Fullerton. Area 10-2, 10-3, and 10-4 generally drain northeast to southwest and tie into an existing Caltrans facility along the I-5 Freeway. The Caltrans facility connects with Houston Channel Lateral, which drains into Houston Channel and ultimately Fullerton Creek Channel. 5.1 Hydrologic Analysis The hydrologic analysis for Basin 10 was performed in accordance with the hydrologic criteria outlined in Chapter 3 and is included in Appendix C. The hydrology map for Basin 10 is included in Appendix B. The following table highlights the flow rates at the key drainage nodes for each of the four drainage areas in Basin 10. The table shows associated drainage areas and flows for 10-, 25-, and 100-year storm events. Table 3 – Basin 10 Summary of Hydrology Area Node Location 10-1 1004 10-1 Drainage Area (ac) 10-Year Flow (cfs) 25-Year Flow (cfs) 100-Year Flow (cfs) Gilbert St and Houston Ave 75 75 90 125 1007 Picadilly Way and Houston Ave 126 95 125 170 10-2 1022 Falmouth Ave and Grayson Ave 12 16 19 25 10-2 1023 Minot St and Rhodes Ave 26 30 35 45 10-3 1032 Falmouth Ave 19 20 25 35 10-4 1042 Devonshire Rd and Rhodes Ave 6 9 11 14 5.2 Analysis of Existing Improvements There are no existing facilities within Drainage Basin 10. Storm water in Basin 10 is conveyed via street flow to catch basins. Runoff from Area 10-1 flows in streets to a catch basin located at the northwest corner of Basin 10 at the I-5 freeway. Runoff from Area 10-2, 10-3, and 10-4 flows in streets to multiple catch basins located on the southwest limits of Basin 10 along the I-5 freeway. 5.3 Proposed Improvements In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains, and also to satisfy the flooded width criteria, the following improvements shown in Figure 5 are recommended for Area 10-1 and Area 10-2. In order to satisfy the City’s flooded width criteria in Area 10-1, 2,092 feet of new storm drain facilities varying in size from 42-inch to 48-inch RCP is recommended in Coronet Avenue. Also, 2,323 feet of new storm drain facilities varying in size from 54-inch to 60-inch RCP is recommended in Houston Avenue. In Area 10-2, another 975 feet of 36-inch RCP storm drain is proposed in Falmouth Avenue. The proposed improvements for Basin 10 are shown in Figure 5, the hydraulic calculations are included in Appendix E and the street flow calculations in Appendix F. An alternative recommendation shown in Figure 6 to the new facilities in Coronet Avenue and Houston Avenue in Area 10-1 is to construct an additional 230 feet of 48-inch RCP in Gilbert Street to tie into the Houston Channel north of the 91 Freeway as shown in Figure 6. This would result in only 1,753 feet of new storm drain facilities varying from 36-inch to 42inch RCP in Houston Avenue, as opposed to 2,323 feet of facilities varying in size from 54inch to 60-inch RCP. 5.4 Cost Estimates The estimated costs summarized in Table 4 include costs for construction, engineering, design, surveying, and construction management. Pipe costs are per linear foot of pipe and have been increased to include excavation, shoring, bedding, backfill, compaction, removal of excess material, and trench resurfacing. The detailed cost estimates for improvements in Area 10-1 and 10-2 of Basin 10 are included in Appendix A. Since the construction of the recommended facilities will be spread out over a number of years, the total cost of master plan implementation will be subject to future construction cost increases. Therefore, it is recommended that the funding programs established for implementation of the Master Plan of Storm Drainage make provisions for the increased cost of deferred construction. Inflation factors should be applied to reflect a specific year’s total cost over the 2010 total costs. Summarized in Table 4 are the construction cost estimates by project location for Areas 10-1 and 10-2 in Basin 10. Table 5 summarizes the cost estimates for the alternative recommendation in Area 10-1. Table 4 – Basin 10 Cost Estimate Area Storm Drain ID 10-1 SD 10-1_01 (P) 10-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Houston Avenue New 60-inch RCP 2,320 $4,335,000 SD 10-1_02 (P) Coronet Avenue New 48-inch RCP 1,080 $1,544,000 10-1 SD 10-1_03 (P) Coronet Avenue New 42-inch RCP 1,015 $1,279,000 $7,158,000 10-2 SD 10-2_01 (P) Falmouth Avenue New 36-inch RCP 980 $1,033,000 $1,033,000 Area Total 16 TOTAL FOR BASIN 10 $8,191,000 $8,191,000 17 Table 5 – Basin 10 Alternative Cost Estimate Area Storm Drain ID 10-1 SD 10-1_01 ALT 10-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Houston Avenue New 42-inch/48inch RCP 1,755 $2,420,000 SD 10-1_02 ALT Coronet Avenue to Gilbert Street New 48-inch RCP 1,310 $1,855,000 10-1 SD 10-1_03 (P) Coronet Avenue New 42-inch RCP 1,015 $1,279,000 $5,554,000 10-2 SD 10-2_01 (P) Falmouth Avenue New 36-inch RCP 980 $1,033,000 $1,033,000 $6,587,000 $6,587,000 TOTAL FOR BASIN 10 WITH AREA 10-1 ALTERNATIVE Area Total 18 10 H AV E -2 _ 01 R () ! FULTON ST GROTON ST SIESTA ST MONTEREY ST VENTURA ST GRAYSON AVE GRAYSON AVE 10-2 FALMOUTH AVE (P VIA PALMA ) 3 10-3 6" 5 DOGWOOD AVE ) ! ( ) 30 Proposed Storm Drains Priority 1 Priority 2 Priority 3 \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps SD 5-1_01 (P) December 9, 2009 Anaheim (Pipe size in inches) County Caltrans Private Lateral 0 500 1,000 Feet Buena Park 1 inch equals 1,000 feet ± Street Right of Way IA AV E Proposed Pipeline ID Drainage Area_Line No. (Proposed) E AV IVY LN R FI 5 Crescent Basin ) ) Anaheim City Limits Existing Storm Drains Drainage Area UO ) Legend 5-1 VALDINA AVE SE Q BR O O K H U R ST S T VALDINA AVE ) 30 ) ) ) ( ! ) SIESTA ST ) MONTEREY ST ) ( ! GREENLEAF AVE GLEN AVE ) VENTURA ST HANSEN ST MORO LN GLENOAKS AVE GRAYSON AVE !) ( ALAMO ST (( ) ! ) ) ! MORO PL ( ! ) 42 MORAGA ST ) REISER CT DORIA ST ) IRENE PL ROANNE PL MODENA PL ) LA PALMA AVE ) ! ( ( ! 45 ) ) DUKE PL HAMPTON ST GREENLEAF AVE ) ) ) ( ! ) ) ( ( ! ! ) VALDINA AVE GLENOAKS AVE 36 ) ( ! MODENA ST ) ) 51 ) ) CAMBRIA ST ) ! ( ) 42 HARON ST HOME PL HANOVER ST FELICIDAD ST SHADOW LN LA PERLA ST ) GLENHAVEN AVE ) 33 FELICIDAD CIR ) ! ( 54 ROANNE ST ) ALONA PL CAMBRIA PL ) MAYFLOWER ST ) CAMBRIA ST ) ( ! ) 24 ) ! ( COLUMBINE PL ROMNEYA DR COLUMBINE ST 36 P. UT HUNTINGTON AVE ) VALLEY ST ) MORAGA ST SD 5 WOODLAND DR FA LM O ALAMO ST AV E ) 42 ) ES CLOVER AVE CATALPA AVE 6 8" R .CLD AETNA ST GILB E ) ) ( ! ! ( ) OD AVE JASMINE ST CI 3" X ) ( ! ARLINGTON AVE NET CORO LOTUS ST W OO D RH DR 60 KN OL LW RT S T FERND ( ! D 48 " CLOVER AVE 10-4 ) 60 AN DL OO 4 2 (P ) 91 SD 10-1_03 (P) 42" N ET A VE CATALPA AVE PL 0 -1_0 ALE S AL E C OR O MINOT ST E ND ) DEVONSHIRE RD ALE AV AV O SD 1 T D AVON 91 10-1 LOTUS PL SD 10-1_01 (P) 60" JASMINE PL 02) 91 ( ! ) 03S WAY HOUSTON AVE 60" l (A AVE BROOKHURST RD ann e PICADIL LY WAY BRITAIN ( ! Ch BAKE R BRAEBURN ST ( ! ) ton ELMIRA ST 69 ) BUCKINGHAM ST 5 MAGNOLIA AVE Ho us PECKHAM ST ORANGETHORPE AVE Figure 5 Drainage Basin 10 Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area PECKHAM ST ORANGETHORPE AVE ) SD 10-1_02 (P) ( ! 36 ) ! ( ) ) ! ( ( ! ) RE AVE GREENAC ) ( ! ( ! County Caltrans Proposed Pipeline ID Drainage Area_Line No. (Proposed) ± Anaheim (Pipe size in inches) 0 500 1 inch equals 1,000 feet \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps December 9, 2009 BROOKHURST ST FULTON ST MONTEREY ST VENTURA ST GROTON ST SIESTA ST ) ) 5 UO DOGWOOD AVE IA 5 AV E FIR AVE IVY LN SIESTA ST SE Q 5 ) ) ) ) Figure 6 Drainage Basin 10 Alternative Proposed Improvements Master Plan of Storm Drainage for Fullerton Creek ChannelTributary Area 1,000 Feet Private Lateral 5 ) ( ! ) VALDINA AVE Basin 10 Priority 1 30 GLEN AVE BROOKHUR ( ! Drainage Basin Existing Storm Drains " MONTEREY ST HANSEN ST Area 10-1 Priority 3 FALMOUTH AVE 33 VENTURA ST DORIA ST GILBERT ST !) ( ) ) MORO PL ) 48 ROANNE ST GENEVA ST CAMBRIA ST ) ) ( ) ! Alternate Drainage Area Street Right of Way Priority 2 36 GRAYSON AVE ) CARAMIN ST!( ) MORAGA ST IRENE PL ) ) Proposed Storm Drains ( P) LA PALMA AVE ) ! ( ( ! ) Legend Anaheim City Limits 01 ) GLENOAKS AVE MODENA ST GREENLEAF AVE HAMPTON ST ) ) ) ( ! ) -2 _ 45 ) ( ( ! ! HARON ST FELICIDAD ST HANOVER ST 42 36 ) ) GLENHAVEN AVE GRAYSON AVE AV E ROMNEYA DR COLUMBINE ST 51 ) ( ! HUNTINGTON AVE MAPLE ST 54 H CLOVER AVE 5 ) ( ! ) ALAMO ST GILBERT ST ) ) ) UT 10 30 MAGNOLIA AVE ) ! ( ) RAINBOW AVE 54 ) 60 ) GREENBRIER AVE GREENLEAF AVE ) ) MO N CORO E ET AV 5 LA PERLA ST ) ( ! ) 91 5 42 SHADOW LN ) ! ( 91 AVE CLOVER AVE 5 24 FELICIDAD CIR VIA PALMA ) FA L SD LA OD WO () ! SA VE ARLINGTON ALAMO ST 42 ) ND ) ) ) ELECTRIC WAY DR ( ! ! ( ) 36 ) DR WOODLAND ) ( ! RH OD E 48 " MORAGA ST ( ! 91 SD 10-1_03 (P) 42" ALT MINOT ST AETNA ST ) 69 91 T AV E 1_0 2 GILBERT ST FERNDALE ST ) ) SD 1 0- DEVONSHIRE RD ( ! BRAEBURN ST ELMIRA ST 42" CO R ONE MAPLE ST 91 48" COLUMBINE PL SD 10-1_01 ALT HOUSTON AVE JASMINE PL 02) VALLEY ST 03S LOTUS PL el ( A LY WA Y LOTUS ST 48" ( ! WAY ann CATALPA AVE BRITAIN ( ! ) DIL Ch BROOKHURST RD PIC A ST ST ) 78 u st on 30 Ho 91 BAKER AVE 6. Drainage Basin 11 Drainage Basin 11 drains approximately 430 acres, and is generally bounded by the 91 freeway on the north, the Euclid Street on the east, a few hundred feet south of La Palma Avenue to the south, and Brookhurst Street on the west. As shown in Figure 7, drainage basins are further divided into drainage areas depending on the existing flow patterns and storm drain outlets. Basin 11 consists of Areas 11-1, 11-2, 11-3, 11-4, 11-5, 11-6, 11-7 and 11-8. In Area 11-1, storm water generally flows from east to west over land to La Palma Avenue and into ties into Caltrans facility along the I-5 Freeway. In Area 11-2 storm water flows southeast to northwest to Brookhurst Street and into a Caltrans facility at the 91 Freeway. In Area 11-3, storm water flows southeast to northwest into a storm drain in Coronet Avenue and into a Caltrans facility at the 91 Freeway. In Area 11-4, 11-5, 11-6, 11-7 and 11-8 storm water flows southwest into catch basins that tie into Caltrans facilities at the I-5 Freeway. The Caltrans facilities drain into Houston Channel, which is tributary to Fullerton Creek Channel. 6.1 Hydrologic Analysis The hydrologic analysis for Basin 11 was performed in accordance with the hydrologic criteria outlined in Chapter 3 and is included in Appendix C. The hydrology map for Basin 11 is included in Appendix B. The following table highlights the flow rates at the key drainage nodes for each of the eight drainage areas in Basin 11. The table shows associated drainage areas and flows for 10-, 25-, and 100-year storm events. 21 Table 6 - Basin 11 Summary of Hydrology Area Node Location 11-1 11004 11-1 Drainage Area (ac) 10-Year Flow (cfs) 25-Year Flow (cfs) 100-Year Flow (cfs) La Palma Ave, 1000 ft East of Fairview St 87 75 95 130 11007 La Palma Ave, 285 ft East of Brookhurst St 151 110 140 190 11-1 11008 La Palma Ave, 170 ft West of Brookhurst St 153 110 140 190 11-2 11035 Brookhurst St, 250 ft South of 91 Frwy Onramp 95 95 120 165 11-2 11036 Brookhurst St and 91 Frwy Onramp 95 95 120 165 11-3 11054 Coronet Ave, 180 ft North of Romneya Dr 67 105 130 175 11-3 11056 Coronet Ave and Mariner Way 160 220 275 375 11-3 11057 Coronet Ave and 91 Frwy 160 220 275 375 11-4 11112 Maple St and I-5 Frwy 3 4 4 6 11-5 11104 Catalpa Ave and Holly St 16 11 15 20 11-6 11122 Ivy Ln and I-5 Frwy 2 3 3 4 11-7 11132 Fir Ave and I-5 Frwy 3 3 4 5 11-8 11142 Dogwood Ave and I5 Frwy 4 5 6 8 6.2 Analysis of Existing Improvements Storm water in Basin 11 is mainly conveyed via street flow in each of the drainage areas except Area 11-3, which has an existing storm drain system. The first storm drain (Line 1) in Area 11-3 begins approximately 500 feet north of La Palma Avenue in Anaheim Shores Drive. The drain flows northeast, then turns north in Coronet Avenue. The drain follows Coronet Avenue northwest to Mariner Way, then turns north and flows to the 91 freeway. This drain varies in size from 24-inch RCP to 7 foot x 4 foot RCB. The second storm drain in Area 11-3 begins approximately 300 feet south of Mariner Way in an alley. The drain follows the alley north, then turns east to Mariner Way. The drain then follows Mariner Way north 22 until it connects to the first drain at Coronet Avenue. This drain varies in size from is 18inch to 27-inch RCP. At this connection point, the system can convey a maximum of 75 cfs, which is 70 percent of a 10-year storm event. This system ties into a Caltrans facility that drains into Houston Channel, which is tributary to Fullerton Creek Channel. The existing hydraulic calculations for Area 11-3 are included in Appendix D. Runoff from Area 11-1 flows in streets to La Palma Avenue, where flow is conveyed west to the I-5 freeway through a 4’ x 2.5’ RCB owned by Caltrans in the intersection of La Palma Avenue and Brookhurst Street. The Caltrans facility drains into Houston Channel Lateral, which is tributary to Fullerton Creek Channel. Runoff from Area 11-2 flows in streets to Brookhurst Street, where flow is conveyed north to the 91 freeway. At this point, the flow enters into Caltrans facilities. The Caltrans facilities drain into Houston Channel, which is tributary to Fullerton Creek Channel. Runoff from Areas 11-4, 11-5, 11-6, 11-7 and 11-8 flow in streets directly into Caltrans facilities located along the I-5 freeway. The Caltrans facilities drain into Houston Channel Lateral, which is tributary to Fullerton Creek Channel. 6.3 Proposed Improvements In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains, and also to satisfy the flooded width criteria, the following improvements are recommended and shown in Figure 7. The hydraulic calculations are included in Appendix E and the street flow calculations are in Appendix F. In order to satisfy the City’s flooded width criteria in Area 11-1, it is recommended that the existing 460-ft 4’ x 2.5’ Caltrans RCB be replaced by a 60-inch RCP. A total of 5,725 feet of additional storm drain varying in size from 42-inch to 60-inch RCP is also recommended in La Palma Avenue. In order to satisfy the flooded width criteria in Area 11-2, a total of 1,783 feet of new pipeline varying in size from 54-inch to 60-inch RCP is proposed in Brookhurst Street. This new storm drain ties into the Houston Channel north of the 91 Freeway. In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains in Area 11-3, a total of 2,093 feet of 60-inch RCP is proposed to parallel the existing system. 6.4 Cost Estimates The estimated costs summarized in Table 7 include costs for construction, engineering, design, surveying, and construction management. Pipe costs are per linear foot of pipe and have been increased to include excavation, shoring, bedding, backfill, compaction, removal of excess material, and trench resurfacing. The detailed cost estimates for Basin 11 are included in Appendix A. Since the construction of the recommended facilities will be spread out over a number of years, the total cost of master plan implementation will be subject to future construction cost increases. Therefore, it is recommended that the funding programs established for implementation of the Master Plan of Storm Drainage make provisions for the increased 23 cost of deferred construction. Inflation factors should be applied to reflect a specific year’s total cost over the 2010 total costs. Summarized in Table 7 are the construction cost estimates by project location for Areas 11-1, 11-2 and 11-3 in Basin 11. Table 7 - Basin 11 Cost Estimate Area Storm Drain ID Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) 11-1 SD 11-1_01 (P) La Palma Avenue Replacement 60-inch RCP /54-inch /60-inch RCP/ New 42-inch RCP 4,155 $6,588,000 11-1 SD 11-1_02 (P) Dogwood Avenue New 48-inch RCP 1,155 $1,647,000 11-1 SD 11-1_03 (P) Dogwood & Mohican Avenue New 42-inch RCP 875 $1,065,000 $9,300,000 11-2 SD 11-2_01 (P) Brookhurst Street New 54-inch/60-inch RCP 2,385 $3,817,000 $ 3,817,000 11-3 SD 11-3_01 (P) Coronet Avenue Parallel 72-inch RCP/ 60inch RCP 2,265 $4,307,000 $4,307,000 $17,424,000 $17,424,000 TOTAL FOR BASIN 11 Area Total 24 EUCLID ST SD 11-2_01 (P) 60" SN ML N JASMINE ST RF 42 ( ! ) ) ) ( ! ) ( ! ) ) ) MINTEER ST ) ) ( ! ) MALBORO AVE ) ) 36 ) ) ( ! ) ) ! ( ) !) ( ( ! ! ) ( ) VO !) ( ) ) 42 ) 45 ROMNEYA DR ( ! ( )! ) ) 24 MEDICAL CENTER DR ) ) DR ( ! ( ! BT COLUMBINE ST AV E DR ( ! ) ) ( ! UT H 54 ! ( ) YA G ) ! ( ) GER WAY GLEN AVE SU R ED ) ( ! ( ! ) ) OR SH BAY COMPASS LNF AL MO FALMOUTH AVE ( ! ) ) ! ( ) ) ) () ! ) ) ) ) ) ) ( ! ) 63 ) ) )! ( ! ) ( ) W AY 27 MAPLE ST ) GRAYSON AVE LOTUS ST FALMOUTH AVE ) ) HO FAT ) () ! l 24 CATALPA AVE 54" 11-2 ( ! CLIPPER ) LN ) ) ) 7' X 3' ! ( ( ! CH A S E FOXFIRE ST le 01 (P) 11-3 CHEVY ) OUTRIG FULTON ST 36" ) ) ) ID E LIGHTHOUSE LN al ( ! ) ) SD 11-3 _ ) ) ER LN ADMIRAL LN ( ! ) ARBOR ST ) ) ( ! ar AV E ) DRESDEN PL ) NE T EB MAPLE ST HOLLY ST COLUMBINE PL LOTUS PL 60" "P 91 6' X 3' 21.6 7'X3 .38'(O PEN 3.0' GROTON ST ( ) )! Y WA RD WA LEE SIESTA ST RO DR 91 R X 5.5' 60 CO UG HA RB OR D WINDLASS COVE HUNTINGTON AVE 7' ) ) SEA COVE DR 36" ) ) ER CLOVER AVE 4' X ANCHORAGE 91 N AK SPIN CLOVER AVE 4' X 7' 91 CORO NET AV E Houston Channel (A03S02) 72" 91 JASMINE PL 91 NEIGHBORS AVE S DEN DRES GLEN AVE T GLEN DR ( ! 5 ) SD 11-1_01 (P) 60" ) SD 11-1_01 (P) 42" GRAMERCY AVE kL ( ! ( ! LAFAYE TTE DR) CLEMSON VALLEY ST 36 ( ! ) at e ral ( 14 x7 CR ES CE NT RC 30 WA Y Proposed Storm Drains Priority 1 Priority 2 Priority 3 \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps SD 5-1_01 (P) December 9, 2009 DRESDEN ST MOHICAN AVE MOHAWK AVE IROQUOIS AVE 48 Carbon Creek (B01) ( ! LAUREL PL 5 Anaheim (Pipe size in inches) County Caltrans Private Lateral 0 500 1,000 Feet Buena Park 1 inch equals 1,000 feet ± Street Right of Way ) Crescent Basin Anaheim City Limits Existing Storm Drains Drainage Area ) CATALPA DR GLENCREST AVE B) Legend 5-1 CATHERINE DR GRAMERCY AVE ) ) ) 51 ee West Anaheim Storm Drain (B01P01) ( ! ) Cr ) FRANCES DR ) Proposed Pipeline ID Drainage Area_Line No. (Proposed) ) ( ! 33 ) GREENLEAF AVE Ca rbo n EUCLID ST ) GREENLEAF AVE 5 FAIRHAVEN ST ) 30 ) MULLER ST 39 ) DOGWOOD AVE ) GLENOAKS AVE ( ! ) ) ( ! ) ) ( ) ! ) ( ! ) ( ! CATALPA AVE MANOR ST VALLEY ST ) ) DR CATHERINE FAIRHAVEN ST GLENOAKS AVE 11-5 CRESCENT AVE ) ) FRANCIS DR PARKWOOD ST E ONONDAGA AVE CATALPA AVE CHIPPEWA AVE CATALPA AVE 5 WICHITA ST A AV KEYSTONE ST FAIRVIEW ST SD 11-1_02 (P) 48" ) ) ) ) SD 11-1_03 (P) 42" DOGWOOD AVE FERN ST GARDEN ST HOLLY ST UO I 11-4 MAPLE ST SEQ 11-7 11-6 IVY LN R FI ) ! ( 45 ) ) DOGWOOD AVE 11-8 E AV 5 BROOKHURST ST 54" 11-1 60" Replacement SIESTA ST LA PALMA AVE ( ! ) 5 ) ) CRESCENT AVE ) ) ) ( ! Figure 7 Drainage Basin 11 Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area 7. Drainage Basin 13 Drainage Basin 13 drains approximately 125 acres, and is generally bounded by the 91 freeway on the north, Harbor Boulevard on the east, La Palma Avenue on the south, and Euclid Street on the west. As shown in Figure 8, drainage basins are further divided into drainage areas depending on the existing flow patterns and storm drain outlets. Since the entire basin drains into the same system, Basin 13 consists of only one drainage area, Area 13-1. Generally, water flows over land from east to west to streets and then into a storm drain in Euclid Street which ties into a Caltrans facilitiy along the 91 freeway. The Caltrans facility drains into Houston Channel, which is tributary to Fullerton Creek Channel. 7.1 Hydrologic Analysis The hydrologic analysis for Basin 13 was performed in accordance with the hydrologic criteria outlined in Chapter 3 and is included in Appendix C. The hydrology map for Basin 13 is included in Appendix B. The following table highlights the flow rates at the key drainage nodes for Area 13-1 in Basin 13. The table shows the associated drainage area and flows for 10-, 25-, and 100-year storm events. Table 8 - Basin 13 Summary of Hydrology Area Node Location 13-1 1304 13-1 13-1 Drainage Area (ac) 10-Year Flow (cfs) 25-Year Flow (cfs) 100-Year Flow (cfs) Euclid St, 685 ft North of Romneya Dr 123 135 170 225 1305 Euclid St and 91 Frwy Offramp 123 135 170 225 1323 Euclid St and Romneya Dr 38 45 55 75 7.2 Analysis of Existing Improvements Water in Area 13-1 is conveyed through a storm drain system consisting of a mainline and a lateral. The mainline begins in Arlington Avenue, approximately 700 feet east of Euclid Street. The drain flows west then turns north in Euclid Street. The drain follows Euclid Street to the 91 freeway. This drain varies in size from 33-inch RCP to double 10.5 foot x 2.0 foot RCB. The lateral begins approximately 100 feet east of Euclid Street in Romneya Drive. The drain flows west, then turns north in Euclid Street, where it connects with the mainline. This drain varies in size from 36-inch RCP to 5.5 foot x 3.0 foot RCB. From this connection point, the system continues north in Euclid Street with a maximum conveyance of 110 cfs, which is 80 percent of a 10-year storm event. This system then ties into a Caltrans facility at the 91 Freeway and drains into Houston Channel, which is tributary to Fullerton Creek Channel. 26 7.3 Proposed Improvements In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains, and also to satisfy the flooded width criteria, the following improvements are recommended and shown in Figure 8. The hydraulic calculations are included in Appendix E and the street flow calculations are in Appendix F. A parallel 36-inch RCP is recommended in Euclid Street from the Caltrans facility to 500 feet south. It is recommended that the 39-inch RCP lateral in Chevy Chase Drive be replaced by 42-inch RCP. An additional 2,125 feet of new 42-inch RCP in Chevy Chase Drive is also recommended. An extension of 1,355 feet of 36-inch RCP is recommended in Romneya Drive. 7.4 Cost Estimates The estimated costs summarized in Table 9 include costs for construction, engineering, design, surveying, and construction management. Pipe costs are per linear foot of pipe and have been increased to include excavation, shoring, bedding, backfill, compaction, removal of excess material, and trench resurfacing. The detailed cost estimates for Basin 13 are included in Appendix A. Since the construction of the recommended facilities will be spread out over a number of years, the total cost of master plan implementation will be subject to future construction cost increases. Therefore, it is recommended that the funding programs established for implementation of the Master Plan of Storm Drainage make provisions for the increased cost of deferred construction. Inflation factors should be applied to reflect a specific year’s total cost over the 2010 total costs. Summarized in Table 9 are the construction cost estimates by project location for Area 13-1 in Basin 13. Table 9 - Basin 13 Cost Estimate Area Storm Drain ID 13-1 SD 13-1_01 (P) Euclid Street Parallel 36-inch RCP 315 13-1 SD 13-1_02 (P) Chevy Chase Drive Replacement 42-inch RCP/ New 42-inch RCP 2,245 $2,820,000 13-1 SD 13-1_03 (P) Romneya Drive Extension 36-inch RCP 1,355 $1,457,000 TOTAL FOR BASIN 13 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) $325,000 $4,602,000 27 21 ) ( !) LIDO ST LOMITA ST LAGUNA ST HERMOSA DR 5' ) X 16 ) ) ' ) ) ( ! DR LA E CATALPA DR NTR ADA DR UMN A UT IN SPR ER 51 LIDO LN REDONDO DR LOARA ST CHIPPEWA AVE FAIRHAVEN ST December 9, 2009 RALEIGH ST RAVENNA ST Crescent Basin ) ) ( ! H ST RE S \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps SD 5-1_01 (P) S ST Proposed Storm Drains Priority 1 Priority 2 Priority 3 Anaheim (Pipe size in inches) County Caltrans Private Lateral 0 500 1,000 Feet Buena Park 1 inch equals 1,000 feet ± Street Right of Way T ON S 30 N PL Proposed Pipeline ID Drainage Area_Line No. (Proposed) ( ! NORTH ST ( ! 2' 7' X 1 ) ST RNE PL ) 66 Anaheim City Limits Existing Storm Drains Drainage Area F GRA ) Legend 5-1 AY NW Z DR GRAMERCY AVE ) KARE JUSTIN PL ) LIDO PL C HE LE N Carbon Creek (B01) PL ) E LA V T NE S TON ( ! E ) ) T GRE ) NN O ) ) ) YV ) GREENLEAF AVE ) ( ! G ST ) GLENOAKS AVE ) LN ATE THG NOR LA V ) ( ! ) ST PINE CIR ) ) ) JANS CATALPA AVE LA PALMA AVE H ST R ES DRESDEN ST 48 7. 2 ) ! ) ) ( () ! CITR ) R ) ST ( ! CATALPA AVE A CL ) ) RON ) LOMITA PL ) ) ST ) GE ED ) TE R ( ! ) ST CATHERINE DR ) ) ! ( MER DR CATHERINE ) ! ( WIN FRANCES DR ) ( ! 42 36 ( ! ) SU M FRANCIS DR ) ( ! BYWOOD AVE 42 ( ! DOGWOOD AVE DOGWOOD AVE 30 ) ( ! ) JULIANA ST ) 18 LOMBARD DR CHERRY WAY VICTOR AVE R ) ) ( ) ! ) ( ! ) HALL AVE 24 ND ROMNEYA DR ) VILLAGE WAY E GL LN ( ! MAYFAIR AVE N ST LOARA ST ) 45 MOHICAN AVE N 4 CIT 36 2 30 ) ( ! ) MOHAWK AVE I C O TR ) ) LODGE AVE 13-1 ) ! () ) ( ! LEISURE CT DE DRES ATECA PL !) ( WEST ST E LA PALMA AVE IROQUOIS AVE CROWN ST ARBOR ST MOHICAN WAY OUTRIGGER WAY GLEN AV ) ) ) ( ! ONONDAGA AVE Y JA CITRON ST 39 ) ) 36 SD 13-1_03 (P) 36" CATALPA AVE UE BL REED LN ST MALBORO AVE LN RIVIERA ST BREWSTER AVE ( ) ! ) GLEN AVE ROBIN PL BREWSTER AVE ) ( ! ) ) ) NEIGHBORS AVE 91 ARLINGTON AVE RALSTON ST ) ) ( ! ) CANARY ST N WRE 42 ) 45 3.0' ) ) ) MINTEER ST 7' X 3' ROMNEYA DR ) ( ! SD 13-1_02 (P) 42" ' X 5.5' VE N ET A COROO LN MAK ( ! 2. 0 ) ROBIN ST ) LOMBARD DR ) MEDICAL CENTER DR ) ( ! ) ) 91 CHEVY CHASE DR 'X 91 ! ( ( ! 54 30 HARBOR BLVD 91 FOXFIRE ST DR 91 .5 10 SNUG HARBOR DRESDEN PL 91 91 EUCLID ST SD 13-1_01 (P) 36" Houston Channel (A03S02) ) WAY KEN ) ( ! Figure 8 Drainage Basin 13 Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area 8. Drainage Basin 15 Drainage Basin 15 drains approximately 225 acres, and is generally bounded by Fullerton Creek Channel and the northerly city limits to the north, Raymond Avenue on the east, the 91 freeway on the south, and Lemon Street on the west. As shown in Figure 9, drainage basins are further divided into drainage areas depending on the existing flow patterns and storm drain outlets. Basin 15 consists of Areas 15-1, 15-2, 15-3, 15-4, 15-5 and 15-6. In Area 15-1, storm water flows from east to west via storm drains in Orangethorpe Avenue and Durst Street, which tie into a storm drain in Lemon Street. This system outlet into Fullerton Creek Channel to the north. In Areas 15-2 and 15-3, storm water flows south to north over land and in streets to pipes connected to Fullerton Creek Channel. In Area 15-4 and 15-6, the flow drains south to north over land and in streets, and is finally conveyed through existing storm drains that tie into A03S05, which is tributary to Fullerton Creek Channel. In Area 15-5, flow drains south to north over land and in streets to a system which ties into A03S05. 8.1 Hydrologic Analysis The hydrologic analysis for Basin 15 was performed in accordance with the hydrologic criteria outlined in Chapter 3 and is included in Appendix C. The hydrology map for Basin 15 is included in Appendix B. The following table highlights the flow rates at the key drainage nodes for each of the six drainage areas in Basin 15. The table shows associated drainage areas and flows for 10-, 25-, and 100-year storm events. 29 Table 10 - Basin 15 Summary of Hydrology Area Node Location 15-1 1504 15-1 Drainage Area (ac) 10-Year Flow (cfs) 25-Year Flow (cfs) 100-Year Flow (cfs) Lemon St and Durst St 29 55 65 85 1505 Lemon St and Orangethorpe Ave 93 160 195 250 15-1 1509 Lemon St and Fullerton Creek Chnl 130 210 255 330 15-2 1542 Fullerton Creek Chnl, 1480 ft East of Lemon St 10 20 25 35 15-3 1552 Elm Via and Fullerton Creek Chnl 31 75 95 115 15-4 1566 Orangethorpe Park and Fullerton Creek Chnl 34 55 65 85 15-5 1572 Fullerton Creek Chnl, 675 ft West of East St 12 25 30 40 15-6 1583 East St and Fullerton Creek Chnl 8 14 16 20 8.2 Analysis of Existing Improvements Storm water in Basin 15 is conveyed through several existing storm drain systems. In Area 15-1, one storm drain begins approximately 600 feet north of the 91 Freeway. The drain flows north to the city limits, where it outlets into Fullerton Creek Channel. This drain varies in size from 36-inch to 72-inch RCP. One lateral is connected to this drain in Durst Street. The lateral is 36-inch RCP. Another lateral is connected to this drain in Orangethorpe Avenue. The lateral varies in size from 48-inch to 54-inch RCP. This system can convey a maximum of 195 cfs, which is equivalent to 93 percent of a 10-year storm event. The existing hydraulic calculations for Basin 5 are included in Appendix D. In Area 15-4, the storm drain begins approximately 200 feet south of the City limits in Orangethorpe Park. The drain flows north to the city limits, where it outlets into A03S05, which is tributary to Fullerton Creek Channel. This drain is 54-inch RCP, and can convey a maximum of 165 cfs, which is greater than a 100-year storm event. In Area 15-6, the storm drain begins approximately 100 feet south of the City limits in Raymond Avenue. The drain flows north to the city limits, where it outlets into A03S05, which is tributary to Fullerton Creek Channel. This drain is 48-inch RCP, and can convey a maximum of 13 cfs, which is equivalent to a 10-year storm event. 30 Runoff from Areas 15-2, 15-3 and 15-5 flow over land and in streets directly into either Fullerton Creek Channel or A03S05, which is tributary to Fullerton Creek Channel. 8.3 Proposed Improvements In order to satisfy the City’s requirement of conveying the 10-year storm event in the storm drains, and also to satisfy the flooded width criteria, the following improvements are recommended and shown in Figure 9. The hydraulic calculations are included in Appendix E and the street flow calculations are in Appendix F. In order to satisfy the City’s flooded width criteria in Area 15-1, an extension of 625 feet of 42-inch RCP in Orangethorpe Avenue is recommended. In addition, 585 feet of 36-inch RCP parallel to the existing system in Orangethorpe Avenue, as well as 1,250 feet of 36-inch RCP parallel to the existing system in Lemon Street, is recommended. In Area 15-4, an extension of 1,741 feet of 42-inch RCP in Orangethorpe Park and Orangethorpe Avenue is recommended to satisfy the City’s flooded width criteria. An alternative recommendation to constructing 585 feet of parallel 36-inch RCP in Orangethorpe is to instead replace the existing 48-inch RCP in Orangethorpe Avenue with a 54-inch RCP. This alternative is shown in Figure 10. 8.4 Cost Estimates The estimated costs summarized in Table 11 include costs for construction, engineering, design, surveying, and construction management. Pipe costs are per linear foot of pipe and have been increased to include excavation, shoring, bedding, backfill, compaction, removal of excess material, and trench resurfacing. The detailed cost estimates for Basin 15 are included in Appendix A. Since the construction of the recommended facilities will be spread out over a number of years, the total cost of master plan implementation will be subject to future construction cost increases. Therefore, it is recommended that the funding programs established for implementation of the Master Plan of Storm Drainage make provisions for the increased cost of deferred construction. Inflation factors should be applied to reflect a specific year’s total cost over the 2010 total costs. Summarized in Table 11 are the construction cost estimates by project location for Area 15-1 and Area 15-4 in Basin 15. Table 12 summarizes the cost estimates for the alternative recommendation for Area 15-1. Table 11 - Basin 15 Cost Estimate Area Storm Drain ID 15-1 SD 15-1_01 (P) 15-1 15-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Orangethorpe Avenue Extension 42-inch RCP 625 $782,000 SD 15-1_02 (P) Orangethorpe Avenue Parallel 36-inch RCP 585 $633,000 SD 15-1_03 (P) Lemon Street Parallel 36-inch RCP 1,250 $1,355,000 Area Total $2,770,000 31 15-4 SD 15-4_01 (P) Orangethorpe Park/Orangethorpe Avenue Extension 42-inch RCP 1,740 TOTAL FOR BASIN 15 $2,168,000 $2,168,000 $4,938,000 $4,938,000 Area Total Table 12 - Basin 15 Alternative Cost Estimate Area Storm Drain ID 15-1 SD 15-1_01 (P) 15-1 15-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Orangethorpe Avenue Extension 42-inch RCP 625 $782,000 SD 15-1_02 ALT Orangethorpe Avenue Replacement 54-inch RCP 585 $1,032,000 SD 15-1_03 (P) Lemon Street Parallel 36-inch RCP 1,250 $1,355,000 $3,169,000 15-4 SD 15-4_01 (P) Orangethorpe Park/Orangethorpe Avenue Extension 42-inch RCP TOTAL FOR BASIN 15 WITH AREA 15-1 ALTERNATIVE 1,740 $2,168,000 $2,168,000 $5,337,000 $5,337,000 32 SD 15-4_01 (P) 42" ( ! ( ! 48 ) ) ( ! ) ) KIMBERLY AVE ORANGETHORPE PARK 15-6 15-5 RAYMOND AVE LEMON VIA MAPLE VIA ELM VIA ( ! 36 ORANGETHORPE AVE ) ( ! ( ! ( ! ORANGEFAIR MALL ) ) DISCOVERY LN ) DURST ST ( ! ( ! ) POMONA AVE ) ) ) ) N ORA AIR GEF ) ) ) 36 ( ! 36 ( ! ) ( ! ( ! LN 30 ( ! MANHATTAN AVE ) ( ! GEMINI PL 36 DURST ST ) 15-4 15-1 ENDEAVOR LN ( ! 42" SD 15-1_01 (P) 42" ORANGETHORPE WAY MISSILE WAY ) 36 LEMON ST CYPRESS VIA WALNUT VIA NATIONAL ST 72 54 ( ! HARBOR BLVD SPRUCE VIA SD 15-1_03 (P) 36" Parallel SD 15-1_02 (P) 36" Parallel ( ! ( ! ! ( ) 15-3 FIR VIA GE VIA ORAN ST LIBERTY AVE ( ) ! 48 15-2 AMERICAN ( ) ! A03S05 54 Fullerton Creek Channel (A03) FREEDOM AVE ) ) ) 36 ( ! ( ! 91 91 BURTON ST 54 24 ) ( ! ( ! ( ! ( ! 66 91 ( ! ( ! 91 91 48 ( ! 91 ( ! ( ! ( ! COMMERCIAL ST ( ! (B k Cr on ) ) ) ) ( ! ( ! ) ) ) E OLIV BALSAM AVE 21 ) ) ) SANDALWOOD AVE BELMON T AVE ) X ) 30 Crescent Basin LA PALMA AVE 42 "L ) ( ! ) ) T TH S NO R BANYAN AVE O -H EA D ( ! ( ! ) T ST ST ST DINA T T ST EL S Y EMIL ) 33 ) ) 27 36 51 ( ! ROMNEYA DR 27 " S EKA TOP ) ZEYN ) ! ( ) 42 ) ( ! PAULINE ST SABINA ST PATT ST KEMP ST ) CL A U 24 ) ) 51 ) DICK NA S ( ! ) HE L E 42 ) ) !) ( ) ( ! ) ! ( ) ROSEMONT ST 60 ( ! ) ) Ca rb OLIVE ST ee 30 ) ( ! JULIANNA AVE)!( 51 66 51 HOMER ST SWAN ST ANAHEIM BLVD ) ( ! ) ( ! ) 24 PARRY AVE ( ! ) ) ) ) ( ! ( ! 30 ST 18 ( ! 48 OD ) 18 ( ! BALSAM AVE KENWOOD AVE RWO JULIANA ST ( ! ! ) ( T ST ) 30 ) BRIA 27 ( ! EA S VICTOR AVE PATT ST CARL KARCHER WAY ) KENWOOD AVE MERONA PL ST ROMNEYA DR 01 ) ( ! LARK ST ( ! ST ( ! NA MERO RALEIGH ST ( ! ) ) 24 6'3" X ( ! ) CANDLEWOOD COMMERCIA L ST ) ) NORWOOD ST ) 54 ) 3'3" ROSEWOOD AVE 54 REED LN ( ! Legend Anaheim City Limits Existing Storm Drains 5-1 Drainage Area 30 ± Street Right of Way Proposed Storm Drains Priority 1 Priority 2 Priority 3 \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps SD 5-1_01 (P) December 9, 2009 Anaheim (Pipe size in inches) County Caltrans Private Lateral 0 500 1,000 Feet Buena Park 1 inch equals 1,000 feet Proposed Pipeline ID Drainage Area_Line No. (Proposed) Figure 9 Drainage Basin 15 Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area ( ! SD 15-4_01 (P) 42" ( ! DURST ST 36 ( ! ) ) ( ! ORANGEFAIR MALL SD 15-1_01 (P) 42" 15-1 ) DISCOVERY LN ) DURST ST ) ( ! ) POMONA AVE ) ) ) 42" 15-4 ( ! ( ! ORANGETHORPE AVE ) ) FAIR N GE ORA ) ) ) 36 ( ! 36 ( ! ) ( ! ( ! LN 30 ( ! MANHATTAN AVE ( ! ) ( ! 15-6 15-5 ENDEAVOR LN ) ) MISSILE WAY LEMON ST ( ! ORANGETHORPE WAY 36 ( ! ( ! ( ! 36 ) GEMINI PL 54 ) KIMBERLY AVE ORANGETHORPE PARK 15-3 SD 15-1_02 54" ALT ( ! ) RAYMOND AVE LEMON VIA MAPLE VIA FIR VIA CYPRESS VIA WALNUT VIA SPRUCE VIA NATIONAL ST 72 ELM VIA SD 15-1_03 (P) 36" Parallel ( ) ! ( ! ! ( HARBOR BLVD E VIA ST 15-2 LIBERTY AVE G ORAN AMERICAN ( ) ! 48 FREEDOM AVE A03S05 54 Fullerton Creek Channel (A03) ) ) ) 36 ( ! ( ! 91 91 BURTON ST 54 24 ) ( ! ( ! ( ! 66 ( ! 91 ( ! ( ! 91 91 48 ( ! 91 ) B0 k( ree Legend Anaheim City Limits Existing Storm Drains 5-1 30 Drainage Area Anaheim (Pipe size in inches) County Caltrans Private Lateral Buena Park Street Right of Way Proposed Storm Drains Priority 1 Priority 2 Priority 3 SD 5-1_01 (P) 0 1,000 Feet December 9, 2009 ROMNEYA DR JULIANNA AVE BALSAM AVE BANYAN AVE SANDALWOOD AVE BELMONT AVE ) ) Figure 10 Drainage Basin 15 Alternative Proposed Improvements Master Plan of Storm Drainage for Fullerton Creek Channel Tributary Area 1 inch equals 1,000 feet \\CHERON\Projects\AnaheimCaCityOf\381357\GIS\Maps ) ( ! ) Proposed Pipeline ID Drainage Area_Line No. (Proposed) ± 500 ) ROSEMONT ST ( ! JULIANNA AVE)!( !) ( ) nC Ca ( ! ) SABINA ST 30 66 ( ! PATT ST KEMP ST ( ! ) ) ) ( ! 30 rbo OLIVE ST ( ! ) ( ! 51 1) PATT ST 60 ( ! ) 48 ST ANAHEIM BLVD 18 ( ! BALSAM AVE KENWOOD AVE OD PARRY AVE SWAN ST ( ! ! ) ( ST 6'3" X RALEIGH ST HOMER ST 30 ) T ST 18 ( ! NA ST KENWOOD AVE MERONA PL M E RO COMMERCIAL ST E AS JULIANA ST ( ! RWO BRIA ) ( ! ( ! CARL KARCHER WAY ) 27 ) ) ( ! 24 VICTOR AVE ( ! ( ! ( ! ROMNEYA DR ( ! ) ) CANDLEWOOD ) ( ! NORWOOD ST ) COMMERCIAL ST ) 54 ) 3'3" ROSEWOOD AVE 54 REED LN 9. Capital Improvement Plan The goal of the Capital Improvement Plan is to identify an organized system for implementing the proposed improvements as financing becomes available. A total of 20 projects totaling $48.9 million dollars (2010 dollars) have been identified as part of this Master Plan. These projects range from small extensions of existing storm drains to large storm drain systems in arterial highways. A priority ranking was developed to identify the most important projects that should be constructed first. This ranking was based on the level to which the existing system meets the City’s flood protection goals. Three categories of improvements were identified as outlined below. Priority 1 - Proposed new storm drain in arterial highway or local street to achieve 10, 25, and 100-year flood protection levels. Priority 2 - Proposed parallel or replacement storm drain in arterial highway or local street to achieve 10, 25, and 100-year flood protection levels. Priority 3 - Proposed new storm drain in a local street where 100-year protection levels are met without the storm drain, however, the storm drain is required to achieve flood protection levels for the 10-year storm. Table 13 outlines those projects designated as Priority 1. There are a total of 7 projects totaling $20.9 million dollars (2010 dollars). Table 13 – Priority 1 Cost Estimate Area Storm Drain ID 10-1 SD 10-1_01 (P) 10-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) Houston Avenue New 60-inch RCP 2,320 $4,335,000 SD 10-1_02 (P) Coronet Avenue New 48-inch RCP 1,080 $1,544,000 11-1 SD 11-1_01 (P) La Palma Avenue Replacement 60-inch RCP /54-inch /60-inch RCP/ New 42-inch RCP 4,155 $6,588,000 11-1 SD 11-1_02 (P) Dogwood Avenue New 48-inch RCP 1,155 $1,647,000 $8,235,000 11-2 SD 11-2_01 (P) Brookhurst Street New 54-inch/60-inch RCP 2,385 $3,817,000 $3,817,000 15-1 SD 15-1_01 (P) Orangethorpe Avenue Extension 42-inch RCP 625 $782,000 15-4 SD 15-4_01 (P) Orangethorpe Park/Orangethorpe Avenue Extension 42-inch RCP 1,740 $2,168,000 Area Total $5,879,000 $782,000 $2,168,000 35 TOTAL $20,881,000 $20,881,000 Table 14 outlines those projects designated as Priority 2. There are a total of 7 projects totaling $19.8 million dollars (2010 dollars). Table 14 – Priority 2 Cost Estimate Area Storm Drain ID 5-1 SD 5-1_03 (P) 5-1 5-1 Street Type of Facility Length (feet) Estimated Cost (2010 Dollars) La Palma Avenue Parallel Relief Drain 42inch/48-inch/54-inch RCP 2,990 $ 4,423,000 SD 5-1_02 (P) Magnolia Avenue Parallel Relief Drain 54inch RCP 2,770 $ 4,577,000 SD 5-1_01 (P) Magnolia Avenue to Dale Avenue Parallel Relief Drain 54inch RCP 2,550 $ 4,227,000 Area Total $13,227,000 11-3 SD 11-3_01 (P) Coronet Avenue Parallel 72-inch RCP/ 60-inch RCP 2,265 13-1 SD 13-1_01 (P) Euclid Street Parallel 36-inch RCP 315 $325,000 $325,000 15-1 SD 15-1_02 (P) Orangethorpe Avenue Parallel 36-inch RCP 585 $633,000 $633,000 15-1 SD 15-1_03 (P) Lemon Street Parallel 36-inch RCP 1,250 $1,355,000 $1,355,000 $19,847,000 $19,847,000 TOTAL $4,307,000 $4,307,000 Table 15 outlines those projects designated as Priority 3. There are a total of 6 projects totaling $8.2 million dollars (2010 dollars). Table 15 – Priority 3 Cost Estimate Area Storm Drain ID 5-1 SD 5-1_04 (P) 10-1 Type of Facility Length (feet) Sequoia Avenue Extension 33-inch RCP 540 SD 10-1_03 (P) Coronet Avenue New 42-inch RCP 1,015 $1,279,000 $1,279,000 10-2 SD 10-2_01 (P) Falmouth Avenue New 36-inch RCP 980 $1,033,000 $1,033,000 11-1 SD 11-1_03 (P) Dogwood & Mohican Avenue New 42-inch RCP 875 $1,065,000 $1,065,000 13-1 SD 13-1_02 (P) Chevy Chase Drive Replacement 42-inch RCP/ New 42-inch RCP 2,245 $2,820,000 13-1 SD 13-1_03 (P) Romneya Drive Extension 36-inch RCP 1,355 $1,457,000 4,277,000 $8,201,000 $8,201,000 TOTAL Street Estimated Cost (2010 Dollars) $ 547,000 Area Total $ 547,000 36 10. Storm Drain Impact and Improvement Fee To finance storm drain improvements and to mitigate the flooding and storm drainage impacts caused by new development and/or by additions and expansions to existing development the City of Anaheim City Council previously adopted an ordinance and storm drain impact fees for certain areas with the City. None of these fees are applicable to the Fullerton Creek Tributary Area. A future study will be conducted to identify financing mechanisms for constructing the improvements. These could include such options as Impact Fees, Assessment Districts or other financing mechanisms. 37 11. Potential Locations for Detention/Infiltration Basins in City Parks An analysis of potential locations for detention and infiltration basins in City parks was made. These detention/infiltration basins could potentially reduce the size or need for downstream storm drain facilities. The analysis was made by looking at the location of each park within the study area and determining if an existing or proposed storm drain facility was located nearby. If a storm drain facility was located nearby, then the potential to reduce downstream storm drain facilities was made. If the basin could reduce downstream facilities, then the location was identified as a potential location for a detention or infiltration basin. The results of the analysis are summarized in Table 16. Detailed analysis will need to be performed to determine the size and effectiveness of basins at these potential locations. Table 16 - Potential Locations for Detention/Infiltration Basins within City Parks Park Name Street by Park MP ‐ Basin SD Nearby 5 ‐ MANZANITA PARK Canary St. FC – 13‐1 Proposed 10 ‐ JOHN MARSHALL FC ‐ 11‐1, PARK La Palma Ave 11‐2 Proposed Notes: 1Could reduce proposed storm drain for street flooding Is SD Deficient Possible D/S of Location Park for Basin Yes Yes1 Yes Yes1 38 Appendix A Cost Estimates 39 Appendix B Hydrology Maps Appendix C Hydrology Calculations Appendix D Existing Hydraulic Calculations Appendix E Proposed Hydraulic Calculations Appendix F Street Flow Calculations
© Copyright 2026 Paperzz