HOBAS Big Diameter Pipe Jacking

16/05/2014
HOBAS Big Diameter
Pipe Jacking
Projects Czajka and
Burakowski
Barbara Prommegger
Sao Paulo, 140516
h Worldwide
Opening of HOBAS
Office in São Paulo in 2012
2
Cayu BAP 121001
1
16/05/2014
HOBAS® - Today
System Supplier
Pipes + Couplings + Fittings + Manholes + Special Fittings
O Diameters:
DN 150 – DN 3600
O Pressure Classes:
PN 1 – PN 40
O Stiffness Classes:
SN 2500 – SN 1000000
3
DST/BAP 120327
HOBAS
protective layers
structural layers
outer
protective
layer
glass fiber rich
layer
(strength, stiffness)
inner
protective
layer / Liner
4
2
16/05/2014
Main Applications for
HOBAS GRP Pipe System
OSewage systems
ODrinking water supply
OIndustrial applications
OPower plant pipelines
OIrrigation systems
OTrenchless applications
(Jacking, Relining, NC....)
OFittings, Manholes
OStorage Tanks
5
Cayu BAP 121001
Project Czajka
3
16/05/2014
Warsaw Main Sewer to
„CZAJKA”
2009 - 2010
o Pipeline to WWTP
„Czajka”
o DA 3000
o L=5,7 km (Right Bank)
o Cover 6 - 10,5 m
o Ground water level up to
5 m above the pipe
DOT/LSK-HPL
Czajka
Trenchless Installation vs. Open cut
8
•
The longest single drive 930 m
•
Installation advanced with average
speed of 22m, at peak 36m daily,
not imaginable by open-cut.
•
Smooth exterior surface of pipes
(sections 1-3 m, wall thickness
100-117mm, weight 1.9 - 2.5t/m)
assured low friction and with few
exceptions no intermediate stations
were applied
•
Contractor used merely 50% of the
machines’ 18000kN-force capacity.
Cayu BAP 121001
4
16/05/2014
Czajka 2009 - 2010
Warsaw Main Sewer
o 16 sections
o The longest single drive 930 m
o 2 curves (r = 450 and 900 m)
o Total of 600 pcs of SN 64000
1 m pipe sections
and 1700 pcs of 3 m
(SN 40000 up to 64000)
o 53 inspection manholes
(43 pcs of GRP)
DOT/LSK-HPL
International Society of
Trenchless Technology Award
10
Cayu BAP 121001
5
16/05/2014
HPL Finance
Project Burakowski „Bis”
O OD 3270 – under Marymoncka street
O e = 127 mm
O SN 64000 / 3 m; 1m
O 22697 kN 0,15° on straight section
O 6983,6 kN o,3° on curved section
O 2800 kg/m
O Combined sewer + retention
O Cover up to 10 m - low to no ground
water
O 1 curved section R=400 m / L=200m
HPL - Burakowski Proj ect - March 13th, 2013
HPL Finance
Project Burakowski
O Start of jacking 18-03-2014
O Construction till march 2015
O Already finished First section
L= 409,6 m
o Straight section 208,9 m
o curve 97,1 m,
o straight 103,6 m
o 13 m per day
HPL - Burakowski Proj ect - March 13th, 2013
6
16/05/2014
HPL Finance
HPL - Burakowski Proj ect - March 13th, 2013
7
16/05/2014
Installation of
InterJack
Station
8
16/05/2014
HPL - Burakowski Proj ect - March 13th, 2013
HPL - Burakowski Proj ect - March 13th, 2013
9
16/05/2014
HPL - Burakowski Proj ect - March 13th, 2013
HPL - Burakowski Proj ect - March 13th, 2013
10
16/05/2014
HPL - Burakowski Proj ect - March 13th, 2013
HPL - Burakowski Proj ect - March 13th, 2013
11
16/05/2014
HPL - Burakowski Proj ect - March 13th, 2013
Thank you!