SVG126/02 Twice Yearly Profiling Trial: Results and Recommendations Meeting Name Supplier Volume Allocation Group Meeting Date 2 August 2011 Purpose of paper For Decision Following recommendations from the Profiling and Settlement Review Group (PSRG) and the Profiling Expert Group (PEG) the SVG (SVG120/06) agreed that a trial be undertaken on twice yearly profiling to shorten the profile production timescales from 2 years to 1. The trial has been carried out to assess the viability of the timescales for the twice yearly Summary approach and the validity of the data produced. The paper reports that a viable set of data has been produced and recommends that the data for next year be produced using the revised timescales. The SVG is invited to note the results of the trial and agree ELEXON’s recommendations for the next steps. 1. Background 1.1 The proposal for twice yearly profiling was presented to the PSRG in June 2010. The paper (see Attachment A) set out the detailed production timescales, risks and benefits of producing profiles twice yearly to shorten the profile production timescale. The rationale for shortening the timescales was to make the profiles react quicker to changes in profile shape driven by roll-outs of Advanced and Smart meters. 1.2 In order to quantify the costs and benefits of this approach, a Draft Change Proposal (DCP0047) was issued to assess any impact on participants. There were seven responses: a) Six were in favour of the proposal on the basis that the profiles would be: More accurate; More relevant ;and More interactive with the Smart metering roll-out. b) One party was against stating: ‘With the current uncertainty around Smart metering and the impact on settlement data and processes, we question if this proposed change is cost effective with the potential limited timescales that profiling will continue to be used. Also, we believe that the volume displacement across Annualised Advance (AA) and Estimated Annual Consumption (EAC) data because of mid- SVG126/02 v1.0 Page 1 of 4 © ELEXON 2011 SVG126/02 year changes, have not been addressed and will have to be taken into consideration, if this proposal is to be progressed.’ 1.3 ELEXON intends to speak to the party to alleviate their concerns, subject to agreement of the recommendations in this paper, as we believe that profiling will continue for at least the next 5 years as Advanced and Smart metering is rolled out, even if there is a move to Half Hourly (HH) settlement. This change supports the maintenance of accurate profiles during the roll-out and helps pick up any changes in customer behaviour due to Smart metering. Furthermore, AAs and EAC will always cross changes in profile coefficients, so a change in the data from one set to another should not ‘displace’ volume just allocate it slightly differently. 1.4 Implementation timescales provided in response to the impact assessment ranged from ‘No advance notice required’ to 6 months lead time. 1.5 It should be noted that the out-turn format of the data will not change, it will merely be based on more recent data. Therefore clarification is being sought from respondents that suggested that there are IT impacts. 1.6 The Profiling Expert Group (PEG) discussed the issue and agreed to recommend a trial of the twice yearly process to the SVG (agreed SVG120/06) to check the viability of producing the profile to tight timescales and the validity of the out turn data. The SVG approved this approach. This paper reports the findings of that trial and invites SVG to agree ELEXON’s recommendations on the next steps. 2. Profiling Trial 2.1 The Profiling trial was set to produce a viable set of coefficients based on the data for the autumn and winter seasons using the most recent data available (autumn and winter 2010/11). A timetable and data analysis plan was developed by ELEXON as the Profile Administrator and its profiling data analyst. The plan has been executed and the profiling data has been successfully produced to the timescales in the plan. The data was then pooled with data from the previous two years to produce the final coefficients. 3. The Profiling Expert Group 3.1 The data has been checked for content and format by ELEXON. The PEG were sent the ‘Friendly Format’ version of the data and have agreed the following comments and the recommendations in this paper: The trial has been a success; The trial has produced a viable set of coefficients that could be used in Settlement; and The trial has met the proposed timescales for production. 4. Lessons Learned from the Trial 4.1 There have been lessons learned in producing the new data: SVG126/02 v1.0 Page 2 of 4 © ELEXON 2011 SVG126/02 The need for clear definition of the data set to be produced including how seasons not being updated should be populated; The requirement for strict version control as several versions of similar data are being processed at the same time; That Bank Holidays for the existing data recalculated based on the latest year (there is a need to ensure existing data does not change); That ‘effective from’ dates for new data need clear definition; Timescales for PEG review are short and can coincide with holiday periods; and The requirement to consider how and when Group Average Annual Consumptions and Default Period Profile Coefficients are calculated and updated. 5. New Approach, CP and MDD timetable 5.1 The profiles being used in settlement for the BSC Year 2011/12 was agreed at the February meeting of the SVG. This profiling data runs until 31/03/2012. The data produced from the trial could potentially be used for autumn and winter 2011. However this would require MDD changes to be both raised and agreed at this meeting with a go live date of 5 September 2011. The data currently in Supplier Volume Allocation Agent (SVAA) systems would also need to be overwritten/ superseded before the formal agreement of the MDD change at the 1 September meeting of the SVG. This would remove the 2 year time lag and make sure the most up to date profiling data was being used. 5.2 However, taking into account the above and the implementation timescales identified the DCP0047 it is recommended not to update the existing data for autumn and winter 2011/12. ELEXON recommends that, if the twice yearly approach is agreed by SVG to provide benefits (as recommended by the PEG), a data set using the Spring, Summer and High Summer data in 2011 can be used to create data for use from the 1 April 2012. This would provide the benefits of the twice yearly approach and reduce the timescales in the profiling production process. 5.3 We propose that a CP be raised for approval by the SVG to introduce twice yearly profiling from April 2012 and to address any changes required to BSCP508, BSCP510 and the PrA Service Description. This will build upon the work of the DCP (DCP0047). 5.4 This would also give participants 6 months to assess any implementation issues in more detail. The outturn data could be single year or pooled as is deemed appropriate. The twice yearly approach would then be employed going forward. 6. Default Period Profile Coefficients 6.1 It is proposed that the Default Period Profile Coefficients for Profile Classes 1, 3 and 5 to 8 and Group Average Annual Consumption are only updated once a year using the latest set of data available. This will be no change to the existing process. SVG126/02 v1.0 Page 3 of 4 © ELEXON 2011 SVG126/02 7. Recommendations 4.1 We invite you to: a) AGREE that the new data should not be used for this year’s autumn and winter as a set has already been agreed and is being used by market participants; b) AGREE that a CP be raised for approval by the SVG to introduce twice yearly profiling from April 2012 and to address any changes required to BSCP508, BSCP510 and the PrA Service Description; c) AGREE that ELEXON instruct the Data Analysis Contractor as to the deliverables required for an April implementation date; d) AGREE that the Default Period Profile Coefficients will only be updated once yearly in the annual refresh (March); e) AGREE that the Group Average Annual Consumption data will only be updated once yearly in the annual refresh (March); f) AGREE that the MDD input file be populated with the existing data (e.g. for spring, summer and high summer or vice versa for autumn and winter) for the seasons which are not being updated to avoid SVAA validation issues; and g) NOTE that any outstanding issues with the timing of MDD releases be considered further and be brought back to SVG for consideration. Attachment: Attachment_A_PSRG_Paper.doc For more information, please contact: Kevin Spencer ELEXON Market Analyst [email protected] 020 7380 4115 SVG126/02 v1.0 Page 4 of 4 © ELEXON 2011 Shortening Profile Production Timescales: Twice Yearly Profile Production Option Background The current Profiling process takes 2 years, from the start of the collection of half hourly demand data (from the samples) to the use of the Profiles (derived from that data) in Settlement. The processes are as follows: Year 1 Demand Data Collection Year 2 Data Validation; Data Analysis; Profiling Expert Group (PEG) review of average demand data; Profile Production; Profile Assessment and PEG review of Regression data and profiles; SVG Approval of the profiles for use in settlement; MDD Change Request Raised; and SVG Approval MDD. Year 3 Use of the profiles in Settlement. This paper defines how an approach can be taken to reduce the production timescale to only 1 year. This approach is based on a twice yearly approach and thereby making the profiles more up to date with regards to changes in customer behaviour. The Profiling Seasons There are five Profiling Seasons these are used in both calculation and application of the Profiling Regression data. The current Profiling season are defined as follows: Winter (Season Id 1): defined as the period from the day of clock change from British Summer Time (BST) to Greenwich Mean Time (GMT) in October, up to and including the day preceding the clock change from GMT to BST in March; Spring (Season Id 2): defined as the period from the day of clock change from GMT to BST in March, up to and including the Friday preceding the start of the Summer period; Summer (Season Id 3): defined as the ten-week period, preceding High Summer, starting on the sixteenth Saturday before the August Bank Holiday; Draft 0.2 Page 1 02 June 2010 High Summer (Season Id 4): defined as the period of six weeks and two days from the sixth Saturday before August Bank Holiday up to and including the Sunday following the August Bank Holiday; and Autumn (Season Id 5): defined as the period from the Monday following the August Bank Holiday, up to and including the day preceding the clock change from BST to GMT in October. The twice yearly profile process It is proposed that a twice yearly process be implemented as follows: First run: Uses Autumn and Winter sample data Second run: Uses Spring, Summer and High Summer sample data The First Profile Production Process 1. Production, Review Approval Period: At the start of Spring and extending through the Summer and High Summer. 2. Data to be processed: The data for the preceding seasons: Autumn and Winter. 3. Profile Data to be used in Settlement: The season following: Autumn and Winter. The Second Profile Production Process 1. Production Review and Approval Period: At the start of Autumn and extending through Winter. 2. Data to be processed: The data for the preceding seasons: Spring, Summer and High Summer. 3. Data to be used in Settlement: The season following: Spring, Summer and High Summer . Draft 0.2 Page 2 02 June 2010 Detailed Production Timescales Using the existing process steps then a detailed timescales would look as follows. The First Profile Production Process Process Period Comment Demand Data Collection Completed by Working Day (WD) +15 from the start date in Spring (Season Id 2) [approx. 20th April depending on Clock Change date] This allows for all data to be either collected by the PrA or provided by Suppliers. Data Validation Completed by WD+15 from data collection end date. Validation can start from Spring (Season Id 2) but will only be complete by this date. [approx. mid May] Data Analysis Completed by WD+15 from data validation end data and sent to PEG [approx, start June] Profiling Expert Group (PEG) review of average demand data Completed by WD+10 of receipt with a meeting in mid June. Profile Production Concurrent with PEG review but completed with incorporation of any changes by the Start of July and sent to PEG Profile Assessment and PEG review of Regression data To be completed by WD+10 of start of June. Recommendation and SVG paper to be prepared for August SVG. SVG Approval of Profiling Data. August SVG MDD Change Request Raised Following August SVG SVG Approval of MDD change MDD changes approved September SVG data will already be loaded as change effectively already approved at August SVG. Use of the data in Settlement. From the start of Autumn (Season Id 5) Draft 0.2 Includes calculation and internal assessment of data. Standing data can be updated prior to the analysis. [approx, mid June] Defaulting to existing data to apply if not agreed by SVG and data loaded into SVAA and MDD pending SVG approval of MDD change. Page 3 02 June 2010 The Second Profile Production Process Process Demand Data Collection Period Comment Completed by WD+15 from the start date in Autumn (Season Id 5). This allows for all data to be either collected by the PrA or provided by Suppliers. [approx. mid September] Data Validation Completed by WD+15 from data collection end date. [approx. mid October] Data Analysis Completed by WD+15 from data validation end data and sent to PEG [approx. start November] Profiling Expert Group (PEG) review of average demand data Validation can start from Autumn (Season Id 5) but will only be complete by this date. Includes calculation and internal assessment of data. Standing data can be updated prior to the analysis. Completed by WD+10 of receipt with a meeting at start November [approx. mid November] Profile Production Concurrent with PEG review but completed with incorporation of any changes by the Start of December and sent to PEG. Profile Assessment and PEG review of Regression data To be completed by First week in January. Recommendation and SVG paper to be prepared for February SVG. SVG Approval of Profiling Data. February SVG MDD Change Request Raised Following February SVG SVG Approval of MDD change MDD changes approved March SVG data will already be loaded as change effectively already approved at February SVG. Use of the data in Settlement From the start of Spring (Season Id 2) Draft 0.2 Defaulting to existing data to apply if not agreed by SVG and data loaded into SVAA and MDD pending SVG approval of MDD change. Page 4 02 June 2010 The Benefits and Risks of a Twice Yearly Approach In assessing the risks and benefits of the proposed approach, it should be noted that the default position under the current process is to use the existing set of data. This would be when the SVG does not approve the new set of the profiles for the next BSC Year, say due to advice from the PEG that the new profiles had some error or were not fit for purpose. Under the twice yearly approach, using the same principle as above, the default would be to the existing baseline (Data will be from Year T – 2). Therefore, the proposed approach would be just as accurate, or better, than the current baseline. Issues relating to profiling accuracy and GSPGCF do not need to be considered. Benefits The main benefit would be that more up to date data would form part of the profiling data set. This would mean that any changes in customer behaviour would be captured in the profiles quicker. It should be noted that the current profiling approach calculates an average profile over the last 3 valid years. This approach seeks to mitigate any adverse affects of temperatures in the sample year. If it was felt that the customer behaviour was changing very rapidly, single year data rather than pooled data could be used (if it was assessed that the change in shape out-weighed issues relating to temperature effects). Additional Effort and Costs The additional effort involved will mainly be for the PrA and ELEXON (including MDD) with increased effort in validating and processing the data twice (albeit in 2 smaller chunks). The Profiling Expert Group would also be affected in assessing the data and SVG in approving the data. There would also be impacts on other parties, Suppliers on receiving and loading (and checking) the data and a minor impact on the SVAA in loading the profiles. The main area of cost is related to the PrA analysis process undertaking the process twice. Since, the PrA Service is currently due for re-procurement, the exact cost of this additional effort cannot be assessed at this time. Potential Risks Risk Risk Number 1 Draft 0.2 The risk that all the data cannot be collected from the sample to the proposed Probability Severity Rationale Mitigation Low Low The risk is estimated as being low since data is collected remotely on a monthly basis. If the last month of data had not been collected processing of previous data could still be implemented. Page 5 02 June 2010 Risk Risk Number Probability Severity Rationale Mitigation timescale. 2 The risk that data not received from Supplier to timescales. Medium Low Slightly higher probability since this is not in direct control of the PrA. PrA can chase missing data. Further Top-Up data can be requested from Suppliers. A ‘lessons learnt’ exercise can be conducted on the existing P223 process to identify any improvements. 3 The risk that data cannot be validated to timescales. Medium Low An over run of validation could occur as a knock on from Risks 1 and 2. This could affect production timescales. More resource could be added to validation if the risk became high. 4 The risk that the overall timescales are affected. Medium Low Delay at any stage could cause an overrun in production timescales. Default the first season to existing data and continue process for following season. E.G. Default Autumn and get the new Winter Season data ready. Draft 0.2 Page 6 02 June 2010 Worked Example for 2010/2011 Day Number Date 28/03/2010 29/03/2010 30/03/2010 31/03/2010 01/04/2010 02/04/2010 03/04/2010 04/04/2010 05/04/2010 06/04/2010 07/04/2010 08/04/2010 09/04/2010 10/04/2010 11/04/2010 12/04/2010 13/04/2010 14/04/2010 15/04/2010 16/04/2010 17/04/2010 18/04/2010 19/04/2010 20/04/2010 21/04/2010 22/04/2010 23/04/2010 24/04/2010 25/04/2010 26/04/2010 27/04/2010 28/04/2010 29/04/2010 30/04/2010 01/05/2010 02/05/2010 Draft 0.2 Season_id 362 363 364 365 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Daytype_id 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Day of Week SU WE WE WE WE GF SA SU EM WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU Key 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Page 7 Data Collection Completion Data Validation Data Analysis PEG Review of GADs Profile Production Profile Assessment SVG TPD approval SVG MDD Approval 02 June 2010 03/05/2010 04/05/2010 05/05/2010 06/05/2010 07/05/2010 08/05/2010 09/05/2010 10/05/2010 11/05/2010 12/05/2010 13/05/2010 14/05/2010 15/05/2010 16/05/2010 17/05/2010 18/05/2010 19/05/2010 20/05/2010 21/05/2010 22/05/2010 23/05/2010 24/05/2010 25/05/2010 26/05/2010 27/05/2010 28/05/2010 29/05/2010 30/05/2010 31/05/2010 01/06/2010 02/06/2010 03/06/2010 04/06/2010 05/06/2010 06/06/2010 07/06/2010 08/06/2010 09/06/2010 10/06/2010 11/06/2010 12/06/2010 13/06/2010 14/06/2010 15/06/2010 16/06/2010 Draft 0.2 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 M1 WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU M2 WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 Page 8 02 June 2010 17/06/2010 18/06/2010 19/06/2010 20/06/2010 21/06/2010 22/06/2010 23/06/2010 24/06/2010 25/06/2010 26/06/2010 27/06/2010 28/06/2010 29/06/2010 30/06/2010 01/07/2010 02/07/2010 03/07/2010 04/07/2010 05/07/2010 06/07/2010 07/07/2010 08/07/2010 09/07/2010 10/07/2010 11/07/2010 12/07/2010 13/07/2010 14/07/2010 15/07/2010 16/07/2010 17/07/2010 18/07/2010 19/07/2010 20/07/2010 21/07/2010 22/07/2010 23/07/2010 24/07/2010 25/07/2010 26/07/2010 27/07/2010 28/07/2010 29/07/2010 30/07/2010 31/07/2010 Draft 0.2 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 Page 9 02 June 2010 01/08/2010 02/08/2010 03/08/2010 04/08/2010 05/08/2010 06/08/2010 07/08/2010 08/08/2010 09/08/2010 10/08/2010 11/08/2010 12/08/2010 13/08/2010 14/08/2010 15/08/2010 16/08/2010 17/08/2010 18/08/2010 19/08/2010 20/08/2010 21/08/2010 22/08/2010 23/08/2010 24/08/2010 25/08/2010 26/08/2010 27/08/2010 28/08/2010 29/08/2010 30/08/2010 31/08/2010 01/09/2010 02/09/2010 03/09/2010 04/09/2010 05/09/2010 06/09/2010 07/09/2010 08/09/2010 09/09/2010 10/09/2010 11/09/2010 12/09/2010 13/09/2010 14/09/2010 Draft 0.2 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU A2 WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 Page 10 02 June 2010 15/09/2010 16/09/2010 17/09/2010 18/09/2010 19/09/2010 20/09/2010 21/09/2010 22/09/2010 23/09/2010 24/09/2010 25/09/2010 26/09/2010 27/09/2010 28/09/2010 29/09/2010 30/09/2010 01/10/2010 02/10/2010 03/10/2010 04/10/2010 05/10/2010 06/10/2010 07/10/2010 08/10/2010 09/10/2010 10/10/2010 11/10/2010 12/10/2010 13/10/2010 14/10/2010 15/10/2010 16/10/2010 17/10/2010 18/10/2010 19/10/2010 20/10/2010 21/10/2010 22/10/2010 23/10/2010 24/10/2010 25/10/2010 26/10/2010 27/10/2010 28/10/2010 29/10/2010 Draft 0.2 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 Page 11 02 June 2010 30/10/2010 31/10/2010 01/11/2010 02/11/2010 03/11/2010 04/11/2010 05/11/2010 06/11/2010 07/11/2010 08/11/2010 09/11/2010 10/11/2010 11/11/2010 12/11/2010 13/11/2010 14/11/2010 15/11/2010 16/11/2010 17/11/2010 18/11/2010 19/11/2010 20/11/2010 21/11/2010 22/11/2010 23/11/2010 24/11/2010 25/11/2010 26/11/2010 27/11/2010 28/11/2010 29/11/2010 30/11/2010 01/12/2010 02/12/2010 03/12/2010 04/12/2010 05/12/2010 06/12/2010 07/12/2010 08/12/2010 09/12/2010 10/12/2010 11/12/2010 12/12/2010 13/12/2010 Draft 0.2 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 Page 12 02 June 2010 14/12/2010 15/12/2010 16/12/2010 17/12/2010 18/12/2010 19/12/2010 20/12/2010 21/12/2010 22/12/2010 23/12/2010 24/12/2010 25/12/2010 26/12/2010 27/12/2010 28/12/2010 29/12/2010 30/12/2010 31/12/2010 01/01/2011 02/01/2011 03/01/2011 04/01/2011 05/01/2011 06/01/2011 07/01/2011 08/01/2011 09/01/2011 10/01/2011 11/01/2011 12/01/2011 13/01/2011 14/01/2011 15/01/2011 16/01/2011 17/01/2011 18/01/2011 19/01/2011 20/01/2011 21/01/2011 22/01/2011 23/01/2011 24/01/2011 25/01/2011 26/01/2011 27/01/2011 Draft 0.2 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 WE WE WE WE SA SU WE WE WE WE SD CD BD SU SU SD SD SD J1 SU SU SD WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 Page 13 02 June 2010 28/01/2011 29/01/2011 30/01/2011 31/01/2011 01/02/2011 02/02/2011 03/02/2011 04/02/2011 05/02/2011 06/02/2011 07/02/2011 08/02/2011 09/02/2011 10/02/2011 11/02/2011 12/02/2011 13/02/2011 14/02/2011 15/02/2011 16/02/2011 17/02/2011 18/02/2011 19/02/2011 20/02/2011 21/02/2011 22/02/2011 23/02/2011 24/02/2011 25/02/2011 26/02/2011 27/02/2011 28/02/2011 01/03/2011 02/03/2011 03/03/2011 04/03/2011 05/03/2011 06/03/2011 07/03/2011 08/03/2011 09/03/2011 10/03/2011 11/03/2011 12/03/2011 13/03/2011 Draft 0.2 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE WE SA SU 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Page 14 02 June 2010 14/03/2011 15/03/2011 16/03/2011 17/03/2011 18/03/2011 19/03/2011 20/03/2011 21/03/2011 22/03/2011 23/03/2011 24/03/2011 25/03/2011 26/03/2011 27/03/2011 28/03/2011 29/03/2011 30/03/2011 31/03/2011 Draft 0.2 348 349 350 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 WE WE WE WE WE SA SU WE WE WE WE WE SA SU WE WE WE WE 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 Page 15 02 June 2010
© Copyright 2026 Paperzz