NEC UK WORKSHOPS 2016 : MAXIMISING SUCCESS WITH THE NEC3 PROGRAMME 25 MAY 2016 | LONDON Sponsored By neccontract.com/events Dear delegate, NEC User’s Group workshop 2016 Welcome to your NEC Users' Group workshop. We are pleased that you have been able to attend and hope that you get the most out of it. Our speakers are all very passionate about NEC and none more so than Ben Walker. Please take the opportunity to get everything you can from Ben today whilst we cover the topic of ‘Maximising success with the NEC3 programme’. Please do contribute as best you can in the sessions. As NEC Users’ Group members, we would love to hear any thoughts you may have on improving your benefits or on any issues during the day. For these, please contact John Donato. After the event we would be grateful to receive your feedback and the form will be emailed to you. We would also appreciate your thoughts on possible future topics for these workshops, your thoughts on topics/speakers for next years' Annual Seminar and any ideas you may have to improve the NEC Users' Group. Have a great day! Robert Gerrard NEC Users’ Group Secretary PROGRAMME 8.30 - 9.00 REGISTRATION AND NETWORKING 9.00 - 10.30 Five functions of the Accepted Programme Programme preparation and revision 10.30 - 10.45 MORNING COFFEE AND NETWORKING 10.45 - 12.30 Transitioning from an administrative chore to a valuable tool Top tips and practical things to implement today Consequences of not having a programme 12.30 - 13.30 LUNCH 13.30 - 15.00 Compensation event assessment Assessment before the event Assessment after the event 15.00 - 15.15 AFTERNOON COFFEE AND NETWORKING 15.15 - 17.00 Case Study workshop Summary 17.00 FINISH BEN WALKER NEC Tutor, Examiner and CEMAR Founding Director Ben has 14 years’ experience working in the construction industry. He has performed various roles on a variety of construction and maintenance contracts. Ben’s company developed the internet based CEMAR system, administering some of the UK’s largest NEC and FIDIC portfolios, collectively worth circa £50 billion. His main areas of expertise are contract strategy, risk, change and programme management. Ben has lectured extensively on the NEC since 2008 as a tutor for Thomas Telford Limited, the owners and publishers of the NEC family of contracts. Ben delivers training and workshops including bespoke courses to a broad range of clients in the UK and overseas. He recently contributed to the drafting of the new national Highways Management Efficiency Programme contract, based on the NEC3 Term Services Contract. Ben is an examiner for the Institution of Civil Engineers’ Law and Contract Management Examinations. His wider NEC experience includes: Led the development of CEMAR - a web-based tool administering NEC and FIDIC programmes with a combined value of circa £50 billion. CEMAR is used across all sectors including airports, nuclear, housing, highways, rail, FM and utilities. Led various major NEC/CEMAR mobilisations and personally trained circa 1,300 practitioners over the last 6 years. Delivered over 150 NEC training courses, workshops, roadshows and lectures throughout the UK and overseas Participated in various procurement and tender evaluation exercises Service Manager for £40m/annum local authority Highway Services NEC3 TSC Delay and disruption analysis over a significant number of NEC ECC compensation events Provision of consultancy advice and support to clients procuring, tendering and implementing NEC contracts Development of various KPIs and innovative/unique contract strategies in an NEC3 setting The introduction of a Quality Management System certified under ISO 9001:2008 for his NEC orientated company Ben works with clients to align their internal processes with NEC procedure to achieve effective, compliant administration and contract management. Ben has a 1st class honours degree in civil engineering. He is familiar with various dispute resolution techniques and has attended introductory courses in adjudication and arbitration through the Chartered Institute of Arbitrators. Maximising Success with the NEC3 Programme NEC Users’ Group Workshop May 2016 © NEC Contracts 1 Welcome Maximising success with the NEC3 Programme NEC Users’ Group Workshop Delivered by Ben Walker May 2016 © NEC Contracts 2 Workshop Programme 8.30 - 9.00 REGISTRATION AND NETWORKING 9.00 - 10.30 • Five functions of the Accepted Programme • Programme preparation and revision 10.30 - 10.45 MORNING COFFEE AND NETWORKING 10.45 - 12.30 • Transitioning from an administrative chore to a valuable tool • Top tips and practical things to implement today • Consequences of not having a programme 12.30 - 13.30 LUNCH May 2016 © NEC Contracts 3 Workshop Programme 13.30 - 15.00 • Compensation event assessment • Assessment before the event • Assessment after the event 15.00 - 15.15 AFTERNOON COFFEE AND NETWORKING 15.15 - 17.00 • Case Study workshop • Summary 17.00 FINISH May 2016 © NEC Contracts 4 Five functions of the Accepted Programme If we don’t have a programme we can’t effectively…. 1. evaluate tenders ‘the how’ to ‘the what - Works Information’, 2. plan the remaining activities, 3. mitigate risk, 4. assess compensation events, 5. forecast Defined Cost to Completion (for Option C to F) 6. assess payments 7. coordinate resources for tests, inspections, acceptances and 8. report on the project….. (Whooops, more than five!) May 2016 © NEC Contracts 5 Programme preparation and revision • what to include and how to present • ‘links’, ‘float’ and ‘terminal float’ • right way to show time risk allowance • timings for submission, revision and replies • showing compensation events reality (clause 31.3) • showing effects of implemented compensation events (clause 32.1) May 2016 © NEC Contracts 6 Programme preparation What does a programme include? • It is useful to think of dates required on the programme in pairs. • Most dates to be shown are either a contractual deadline / milestone or a reality / planned reality. • It is not helpful to have one without the other. • Contractual dates can only change in accordance with the conditions of contract. • Some dates are defined terms or identified terms, or both. Always look them up. ‘contractual / deadline’ ‘planned reality / actual’ starting date order and timing of work access dates order and timing of work Key Dates date when planned to meet Condition for Key Date Completion Date May 2016 Completion or planned Completion 7 © NEC Contracts Programme preparation Example of a paired dates… Completion and Completion Date. • Gives rise to ‘terminal float’ - not defined term • float is available to accommodate the effects of a compensation event or lack of progress by the Contractor. • ‘terminal float’ or ‘Contractor’s float’ is • • • A float B float C D the period between planned Completion and the Completion Date, owned by the Contractor and can’t be used to mitigate compensation events and quicker to say than reciting clause 63.3. E planned Completion terminal float Completion Date May 2016 © NEC Contracts 8 GROUP WORKING 1 Where are defined and identified terms? Explain for each date in the previous table the reason for it being defined, identified or both… May 2016 © NEC Contracts 9 Programme preparation • Contract Date – date when this contract came into existence 11.2 (4). • starting date – identified in Contract Data part one. The date when the Contractor’s obligations begin • access date - identified in Contract Data part one. The date when the Contractor gets access to the site. There may be more than one access date. • Completion Date – This is the date when the Employer requires the project to be completed 11.2 (3). The Completion Date is identified as the completion date in either contract data part one or two. ....unless changed in accordance with the contract. • Key Date is the date by which work is to meet the Condition stated 11.2(9). • The key date and the condition is identified in Contract Data part 1 and may be changed in accordance with the Contract. Used to manage the interface risk between different contractors on the same project. May 2016 10 © NEC Contracts Programme preparation What does a programme include?… continued • • • • • order and timing of operations order and timing of work of Employer and Others provisions for float, time risk allowances, health and safety acceptances for each operation, a statement of how Contractor plans to do work identifying principal Equipment and resources May 2016 11 © NEC Contracts Programme preparation • order and timing of operations – example links THE FINISH TO START LINK THE START TO START LINK E.g. A = install cable, E.g. A = Dig a hole B = electrical testing Activity ‘A’ Activity ‘B’ Activity ‘B’ ‘B’ cannot start until ‘A’ is complete May 2016 B = Remove waste material Activity ‘A’ ‘B’ can start at the same time as ‘A’ © NEC Contracts 12 Programme preparation • order and timing of operations – example links THE START TO START LAG LINK THE FINISH TO FINISH LINK E.g. A = Excavate trench, E.g. A = Installation B = Install pipe B = minor Defect correction Activity ‘A’ Activity ‘A’ Activity ‘B’ Activity ‘B’ ‘B’ can start so many days/weeks after the start of ‘A’ May 2016 ‘B’ can finish at the same time as ‘A’ 13 © NEC Contracts Programme preparation • float Activity ‘A’ TOTAL FLOAT Activity ‘B’ FREE FLOAT TOTAL FLOAT Activity ‘C’ Activity ‘D’ • Activity ‘A’ can move along its float & will move activity ‘B’. When the end of the float is reached it becomes critical. • Is available to accommodate • the time effects of a compensation event • lack of progress by the Contractor May 2016 © NEC Contracts 14 Programme preparation • what is the critical path? • the critical path is simply the longest path of work activities through the programme from start to end • the critical path controls the duration of the programme • critical path activities are said to have no float May 2016 © NEC Contracts 15 Programme preparation • what is risk allowance? • risk allowance is the difference between best productivity and likely/realistic productivity • risk allowances are not float • they are owned by the Contractor as part of thier realistic planning to cover their risks • they are not used for mitigating the effects of compensation events May 2016 16 © NEC Contracts Programme preparation • showing time risk allowance activity duration time risk allowance A 15 3 B 10 2 activity 15 25 OPTION 1 duration time risk allowance A 12 n/a A (TRA) 3 n/a B 8 n/a B (TRA) 2 n/a activity duration time risk allowance A 12 n/a B 8 n/a Total TRA n/a 5 May 2016 0 OPTION 2 OPTION 3 © NEC Contracts 17 GROUP WORKING 2 Which method of showing risk allowance from previous slide is ‘best’? What are the advantages and disadvantages of each option? Why is resourcing essential? What can’t we do without this information? May 2016 © NEC Contracts 18 Programme preparation Showing time risk allowance activity duration time risk allowance A 15 3 B 10 2 activity 0 15 25 OPTION 1 duration time risk allowance A 12 n/a A (TRA) 3 n/a B 8 n/a B (TRA) 2 n/a activity duration time risk allowance A 12 n/a B 8 n/a Total TRA n/a 5 OPTION 2 OPTION 3 May 2016 19 © NEC Contracts 0 4 Start Activity A 8 12 Time Risk Allowance = 3 days 4w 4w Activity B 4w Activity C 3w Activity D 3w Activity E 3w float 3w Activity F planned Completion Completion Date 01/07/2015 Version 2 20 © NEC Contracts 0 4 8 Activity A 4w 4w Activity B 4w Activity C Activity D 12 CE = 3 day delay access to A Start 3w Activity E 3w 3w Activity F planned Completion Completion Date 01/07/2015 Version 2 © NEC Contracts 21 0 4 Start Activity A 3w 2d 8 12 ? 4w Activity B 4w Activity C 3w Activity D 3w Activity E 3w Activity F planned Completion Completion Date 01/07/2015 Version 2 22 © NEC Contracts 0 4 Start Activity A 8 4w 4w Activity B 4w Activity C Activity D 12 3w Activity E 3w 3w Activity F 3 days planned Completion Completion Date 01/07/2015 Version 2 © NEC Contracts 23 Programme preparation …so a programme is much more than just a bar chart. It’s a collection of documents, including method statements, risk and resourcing… May 2016 © NEC Contracts 24 Programme preparation How is a programme presented? Likely a collection of • resource statements / histograms • schedules • network diagrams • Gantt charts • method statements • slide shows May 2016 © NEC Contracts 25 Programme revision • timings for submission and replies • Clause 31.1 – If no programme is identified in Contract Data, the Contractor submits a first programme to the Project Manager for acceptance within the period stated in the Contract Data. • Consider clause 50.3. Note its limitations i.e. only applies to first programme and doesn’t need to be accepted to release retained sums, just needs to show the information required. May 2016 © NEC Contracts 26 Programme revision • timings for submission and replies • Clause 32.1 - Contractor shows on each revised programme: – actual progress achieved on each operation and affect upon remaining work – effects of implemented compensation events – how Contractor plans to deal with any delays and to correct notified Defects – any other changes that Contractor proposes to make The second bullet is much commentated on. Lets take a look after the break, at what this means and more importantly what it doesn’t mean… May 2016 © NEC Contracts 27 Workshop Programme Coffee & Networking 10.30* – 10.45 (*unless we’re in delay) May 2016 28 © NEC Contracts Programme revision Showing reality and effects of implemented compensation events 1. programme before impact 2. programme showing impact of instruction, weather, delay etc. 3. programme showing effects of implemented* compensation event, i.e. change to Completion Date. 1 planned Completion *Clause 32.1 does not prevent a programme from showing the impact of non implemented compensation events. terminal float Completion Date PMI-057 PMI-057 2 planned Completion 3 planned Completion terminal float Completion Date terminal float Completion Date 29 Programme revision • timings for submission and replies • Clause 32.2 - Contractor submits a revised programme: – Within the period for reply after Project Manager has instructed – When the Contractor chooses to – At no longer interval than stated in the Contract Data • Project Manager replies within two weeks May 2016 © NEC Contracts 30 Programme revision • timings for submission and replies Clause 31.3 - gives four reasons for withholding accept of a programme: • The Contractor’s plans which it shows are not practicable, • It does not show the information which this contract requires, • It does not represent the Contractor’s plans realistically or • It does not comply with the Works Information. May 2016 31 © NEC Contracts Programme revision Common misconceptions… • silent acceptance • Completion Date is not Works Information. Completing late is not a breach of clause 20.1. • Showing planned Completion later than the Completion Date, is not ‘desirable’, but is ‘acceptable’. planned Completion planned Completion Completion Date May 2016 Completion Date © NEC Contracts 32 Programme revision • timings for submission and replies • If the Project Manager withholds acceptance for a reason not stated in contract it is compensation event under clause 60.1(9) • Acceptance of a programme by the Project Manager is not a condition precedent to the Contractor proceeding with the work May 2016 © NEC Contracts 33 Practical tips to implement today Transition from a chore to a valuable tool…. • Do not take the too long to reply to a programme submitted for acceptance (two weeks is too long) • If not accepted promptly, there is increasing progress, hindsight, and likely more compensation events to muddy the waters May 2016 © NEC Contracts 34 Practical tips to implement today Transition from a chore to a valuable tool…. • Day 1 – Contractor submits programme to Project Manager for acceptance • Day 2 - programme review meeting with Project Manager – focused on critical activities and programme narrative, changes from last submission • Day 4/5 – Project Manager accepts programme – becomes Accepted Programme • Day 5 – re-baseline programme and use that programme to progress and monitor the work May 2016 © NEC Contracts 35 Practical tips to implement today Transition from a chore to a valuable tool…. • Awareness of clause 14.1 • Works Information Guidance suggests schedule of Employer / Other deliverables, commitments. Do you think this is a good idea? • Update daily • Use a white board first, ground up… [yesterday / today / tomorrow] • Build other management activities around it • Synergy with Works Information, forecasts, payment, Activity Schedule etc. May 2016 © NEC Contracts 36 GROUP WORKING 3 Let’s take a look at the sanctions and motivators. 14.1, 50.3, 60.1(6), 60.1(9), 64.1, 64.2. May 2016 37 © NEC Contracts Consequences of not having a programme • Huge disadvantage to both Parties – refer to ‘five(+) functions of the programme’ • If Contractor fails to submit: – Clause 50.3 – Clause 64.1, 64.2 ‘does’ not ‘may’. Any Project Manager thinking withholding acceptance is easy option, must remember they are taking on compensation event assessments • If Project Manager fails – to reply, clause 60.1(6) – to give reasons in the contract, clause 60.1(9) May 2016 38 © NEC Contracts …a slight deviation from programme compensation events… • Do we really understand the principle of clauses 63.1 and 63.3 and how compensation events are to be assessed? An understanding of this helps us to approach delay effects more appropriately… existing Activity Schedule price = £8,000 100 KW Generator revised Activity Schedule price = £ ????? • • • 14.3 instruction 61.1 notification [60.1(1)] 61.1 instruction for quotation • Quotation – but how is it calculated? What is the assessed change to the Prices? Clause 63.1 / 63.12 150 KW Generator Defined Cost = £15,000 May 2016 © NEC Contracts 39 GROUP WORKING 4 Read clause 63.1 carefully. How do we approach the compensation event and arrive at a revised Activity Schedule price for the bigger generator? May 2016 © NEC Contracts 40 Workshop Programme Lunch 12.30 – 13.30 May 2016 © NEC Contracts 41 GROUP WORKING 5 List the ways in which the Completion Date can change and in which direction. (hint… we think there are four) List some factors that may affect planned Completion. May 2016 © NEC Contracts 42 Assessing compensation events Clause 63.3 “A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later than planned Completion on the Accepted Programme.” Let’s take a look… May 2016 43 © NEC Contracts Assessing compensation events 0 4 8 Start 4w Activity A 12 Accepted programme 4w Activity B 4w Activity C 3w Activity D 3w Activity E 3w float 3w Activity F planned Completion Completion Date May 2016 44 © NEC Contracts Assessing compensation events 0 4 8 12 Start 4w Activity A 4w Activity B Activity C Activity D 4w CE 3w Activity E 3w 3w Activity F planned Completion Completion Date May 2016 © NEC Contracts 45 Assessing compensation events 0 4 8 Start 4w Activity A 12 Accepted programme 4w Activity B Activity C 4w CE 3w Activity D 3w Activity E 1w float 3w Activity F planned Completion Completion Date May 2016 46 © NEC Contracts Assessing compensation events 0 4 8 12 13 Start 1w delay 4w Activity A (Delay Damages) 4w Activity B Activity C 4w CE 3w Activity D 3w Activity E 3w Activity F 2w planned Completion Completion Date May 2016 47 © NEC Contracts Assessing compensation events 0 4 8 12 13 Start 4w Activity A Activity C 1w float 4w Activity B 4w CE Activity D 3w 3w Activity E 3w Activity F 2w planned Completion Completion Date May 2016 © NEC Contracts 48 Assessing compensation events 0 4 8 Start 4w Activity A 12 Accepted programme 4w Activity B 4w Activity C 3w Activity D 3w Activity E 1w float 3w Activity F planned Completion Completion Date May 2016 49 © NEC Contracts Assessing compensation events 0 4 8 12 Start 4w Activity A 4w Activity B 4w Activity C 3w Activity D 3w Activity E CE 3w Activity F planned Completion Completion Date May 2016 50 © NEC Contracts Assessing compensation events 0 4 8 12 13 Start Activity A 4w 4w Activity B 4w Activity C Activity D 3w Activity E 3w CE 3w Activity F planned Completion Completion Date May 2016 © NEC Contracts 51 Assessing compensation events 0 4 8 12 13 1w float Start 4w Activity A No delay damages 4w Activity B 4w Activity C Forecast cost 1 week delay in CE 3w Activity D 3w Activity E CE 3w Activity F planned Completion Completion Date May 2016 © NEC Contracts 52 GROUP WORKING 6 Some assessments happen in advance of the event, many happen after the event. How is clause 61.3 relevant? May 2016 © NEC Contracts 53 GROUP WORKING 7 Some assessments happen in advance of the event, many happen after the event. Let’s look at some standard* techniques. - ‘as-planned’ - ‘collapsed as-built’ *Do they work with NEC3? May 2016 © NEC Contracts 54 Workshop Programme Coffee & Networking 15.00 – 15.20 May 2016 55 © NEC Contracts Compensation event assessment One suggested approach… • progress programme with works to date • reschedule programme and check if any effect to Key Dates or planned Completion. If yes – reschedule to mitigate effect • rebase line (interim) programme • input compensation event and reschedule programme to assess effects • save a filtered programme demonstrating the effect the compensation event has had (clause 62.2 programme) • if there is a second compensation event to input, re-baseline and repeat the process Is this compliant? May 2016 56 © NEC Contracts Systematic input of a CE into a programme WEEK NUMBERS 2 4 6 8 10 14 16 EXCAVATE CE001 WORKS INSTALL PIPE INSTALL ACCESS ROAD BACKFILL REFURB BUILDING PLANNED COMPLETION • 01/07/2015 Version 2 Accepted Programme from week 6 – now week 8 • CE002 involves 2 weeks additional works to Refurb Building 1. Progress programme 2. Rebaseline 3. Input CE, add logic links and rebaseline © NEC Contracts 57 Systematic input of a CE into a programme WEEK NUMBERS 2 4 6 8 10 14 16 EXCAVATE CE001 WORKS INSTALL PIPE INSTALL ACCESS ROAD BACKFILL REFURB BUILDING PLANNED COMPLETION 1. Progress programme 01/07/2015 Version 2 58 © NEC Contracts Systematic input of a CE into a programme WEEK NUMBERS 2 4 6 8 10 14 16 EXCAVATE CE001 WORKS INSTALL PIPE INSTALL ACCESS ROAD BACKFILL REFURB BUILDING PLANNED COMPLETION 1. Progress programme 2. Rebaseline (Interim) 01/07/2015 Version 2 59 © NEC Contracts Systematic input of a CE into a programme WEEK NUMBERS 2 4 6 8 10 14 16 17 EXCAVATE CE001 WORKS INSTALL PIPE INSTALL ACCESS ROAD BACKFILL REFURB BUILDING CE002 ADDITIONAL WORKS PLANNED COMPLETION 1. Progress programme 2. Rebaseline (interim) 3. Input CE002, add logic links and rebaseline 01/07/2015 Version 2 © NEC Contracts 60 Systematic input of a CE into a programme WEEK NUMBERS 2 4 6 8 10 14 16 17 EXCAVATE CE001 WORKS INSTALL PIPE INSTALL ACCESS ROAD BACKFILL 1 week float REFURB BUILDING CE002 ADDITIONAL WORKS PLANNED COMPLETION 1. Progress programme 2. Rebaseline (interim) 3. Input CE, add logic links 4. Once agreed – Rebaseline (permanent) and note any change to Critical Path 01/07/2015 Version 2 © NEC Contracts 61 GROUP WORKING 8 Feedback session. How do you assess time effects? Do we all agree with this approach? Is it compliant? Why don’t we just accept the programme more frequently? May 2016 Questions © NEC Contracts 62 18/05/2016 © NEC Contracts 64 18/05/2016 © NEC Contracts 66 Notepaper NEC Accreditation Suite The NEC Gold Standard ECC Project Manager Accreditation ECC Supervisor Accreditation TSC Service Manager Accreditation Advanced level training for aspiring and practicing project leaders Unique NEC accreditations Embedding best practice in organisations, upskilling managers and their teams Recognised by employers Discover more at neccontract.com/accreditation Sponsorship opportunities available 0207 665 2445 NEC Golf Day 3 August 2016 PGA National Course, The Belfry, Birmingham • H eld at the world famous Belfry Golf Club near Birmingham • A unique chance to network with other NEC users’ including clients, consultants and contractors • A hearty breakfast including bacon rolls and tea/coffee • Lots of prizes to be won, including: –– Best team –– Best individual –– Longest drive –– Closest to the pin • Drinks reception and BBQ dinner • Awards ceremony Visit neccontract.com/golf16
© Copyright 2026 Paperzz