THE CONSTRUCTION OF DADREG ECD CENTRE FOR CHILDREN REHABILITATED FROM THE DUMPSITE THE EARLY CHILDHOOD DEVELOPMENT CENTRE REPORT The Early Childhood Development Centre is a project that will provide children below six years working or accompanying their mothers in the dumpsite an opportunity to have space where they can learn, play, counselled and given medical attention enabling them to grow healthy away from the toxic wastes from the dumpsite. The children who spend much of their time accompanying their mothers in the dumpsite are exposed to a much greater health risk from the toxic waste in the dumpsite. This project is expected to contribute to improving access to adequate early education, effective and relevant education, sufficient nutrition, adequate health care and protection for children between 0 and 6 years old. The Centre will be designed in such a way to accommodate children with disabilities including safe playing spaces. At the ECD Centre, there will be teachers, nutritionists, counsellors, social and healthcare workers to oversee the development of these children in holistic ways. Early Childhood Development Construction Report The construction work of the Early Childhood Development Centre started very late due to unavoidable circumstances. This includes getting construction permissions from the County Government, passing of drawings and site visit by the authorities issuing construction permits. However, even when the construction work started, we were confronted with the fact that the site once acted as a dumping site for developers who used to construct residential houses within Dandora. This means that we had to hire bulldozer to dredge the foundation to the level where hard-core was found to make the building strong. This again was based on the recommendation by the agency issuing construction permits in the city. Despite all this, we have tried our best and the construction work has come up very beautifully. We are hopeful that when it starts to rain again, we shall be able to move very fast with the work. This is in spite of the fact that much of the funding would reach us to roofing level. We have ambitions plan to have the construction work go up to level three given that we do not have much land and foreseeing the number of children who are coming to seek for education through the temporary structures we have since put up. Bulldozer at site digging out the wastes Construction site after waste was removed. Setting up the pillars to make the foundation strong Re-filling the site with hard core materials Casting the foundation before re-filling Laying the foundation at the casted foundation Re-filling the casted foundation Murram compacted ready for foundation setting Foundation footing Walling starts Construction stage as at present Challenges DADREG has faced in constructing ECD 1. Dredging the construction site: We never thought that setting up a foundation was going to involve dredging the whole site. It took 20 tones Lorries to go 29 trips to clear the wastes. It also took 20 tone Lorries to go 30 trips to bring in hard core to fill in the dredged site where waste soils were removed. The excavation costs, transportation, refilling and foundation setting were very high as they were never part of the budget that we presented. Thus it eats in our budget line. 2. Construction Permits: It took DADREG four months to receive the construction permit. This really took allot of time to settle and start the construction work. 3. Drought: Since October 2016, Kenya has been experiencing long dry spell. This has meant that we are to stop the construction work due to lack of water. EXPENDITURE: Total grant from the Lara Jones Charitable Foundation was £19,851 (Kshs.2,818,842) NATURE OF WORK DONE Detail Units Preliminary drawings and approvals by county government As per our statutory requirements, we needed approvals of our drawings from a locally registered architect who registers our works with the county government to meet the required building codes structurally as well as architectural. Statutory charges for site board ( This was paid by DADREG) Unit costs 197,500.00 Sub Total 1. EXCAVATION/ SETTING OUT Sub Total Costs 197,500.00 The site had previously been used as a dumping ground and hence more work was involved in the excavation works to reach the actual depth for foundation bases. Costs were charged by the county government for soil dumping. (This work was subcontracted because of the nature of works and equipment involved) Hiring 1 excavator (bulldozer) to excavate and load wastes into trucks. Transport of wastes to the government designated site, including dumping charges (20 trips of lorries) 310,000 310,000 6,000 120,000 430,000 2. FOUNDATION FOOTING/ COLUMN BASES This process involves mixing mortar (sand, cement and ballast) to form a firm face so as to prepare to lay the foundation bed and column reinforcements. As recommended by the structural Engineer. Hire of mortar to smoothen the hardcore & smoothen surface 54 bags of cement Y12 Steel (20 m) 4,000 710 1,200 38,340 24,000 Sand (3 lorries) 24,000 72,000 Ballast (4 lorries) 32,000 128,000 550 2,400 1,200 17,600 2,400 10,800 Y8 Steel (32m) Binding Wire Labour (1 foreman) x 9 days Labour (8 casuals) x 7 days 850 47,600 72 344,740 79,200 Sub Total 3. FOUNDATION WALLING Setting and laying building blocks 9by9 as recommended by the engineer. Building block 9by9 (1,100 stones) This is the process of filling the foundation area with murram, compacting and leveling to prepare for the ground floor slab Contract for re-filling (murram) Labour (I foreman) x 4 days Labour (7 casuals) – to spread the murram ready for compacting x 4 Cement (94 bags) Sand (2 lorries) Labour (1 foreman) x 9 days Labour (7 casuals) x 6 days 710 24,000 1,200 850 66,740 48,000 10,800 35,700 240,440 280,000 1,200 850 280,000 4,800 23,800 Sub Total 4. BACK FILLING Sub Total 5. CASTING SLAB(GROUN D)/COLUMNS 308,600 To prepare the surface for casting, We use a polythene sheet as an under slab vapor barriers and BRC 145 for reinforcing the force spread and firmness of the floor slab. Hire of mortar mixer Hire of vibrator machine Cement (158 bags) Sand (5 lorries) Ballast (3 lorries) Y8 (25 M) Labour (foreman 1) x 3 days Labour (casuals 12) x 1 day 21,000 8,000 710 24,000 32,000 550 1,200 850 Preparing boxes for the columns poles and trappers for the verandah. Polythene sheet (2 rolls) Binding wire (2 rolls) Wooden Planks (hiring) Y12 Steel (40 m) 3,500 2,400 7,500 850 21,000 8,000 112,180 120,000 96,000 13,750 3,600 10,200 384,730 7,000 4,800 7,500 34,000 Y16 Steel (20 m) 1,200 24,000 Nails 3 inch (2kg) Nails 4 inch (3 kg) Labour (foreman 1) x 1 day 12 16 1,200 24 48 1,200 850 10,200 Building stones (6 by 6) 640 units 54 91,972 34,560 Building stones (6 by 9) 2,100 units 62 130,200 710 1,200 850 119,280 14,400 76,500 374,940 Sub Total 6. FORMWORK/ REINFORCEME NT FOR COLUMNS Labour (casual 12) x 1 day Sub Total 7. WALLING Sub Total TOTAL AMOUNT Building the walls and partitioning of the building as illustrated on the architectural drawing. The walling was done at least 7 courses Cement (168 bags) Labour (1 foreman) x 12 days Labour (casuals 9) x 10 days 2,175,422
© Copyright 2026 Paperzz