Dr. Charles Drew College Preparatory Academy Paint Plan

Dr. Charles Drew College Preparatory Academy
Paint Plan
SFUSD FUTURE DINING EXPERIENCE
SFUSD FUTURE DINING - DR. CHARLES DREW COLLEGE PREPARATORY ACADEMY
February 3, 2017
DO NOT REMOVE THIS
PAINTING
WALL
Benjamin Moore
White Dove
OC-17
WALLS
Benjamin Moore
White Dove OC-17
EXIT ALCOVE
BEYOND STAGE
Benjamin Moore
White Dove
OC-17
DOORS
Benjamin Moore
Cinnabar
CSP-1165
TRIM & STAGE
Benjamin Moore
Brownstone
CSP-240
General Sheet Notes:
1. Paint all previously painted wall surfaces, including columns.
2. Paint all conduits (including those not previously painted) on all walls, columns, and
other surfaces scheduled for painting under this contract.
3. Remove all existing paintings, artwork, bulletin boards or tackboard surfaces, posters, pictures, etc. on affected walls to be painted, and SALVAGE for school
4. Preserve mural and picture of Dr. Charles Drew near stage as noted on the drawings.
CAFETERIA WINDOW WALL ELEVATION - EXISTING CONDITIONS
NOT TO SCALE
SFUSD FUTURE DINING - DR. CHARLES DREW COLLEGE PREPARATORY ACADEMY
October 27, 2016
ACT+TILE WALLS
Benjamin Moore
White Dove
OC-17
DOORS
Benjamin Moore
Cinnabar
CSP-1165
UPPER WALL AREA
Benjamin Moore
White Dove
OC-17
DOOR TRIM & RADIATORS
Benjamin Moore
Brownstone
CSP-240
WALLS
Benjamin Moore
White Dove OC-17
DO NOT PAINT OVER
MURAL!!!
General Sheet Notes:
1. Paint all previously painted wall surfaces, including columns.
2. Paint all conduits (including those not previously painted) on all walls, columns, and
other surfaces scheduled for painting under this contract.
3. Remove all existing paintings, artwork, bulletin boards or tackboard surfaces, posters, pictures, etc. on affected walls to be painted, and SALVAGE for school
4. Preserve mural and picture of Dr. Charles Drew near stage as noted on the drawings.
CAFETERIA ENTRY WALL ELEVATION - EXISTING CONDITIONS
3/16”=1’-0”
SFUSD FUTURE DINING - DR. CHARLES DREW COLLEGE PREPARATORY ACADEMY
October 27, 2016
ACT & TILE WALL
Benjamin Moore
White Dove
OC-17
UPPER WALL AREA
Benjamin Moore
White Dove
OC-17
WALLS
Benjamin Moore
White Dove OC-17
VESTIBULE
Benjamin Moore
White Dove
OC-17
DOORS
Benjamin Moore
Cinnabar
CSP-1165
TRIM & PONY WALL NEXT
TO FOUNTAIN
Benjamin Moore
Brownstone
CSP-240
General Sheet Notes:
1. Paint all previously painted wall surfaces, including columns.
2. Paint all conduits (including those not previously painted) on all walls, columns, and
other surfaces scheduled for painting under this contract.
3. Remove all existing paintings, artwork, bulletin boards or tackboard surfaces, posters, pictures, etc. on affected walls to be painted, and SALVAGE for school
4. Preserve mural and picture of Dr. Charles Drew near stage as noted on the drawings.
CAFETERIA SERVERY WALL ELEVATION - EXISTING CONDITIONS
3/16”=1’-0”
SFUSD FUTURE DINING - DR. CHARLES DREW COLLEGE PREPARATORY ACADEMY
October 27, 2016
ACT & TILE WALL
Benjamin Moore
White Dove
OC-17
UPPER WALL AREA
Benjamin Moore
White Dove
OC-17
WALLS
Benjamin Moore
White Dove OC-17
PLEASE PAINT
VESTIBULE BM
OC-17 WHITE
DOVE
DOOR TRIM & RADIATOR
Benjamin Moore
Brownstone
CSP-240
DOORS
Benjamin Moore
Cinnabar
CSP-1165
General Sheet Notes:
1. Paint all previously painted wall surfaces, including columns.
2. Paint all conduits (including those not previously painted) on all walls, columns, and
other surfaces scheduled for painting under this contract.
3. Remove all existing paintings, artwork, bulletin boards or tackboard surfaces, posters, pictures, etc. on affected walls to be painted, and SALVAGE for school
4. Preserve mural and picture of Dr. Charles Drew near stage as noted on the drawings.
CAFETERIA STAGE WALL ELEVATION - EXISTING CONDITIONS
NOT TO SCALE
SFUSD FUTURE DINING - DR. CHARLES DREW COLLEGE PREPARATORY ACADEMY
October 27, 2016