Official PDF , 6 pages

Public Disclosure Authorized
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
Fifth Power System Development Project (P115566)
SOUTH ASIA | India | Energy & Extractives Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2010 | Seq No: 13 | ARCHIVED on 24-Jul-2015 | ISR19654 |
Public Disclosure Authorized
Implementing Agencies:
Key Dates
Key Project Dates
Board Approval date:22-Sep-2009
Effectiveness Date:08-Jan-2010
Planned Mid Term Review Date:16-Sep-2013
Actual Mid-Term Review Date:26-Oct-2013
Original Closing Date:30-Jun-2015
Revised Closing Date:31-May-2017
Public Disclosure Authorized
Project Development Objectives
Project Development Objective (from Project Appraisal Document)
The project development objective is to strengthen India's electricity transmission system in order to increase reliable power exchange between
regions and states.
Has the Project Development Objective been changed since Board Approval of the Project Objective?
No
PHRPDODEL
Components
Name
Public Disclosure Authorized
Transmission System Stregthening Schemes:(Cost $1000.00 M)
Overall Ratings
Name
Previous Rating
Current Rating
Progress towards achievement of PDO
 Satisfactory
 Satisfactory
Overall Implementation Progress (IP)
 Satisfactory
 Satisfactory
Overall Risk Rating
 Low
 Low
Implementation Status and Key Decisions
The implementation support mission for the project was carried out from April 13-June 30, 2015. Almost 66% of the loan stands disbursed as on date
7/24/2015
Public Disclosure Copy
Page 1 of 6
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
with two years remaining for loan closing date.
As of end March 2015, the outcome indicator (inter-regional power exchange in a year) has out-performed (provisional: 84,368MU) its revised targets
(70,000 MU). In addition to the Outcome Indicator, four other key results indicators that helped track project performance are: (a) transmission capacity measured in overall circuit kilometers of transmission lines built and operated by POWERGRID; (b) transformation capacity - measured in circuit
kilometer; (c) Percent of project affected people rehabilitated - measured in percent; and, (d) cumulative transmission capacity per meter width of rightof-way within forest area.. At the end of March 2015, the transmission capacity was 115,637ckm (actual) against a target of 114,000 ckm. Similarly,
POWERGRID's transformation capacity was 231,709MVA (actual) against a target of 200,000 MVA. With regard to indicators on environment and
social, POWERGRID has also met its targets for FY2015 (% of people rehabilitated - Actual 100% against target of 100%); and, cumulative
transmission capacity per meter width of RW within forest areas - Actual 23.08 MW/ meter against target of 21.5 MW / meter.
Risks
Systematic Operations Risk-rating Tool
Risk Category
7/24/2015
Rating at Approval
Public Disclosure Copy
Previous Rating
Current Rating
Page 2 of 6
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
Political and Governance
 --
 Low
 Low
Macroeconomic
 --
 Moderate
 Moderate
Sector Strategies and Policies
 --
 Moderate
 Moderate
Technical Design of Project or Program
 --
 Moderate
 Moderate
Institutional Capacity for Implementation and
Sustainability
 --
 Low
 Low
Fiduciary
 --
 Low
 Low
Environment and Social
 --
 Low
 Low
Stakeholders
 --
 Moderate
 Moderate
Other
 --
 --
 --
Overall
 --
 Low
 Low
Results
Project Development Objective Indicators
PHINDPDOTBL

Growth in power exchange between and across regions (Millions kWh) (Text, Custom)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
46,027 Gwh
78,384 GWh
84,368 GWh
75,000 Gwh
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
71,447 ckt-km
106,804 ckm
115,637 ckm
125,000 ckm
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
Overall Comments
Intermediate Results Indicators
PHINDIRITBL

Growth in transmission capacity (circuit km) (Text, Custom)
7/24/2015
Public Disclosure Copy
Page 3 of 6
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
PHINDIRITBL

Growth in transformation capacity (MVA) (Text, Custom)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
79,522 MVA
205,923 MVA
231,709 MVA
222,000 MVA
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
PHINDIRITBL

Implementation of ESPP - Social (percent of PAPs rehabilitated) (Text, Custom)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
0%
100%
100%
100%
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
PHINDIRITBL
 Implementation of ESPP - Environment - Cumulative transmission capacity (MW) per meter width of right-of-way within forest
area (Text, Custom)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
18.6 MW/metre
22.15
23.08
21.7 MW/metre
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
PHINDIRITBL

Transmission lines constructed or rehabilitated under the project (Kilometers, Core)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
0.00
1115.00
1115.00
3628.00
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
7/24/2015
Public Disclosure Copy
Page 4 of 6
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
PHINDIRITBL

Transmission lines rehabilitated under the project (Kilometers, Core Breakdown)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
0.00
0.00
0.00
0.00
Date
31-Mar-2009
31-Mar-2014
31-Mar-2015
31-May-2017
PHINDIRITBL

Transmission lines constructed under the project (Kilometers, Core Breakdown)
Baseline
Actual (Previous)
Actual (Current)
End Target
Value
0.00
1115.00
1115.00
3628.00
Date
31-Mar-2009
28-Feb-2014
31-Mar-2015
31-May-2017
Overall Comments
Data on Financial Performance
Disbursements (by loan)
Project
Loan/Credit/TF
Status
Currency
Original
Revised
Cancelled
Disbursed
Undisbursed
Disbursed
P115566
IBRD-77870
Effective
USD
1,000.00
1,000.00
0.00
664.01
335.99
66%
Key Dates (by loan)
Project
Loan/Credit/TF
Status
Approval Date
Signing Date
Effectiveness Date
Orig. Closing Date
Rev. Closing Date
P115566
IBRD-77870
Effective
22-Sep-2009
13-Oct-2009
08-Jan-2010
30-Jun-2015
31-May-2017
Cumulative Disbursements
7/24/2015
Public Disclosure Copy
Page 5 of 6
Public Disclosure Copy
The World Bank
Implementation Status & Results Report
Fifth Power System Development Project (P115566)
Restructuring History
Level 2 Approved on 23-May-2014
Related Project(s)
There are no related projects.
7/24/2015
Public Disclosure Copy
Page 6 of 6