DESIGN AND CONSTRUCTION OF A CUT-OFF WALL IN WARM PERMAFROST Steven L. Anderson, P.E., Senior Geotechnical Engineer and Associate, Golder Associates Inc. Brian W. Wilson, P.Eng., Regional Leader – Western Canada, GAIA Contractors Matthew Tonner, E.I.T., Engineer, GAIA Contractors A cut-off wall has been designed and is currently under construction along the Back Dam of the existing tailings impoundment at Red Dog Mine, Alaska. The cut-off wall, which will be in the order of 5,000 ft long and up to 150 ft deep, when complete, is being excavated using a 40 metric ton Bauer trench cutter head mounted on a Liebherr crawler crane, in combination with a closed loop slurry pumping and de-sanding system. The tailings impoundment is situated in an area of warm permafrost and high potential seismic activity. Design incorporated an assessment of rock jointing to define the final depth of the wall along the alignment requiring the use of plastic concrete backfill to address the concerns associated with potential cracking of the wall due to settlement and during seismic activity. The results of the geotechnical investigation program, particularly with respect to variation in rock hardness along the wall alignment are discussed, as are the design criteria for the plastic concrete backfill, the challenges faced during construction, including scheduling of the work with the on-going dam raise activities of the mine, and the lessons learned with respect to potential productivities and selection of cutter wheels and teeth. Also described are the requirements for and advantages of utilizing a slurry boosting system to meet pumping requirements, re-design of the plastic concrete mix to consider workability and optimization of cutter teeth configurations to reduce wear through highly varied rock hardness. Keywords: Cut-off wall; dam design; geotechnical investigation; trench cutter. Introduction In 2002 Teck Alaska Inc. (TAK) commissioned Golder Associates Inc. (Golder) to design a Back Dam to minimize the potential for seepage at the southern end of the tailings impoundment at Red Dog Mine, Alaska. The Back Dam was to be designed for an elevation of 960 ft with a planned closure elevation of 986 ft and was to include provisions to reduce long-term seepage through the native materials and weathered bedrock. Figure 1: Back Dam Location The initial design concept included construction of a cofferdam with installation of a geomembrane liner on the upstream face of the Overburden Stockpile that would be keyed into silty native soil of relatively low permeability. A geotechnical investigation completed by Golder in 2004 found ice-rich and organic materials as well as highly fractured bedrock near the liner keyin elevations, effectively rendering this concept unacceptable. During revision of the Back Dam design to account for the findings of the 2004 investigation, and to address the concerns of regulatory bodies, TAK requested that Golder revise the design and incorporate a cut-off through the proposed Back Dam embankment, extending to low permeability frozen bedrock to reduce the risk of long-term seepage through the native materials and weathered bedrock. Several cut-off wall options were evaluated including sheet pile installation, vibrated beams and slurry trench installation, extension of the geomembrane liner into a trench, and a cut-off wall constructed using a deep soil mixing process; specifically with the Bauer Cutter Soil Mixer (CSM). Following discussions with Golder Associates Innovative Applications (GAIA) Inc., and review of the CSM operation at a site in British Columbia, Canada, the option of constructing the cut-off wall using the Bauer CSM through an embankment situated between the Overburden Stockpile and the cofferdams was selected. Subsequent discussions with the regulators indicated that completion of a cut-off to the frozen bedrock alone would not be adequate and that the design should consider the effects of some thawing of the permafrost with possible seepage through the thawed bedrock. In 2005 and 2006, Golder completed additional geotechnical investigations along the southern cofferdam to determine the depth to unweathered, low permeability bedrock, assuming thawed conditions. Ice-rich materials and organics were encountered in the overburden soils overlying weathered and highly fractured bedrock. Low permeability bedrock was encountered and recorded at variable depths along the alignment, with the deepest section at about 170 ft below the proposed dam crest elevation of 960 ft. Following this investigation it was obvious that use of the Bauer CSM would no longer be practical due to the extent of rock excavation required, hence this method was withdrawn and replaced by a deeper cut-off constructed using a Bauer Trench Cutter. Design proceeded on this basis with TAK planning to construct the embankment dam using their own forces, whilst retaining GAIA in 2007 in the role of general contractor for construction of the cut-off through the Back Dam. that surface water and shallow groundwater greatly influenced the thermal stability of the permafrost soils. Between 1995 and 1997, seven thermistor strings were installed within the Overburden Stockpile. Temperature readings from these thermistor strings indicate the permafrost had aggraded into portions of the stockpile and the depth to the top of permafrost varied between about 15 ft to 70 ft below the ground surface (Water Management Consultants 1999). Thermistor readings were also taken during the 2005/2006 geotechnical investigation that indicated an average thaw depth of 18 ft below the native soil surface and average permafrost temperatures of about 31°F (-0.6°C). The deepest thaw depths were located near historic drainages. Subsurface Conditions Subsurface conditions have been characterized near the proposed cut-off wall location from the geotechnical investigations completed in 2004 through 2006 that included 15 boreholes near the north face of the Overburden Stockpile and 26 boreholes along the southern cofferdam and near the abutments. The locations of these boreholes are shown in Figure 2 with subsurface profiles shown in Figures 3 and 4. These investigations also included test pits, thermistor string readings, packer tests, and laboratory testing. Site Characteristics The Red Dog Mine is located approximately 90 miles north of Kotzebue, Alaska at about 68 degrees latitude. The proposed Back Dam is located at the north end of the Overburden Stockpile, as shown in Figures 1 and 2. Climate The climate at the Red Dog Mine is characterized by long, cold winters and moderately warm, windy and somewhat rainy summers. The average annual temperature is 24°F (-4°C) with an air freezing index (AFI) of 4731°F-days and an air thawing index (ATI) of 1899°F-days. Total precipitation is generally between 10 to 13 inches per year and the average annual snowfall is 48 inches. Thermal Conditions In the early 1980’s the Red Dog Mine site was the subject of various feasibility and design studies. These early investigations (including the installation of about 50 thermistor strings) indicated that relatively warm permafrost was present at the mine site, and Fill materials were encountered on the haul roads, cofferdam, and Overburden Stockpile. The waste rock fill materials at the haul road and cofferdam generally had a composition of silty gravelly soil with occasional cobbles and boulders. Fill materials at the Overburden Stockpile mainly consist of Kivalina shale that had been stripped from the mining area. The native soils are colluvial and alluvial materials comprised of organic soil, ice and ice-rich soil, silty clayey soil and sandy gravelly soil. The shale bedrock underlying the colluvial and alluvial materials is typically highly to completely weathered near the contact surface becoming fresher with depth. The rock is generally fractured with a rock quality designation (RQD) of less than 20%. Rock strengths vary from weak (R2) to very strong (R5) with estimated uniaxial compressive strengths (UCS) up to 22,010 psi. The majority of bedrock encountered during the investigations, about 75%, had a UCS that was less than 7,500 psi. Design Considerations Cut-off Wall Alignment The embankment dam and associated cut-off wall alignment was selected to limit the amount of excavation into the Overburden Stockpile and minimize disturbance of the cofferdam. Using an excavation surface derived from the borehole and ground topography data, an alignment for the embankment and cut-off wall was developed based on criteria that included: Figure 2: Borehole Locations Figure 3: Section A through Cofferdam Maintaining the cut-off wall within the center of the constructed embankment to protect the cut-off wall from slope instability issues. Using 1H:2V (horizontal to vertical) slopes for the excavation prism starting a distance of 1.5 ft out from the alignment centerline at an elevation of 986 ft. The offset distance was based on a 3 ft cut-off wall width and the slope angle was based on the 2 to 1 stress distribution method, which is an empirical approach based on the assumption that the area over which the load acts increases in a systematic way with depth. Figure 4: Section B through Overburden Stockpile Cut slopes were developed based on natural slope angles with flatter cut slopes expected on the northern side of the alignment within the impoundment area. A limited amount of excavation into the cofferdam was considered tolerable depending on the seepage flows encountered after dewatering. Cut-off Wall Embankment Section The cut-off wall embankment was designed to consist of a central section composed of select fill produced from screened crushed rock and compacted in controlled lifts to 95% maximum dry density (modified proctor) to optimize strength and limit impacts from settlement. The select fill width was arbitrarily set at 20 ft for crest elevations of 986 ft and higher with 1H:3V side slopes. This provides a base width that is equivalent to the estimated deepest fill height (a criterion similar to what is used for impervious core dams) and keeps the select fill within the base excavation limits. The 20 ft width also allows for future raises, if required. Rockfill, placed in controlled lifts and compacted with a minimum number of passes with a roller, was used as fill outside of the select fill prism to provide additional stability with 3H:1V side slopes. The rockfill materials were produced from waste rock from the mining operations or borrowed from other rock quarry areas. Some maintenance and additional fill placement is expected as the underlying ice-rich materials slowly thaw and consolidate, possibly including as much as 9 ft of differential settlement in areas where the ice thaws quickly. The integrity of the cut-off wall, which is supported by the select fill section, would not be affected by these deformations since they would likely be restricted to the fill materials outside of the select fill section. The proposed trench cutter and base carrier require a minimum work area of about 30 ft from the centerline of the cut-off wall alignment; therefore, the width of the embankment crest was designed to be about 60 ft to keep the cut-off wall within the center of the embankment. Due to the nature of the equipment, cut-off wall construction requires a level work surface for the trench cutter to sit on. Stepped benches were therefore incorporated into the design where the elevation increases at the abutments. In addition, a stepped bench was required at the deepest wall section due to the excavation limits of the proposed trench cutter. The BC40 carrier was equipped with a cable reel that could only extend the cutter to 150 ft, necessitating a wall raise for the deepest sections. Cut-off Wall Panel Target Depths The depth to low permeability bedrock, which was defined as rock having a permeability of 1x10-6 cm/sec or lower, was established during the 2005/06 geotechnical investigation. Since the rock was frozen, conventional packer tests were impractical. Permeability of the bedrock was therefore typically determined using visual methods. The visual criterion for apparent low permeability was one or less tight fractures per foot for a minimum length of three feet. Based on this criterion, the depth to apparent low permeability bedrock is shown in Figure 3. The cut-off wall panels were designed to be keyed 3 ft into the apparent low permeability bedrock. As is evident, the depth to the low permeability zone varies significantly along the length of the wall. The deepest panel areas are located near historic drainages. These deeper zones of higher permeability bedrock are believed to be caused by freeze/thaw cycles and other weathering affects. The shallower panels are located outside of these historic drainages and in areas where the bedrock surface was encountered at a higher elevation. Therefore, these higher areas have not been exposed to the same degree of weathering and are less fractured at depth. There appeared to be no apparent correlation of rock hardness with depth, hence productivity of the cutter could not be used as an inferred guide to modify planned depths in the field, and construction had to rely on the visual interpretation of target depth from the investigation. Thermal Considerations The cut-off wall is expected to be susceptible to degradation from freeze-thaw cycles; therefore, once a section is complete, an insulated section is installed over the top of the wall to prevent frost penetration into the top of the cut-off wall. Due to the warm permafrost temperatures, which are near 31°F, the frozen ground conditions are not expected to affect the cut-off wall installation, and in particular the hydration of cement in the plastic concrete mix. After the cut-off wall has been constructed, we expect the permafrost will aggrade into the fill embankment as it did into the Overburden Stockpile. Engineering Analyses Engineering Analyses performed for the design included seepage modeling, slope stability analyses (for the constructed embankment and cofferdam), hydrology and hydraulic analyses, thermal modeling, settlement, trench stability, and mix design of the cut-off wall materials. Mix Design The performance goals for the mix design were developed based on the engineering analyses described above with the requirement that the cut-off maintain its function as a low permeability barrier following settlement of the embankment as a result of thaw of the underlying permafrost, or following seismic activity. Since the analyses indicated that settlements and stability are not expected to be major design concerns, the minimum mix design compressive strength and deformity was determined qualitatively to be 100 psi and 5% strain, respectively. A minimum permeability of 1x10-6 cm/sec was selected based on the seepage analyses; however, a performance specification was provided based on a flux value of 0.007 gpm/ft width for a head loss of 23 ft and a minimum wall thickness of 2.6 ft to possibly reduce material quantities and save costs. This specification was to provide a maximum flow rate of about 40 gpm across the entire cut-off wall. Mix design testing was carried out at Golder’s laboratory in Burnaby, British Columbia, Canada using the following available materials: Potable water available at site (pH = 7) Type I cement meeting ASTM C150 Bentonite meeting API 13A, Section 9 ¾-inch minus crushed rock from site, which was passed through an LA abrasion device to simulate cuttings from the Trench Cutter The mix design results are shown in Table 1. Based on these results, Mix Design No. 4, which is 19% water, 10% cement, 3% bentonite, and 68% aggregate, met the performance criteria of 100-psi minimum compressive strength and a maximum permeability of 1x10-6 cm/sec at a strain of 5%. As is discussed below however, this mix design was modified in the field to better suit constructability requirements. Construction Additional Investigation and Re-design The original geotechnical investigation programs were completed from the cofferdam or the overburden stockpile and so were not on the actual alignment of the proposed cut-off wall. The data from these investigations had been used to formulate the original design which had formed the basis of the agency approvals to proceed with the construction. Based on a review of this data, and in particular the dip angle of the joints within the rock, it was considered likely that additional investigations along the final alignment may yield reduced excavation depths as a result of encountering low permeability rock at shallower depth. TAK agreed to complete additional investigations and commissioned a drilling program that was carried out in late 2007 along the 2008 alignment construction zone and late 2008 along the 2009 and 2010 alignment construction zones. As suspected this investigation did indeed indicate low permeability rock at shallower depths directly on the cut-off alignment as shown in Figure 5. These findings allowed development of a revised configuration for the wall and removed the need for a lower stepped bench along what was previously the deepest portion of the cut-off wall. The revised configuration streamlined the embankment construction and effectively reduced the cut-off wall surface area by approximately 70,000 ft2 with consequent savings in the order of $3M. Figure 5: Revised Panel Depths (Cross Hatch Represents Area Removed from Original Panel Depths) Excavation and Embankment Construction Excavation and embankment construction is being carried out by TAK in advance of the cut-off wall construction, with construction quality control (CQC) provided by Golder. All ice-rich and organic soils are removed from within the embankment footprint to expose suitable native sub-grade prior to placing the select fill central section. The select fill material for the embankment construction is crushed on site and placed in one-foot lifts using a fleet of bottom-dump haul trucks. The material is spread using a grader, and compacted using an 8-ton vibratory roller. An example of some of the ice-rich materials encountered during the excavation is shown in Figure 6. Embankment construction started in May 2007 over the western half of the alignment, but had only advanced to an elevation of 960 ft prior to beginning the cut-off wall construction in July/August of that year. During the winter of 2007/2008 the design crest elevation was raised to 970 ft due to discharge limitations of the impoundment. This increased design elevation required a 10 ft raise of the cut-off wall sections constructed from the 960 ft elevation. Due to the requirement for TAK resources on other projects at the site further progress of embankment construction was slow in 2008 and in the early part of 2009, increasing the necessary length of the 10 ft wall raise. These constraints were effectively managed by TAK staff to keep the embankment construction ahead of the cut-off wall construction. Embankment construction continued throughout the 2009 season ensuring completion of the entire alignment in advance of the 2010 cut-off wall construction. Figure 6: Massive Ice Encountered During Excavation Table 1: Mix Design Results Mix Type Sample Number Age Wet Density (days) (cm/sec) 1A 46 83 3A 19 78 4B 42 129 Plastic 4A 80 129 Concrete 5A 19 131 Strain of Sample 5A limited by capacity of load cell Plastic Cement Permeability Before Strain (cm/sec) 2.6E-07 6.3E-06 6.8E-08 6.0E-08 3.5E-08 Maximum Deviator Stress (psi) 231 26 452 514 749 Tangent Modulus Maximum Strain Permeability After Strain (tsf) 2109 829 5127 3592 8135 (%) 8.3 8.1 7.7 17.7 1 (cm/sec) 2.8E-7 8.6E-6 8.4E-7 1.8E-6 6.9E-7 Cut-off Wall Construction The cut-off wall is being constructed by GAIA Contractors, the wholly owned specialized contracting subsidiary of Golder’s Canadian company. The work is being completed with specialist assistance from Bauer Maschinen and subcontractor Alaska Interstate Construction (AIC) who have provided much of the support equipment and associated labor. About 4,000 ft2 of cut-off wall was constructed in 2007 to evaluate the performance of the cutter heads, the slurry transport systems, and the mix design. Cut-off wall construction continued in 2008 and 2009 operating with two 12-hour shifts from May to October. Approximately 148,000 ft2 of wall was completed in 2008 and 150,000 ft2 in 2009. In addition, 700 lineal feet of wall raise was completed in 2009. The project is expected to be completed in late August 2010. Methodology The cut-off wall is constructed by excavating and installing the wall in a series of primary and secondary panels with 6” overlaps to ensure a continuous cut-off wall. Construction begins by installing reinforced concrete guide walls to help support the near surface soils and provide alignment and continuity for the cut-off wall. The panel is then pre-excavated to sufficient depth and slurry introduced into the shallow trench between the guide walls to allow submergence of the slurry mud pump situated on the trench cutter. Cutting of the wall can then begin. Proper installation of the guide walls is paramount to maintain stability of the upper portion of the trench and to control the alignment of the trench cutter. The lateral load from the base carrier and the low differential head provided by the bentonite slurry near the surface render the guide walls absolutely necessary to provide an active form of support to the surrounding soils. The guide walls also serve to properly support and align the cutter guide frame, a vital piece of equipment used to launch the cutter on a straight and aligned path. In addition the guide walls act as a secure location for marker pin installation on the outer limits of the panels ensuring effective survey quality control. As excavation proceeds the operator utilizes the steering plates situated near the top and bottom of the cutting frame to ensure that the alignment of the cutter is plumb and the panel excavated vertically at the desired location. The verticality of the panel is monitored using inclinometers outfitted on the cutter frame and recorded using real time software which is downloaded daily for quality control purposes. Excavation of each panel continues to the design depths with additional slurry being added as necessary to ensure that the hole remains full. The deeper panels on the alignment take in the order of 14 hours to complete. During excavation, the slurry, which contains the cuttings from the overburden and rock, is pumped through a screen and cyclone-based desander where the cuttings are removed from the slurry down to a 0.060-mm grain size. The re-conditioned bentonite is then recycled and continually used for stabilizing the trench and transporting the cuttings to the desander, or is sent to the storage tanks when the system is overloaded or shutdown. Once the panel has been cut to the target depth, the working slurry in the excavated column is tested for sand content. Slurry with a sand content of less than 1% is adequate in providing a clean displacement during the plastic concrete backfilling process. Alternatively, the panel will be flushed with fresh bentonite to produce the desired sand content before the plastic concrete is backfilled using a tremmie pipe. An aerial view of the on-going work is shown in Figure 7. Wall Raises As previously discussed, to accommodate the delays in alignment fill placement, the trench cutting test pilot work carried out in 2007 and much of the work carried out in 2008 were completed from an embankment crest elevation of 960 ft, ten feet below the 970 ft design crest elevation. As a result these sections of cut off wall (about 700 lineal feet) required construction of a vertical extension to the final grade. Figure 7: Embankment Showing Bauer Trench Cutter in Operation, On-Going Concrete Backfilling Process and the Bentonite Treatment Plant Originally it was envisioned that this work would be completed using conventional concreting techniques by forming and pouring the wall, effectively cutting off all alignment access for remaining construction works. However, a method was developed on site that allowed the embankment to be filled to the final grade while providing continual alignment access and no subsequent delays in the trench cutting. The method used as-built survey information to install the guide walls at elevation 970 ft along the alignment over the existing top of the cut-off situated ten feet below grade at elevation 960 ft. Similar to the trench cutting process, the installed guide walls provided active support of the soil at ground surface during a 30-foot long, 14-foot deep trench excavation required to expose the top of the existing wall and provide adequate key in. The wall raise excavation was completed using a flat edge clean up bucket that scraped the top of the existing wall clean of any sloughed gravel and residual hydrated bentonite. A cement bentonite grout was poured and mixed on to the existing wall to provide a bond between the existing cured plastic concrete and the freshly backfilled plastic concrete bentonite. Cutter Wheels and Cutter Teeth Trench cutters are typically fitted with one of three types of wheels and teeth. The configuration of cutting wheel used in Red Dog is called the round shank mount (RSM) wheels (Figure 8). These wheels cut a variety of rock hardness ranging from R1 to R5 and are ideally suited for the conditions encountered along the Back Dam alignment. The other two widely used wheel configurations include the flat tooth wheels (the original wheel set used in the 2007 pilot test) and bullet tooth wheels. Flat tooth wheels are extremely efficient in soft rock and clay like conditions as they are able to cut and scoop large quantities of material, but are unproductive for the R2 to R5 rock that makes up 60% of the required cutting through the Back Dam alignment. Bullet tooth wheels are a configuration of large conical shanks with multiple carbide tips capable of grinding and cutting large columns of R4 to R6 rock, but were not economically feasible for this particular application. For construction through the 2008 season, ten types of RSM teeth were purchased in an effort to optimize tooth wear and cutting production. Supplied by Betek, Sandvik, and Kenametal, all of these teeth proved capable through various rock conditions; however, the small surface area on the tips of the Betek and Sandvik teeth made them more capable through the harder rock zones. The larger surface area of the Kenametal teeth made them more useful in areas of softer and more weathered rock. Due to varying teeth lengths and thicknesses it is crucial that the same types of teeth are used in unison on the wheels for even wear. Since the teeth used were adapted to match the anticipated rock hardness on a day to day basis, the production variations among the teeth types were negligible through the 2008 and 2009 season staying relatively consistent at 0.04 teeth/square foot. A new order of the less expensive Sandvik teeth, capable of cutting in the majority of the conditions found at Red Dog, and some Betek teeth will finish out the 2010 seasons. The smaller quantities of Betek teeth are required as they prove most useful on the flap teeth, an important tooth that cuts underneath the cutter gear box, allowing the cutter to proceed down the hole without getting hung up on a ridge of rock that would otherwise be uncut. Slurry Booster System The slurry mud pump housed in the cutter is able to efficiently pump cutting-contaminated slurry up to a distance of 1500 linear feet back to the slurry treatment plant. When the cutter is operating more than 1500 linear feet from the treatment plant, the cutting progress is held up by the inability to transport the cuttings back to the plant at a rate that can match the cutter progress. On initial project set-up the slurry handling system was situated at approximate station 16+00 along the 5,000 foot long alignment. Under these circumstances it was anticipated that the treatment plant including all of the tanks, pumps, de-sanding equipment, piping, electrical and water lines would be moved at least once during the project to accommodate the maximum pumping distance of the cutter mud pump. However, scheduling issues meant that relocation of the plant had the potential to seriously impact the overall Back Dam construction schedule. As a result a slurry booster system was added to the existing system in 2009. Figure 8: Bauer Cutter Heads Showing RSM Wheel Setup The slurry booster system included a 6” diesel powered booster pump accompanied by an increased pipe diameter in the slurry return line. The ability to easily move the remote controlled pump along the alignment as required maintains consistent flows that, at a minimum, will keep up with the faster cutting rates experienced in the top 30 to 50 feet of select fill. The booster system increases production considerably in areas where minimal cutting effort is required. The added cost of the booster system equated to 2 weeks of crew site time, insufficient time to move the treatment plant to an alternate location, thus making the booster system economically feasible and extremely advantageous. Plastic Concrete Mix Design and Placement As previously discussed the review of preliminary mix designs indicated that Mix No. 4 would provide the appropriate properties for the design. However, after initial use of this mix during the 2007 pilot tests it was evident that the overall process and productivity could be enhanced with a changed mix design. The new mix design was developed around two additional criteria to the strength and permeability specifications. First, the new plastic concrete mix incorporated lower density bentonite slurry, as the slurry used in the original mix could not properly circulate through the pumps in the storage tanks. Second, the plastic concrete mix was developed around a minimum allowable slump of 7 inches to reduce the manual labor required in the backfill tremmie process and eliminate the bridging in the tremmie pipe that was inherent with the low slumps in Mix No. 4 (slumps of approximately 4 inches). Based on the desired plastic concrete mix quantity the concrete trucks load up with a volumetric amount of bentonite slurry at the treatment plant and then drive to a concrete batching plant to be loaded with aggregate and cement. Mixing is then completed in the ready mix truck prior to discharging into the panel excavations with the use of tremmie pipes. Instrumentation and Monitoring The final element of construction will be the installation of instrumentation and monitoring equipment. Instrumentation, including thermistor strings, piezometers, and survey monuments will be important to monitor the performance of the seepage reduction structure. Thermistor strings will be installed to monitor degradation or aggradations of the permafrost while standpipe piezometers will be installed to monitor water levels and seepage potential across the cut-off wall. Surficial survey monuments will be used to monitor settlement. Additional instruments installed within the cut-off wall, such as inclinometers and extensiometers will be used to monitor vertical and horizontal movements, which are also vitally important to our understanding of the performance of the cut-off wall. Conclusions Experience on this project indicates that the trench cutter is a very effective tool for the construction of deep cut-off walls extending through both overburden and rock. Careful selection of the type of cutting wheel, as well as type of tooth, is important to generate optimal production, particularly when dealing with highly variable rock strengths. Management of the slurry mixing and delivery processes, as well as careful consideration of the handling properties of the mix design for the wall should also be given detailed consideration during planning of the project. References HAMMER, T.A. et al. 1985. Ground temperature observations. Thermal Design Considerations in Frozen Ground Engineering, pp 8-52. WATER MANAGEMENT CONSULTANTS. 1999. The phase II hydrologic characterization of the tailings impoundment.
© Copyright 2026 Paperzz