PARKS CANADA AGENCY ESPACE 400e AUDIT QUEBEC CITY FINAL OCTOBER 2007 Espace 400e Audit Parks Canada Agency © Her Majesty the Queen in right of Canada, represented by the Chief Executive Officer of the Parks Canada Agency, 2007 Catalogue Number: ISBN: OIAE 2 September 2007 Espace 400e Audit Parks Canada Agency TABLE OF CONTENTS SUMMARY 4 1. BACKGROUND 5 2. OBJECTIVES AND SCOPE 5 3. METHODOLOGY 6 4. ASSURANCE STATEMENT 7 5. CONCLUSION 7 6. OBSERVATIONS AND RECOMMENDATIONS 7 6.1 Management control framework 7 6.1.1 Conceptualization 8 6.1.2 Planning 9 6.1.3 Performance 11 6.1.4 Completion 11 6.2 Funds spent as planned 12 6.3 Fair and optimal use of contracting resources 13 APPENDIX A 14 OIAE 3 September 2007 Espace 400e Audit Parks Canada Agency SUMMARY 2008 will be the 400th anniversary of the founding of Quebec City, the first permanent French colony in North America. A committee made up of federal, provincial, Aboriginal and municipal government representatives is coordinating the anniversary celebrations. In May 2005, Treasury Board allocated $24 million to the Parks Canada Agency to develop the Louise Basin and the Espace 400e Pavilion, which will become a Parks Canada Discovery Centre in 2009. The Espace 400e project audit, a requirement of the Treasury Board submission, had been included in the Office of Internal Audit and Evaluation’s three-year plan for the 2007-08 fiscal year and was conducted by a team from the Office of Internal Audit and Evaluation. The objective of the audit was to provide senior management with an independent evaluation of the existence of an effective management control framework and give assurance that the funds allocated were spent as planned and that there was fair and optimal use of contracting resources. Visits to the Quebec City Field Unit and Service Centre were conducted between August 6 and August 31, 2007. Managers and staff in the field unit responsible for key financial processes were interviewed. The relevant supporting documents, contracts and invoices for the period of April 2005 to July 2007 were examined. In our opinion, the audit work carried out and the evidence gathered are sufficient to support the findings set out in this report. Overall, the audit team observed sound management and good cooperation between the various stakeholders involved in managing the Espace 400e project. The systems and controls in place are adequate and minimize the risk of non-compliance with PCA policies and procedures. The management control framework, expenditure of allocated funds, and fair and optimal use of contracting resources are under control; no recommendation is needed. According to the rating system used for audit reports, our observations allow us to conclude that the overall rating is: GREEN OIAE Controlled Controls are functioning as intended and no additional actions are necessary at this time. 4 September 2007 Espace 400e Audit Parks Canada Agency 1. BACKGROUND 2008 will be the 400th anniversary of the founding of Quebec City, the first permanent French colony in North America. This oldest city in Canada is the source of the Canadian values of cultural diversity and linguistic duality. In addition, the historic district of Quebec City is a UNESCO World Heritage Site. A committee made up of federal, provincial, Aboriginal and municipal government representatives is coordinating the anniversary celebrations. In May 2004, the committee, known as the Société du 400e anniversaire de Québec, commissioned an analysis of potential sites for “Espace 400e - un lieu de rencontre,” a focal point for the festivities marking the 400th anniversary. The Louise Basin in the Old Port of Quebec City was selected as the ideal venue for Espace 400e. In May 2005, a Treasury Board submission was approved giving the Parks Canada Agency (PCA) $24 million to develop the Louise Basin and the Espace 400e Pavilion (hereinafter referred to as “the project”). The Director General for Eastern Canada is responsible for establishing the general direction of the project and approving the management structure. Under his authority, the Director of the Quebec City Field Unit is responsible for overall management of the project. The Director works with the Quebec City Port Authority, the Société du 400e, the Commission de la capitale nationale du Québec, Public Works and Government Services Canada and Quebec City. The project consists more specifically in the expansion of the Old Port interpretation centre, which will become a Parks Canada Discovery Centre in 2009; production of cultural and thematic exhibits; upgrading of infrastructures around the Louise Basin; and development of temporary facilities for Espace 400e. The Espace 400e project audit, a requirement in the Treasury Board submission, had been included in the Office of Internal Audit and Evaluation’s three-year plan for the 2007-08 fiscal year and was conducted by a team from the Office of Internal Audit and Evaluation. 2. OBJECTIVES AND SCOPE The objectives of the audit, set out in the Treasury Board submission, were to provide senior management with an independent evaluation of: - the existence of an effective management control framework; and give assurance that: - the funds allocated were spent as planned; and - there was fair and optimal use of contracting resources. The criteria used to attain these objectives are listed in Appendix A. OIAE 5 September 2007 Espace 400e Audit Parks Canada Agency The audit covers only transactions posted between April 1, 2005, and July 31, 2007, and processes developed and implemented during that period. The audit is the first of two included in the Treasury Board submission. The second audit is to be done when the project ends in 2009. 3. METHODOLOGY Visits to the Quebec City Field Unit and Service Centre were conducted between August 6 and August 31, 2007. The following activities were carried out during these visits: - interviews with managers and staff in the field unit responsible for key financial processes; visit to the Espace 400e site; examination of relevant documents, including analyses, studies, agreements between PCA and Public Works and Government Services Canada and between PCA and the Quebec City Port Authority, miscellaneous financial reports and minutes of meetings; examination of contracts and invoices. - - Our observations and recommendations were made in accordance with the audit report rating system described below: Audit Reporting Rating System RED Unsatisfactory Controls are not functioning or are nonexistent. Immediate management actions need to be taken to correct the situation. ORANGE Significant Improvements Needed Controls in place are weak. Several major issues were noted that could jeopardize the accomplishment of program/operational objectives. Immediate management actions need to be taken to address the control deficiencies noted. YELLOW Moderate Improvements Needed Some controls are in place and functioning. However, major issues were noted and need to be addressed. These issues could impact on the achievement or not of program/operational objectives. Minor Improvements Needed Many of the controls are functioning as intended. However, some minor changes are necessary to make the control environment more effective and efficient. Controlled Controls are functioning as intended and no additional actions are necessary at this time. BLUE GREEN OIAE 6 September 2007 Espace 400e Audit Parks Canada Agency Once the on-site work was completed, a preliminary report was submitted to the project manager. 4. ASSURANCE STATEMENT In our opinion, the audit work carried out and the evidence gathered are sufficient to support the findings set out in this report. 5. GENERAL CONCLUSION Management of the Espace 400e project exemplifies sound management and good cooperation between the various stakeholders. The management control framework in place is effective. The project has clearly-identified objectives, the roles and responsibilities are defined, and the division of tasks is clear. In periodic meetings with the various stakeholders, cost and schedule changes were examined and monitored in order to comply with the project limitations. All of the funds allocated by Treasury Board and used to date have been spent solely for the purposes of the project. The contracting process was followed to the letter. The following section describes the various elements. 6. OBSERVATIONS AND RECOMMENDATIONS 6.1 Management control framework GREEN Controlled Controls are functioning as intended and no additional actions are necessary at this time. A management control framework is a set of procedures and directives aimed at ensuring that the established objectives are met. Establishing a management control framework facilitates cohesion and coordination between activities and provides direction for the various stakeholders involved. Implementing an effective management control framework enables the manager to track the progress of a project, quickly identify situations or activities that present a risk (for example, late delivery, cost overrun) and maximize the chances of completing the project on time and within budget. By definition, a project is a temporary undertaking aimed at meeting a specific goal. The chances of a project succeeding are increased if the following four steps are put in place and monitored: • • • OIAE conceptualization (i.e., setting objectives, a budget and general deadlines); planning (i.e., acquiring financial and human resources, assigning duties and coordinating activities); execution (i.e., monitoring operations and costs, adjusting or modifying plans, and completing the project on time and within budget); 7 September 2007 Espace 400e Audit Parks Canada Agency • delivery (i.e., delivery to the user). In most cases, completion of a project requires input from various stakeholders and coordination of multiple simultaneous or consecutive activities. The temporary nature of a project often assumes the existence of a time limit that is an important consideration in making decisions. The development of Espace 400e fits this definition perfectly. Consequently, the effectiveness of its management framework was evaluated according to the abovementioned steps other than delivery, since the audit was conducted before work was completed. For that final phase, the emphasis was primarily on meeting deadlines in order to ensure timely delivery of the product. 6.1.1 CONCEPTUALIZATION Objectives The objectives phase of the creation of Espace 400e was carried out before the Parks Canada Agency became involved in the project. However, when it came on board with the project, PCA embraced the development concept. A review of the various preliminary studies conducted to evaluate potential sites and assess environmental impact showed that every effort was made to maximize the selection of an ideal site for Espace 400e. Moreover, a risk analysis was conducted by Public Works and Government Services Canada and was included in the Treasury Board submission. Budget From the outset of the project, budget management has been handled by one manager. That person has now retired but will continue to oversee the project for the next six months. The work will be done on a part-time basis as the project progresses. An advisory committee has been set up, and signing authority will be given to the Executive Director for Quebec. Given that the initial budget estimates for the project submitted in April 2005 by Société du 400e totalled more than $34 million, the budgets were reviewed and adjusted so as not to exceed the allocated envelope. The original project was modified to ensure that the total cost of the project would stay within budget. The initial allocation of expenditures included $4.3 million for specific purposes: $1.7 million to cover management and administrative costs and $2.6 million to cover the Parks Canada exhibit. Rolling those costs into the project eliminated the financial pressure that would otherwise have been placed on the field unit to manage the project. This is a very good management practice. Deadlines Every sub-project has a delivery date. Possession of the site is scheduled for February 2008. Completion of work on the pavilion is scheduled for December 2007. Development of the Louise Basin should be completed by the end of October 2007. The OIAE 8 September 2007 Espace 400e Audit Parks Canada Agency temporary facilities should be ready by May 2008 and the Parks Canada exhibit should be available in March 2009. A timetable has also been established by the contractors for timely delivery of the interpretation centre, the focal point of Espace 400e. The timetable is reviewed regularly to ensure that there are no delays. The site visit provided an opportunity to determine the status of the work and according to the records, the project is on track. 6.1.2 PLANNING Resources The $24 million authorized by Treasury Board represents the full amount of the financial resources allocated to Parks Canada for the Espace 400e project. This amount was allocated over four years, and the field unit receives a payment in April of each year as part of the previously established budget program. The only extra staff provision in the field unit for Espace 400e was a student hired for the exhibit phase of the project. Current staff will carry out the entire project in addition to their regular duties. Salaries for project staff are therefore covered by the funds received for the project, and a separate line item has been created. Assignment of tasks The Director General, Eastern Canada has designated the Quebec City Field Unit as the Parks Canada representative. The field unit is therefore responsible for overall management of the project, which includes identifying general project needs and specific needs and coordinating activities, resources, committees and budget management in accordance with PCA policies. Owing to the specialized nature of the work, Parks Canada has signed an agreement with PWGSC under which Public Works will assume responsibility for identifying technical and professional needs, awarding and administering contracts, negotiating costs and agreements with consultants and contractors, and providing goods and services. One project manager and two component managers have been designated to represent Public Works and Government Services Canada. Signing of contracts and validation of any extras that arise throughout the life of the project but that are not included in the initial contract are the responsibility of the project manager. Work is monitored by the component managers, one of whom is responsible for the development of the Louise Basin, the other for the pavilion project. These managers are responsible for validating expenditures submitted to them and sending status reports to Parks Canada. A consulting firm has been hired to be on site at all times in order to ensure the quality of the product. The consultants validate the invoices submitted by contractors, sign them and send them to PWGSC for processing. PWGSC then prepares invoices for Parks Canada. A PWGSC employee carries out daily monitoring of the site; however, the manager responsible for the Agency is very involved in project management. OIAE 9 September 2007 Espace 400e Audit Parks Canada Agency Coordination of activities When the Louise Basin was chosen as the site for Espace 400e, a five-year plan was developed jointly with the various stakeholders involved in the project. A number of committees were created, including a technical project development committee made up of representatives of the Quebec City Port Authority, the Parks Canada Agency, Public Works and Government Services Canada, the Société du 400e, the Commission de la capitale nationale de Québec and the environmental monitoring committee, with input from fifteen other organizations, including the Canadian Environmental Assessment Agency, Health Canada and Environment Canada. At the start of the project, meetings were held periodically to track information, timetables and costs. The committee is still in place, but meetings are now held as needed. Because the various project initiatives were being carried out on Government of Canada property, including property owned by the Quebec City Port Authority, the Parks Canada Agency and Public Works and Government Services Canada, agreements were made in order to define the roles and responsibilities of the various stakeholders, define authority and determine responsibility for infrastructure management. Site meetings are held every two weeks. Minutes are kept. The schedules set by the contractor are reviewed regularly, and copies are attached to the minutes. Coordination of activities among the various stakeholders is going well, largely owing to ongoing dialogue and regular meetings. One example of coordination is the development of the bicycle path that cuts through the various properties, but is managed in its entirety by Quebec City. Development takes the various needs into account in order to ensure that work does not have to be redone because something was overlooked (e.g., water pipes, wiring). Regarding the coordination of activities within the Parks Canada Agency, the Director General for Eastern Canada is PCA’s authority for the project as a whole. The project has been incorporated into the activities of the Quebec City field unit, and a manager has been specifically designated to oversee project operations. Once the work is done and the portion related to the 400th anniversary activities is complete, project management will be transferred to the Director of the Quebec City Field Unit, who will oversee the conversion of the interpretation centre to a Parks Canada Discovery Centre by 2009. Moreover, to enable the Director General for Eastern Canada to assume his designated responsibilities, an internal monitoring committee was recently created. The committee, headed by the Executive Director of Quebec, will report directly to the Director General. Since this is a new committee, tasks among the members had not yet been determined at the time of the audit. Since the project started, presentations have been made to the Parks Canada steering committee in order to provide progress reports. The last meeting was held in April 2007. OIAE 10 September 2007 Espace 400e Audit Parks Canada Agency 6.1.3 PERFORMANCE Tracking of operations and costs As stated earlier, management of operations related to construction and development of the site has been assigned to PWGSC under a specific service agreement (SSA) for the duration of the project. Since this is a multi-year project, Parks and PWGSC reach an agreement at the beginning of each fiscal year on a budget envelope for the year. In December, the numbers are reviewed and adjusted as needed. If there is any change, the SSA is amended. The SSA and any amendments made at the time of the audit were in the file. Despite the project management agreement between PWGSC and Parks Canada, the Quebec City field unit retained full responsibility for financial management of the Espace 400e project and had to put in place controls to ensure proper tracking of costs. The involvement of the Parks Canada manager at all stages of the project and constant communication among the various stakeholders made it possible to ensure very good tracking, reflected in the fact that the project is on time and within budget. Project adjustments and modifications The contractors on the project carry out construction work from previously approved plans. If changes become necessary, the contractors annotate the plans as the work proceeds. At the end of the project, copies of the plans will be given to the consultant representing the architectural firm; the consultant is responsible for updating the official plans that will be given to Parks Canada when the project is delivered. When a change is necessary, the consultant submits a notice of change and the contractor submits a price. The consultant analyses and recommends proceeding with the notice of change to PWGSC. The PWGSC manager is then responsible for validating the information and allowing the contractor to proceed with the proposed change. All change notices are numbered. The action taken on a change notice and the authorizations granted are reflected in the minutes. Expenditures are monitored closely, and budget amendments are made as planned activities are changed. For example, a project to build a walkway at the end of the basin was cancelled because the activities originally planned for that area would not be taking place. That change in the project freed up money that will be redirected to other potential projects related to Espace 400e. 6.1.4 COMPLETION The involvement of the Quebec City Field Unit in the Espace 400e project was aimed at meeting two separate objectives, namely: (1) preparation of the site as a gathering place during the festivities with a temporary exhibit showcasing the 400th anniversary of the founding of Quebec City OIAE 11 September 2007 Espace 400e Audit Parks Canada Agency (2) conversion of the pavilion to a Parks Canada Discovery Centre with permanent exhibits. Time is a major limitation for the Espace 400e project, because the product timelines could affect the various activities that will take place as part of the festivities. At the time of the audit, most of the activities related to the first objective were on time and within budget. The only exception was site development: the expectation was that there would be an overrun on the initial budget for that phase, but not on the total budget. Regarding the second objective, namely preparing the exhibit for the discovery centre, it was too early to audit these expenditures. This item will have to be covered in the second audit, which will take place in 2009. There were also a few clauses remaining to be finalized before signing a lease with Société du 400e for use of the building. The document was supposed to be reviewed by officials from the Department of Justice prior to signing. It should be noted, however, that there is an agreement in principle between the parties. At the time of the audit, various projects were being reviewed in order to complete the site. Those new projects include negotiations with the American consulate for a small U.S. square. The entire estimated cost of $25,000 would be covered by the United States. Another project is being considered to highlight the exodus of Canadians to the northeastern United States. The estimated cost of that project is $50,000 and should also be covered entirely by the United States. Recommendation: None 6.2 Funds spent as planned GREEN Controlled Controls are functioning as intended and no additional actions are necessary at this time. The specific purpose of this section is to evaluate the quality of internal control, that is, ensure that controls are in place and functioning well, and that all expenditures are related to the project for which the funds were allocated. To facilitate tracking of project costs and payment of expenditures during the year, an internal order number has been assigned to each sub-project. Very few purchases are made directly by PCA. PWGSC is responsible for awarding and managing contracts, which account for most of the project costs. Because they are the ones who monitor the work, PWGSC managers validate invoices as the work proceeds. A total monthly invoice covering the various costs incurred is then submitted to Parks Canada for payment. An audit of the files showed that spending was tracked and some expenditures were OIAE 12 September 2007 Espace 400e Audit Parks Canada Agency questioned such as corrections to hourly rates or changes to the work completion percentage. From PCA’s perspective, using the specific internal order number for each sub-project makes it easier to monitor expenditures related to those sub-projects and thus significantly improves tracking and accountability. The financial officer in the field unit does allocation of costs among the various projects when the PWGSC invoices are received. Data is not entered in the STAR financial system until everything has been balanced. The same person enters the salaries of employees working on the project in STAR. The data is taken from the Salary Management System (SMS). Recommendation: None 6.3 Fair and optimal use of contracting resources GREEN Controlled Controls are functioning as intended and no additional actions are necessary at this time. By using PWGSC services, PCA delegated day-to-day project management authority, but retained a veto. Analysis of the files showed that the contracting process was respected and that no change was made to the project without justification or prior analysis. An example of optimization of resources and thus, sound management, is the $1.4 million Specific Service Agreement between Parks Canada and PWGSC. The agreement made it possible to pre-purchase windows at a good price instead of waiting until it was time to install and taking the chance that the cost would be higher because of market conditions. We did not find any deficiencies in the awarding of contracts by the field unit. However, some of the rationales for choosing a sole supplier were not sufficiently detailed. Discussions with the manager responsible for the project made it possible to clarify the specific needs regarding the themed exhibit and thus justify the use of a sole supplier. Measures were taken to ensure that files were more complete. Recommendation: None OIAE 13 September 2007 Espace 400e Audit Parks Canada Agency Appendix A: Criteria used to meet the objectives Objective 1 – Effectiveness of the management control framework, i.e., conceptualization and planning of the project Criteria: 1 Clear objectives are identified for the project 2 Roles and responsibilities are clearly defined, documented and disseminated 3 Costs are clearly identified and properly monitored 4 The control environment in place fosters sound, effective management; the systems in place are reliable and provide quality information (i.e., information available and easily accessible; project on time and within budget; adequate controls) Objective 2 – Funds spent as planned, i.e., project execution Criteria: 1 Funds received from the Treasury Board Secretariat for the 400e project are used only as planned; 2 All costs incurred (salaries, materials, etc.) are properly tracked and accounted for; 3 All expenditures are supported and approved by the competent authority. Objective 3 – Fair and optimal use of contracting resources, i.e., project completion Criteria: 1. Before a contract is signed, needs are clearly identified and set out in writing. 2. Contracting activities comply with policies and procedures. 3. The contracting method used is appropriate. OIAE 14 September 2007
© Copyright 2025 Paperzz