INCIDENT REPORT Confidential INCIDENT REPORT DATA CENTRE POWER FAILURE Date : 17th May 2014 Time : 16:45-18:20 (1 hour 35 minutes) Location : VADS DC, Level 2 & 3, CBJ2 Summary of the Event Planned power maintenance and upgrading work by Telekom Malaysia Property Operations (TM PO) was scheduled to start at 09:00 (17th May 2014) and to complete at 23:59 (18th May 2014) The load from TNB utility was successfully transferred to two nos of the building generator sets (Genset) at 10:20. The power maintenance exercise experiencing difficulty when both of Gensets shutdown at 14:15 and 14:30 respectively. The shutdown of the both Gensets had interrupted both DC cooling and power supply to customer racks (after UPS batteries drained and flat) Cause of Problem Both building Gensets shutdown after running almost 4 hours. The failure was due to fuel level switch failed and did not trigger fuel auto pump to pump diesel from main tank to service tank. This has caused static Gensets to shut down due to no diesel being fed into the Gensets from service tank. Chronology Chronology: of the event and Action 17th May 2014 Plans Time Event/Action 10.20 TM PO maintenance work started by shutting down the 11kV dual feeder to CBJ2 HT panel. Both 2MVA Gensets (Genset#1 and Genset#2) were running on-load with load approximately 800Amps per Genset 14:15 Genset#1 which is connected to MSB#1 shutdown. All supplies to MSB#1 are cutoff. UPS Socomec (300kVa x 2 nos) and all connected rectifiers switch to Battery-on-load mode. 14:30 Genset#2 which is connected to MSB# 2 shutdown. All supplies to MSB#2 are cutoff. UPS APC (240kVa x 2 nos), UPS Liebert (160kVa x 2 nos) and connected rectifiers switch to Battery-on-load mode 15:00 TM PO Contractor was called to mobilize 2 nos of mobile Genset to Cyberjaya 2. 16:00 TM PO’s Mobile Genset was up and running to supply load for INCIDENT REPORT 16:34 16:45 16:45 17:00 18:00 18:05 18:05 18:20 18:20 18:20 18:40 18:40 Confidential MSB#1 and UPS Socomec. UPS APC and UPS Liebert shutdown due to battery drained, and all load transferred to UPS Socomec. (Both UPS Liebert and UPS APC had back-up load for 2 hours). TM PO’s Mobile Genset unstable (due to high load), causing the UPS Socomec to switch to Battery-on-load and shutdown due to earlier battery-on-load (battery drained) and caused total shutdown to all load connected to UPS. Most power supplies to level 2 and level 3 customer racks were interrupted. Except UPS APC 200KVA still sustain to support several customer racks at level 3. 2 nos of Mobile Genset from TM PO Contractor reached Cyberjaya 2 and immediately being readied to connect to both MSB. TM PO Contractor’s Mobile Genset connected to MSB#2 and re-energize. UPS APC and UPS Liebert back on. Genset#1 back on and re-energize MSB#1. UPS Socomec back on. Cooling system at the DC immediately restored and DC temperature resume normal. All output breakers to STS /PDU at level 2 were switched ON and power supply to level 2 customer racks are being normalized. Power supply fully resumed to all racks at CBJ2 DC level 2 DC network services restored All output breakers to STS /PDU at level 3 were switched ON and power supply to level 3 customer racks are being normalized Power supply fully resumed to all racks at CBJ2 DC level 3 18th May 2014 Time 03:20 Event/Action TM PO has normalized the incoming power back to TNB supply. TMPO has halted and postponed the building power upgrading/ maintenance work until further notice. Solutions i) TM PO temporarily using Mobile Gensets to supply power to the building (17th may 2014 at 18:00) ii) TM PO reverted to TNB utility power source (18th May 2014 at 03:20) INCIDENT REPORT Mitigation Plans Confidential Proposed mitigation plans by TM PO: i) To built up separate service tank complete with own fuel auto pump for respective static Genset in Cyberjaya 2 ii) To replace faulty fuel level switch for existing service tank iii) To ensure all manual changeover at each MSB being equipped with mobile Genset termination box iv) To ensure all diesel motor pump system function properly during Genset on load test and prolong TNB power supply failure (more than 1 hour) Customers Affected Power Issue : All customers at Level 2 and Level 3, CBJ2 DC Network Issue : All customers CBJ1, CBJ2, CBJ5 and CBJ6 DC affected for 2 hours. Network restored at 18:20 . Status The power supply to the building was fully restored and powered by mobile Gensets at 18:00. All breakers/PDU are normalized by stages between 18:20 – 18:40 (17th May 2014) TM PO has successfully normalized the incoming power back to TNB supply at 03:20 (18th May 2014) TM PO postponed the power upgrading/maintenance work until further notice. All DC power supply and cooling had resumed normal operation. ** End of Report ** Prepared by, Data Centre Operation CBJ2
© Copyright 2026 Paperzz