Feed-in Tariff factsheet 2 Introducing Feed-in Tariffs The Feed-in Tariff (FIT) scheme is a government initiative that pays householders and businesses to generate their own energy from renewable sources. The FIT scheme makes it more financially viable for householders and businesses to buy and install a renewable energy generator, such as solar photovoltaic (PV) panels or a wind turbine. Qualifying generators will be eligible to receive a set payment rate for every unit (kWh) of electricity produced, even if this electricity is used on site. Additional export payments may also apply. Payment rates for both generated and exported electricity are fixed (and Retail Price Index adjusted each year), and for solar PV, generation rates apply for up to 20 years. This gives anyone participating in the scheme the security of a long-term market for the electricity they produce. Electricity used Electricity flows Electricity generated Import meter Total generation meter Export meter On-site generation unit Network 3 The benefits of Feed-in Tariffs As well as receiving FIT payments, there are other important reasons why you should consider installing a renewable energy generator. • Research has shown that property buyers are willing to pay more for a property that has been fitted with a renewable energy generator.* • DECC have designed the tariffs so that it is possible to recoup the entire cost of buying and installing eligible generators and potentially make a profit. • Y ou could make a valuable contribution to reducing carbon emissions, helping to protect our environment. • Your electricity bills should be reduced because you’re likely to need to buy less electricity from your energy supplier. * Source: Energy Saving Trust Market Research, September 2009 Which renewable energy generators will qualify? The following generators may be eligible for FIT payments: • Solar PV • Wind • Hydro • Anaerobic digestion • Domestic micro CHP (with an installed capacity of 2kW or less). 4 Feed-in Tariff elements Generation payment You’ll receive a generation payment for every kWh of electricity you generate, whether you use it yourself or export it to the Electricity Network. The rate per kWh varies depending on factors, such as the generator type and size. To provide investor certainty, Generation Tariff rates are largely fixed throughout the duration of your FIT agreement; but will move in line with the Retail Prices Index (RPI) to ensure inflation is taken into account. Generation payment rates (p/kWh) Generator Scale Anaerobic <250kW 15.16 20 250kW-500kW 14.02 20 500kW+ 9.24 20 CHP <2kW 12.89 10 Hydro <15kW 21.65 20 15kW-100kW 20.21 20 100kW-500kW 15.98 20 500kW-2mW 12.48 20 2mW+ 3.23 20 <4kW 15.44 20 4kW-10kW 13.99 20 10kW-50kW 13.03 20 50kW-100kW 11.50 20 100kW-150kW 11.50 20 150kW-250kW 11.00 20 250kW+ 7.10 20 Standalone 7.1 20 <1.5kW 21.65 20 1.5kW-15kW 21.65 20 15kW-100kW 21.65 20 100kW-500kW 18.04 20 500kW-1.5mW 9.79 20 1.5mW+ 4.15 20 <50kW 10.21 20 See the table to the right for an overview of the current rates and tariff lifetimes. These rates should apply until 31 March 2014 when the next RPI changes come into effect, however the government may revise prices before then. Export payment For all eligible generators connected to the Electricity Network, an export payment, currently fixed at 4.5p per kWh will be available. Although this rate is fixed (and RPI adjusted) again the Government has reserved the right to change the export rate should they consider it appropriate to do so. Export payments are made in addition to the generation payment. NB: If your generator is ‘off-grid’, you won’t be able to export electricity and so will not be eligible to receive export payments. Solar Wind *This tariff is only available for 30,000 micro CHP installations. A review will take place when 12,000 units have been installed. **Assumes EPC level D and no Multi Installation Tariff reduction. Source: Department of Energy & Climate Change. ***Actual rate dependant on EU approval. Installations registered in FITs Year 4 (01 April 2013 31 March 2014) Tariff received Tariff until 31 March lifetime 2014 (years) ROO Migrated Installations 5 How much could you be paid? Take a look at the diagram below to see how much a typical household could receive in FIT payments. This is an illustrative example only, and is based upon solar PV panels with an installed capacity of 4kW or less, fitted to an older property (ie not installed as part of a new build). • If your generator has an installed capacity greater than 30kW, it is mandatory that you have an export meter fitted to measure the amount of electricity being exported to the Electricity Network. If you do not already have an export meter, we can arrange for one to be fitted.* • If your generator has an installed capacity of 30kW or below, you do not need an export meter as we’ll deem (or estimate) your export amount based upon 50% of your total generation (75% for hydro). Meters, meter readings and payments To qualify for the FIT scheme, you must have an approved generation meter fitted to measure how much electricity you’re generating. You’ll need to supply us with quarterly readings from your relevant meters so that we can calculate your FIT payments. We’ll then pay these into your nominated bank account when due. If you’re exporting electricity to the Electricity Network, you may also need an approved export meter fitted. We can supply and install both generation and export meters*, so please contact us for details. * There is a charge for this service. Generation Total generation 2,500kWh Differs by technology and scale Sola r pa nel Imported Electricity usage 4,500kWh This customer has generated 3,400kWh of their own electricity, avoiding costs for 1,700kWh from their supplier. Export tariff Total export 1,250kWh Fixed at 4.5p/kWh Example Elements Without solar panels With solar panels Import costs 3,300 x 16pkWh = £528/Annum 2,300 x 16p/kWh = £368/annum Generation costs 0 3,400 x 15.4p/kWh = £525/annum Export tariff 0 1,700 x 4.6p/kWh = £78/annum Total -£528/annum +£235/annum 6 Eligibility for FIT payments If your renewable energy generator was installed after 1 April 2010, the key rules for qualification are that your generator must: • have an installed electrical capacity of 5MW or less (2kW or less for domestic scale micro CHP units) • be one of five approved types: • Anaerobic digestion • Solar PV • Wind • Hydro •D omestic scale micro CHP units (with a capacity of 2kW or less). • have appropriate accreditation in place •G enerators with an electrical capacity of 50kW or less (other than anaerobic digestion) must be appropriately accredited under the Microgeneration Certification Scheme (MCS). If you’re unsure if your device is MCS accredited, please check with your installer. • be connected to the Electricity Network to claim FIT export payments. If your installed electrical capacity is above 30kW in size, you must also have an appropriate export meter to measure the amount of electricity being exported. • not be registered to receive FIT generation payments from more than one energy supplier. • not be registered to claim ROCs at the same time as any FIT payments. • comply with eligibility requirements where grants have been issued. • from 1 April 2012 obtain an EPC level D certificate to ensure higher generation rate are paid for PV installations below 250kWh. If your renewable energy generator was installed prior to 1 April 2010, please contact us to find out if you’re eligible. And finally when you complete your application please ensure the following are included: • Proof of ID • Generators with an electrical capacity above 50kW up to and including 5MW (and anaerobic digestion) must be accredited under the Renewables Obligation Order (ROO) FIT process. If your generator is not currently accredited, please contact Ofgem for further advice. • Proof of ownership • have an approved generation meter. If you don’t already have one, we can arrange for one to be fitted as part of your application*. • EPC certificate • valid Start Reading • evidence of rights to generate (if relevant) • generator accreditation if 50kW and below • appropriate solar PV declaration Failure to do this will result in your application being invalid. * There is a charge for this service. 7 Glossary of terms Further reading Carbon Dioxide (CO2) A greenhouse gas. You can read more about Feed-in Tariffs and their background at the following websites: Kilowatt (kW) One thousand watts. www.decc.gov.uk Megawatt (MW) One thousand kilowatts. www.FITariffs.co.uk Micro Combined Heat and Power unit (mCHP) It heats the building in the same way as a gas boiler and also generates electricity, most of which is used in the building. www.ofgem.gov.uk Microgen A device that produces electricity from a low carbon source with an installed capacity of 50kW or below. Useful contact details Microgeneration The production of heat and/or electricity on a small scale from a low carbon source. Microgeneration Certification Scheme (MCS) A process of accreditation to be undertaken for generating units with an installed capacity of 50kW or less. Off Grid A generation unit which is connected to a private wire network and not the Electricity Network. Renewables Obligation Certificate (ROC) An existing government scheme to reward generators with an installed capacity above 50kW. Solar Photovoltaic (PV) Converts sunlight into electricity. How to apply for the FIT scheme Before you apply, please check to make sure that your generator qualifies. If you need more information, read our FAQs or call us on 0845 301 4884 for advice, or to request an application form. Our opening hours are 9am to 6pm Monday to Friday, 8am to 4pm Saturday. You can also download the form from our website: eonenergy.com/feedintariffs www.energysavingtrust.org.uk www.lowcarboneconomy.com E.ON FIT helpline: 0845 301 4884 MCS helpdesk: 0207 090 1082 Ofgem: ofgem.gov.uk Ofgem Renewables and CHP Register: 0207 901 7310 8 Frequently asked questions What are FIT payments based on? The Government sets minimum FIT rates which are priced to offer around a 5-8% return on your investment, based on average calculations for an appropriately located generator. As an illustrative example only, if you’ve spent £10,000 on FIT-eligible solar photovoltaic (PV) panels, you can typically expect to receive between £500 and £800 a year in FIT-related ‘benefit’ (this benefit includes typical expected savings as a result of reduced electricity bills due to generating and consuming electricity on site). How do I define the date of commission of my technology? This is assumed to be the date on which your generator was installed and confirmed to be working (generating). Can I claim Renewable Obligations Certificates (ROCs) at the same time as FIT payments? No. If you have a choice between the two schemes, you must choose one only. Note: Microgenerators (generation with an installed electrical capacity of 50kW or less) from 1 April 2010, can only register for the FIT scheme (not ROCs). Small-scale generators with an installed electrical capacity above 50kW and not greater than 5MW who had applied under the Renewables Obligation (RO) for ROCs, before 15 July 2009, will remain in the RO and will not be eligible to transfer to the FIT scheme. Can E.ON accredit my installation? No. With the exception of anaerobic digestion, eligible microgeneration (with an installed electrical capacity of 50kW and below) and installed after 1 April 2010 must be accredited under the Microgeneration Certification Scheme (MCS). Generators with an installed capacity of more than 50kW and anaerobic digestion must be accredited under the Renewables Obligation Order (ROO-FIT accreditation) as administered by Ofgem. Please see back page for contact details. What happens if I have more than one eligible generator on a single site? If each different type of eligible generator has an installed electrical capacity not exceeding 5MW (2kW or less for domestic scale micro CHP), you’ll be able to receive FIT payments for each of your eligible generators. Will my electricity Direct Debit payment go down? The amount won’t change just because you’ve signed up to the FIT scheme. But if you start buying less electricity, your Direct Debits should be adjusted when your payment amount is periodically reviewed. Do I need to be on a green energy tariff to qualify for the FIT scheme? No, you can be on any type of energy tariff. As I’m getting paid for exporting electricity, is it in my interests to export everything I generate? Typically, no. The FIT scheme is designed to encourage efficient use of the electricity you generate on site. This should reduce the amount of electricity you need to buy from your energy supplier, resulting in lower bills. Improving energy efficiency should enable you to export more ‘surplus’ electricity to the Electricity Network. Fixed FIT export payments will attract a payment of 3p/kWh. Will I be taxed on the generation and export payments I receive? Householders will not be taxed on the payments they receive. Businesses and corporations should check their tax liability with HM Revenue & Customs (HMRC). Are generation and export payments inflation-linked? Yes. Payment levels will be adjusted every year in line with the Retail Price Index (RPI). Will you read my meters? You’ll need to read your generation and export meters quarterly and submit the readings to us. However, we’ll periodically read these meters for audit purposes. Your import meter will continue to be read as normal. What happens if I move house or business premises? You can agree change of ownership of your generator as part of your property sale. Can landlords claim FIT payments for generators at tenants’ properties? Yes. If you’re a landlord installing FIT-eligible generation at your property(s) you can claim FIT payments. You’ll need to agree provision of these meter reads with your tenants. Can builders receive FIT payments if they install renewable energy generators at new properties? Under the Code for Sustainable Homes, builders can claim FIT payments on new builds. The Government sees this as a good way of helping builders meet the costs of achieving Zero Carbon Buildings. A more detailed list of FAQ’s is available on our FIT website: eonenergy.com 9 Appendix Feed-in tariff payment rate tables for eligible installations Depending on the year when eligibility commenced please refer to appropriate appendix for latest prices. Appendix 1 Appendix 2 Appendix 3 Appendix 4 1 April 2010 - 31 March 2011 1 April 2011 - 31 March 2012 1 April 2012 - 31 March 2013 1 April 2013 - 31 March 2014 (FIT Year 1) (FIT Year 2) (FIT Year 3) (FIT Year 4) All FIT payment rates are pence per kilowatt hour (p/kWh) at 2013/14 values. Appendix 1 1 April 2010 - 31 Mar 2011 (FIT Year 1) Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1) Technology type Generation level Period in Year Eligibility Started Technology Description p/kWh Anaerobic <250kW 1 Apr 10 - 31 Mar 11 Anaerobic digestion with total installed capacity of 250kW or less 13.1 250kW-500kW 1 Apr 10 - 31 Mar 11 Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW 13.1 500kW and over 1 Apr 10 - 31 Mar 11 Anaerobic digestion with total installed capacity greater than 500kW 10.2 CHP <2kW 1 Apr 10 - 31 Mar 11 Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units) 11.3 Hydro <15kW 1 Apr 10 - 31 Mar 11 Hydro generating station with total installed capacity of 15kW or less 22.6 15kW-100kW 1 Apr 10 - 31 Mar 11 Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW 21.7 100kW-500kW 1 Apr 10 - 31 Mar 11 Hydro generating station with total installed capacity greater than 100kW but not exceeding 500kW 12.5 500kW-2mW 1 Apr 10 - 31 Mar 11 Hydro generating station with total installed capacity greater than 500kW but not exceeding 2MW 12.5 2mW+ 1 Apr 10 - 31 Mar 11 Hydro generating station with total installed capacity greater than 2MW 5.1 10 Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1) Technology type Generation level Period in Year Eligibility Started Technology Description p/kWh 10.2 ROO Migrated Installations <50kW 1 Apr 10 - 31 Mar 11 Eligible Installations with a declared net capacity of 50kW or less commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010 Solar <4kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 46.8 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 40.8 Wind Export 4kW-10kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 40.8 10kW-50kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW 35.6 50kW-100kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 35.6 100kW-150kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 33.2 150kW-250kW 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 33.2 250kW+ 1 Apr 10 - 31 Mar 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW 33.2 n/a 1 Apr 10 - 31 Mar 11 Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building) 33.2 <1.5kW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity of 1.5kW or less 39.1 1.5kW-15kW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity greater than 1.5kW but not exceeding 15kW 30.2 15kW-100kW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity greater than 15kW but not exceeding 100kW 27.3 100kW-500kW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity greater than 100kW but not exceeding 500kW 21.2 500kW-1.5mW 1 Apr 10 - 31 Mar 11 Wind with total installed capacity greater than 500kW but not exceeding 1.5MW 10.7 1.5mW+ 1 Apr 10 - 31 Mar 11 Wind with total installed capacity greater than 1.5MW 5.1 n/a 1 Apr 10 - 31 Mar 11 All FIT Export Tariff Rate 3.3 11 Appendix 2 1 April 2011 - 31 March 2012 (FIT Year 2) Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1) Technology type Generation level Period in Year Eligibility Started Technology Description p/kWh Anaerobic <250kW 1 Apr 11 - 29 Sept 11 Anaerobic digestion with total installed capacity of 250kW or less 13.1 30 Sept 11 - 31 Mar 12 Anaerobic digestion with total installed capacity of 250kW or less 15.2 1 Apr 11 - 29 Sept 11 Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW 13.1 30 Sept 11 - 31 Mar 12 Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW 14.0 500kW and over 1 Apr 11 - 31 Mar 12 Anaerobic digestion with total installed capacity greater than 500kW 10.2 CHP <2kW 1 Apr 11 - 31 Mar 12 Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units) 11.3 Hydro <15kW 1 Apr 11 - 31 Mar 12 Hydro generating station with total installed capacity of 15kW or less 21.9 15kW-100kW 1 Apr 11 - 31 Mar 12 Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW 19.6 100kW-500kW 1 Apr 11 - 31 Mar 12 Hydro generating station with total installed capacity greater than 100kW but not exceeding 500kW 12.1 500kW-2mW 1 Apr 11 - 31 Mar 12 Hydro generating station with total installed capacity greater than 500kW but not exceeding 2MW 12.1 2mW+ 1 Apr 11 - 31 Mar 12 Hydro generating station with total installed capacity greater than 2MW 4.9 ROO Migrated Installations <50kW 1st Apr 11 - 31 Mar 12 Eligible Installations with a declared net capacity of 50kW or less commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010 10.2 Solar <4kW 1 Apr 11 - 2 Mar 12 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 46.8 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 40.8 250kW-500kW 12 Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations Technology type Generation level Solar (cont.d) 4kW-10kW 10kW-50kW 50kW-100kW 100kW-150kW 150kW-250kW Period in Year Eligibility Started Technology Description p/kWh 3 Mar 12 - 31 Mar 12 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 21.7 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 21.7 1 Apr 11 - 2 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 40.8 3 Mar 12 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 17.3 1 Apr 11 - 2 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW 35.6 3 Mar 12 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW 15.7 1 Apr 11 - 31 July 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 35.6 1 Aug 11 - 2 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 20.5 3 Mar 12 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 13.3 1 Apr 11 - 31 July 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 33.2 1 Aug 11 - 2 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 20.5 3 Mar 12 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 13.3 1 Apr 11 - 31 July 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 33.2 1 Aug 11 - 2 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 16.2 Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations Technology type Period in Year Eligibility Started Technology Description p/kWh 3 Mar 12 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 13.3 1 Apr 11 - 31 July 11 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW 33.2 1 Aug 11 - 31 Mar 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW 9.2 1 Apr 11 - 31 July 11 Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building) 33.2 1 Aug 11 - 31 Mar 12 Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building) 9.2 <1.5kW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity of 1.5kW or less 39.1 1.5kW-15kW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity greater than 1.5kW but not exceeding 15 kW 30.2 15kW-100kW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity greater than 15kW but not exceeding 100kW 27.3 100kW-500kW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity greater than 100kW but not exceeding 500kW 21.2 500kW-1.5mW 1st Apr 11 - 31 Mar 12 Wind with total installed capacity greater than 500kW but not exceeding 1.5MW 10.7 1.5mW+ 1st Apr 11 - 31 Mar 12 Wind with total installed capacity greater than 1.5MW 5.1 n/a 1st Apr 11 - 31 Mar 12 All FIT Export Tariff Rate 3.3 Generation level Solar (cont.d) 250kW+ n/a Wind Export 13 Appendix 3 1 April 2012 - 31 March 2013 (FIT Year 3) Eligibility Start Date: 1 April 2010 - 31 Mar 2011 (FIT Year 1) Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Anaerobic <250kW 1 Apr 12 31 Mar 13 Anaerobic digestion with total installed capacity of 250kW or less 15.2 250kW-500kW 1 Apr 12 31 Mar 13 Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW 14.0 500kW and over 1 Apr 12 31 Mar 13 1 Dec 12 31 Mar 13 CHP <2kW Before the conditional date* After the conditional date* Hydro <15kW 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 15kW-100kW 1 Apr 12 31 Mar 13 100kW-500kW Before the conditional date* After the conditional date* 500kW-2mW 1 Apr 12 31 Mar 13 2mW+ 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 Anaerobic digestion with total installed capacity greater than 500kW Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units) 10.2 9.2 11.3 12.9 22.6 Hydro generating station with total installed capacity of 15kW or less 21.7 Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW 20.2 12.5 16.0 12.5 5.1 Hydro generating station with total installed capacity greater than 2MW 4.6 Higher rate Middle rate Lower rate Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement Higher rate Middle rate Lower rate Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 21.7 17.3 9.3 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 21.7 17.3 9.3 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 16.5 14.9 7.3 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 16.5 14.9 7.3 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 15.4 13.9 7.1 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 15.4 13.9 7.1 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 17.3 13.8 9.3 15.0 13.5 7.3 14.0 12.6 7.1 15.7 12.6 9.3 13.9 12.5 7.3 13.0 11.7 7.1 n/a Solar <4kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 1 Nov 12 31 Mar 13 4kW-10kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 1 Nov 12 31 Mar 13 10kW-50kW Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 1 Nov 12 31 Mar 13 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Solar (cont.d) 50kW-100kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 1 Nov 12 31 Mar 13 100kW-150kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 1 Nov 12 31 Mar 13 150kW-250kW Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 1 Nov 12 31 Mar 13 250kW+ 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 9.2 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW 1 Nov 12 31 Mar 13 Standalone 1 Nov 12 31 Mar 13 Wind <1.5kW 7.1 1 Apr 12 - 31 Jul 12 1 Aug 12 31 Oct 12 9.3 Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building) 7.3 7.1 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 7.3 36.9 Wind with total installed capacity of 1.5kW or less 21.7 Higher rate Middle rate Lower rate 13.3 10.6 9.3 11.9 10.7 7.3 11.5 10.4 7.1 13.3 10.6 9.3 11.9 10.7 7.3 11.5 10.4 7.1 13.3 10.6 9.3 11.3 10.2 7.3 11.0 9.9 7.1 Feed-in Tariff Payment Rate Table for Photovoltaic Eligible Installations Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Wind (cont.d) 1.5kW-15kW 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 15kW-100kW 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 100kW-500kW 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 500kW-1.5mW 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 1.5mW+ 1 Apr 12 30 Nov 12 1 Dec 12 31 Mar 13 ROO Migrated Installations <50kW 1 Apr 12 31 Mar 13 Export n/a 1 Apr 12 - 31 Jul 12 Wind with total installed capacity greater than 1.5kW but not exceeding 15 kW Wind with total installed capacity greater than 15kW but not exceeding 100kW Wind with total installed capacity greater than 100kW but not exceeding 500kW Wind with total installed capacity greater than 500kW but not exceeding 1.5MW Higher rate Middle rate Lower rate 28.9 21.7 26.2 21.7 21.2 18.0 10.7 9.8 5.1 Wind with total installed capacity greater than 1.5MW 4.6 Eligible Installations with a declared net capacity of 50kW or less Commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010 10.2 3.3 Solar Export Tariff Rate 1 Aug 12 31 Mar 13 4.6 1 Apr 12 30 Nov 12 4.6 Non Solar Export Tariff Rate 1 Dec 12 31 Mar 13 4.6 *The Conditional Date referred to in the entries for certain descriptions of installations applies only where the European Commission gives state aid approval on or before 31 March 2013 for the higher rate specified in the entry and in such case the conditional date is the later of (a) 1 December 2012, or (b) the date on which the approval is given. If state aid approval is not given on or before 31 March 2013, the lower rate specified in the entry applies throughout FIT Year 3. Appendix 4 1 April 2013 - 31 March 2014 (FIT Year 4) Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4) Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Higher rate Middle rate Lower rate <250kW 1 Apr 13 31 Mar 14 Anaerobic digestion with total installed capacity of 250kW or less 15.2 250kW-500kW 1 Apr 13 31 Mar 14 Anaerobic digestion with total installed capacity greater than 250kW but not exceeding 500kW 14.0 500kW and over 1 Apr 13 31 Mar 14 Anaerobic digestion with total installed capacity greater than 500kW 9.2 CHP <2kW After the conditional date* Combined Heat and Power with total installed electrical capacity of 2kW or less (Tariff available only for 30,000 units) 12.9 Hydro <15kW 1 Apr 13 31 Mar 14 Hydro generating station with total installed capacity of 15kW or less 21.7 15kW-100kW 1 Apr 13 31 Mar 14 Hydro generating station with total installed capacity greater than 15kW but not exceeding 100kW 20.2 100kW-500kW 1 Apr 13 31 Mar 14 Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW 16.0 500kW-2mW 1 Apr 13 31 Mar 14 Hydro generating station with total installed capacity greater than 100kW but not exceeding 2MW 12.5 2mW+ 1 Apr 13 31 Mar 14 Hydro generating station with total installed capacity greater than 2MW 3.2 1 Apr 13 31 Mar 14 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a building which is already occupied 15.4 13.9 7.1 Solar photovoltaic with total installed capacity of 4kW or less, where attached to or wired to provide electricity to a new building before first occupation 15.4 13.9 7.1 Anaerobic Solar <4kW Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4) Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Solar (cont.d) Middle rate Lower rate 4kW-10kW 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 4kW but not exceeding 10kW 14.0 12.6 7.1 10kW-50kW 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 10kW but not exceeding 50kW 13.0 11.7 7.1 50kW-100kW 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 50kW but not exceeding 100kW 11.5 10.4 7.1 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 100kW but not exceeding 150kW 11.5 10.4 7.1 150kW-250kW 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 150kW but not exceeding 250kW 11.0 9.9 7.1 250kW+ 1 Apr 13 31 Mar 14 Solar photovoltaic (other than stand-alone) with total installed capacity greater than 250kW 7.1 Standalone 1 Apr 13 31 Mar 14 Stand-alone (autonomous) solar photovoltaic (not attached to a building and not wired to provide electricity to an occupied building) 7.1 <1.5kW 1 Apr 13 31 Mar 14 Wind with total installed capacity of 1.5kW or less 21.7 1.5kW-15kW 1 Apr 13 31 Mar 14 Wind with total installed capacity greater than 1.5kW but not exceeding 15 kW 21.7 15kW-100kW 1 Apr 13 31 Mar 14 Wind with total installed capacity greater than 15kW but not exceeding 100kW 21.7 100kW-500kW 1 Apr 13 31 Mar 14 Wind with total installed capacity greater than 100kW but not exceeding 500kW 18.0 100kW-150kW Wind Higher rate Eligibility Start Date: 1 April 2013 - 31 Mar 2014 (FIT Year 4) Technology type Generation level Period in Year Eligibility Started Technology Description EPC Level Requirement n/a Wind (cont.d) 500kW-1.5mW 1 Apr 13 31 Mar 14 Wind with total installed capacity greater than 500kW but not exceeding 1.5MW 9.8 1.5mW+ 1 Apr 13 31 Mar 14 Wind with total installed capacity greater than 1.5MW 4.2 10.2 4.6 ROO Migrated Installations <50kW 1 Apr 13 31 Mar 14 Eligible Installations with a declared net capacity of 50kW or less Commissioned on or before 14th July 2009 and accredited under the ROO on or before 31st March 2010 Export n/a 1 Apr 13 31 Mar 14 Non Solar Export Tariff Rate Higher rate Middle rate Lower rate 0172/07/12 E.ON UK plc Westwood Way Westwood Business Park Coventry CV4 8LG Registered in England and Wales No 2366970 eonenergy.com/business
© Copyright 2026 Paperzz