Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Tornillo/Guadalupe International P.O.E. Project SEA Amendment #22 January 28, 2013 IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. In the original contract dated October 8, 2001 to the Professional Services Agreement between the County of El Paso and SEA, Inc., a portion of Exhibit A to the Original Contract was omitted by mutual error. Amendment Four added the missing pages describing the Scope of Work for a portion of Phase 2 and all of Phases 3 and 4. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. • • • • Amendment #22 is being done to maintain the necessary services to complete the Port of Entry Project. There are 7 items that being requested for the Court to approve. Items 3 & 4 - pertains to added supervision to the International Bridge once Mexico begins their portion. Item 5 - pertains to the cost to review the design to correct improper work on a bridge that cross over irrigation ditches on the Phase 1 project, these funds will be reimbursed to the County by the Contractor. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc • • • • Item 6 - compensates SEA for the work necessary to the adjustments made at the LPOE bridge site because GSA’s contractor left the finish elevation 1’ to high. Item 7 - compensates SEA for the work necessary to change the fencing on the International Bridge as per CBP contract with the County. Item 8 - adds the services to oversee the construction of International Bridge that were never added by amendment to their contract. Item 9 allows SEA to provide Overall Project Management through the construction end date, presently anticipated to be December 2013 due to the extended timelines of this project. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. SEA will provide Observation of Mexican Construction, and Final Reviews, Punch Lists, and Project Acceptance of their portion of the International Bridge. The cost for these services is $41,754.72 and will cover Quality Control oversight for the Mexican portion of the bridge for approximately 12 months of time, until the final completion inspection is complete. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates, Inc. SEA will continue Bi-National coordination and Construction Contract Negotiation services at a cost of $38,804.48 and it will cover continuing efforts to finalize the Bi-National construction contract and Bi-National project timeline negotiations and other coordination issues. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA will continue to provide engineering services in order to finalize the Punch List inspection for the Major Arterial Roadway Project Phase 1. The cost of $11,370.20 is required to make the necessary corrections of improper work to a bridge deck by the Contractor. The County will be seeking reimbursement of these costs from the Contractor. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. In order to address requirement by the U.S. Border Patrol, SEA provided revisions to the Tornillo-Guadalupe International Bridge design. The cost for this work is $11, 850.04 and will cover changing the bridge design in order to retrofit a 15 foot tall straight fence into the bridge plans in lieu of the 8’ 3” curved chain link fence found in the original bridge design. SEA will also initiate a Change Order for use by the company building the bridge for the County. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA will be compensated for its work to revise the plan sheets for the International Bridge caused by elevation revisions by General Services Administration that impacted the Design of the International bridge and bridge approaches. The cost of $17,233.04 expended on the County’s behalf were required to adjust LPOE elevation, adjust Vertical Profile Deviations, lengthen drill shaft tops at the Border Fence and for additional overall project management/coordination. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. Construction Phase Services were not previously identified or amended into the contract with SEA for the International Bridge Phase. SEA will provide these services for the U.S. Portion of the International Bridge, and will be Construction Observation, Monthly Project Meeting, and Final Reviews, Punch Lists, and Project Acceptance at a cost of $45,633.04. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA’s Overall Project Management services that was covered in Amendment #17 ended on at the end of December 2012. It is anticipated that SEA will continue to provide these services due to the extended project timelines. These services will be provided at a cost of $50,494.08 and will provide services through the construction end date, presently anticipated to be December 2013 and will include the professional services necessary for coordinating the demolition of the existing Fabens-Caseta bridge. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Tornillo/Guadalupe International P.O.E. Project SEA Amendment #22 January 28, 2013 IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. In the original contract dated October 8, 2001 to the Professional Services Agreement between the County of El Paso and SEA, Inc., a portion of Exhibit A to the Original Contract was omitted by mutual error. Amendment Four added the missing pages describing the Scope of Work for a portion of Phase 2 and all of Phases 3 and 4. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. • • • • Amendment #22 is being done to maintain the necessary services to complete the Port of Entry Project. There are 7 items that being requested for the Court to approve. Items 3 & 4 - pertains to added supervision to the International Bridge once Mexico begins their portion. Item 5 - pertains to the cost to review the design to correct improper work on a bridge that cross over irrigation ditches on the Phase 1 project, these funds will be reimbursed to the County by the Contractor. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc • • • • Item 6 - compensates SEA for the work necessary to the adjustments made at the LPOE bridge site because GSA’s contractor left the finish elevation 1’ to high. Item 7 - compensates SEA for the work necessary to change the fencing on the International Bridge as per CBP contract with the County. Item 8 - adds the services to oversee the construction of International Bridge that were never added by amendment to their contract. Item 9 allows SEA to provide Overall Project Management through the construction end date, presently anticipated to be December 2013 due to the extended timelines of this project. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineering Associates, Inc. SEA will provide Observation of Mexican Construction, and Final Reviews, Punch Lists, and Project Acceptance of their portion of the International Bridge. The cost for these services is $41,754.72 and will cover Quality Control oversight for the Mexican portion of the bridge for approximately 12 months of time, until the final completion inspection is complete. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates, Inc. SEA will continue Bi-National coordination and Construction Contract Negotiation services at a cost of $38,804.48 and it will cover continuing efforts to finalize the Bi-National construction contract and Bi-National project timeline negotiations and other coordination issues. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA will continue to provide engineering services in order to finalize the Punch List inspection for the Major Arterial Roadway Project Phase 1. The cost of $11,370.20 is required to make the necessary corrections of improper work to a bridge deck by the Contractor. The County will be seeking reimbursement of these costs from the Contractor. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. In order to address requirement by the U.S. Border Patrol, SEA provided revisions to the Tornillo-Guadalupe International Bridge design. The cost for this work is $11, 850.04 and will cover changing the bridge design in order to retrofit a 15 foot tall straight fence into the bridge plans in lieu of the 8’ 3” curved chain link fence found in the original bridge design. SEA will also initiate a Change Order for use by the company building the bridge for the County. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA will be compensated for its work to revise the plan sheets for the International Bridge caused by elevation revisions by General Services Administration that impacted the Design of the International bridge and bridge approaches. The cost of $17,233.04 expended on the County’s behalf were required to adjust LPOE elevation, adjust Vertical Profile Deviations, lengthen drill shaft tops at the Border Fence and for additional overall project management/coordination. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. Construction Phase Services were not previously identified or amended into the contract with SEA for the International Bridge Phase. SEA will provide these services for the U.S. Portion of the International Bridge, and will be Construction Observation, Monthly Project Meeting, and Final Reviews, Punch Lists, and Project Acceptance at a cost of $45,633.04. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient Building on our legacy, illuminating . innovation, succeeding beyond borders . est. 1850 Contract Amendment Twenty Two for Additional Services to Professional Services Agreement between the County of El Paso and Structural Engineers Associates Inc. SEA’s Overall Project Management services that was covered in Amendment #17 ended on at the end of December 2012. It is anticipated that SEA will continue to provide these services due to the extended project timelines. These services will be provided at a cost of $50,494.08 and will provide services through the construction end date, presently anticipated to be December 2013 and will include the professional services necessary for coordinating the demolition of the existing Fabens-Caseta bridge. IntegrityInnovativeCollaborativeProfessionalResponsiveRespectfulEthicalTransparentCustomer first!Effective & efficient
© Copyright 2026 Paperzz