Pre Development BS5837 Arboricultural Implications Assessment Jesmond Towers BS5837.AIA.JT.04.2012.V2 Produced For Glen Kemp By Jim Richardson BSc For. HND Arb. Tech.Arbor.A Pre Development BS5837 Arboricultural Implications Assessment Jesmond Towers BS5837.AIA.JT.04.2012.V2 Contents Introduction................................................................................................................. 3 Summary of Findings ................................................................................................. 4 2.1. Statutory Tree Protection........................................................................................ 5 3. Arboricultural Impact Assessment ............................................................................ 6 4. Arboricultural Method Statement .............................................................................. 8 4.1. Aerial Protection ..................................................................................................... 8 4.1.1. Construction of Protective Fencing .................................................................. 8 4.1.2. Protective Fencing Minimum Distances........................................................... 9 4.2. Construction Exclusion Zones ................................................................................ 9 4.3. Special Construction Techniques ......................................................................... 10 4.3.1. Principle Rules of No Dig Construction ............................................................. 10 4.1.1. No Dig Construction Method: ............................................................................ 10 4.3.2. Foundation Construction Within CEZs........................................................... 11 4.3.3. Instillation of Underground Utilities ................................................................ 11 4.3.4. Ground Protection During Works Within CEZs .............................................. 11 4.3.5. New Surfacing Within Root Protection Areas ................................................ 12 4.3.5.1. Instillation of Permeable Surfacing............................................................. 12 4.3.6. Excavations Within Root Protection Areas .................................................... 14 4.5. North Jesmond House Garden ............................................................................. 16 4.7. Grotto Wood ......................................................................................................... 17 4.8. Main Junction ....................................................................................................... 17 4.9. Western Access Road .......................................................................................... 18 4.10. South Lodge Area ............................................................................................. 19 Tree Works ....................................................................................................... 19 4.11. 4.12. Schedule of Arboricultural Works ...................................................................... 20 4.13. Arboricultural Supervision ................................................................................. 22 5. Other Arboricultural Site Factors ............................................................................ 23 5.1. Hazard Trees ....................................................................................................... 23 5.2. Recent Management ............................................................................................ 23 5.3. Future Management ............................................................................................. 23 5.4. Protected Wildlife ................................................................................................. 23 Appendices ....................................................................................................................... 24 I. Notes on Tree Assessment ................................................................................... 24 Protective Fencing Details ................................................................................. 25 II. 1. 2. Date of Survey Report Production Surveyor Consultant: AJT Environmental Consultants survey April 2012 AJT Environmental Consultants survey Jim Richardson BSc For. HND Arb. Tech.Arbor.A BS5837.AIA.JT.04.2012.V2 2 1. Introduction Glen Kemp have commissioned this arboricultural impact assessment on behalf of their clients for the proposed re-development of the Jesmond Towers site. The survey and resulting report have been produced to be submitted as part of the planning application for the site to the local planning authority and have been produced in accordance with the best practice guidelines set out in BS 5837 (2005) Trees In Relation To Construction Sites: Recommendations. The tree survey details were collected by AJT Environmental Consultants and tree details should be referenced to their tree survey data records. Eighty Two significant trees were surveyed as individuals and a further 35 tree groups were surveyed as collective groups. The sites trees consist of a variety of mature and semi mature native and exotic broadleaves and evergreens. Numerous sapling and small shrubs are also present on site. A vegetation management plan has been produced to accompany the planning application and all management of vegetation not directly relating to development issues should be referenced to this plan. Woodsman were provided with a site plans of the area with tree locations canopies and root protection areas marked on both pre and post development. Drawing 590 Tree Survey Fig 3 is effectively the Arboricultural Constraints Plan. Tree Protection Plans (TPPs) have been adapted from the site plans provided. Tree locations and protective measures should be referenced to the Tree Protection Plans (JT.TPP.01 – JT.TPP.13). 3 BS5837.AIA.JT.04.2012.V2 2. Summary of Findings The tree survey details were collected by AJT Environmental Consultants and tree details should be referenced to their tree survey data records. Eighty Two significant trees were surveyed as individuals and a further 35 tree groups were surveyed as collective groups. The sites trees consist of a variety of mature and semi mature native and exotic broadleaves and evergreens. Numerous sapling and small shrubs are also present on site. The trees have had little significant recent management. Collectively the trees provide the site with good amenity and screening. Some of the trees surveyed are beyond the boundaries of the development areas. The proposed development will require the removal of 35 significant individual trees. Some development works including resurfacing are scheduled in close proximity to retained trees within Root Protection Areas (RPAs). These works must employ special construction techniques in order to minimise disturbance to tree roots. Providing that appropriate protective measures and construction techniques are enforced during development the trees on site can be retained and should provide amenity benefits for the site into the future. The development should not have a major long term impact on the sites tree stock. Extensive planting following construction should mitigate for the tree losses that are necessary to allow the current design layout to be achieved. Retained trees should not conflict significantly with site usage other than some shading of plots immediately adjacent to retained mature specimens. BS5837.AIA.JT.04.2012.V2 4 2.1. Statutory Tree Protection Many of the trees on site are protected by the Tree Preservation Order TREE PRESERVATION ORDER NO 2011/003 - JESMOND TOWERS ESTATE, NEWCASTLE UPON TYNE. The site is also protected by conservation area status. It is therefore advised that permission be sought from the local planning authority prior to any tree works being carried out on site. 5 BS5837.AIA.JT.04.2012.V2 3. Arboricultural Impact Assessment The proposed development will require the removal of 35 significant individual trees. Of those trees scheduled for removal twenty six are protected by the tree preservation order including; · T2 (TPO W1), · Trees within G6, T11, T13, T17, T20, T36, x2 Ash (unnumbered), x1 Oak (unnumbered) and x1 other (unnumbered),- (Within TPO W2), · T17, 18, 19, 20, 21, 25 and 26 (Within TPO G2), · T34, 35, 40, 41, 46, 47 and 53 (Within TPO G3), · G4 (TPO T10 and T11), Some development works including resurfacing and minor ground works are scheduled in close proximity to retained trees within Root Protection Areas (RPAs). These works must employ special construction techniques in order to minimise disturbance to tree roots. Special construction techniques will be required in several areas including works beneath; T78 and 79 (Mathew Bank Apartments – adjacent to plot 19 and 20), T80, 81 and 82 (North Jesmond House Garden – adjacent to plots 21-26), T36-66 (Grotto Wood Area), T61, 27, 22 and 23 (Main Junction Area), Unnumbered local authority Lime street trees (Western Access Road – beneath removed T28) and T11, 12, (South Lodge Area Entrance). Providing that appropriate protective measures and construction techniques are enforced during development the majority of trees on site can be retained and should provide wildlife and amenity benefits for the site into the future. BS5837.AIA.JT.04.2012.V2 6 The development should not have a major long term impact on the sites tree stock. Extensive planting following construction should mitigate for the tree losses that are necessary to allow the current design layout to be achieved. Retained trees should not conflict significantly with site usage other than some shading of plots immediately adjacent to retained mature specimens. 7 BS5837.AIA.JT.04.2012.V2 4. Arboricultural Method Statement The retained trees will need protection for roots trunks and branches during demolition and construction. The trees will be protected by erecting barrier fencing as depicted on the Tree Protection Plan. 4.1. Aerial Protection Arial protection should take the form of barrier fencing constructed as per BS5837 Guidelines. 4.1.1. Construction of Protective Fencing Barriers should consist of a scaffold framework in accordance with BS 5837:2005 Trees in relation to construction - Recommendations; section 9, comprising a vertical and horizontal framework, well braced to resist impacts, with vertical tubes spaced at a maximum interval of 3m. Onto this, weld-mesh panels should be securely fixed with wire or scaffold clamps. Weld-mesh panels on rubber or concrete feet are not resistant to impact and should not be used unless they are effectively pinned down and braced The use of any alternative method of fencing should only be allowed following prior approval from the site Arboricultural Consultant or the Local Planning Authority. NOTE: The above is preferred because it is readily available, resistant to impact, can be re-used and enables inspection of the protected area. Protective fencing should enclose tree canopies in all areas where ground-works are not required (other than where canopies extend over parking and access routes). The fencing will remain in place until completion of the development and then only removed with the consent of the local planning authority to permit completion of the scheme. BS5837.AIA.JT.04.2012.V2 8 Other than works detailed within this method statement or approved in writing by the local planning authority, no works including storage or dumping of materials shall take place within the Construction Exclusion Zones (CEZs) as defined by the protective fencing. 4.1.2. Protective Fencing Minimum Distances Distances for protective fencing should be referenced to the Tree Protection Plans 4.2. Construction Exclusion Zones No works access should be allowed into the CEZs (Construction Exclusion Zones) during the development phase. No storage of any building materials or any other materials should be allowed within the CEZs. Once the exclusion zones have been protected by barriers and/or ground protection, construction work can commence. All weather notices should be erected on the barrier with words such as: “Construction Exclusion Zone — Keep out”. In addition the following should be addressed or avoided. A. Care should be taken when planning site operations to ensure that wide or tall loads or plant with booms, jibs and counterweights can operate without coming into contact with retained trees. Such contact can result in serious damage to them and might make their safe retention impossible. Consequently, any transit or traverse of plant in close proximity to trees should be conducted under the supervision of a Banks-man to ensure that adequate clearance from trees is maintained at all times. In some circumstances it may be impossible to maintain adequate clearance thus necessitating access facilitation pruning - see T80, 81 and 82. B. Material which will contaminate the soil, e.g. concrete mixings, diesel oil and vehicle washings, should not be discharged within 10 m of the tree stem. C. Fires should not be lit in a position where their flames can extend to within 5 m of foliage, branches of trunk. This will depend on the size of the fire and the wind direction. 9 BS5837.AIA.JT.04.2012.V2 D. Notice boards, telephone cables or other services should not be attached to any part of the trees. E. It is essential that allowance should be made for the slope of the ground so that damaging materials such as concrete washings, mortar or diesel oil cannot run towards trees. 4.3. (Para BS5837) Special Construction Techniques Some development works including resurfacing are scheduled in close proximity to retained trees within Root Protection Areas (RPAs). These works must employ special construction techniques in order to minimise disturbance to tree roots. If the development is to proceed with the current design layout then special no dig construction techniques will be required for the creation of new paths and driveways and for the re-surfacing of existing hard surfaces within the areas that would normally form part of the CEZs. 4.3.1. Principle Rules of No Dig Construction The principal rules of no dig construction are as follows: 1. No roots are to be severed 2. Soil must not be compacted 3. Oxygen and water must be able to diffuse into the soil beneath engineered surfaces 4. The construction of the roads, footpaths or parking bays will have to be above existing ground level and at least 1.5m away from the trunks of the retained trees. 4.1.1. No Dig Construction Method: Construction should ideally be undertaken between May and October when the ground is at its driest and is less prone to compaction BS5837.AIA.JT.04.2012.V2 10 Ground vegetation should be carefully removed with any organic material being removed to prevent the build-up of anaerobic conditions beneath the surfacing which will damage the tree roots. No digging should take place within the protective zone except for the careful removal of organic matter by hand tools. Hollows must be filled with sharp sand, any digging to remove rocks or protrusions must be by hand taking care not to sever any roots over 2.5cm in diameter. Stumps should be ground out rather than excavated to prevent damage to the retained trees roots. 4.3.2. Foundation Construction Within CEZs No use of specialist foundations is required with the current design layout. Extreme care is required to avoid damage to tree roots during foundation construction. Foundation design should follow the principles of the ‘House deck’ or Swift foundation systems (www.abbeypynford.co.uk / www.swiftfoundations.co.uk ) utilising mini-piles on which a raft is installed above ground level leaving a void beneath the building. This void allows for gaseous and moisture exchange in the soil and prevents soil compaction. Temporary protective surfacing should be installed prior to accessing the area for foundation construction 4.3.3. Instillation of Underground Utilities If underground utilities are to be installed within RPAs extreme care will be required in order to avoid damage to tree roots. These works should follow the guidelines set out below (Excavations Within Root Protection Areas). 4.3.4. Ground Protection During Works Within CEZs If access is required within CEZs then ground protection will be required. Where required a practical solution to ground protection within areas requiring special construction techniques is the installation of a temporary surface to reduce ground compaction. This should take the form of a multi-layered protective barrier as detailed below: 11 BS5837.AIA.JT.04.2012.V2 Temporary Ground Protection Layers · Base Layer – Undisturbed soil containing tree roots. · Layer 1 – Sharp sand loosely tipped and lightly tamped to level uneven ground. · Layer 2 – Geo-textile (e.g. Terram 1000). · Layer 3 – Minimum 10cm depth of compressible fill (e.g. woodchip) – must be replenished if on-going compression occurs. · Layer 4 - Top layer – temporary boarding system capable of forming construction access for vehicles (e.g. Greentek Ground guards). (or possibly lesser surfacing for foot access only) 4.3.5. New Surfacing Within Root Protection Areas New surfacing such as re-surfacing and pathways must use a non-compacting porous surface such as Cell Web (from Geosynthetics) or a similar cellular confinement system. No changes to ground level should be allowed prior to installation of new surfacing which should be installed above the existing ground level. 4.3.5.1. Instillation of Permeable Surfacing The construction method below is suitable for the construction of permeable surfaces. It is not a finished engineering solution. It is a methodology designed to allow the construction without damaging the nearby tree root systems. · Lay a non-woven geotextile (Fibretex F4M or similar) on to the existing subgrade. - Overlap dry joints by 300mm · Lay and expand the cellular confinement system (Cellweb) and anchor open during infilling. · Fill the cellular confinement system with a minimum of 75mm of aggregate (75mm is the minimum depth for domestic traffic). The aggregate should not contain any fines and be of an inert type material such as whinstone chips rather than any lime based product. The angular particle dimensions should be 20-40mm. As most urban soils are already alkaline in nature, the use of BS5837.AIA.JT.04.2012.V2 12 dolomite, limestone or crushed concrete is not suitable for this application as it can react with rain water with the potential to change the soil pH and form impenetrable layers which impede water movement and gaseous exchange · Place the final surface material. o Block Paving – lay a second layer of Fibrex F4M Geotextile separation fabric over the in-filled Cellweb sections. Lay a sharp sand bedding layer compacted with a vibro compaction plate to recommended depth. Places paviors as per the manufacturer’s instructions. The use of porous blocks such as Aquaflow by Formpave are particularly tree friendly and allow natural rainfall to reach the rooting area. o Porous tarmac – place 25mm surcharge of the granular material above the Cellweb system and lay the bitumen base and wearing course o Loose Gravel- Place a second layer of Geotextile separation fabric over the in-filled Cellweb sections. Place decorative aggregate to the required depth. A treated timber edge should be provided to restrict gravel movement o Grass blocks or gravel in-filled blocks - Lay a second layer of Geotextile separation fabric over the in-filled Cellweb sections. Place 50/50 rootzone bedding layer to the required depth. Lay recycled Duo Block 500 Grass protection system in-filled with 50/50 rootzone mix. Seed as required. Alternatively the grass blocks may be in-filled with gravel. 13 BS5837.AIA.JT.04.2012.V2 Edging supports such as angled steel section is advised although there varying kerbing options available which do not require any excavation and could be used above the existing ground level. Edging material must not encroach into the protected area and the use of conventional kerbing is not possible as the depth of excavation required for their installation will sever the tree roots. Wherever footpaths go through a protective zone, it is often not possible to erect the normal permanent protective fencing at the correct distance from the tree whilst maintaining access to construct the hard surfacing. The permanent protective fencing must be erected as per the plan as close to the edge of the working area as possible. Extreme care must be taken to avoid damage to unprotected areas prior to the surfacing system being laid and access must be prevented especially to vehicles and plant. Temporary Herras fencing should be erected at distance indicated on the Tree Protection Plan until the hard surfacing is constructed. 4.3.6. Excavations Within Root Protection Areas All excavations for landscaping or re-surfacing works within RPAs must be carried out following the guidelines set out in NJUG Volume4 (National Joint Utilities Guidance Volume 4 Guidelines for the Planning, Installation And Maintenance Of Utility Apparatus in Proximity To Trees issue 2). 4.3.6.1. Root Protection Fine roots are vulnerable to desiccation once they are exposed to the air. Larger roots have a bark layer which provides some protection against desiccation and temperature change. The greatest risk to these roots occurs when there are rapid fluctuations in air temperature around them e.g. frost and extremes of heat. It is therefore important to protect exposed roots where they are to be left open overnight where there is a risk of frost. In winter, before leaving the site at the end of the day, the exposed roots should be wrapped with dry sacking. This sacking must be removed before the trench is backfilled. BS5837.AIA.JT.04.2012.V2 14 All roots greater than 25mm diameter should be preserved and worked around. These roots must not be severed unless absolutely necessary following approval from the sites Arboricultural Consultant. If after consultation severance is unavoidable, roots must be cut back using a sharp tool to leave the smallest wound possible. No roots above 50mm in diameter will be severed without prior approval from the local authority’s arboricultural officer. It is not anticipated that severance of any large roots will be required. Careful hand digging will be employed within the RPAs with extreme care being taken not to damage tree roots and root bark. Exposed roots if left overnight will be covered to offer protection from the elements. No roots above 25mm in diameter will be severed. 4.3.6.2. Hand Digging/Airspade The objective of hand digging is to retain as many undamaged roots as possible. Hand digging within RPA must be undertaken with great care preferably using an airspade, preferably under supervision from the sites arboricultural consultant. After careful removal of any hard surface materials digging must proceed with hand tools. Clumps of roots less than 25mm in diameter (including fibrous roots) should be retained in situ without damage. Throughout the excavation works great care should be taken to protect the bark around the roots. 4.3.6.3. Backfilling Backfilling should where required be carefully carried out to avoid direct damage to roots and excessive compaction of the soil around them. The backfill should, where possible, include the placement of an inert granular material mixed with top soil or sharp sand (not builder’s sand) around the roots. This should allow the soil to be gently compacted prior to construction without damage to the roots securing a local aerated zone enabling the root to survive in the longer term. If required backfilling outside the direct influence of tree roots should be carried out using the excavated soil. This should not be compacted but lightly “tamped” and 15 BS5837.AIA.JT.04.2012.V2 usually left slightly proud of the surrounding surface to allow natural settlement. Other materials should not be incorporated into the backfill. 4.4. Mathew Bank Apartments Area In this area beneath T78 and 79 existing hard standing must be removed and no-dig porous surfacing and soft landscaping installed. Removal of existing hard-standing must be carried out by hand with surfacing being broken into small pieces before being lifted. Any minor discrepancy in ground levels must then be filled using sharp sand prior to the installation of the non-dig porous surfacing and landscaping. All works within Root Protection Areas must be carried out under supervision and using the principles specialist construction methods detailed in section 4.3 (above). See Plan Number JT.TPP.04. 4.5. North Jesmond House Garden In this area beneath T80, 81 and 82 existing hard standing must be removed and replaced and soft landscaping installed. The area of hard-standing beneath T80 consisting of concrete slabs will be removed and replaced. The existing surface beneath T 81 and 82 will be re-surfaced. In addition the small brick building between T81 and 82 must be removed. Removal of existing hard-standing must be carried out by hand with surfacing being broken into small pieces before being lifted. Any minor discrepancy in ground levels must then be filled using sharp sand prior to the installation of the new surfacing and landscaping. Compaction must be avoided and new surfacing must not be tamped hard down. Temporary ground protection may be required at the Arboricultural Consultants discretion once the original surface is removed. BS5837.AIA.JT.04.2012.V2 16 The removal of the small brick building between T81 and 82 must be carried out by hand. All works within Root Protection Areas must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). See Plan Number JT.TPP.04. 4.6. Grotto Wood In this area beneath T 34-61 new footpath are to be installed using special non-dig construction methods. Special care will need to be taken when installing protective fencing and edging of the footpaths so as not to damage the surface roots which are prominent throughout the Grotto Wood Area. Pins for placing protective fencing and footpath edging must not be driven into the surface roots. All works within Root Protection Areas must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). See Plan Number JT.TPP.02. 4.7. Main Junction This area beneath T 23, 27, 59 and 61 requires the removal of existing driveway surfacing and replacement with non-dig porous surfacing. 17 BS5837.AIA.JT.04.2012.V2 Where existing driveway surfacing is to be replaced rather than removing the surface driveway altogether only the surface should be removed and re-surfaced. Where new surfacing is required non-dig construction methods must be employed. All works within Root Protection Areas must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). See Plan Number JT.TPP.06. 4.8. Western Access Road This area beneath local authority lime trees and removed T28 requires the installation of new gateposts and driveway and footpath surfacing. Removal of existing gateposts and wall must be carried out by hand down to ground level with any foundation beneath ground level remaining in situ. Installation of foundations for new gateposts must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). Should digging for gateposts reveal significant roots within the foundation area then the roots must be bridged using concrete lintels whilst allowing ample room for future root expansion. Where existing driveway surfacing is to be replaced rather than removing the surface driveway altogether only the surface should be removed and re-surfaced. Where new surfacing is required non-dig construction methods must be employed. All works within Root Protection Areas must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). See plan number JT.TPP.13 BS5837.AIA.JT.04.2012.V2 18 4.9. South Lodge Area This area Beneath T11 and 12 requires the installation of new gateposts and footpath surfacing. Removal of existing gateposts and wall must be carried out by hand down to ground level with any foundation beneath ground level remaining in situ. Installation of foundations for new gateposts must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). Should digging for gateposts reveal significant roots within the foundation area then the roots must be bridged using concrete lintels whilst allowing ample room for future root expansion. All works within Root Protection Areas must be carried out under supervision and using the principles of specialist construction methods detailed in section 4.3 (above). See Plan Number JT.TPP.12. 4.10. Tree Works All tree pruning and removal works must conform to BS3998 Recommendations for Tree Works, and must use target pruning in accordance with best practice. The tree works scheduled below refer only to those works which relate directly to development issues. 19 BS5837.AIA.JT.04.2012.V2 4.11. Schedule of Arboricultural Works 1. Provide site managers with a copy of Arboricultural report. 2. Tree Protection Plans to be mounted in works cabins. 3. Brief all site staff regarding protective measures (on-going). 4. Mark out trees for removal and remedial works with temporary marker paint. 5. Facilitation Access prune - Crown-Raise T80, 81, 82 to give 3m clearance from ground level. 6. Remove trees with TPO status · T2 (TPO W1), · Trees within G6, T11, T13, T17, T20, T36, x2 Ash (unnumbered), x1 Oak (unnumbered) and x1 other (unnumbered),- (Within TPO W2), · T17, 18, 19, 20, 21, 25 and 26 (Within TPO G2), · T34, 35, 40, 41, 46, 47 and 53 (Within TPO G3), · G4 (TPO T10 and T11), 7. Remove other trees. – T7, T9, T10, T28, 30, 32, 72, x1 tree from G2 (unnumbered) and x2 trees by north lodge (unnumbered). 8. Mark out lines of protective fencing and areas for special construction techniques. 9. Install protective fencing including information signs. 10. Remove existing hard-standing by hand beneath T78, 79 and 80 (Mathew Bank Apartments and North Jesmond House Garden.* 11. Remove small brick building between T81 and 82 by hand.* 12. Install no-dig surfacing beneath T78 and 79.* 13. Install soft landscaping beneath T78 and 79.* BS5837.AIA.JT.04.2012.V2 20 14. Re-install non porous surfacing beneath T80, 81 and 82.* 15. Install soft landscaping beneath T80.* 16. Install no-dig footpath/driveway within Grotto Wood (Beneath T34-61)* 17. Remove surface of existing hard-standing at Main Junction (Beneath T23, 27, 59 and 61)* 18. Install no-dig surfacing at Main Junction (Beneath T23, 27, 59 and 61)* 19. Remove and replace existing gateposts – hand digging only at Western Access Road (Beneath local authority lime trees and removed T28)* 20. Install no-dig surfacing at Western Access Road (Beneath local authority lime trees and removed T28)* 21. Refurbish existing wearing course at Western Access Road (Beneath local authority lime trees and removed T28)* 22. Remove and replace existing gateposts – hand digging only at South Lodge Area entrance (beneath T11).* 23. Install no-dig surfacing at South Lodge Area entrance and raise adjacent tarmac surface (beneath T11 and 12).* 24. Construction Phase – including all further construction works. 25. Landscaping works. – Any works within Root Protection Areas to be supervised.* 26. De-install protective fencing – only once all other development activity is completed. 27. Completion *Works requiring arboricultural supervision. 21 BS5837.AIA.JT.04.2012.V2 All staff on site should be briefed regarding the protective measures to be enforced. Construction should not proceed prior to the installation of the protective measures and these should remain in place for the entire duration of the construction phase. Only once the construction phase is completed in its entirety should the protective fencing be removed. 4.12. Arboricultural Supervision Tree protection measures on this site are complex and special construction techniques are required. Arboricultural supervision from the sites Arboricultural Consultant is therefore considered necessary during the installation new surfacing and significant ground works within Root Protection Areas. On-going Arboricultural supervision is advised throughout the development process. Any deviation from the prescribed method statement or the occurrence of any unforeseen damage to the sites trees must be immediately reported to the sites Arboricultural Consultant. All works around the affected area on site must be halted immediately. The Arboricultural Consultant will make a site visit to assess the extent of the damage or deviation from the prescribed method statement and any resulting works required. The local authority planning department will also be immediately informed and Woodsman will provide them with a written assessment of any such damage or deviation from the prescribed method statement. BS5837.AIA.JT.04.2012.V2 22 5. Other Arboricultural Site Factors 5.1. Hazard Trees A vegetation management plan has been produced to accompany the planning application and all management of vegetation not directly relating to development issues should be referenced to this plan. 5.2. Recent Management The trees have had little significant recent management. 5.3. Future Management A vegetation management plan has been produced to accompany the planning application and all management of vegetation not directly relating to development issues should be referenced to this plan. 5.4. Protected Wildlife It is an offence under the Wildlife and Countryside Act 1981 (and amendments) and the EU Habitats Directive to disturb and or destroy the nests of bats, birds and other protected wildlife. It is therefore advised that tree contractors check for the presence of bats and birds’ nests prior to carrying out tree removals. 23 BS5837.AIA.JT.04.2012.V2 Appendices I. Notes on Tree Assessment The tree survey details were collected by AJT Environmental Consultants and tree details should be referenced to their tree survey data records. The trees on site have been assessed and categorised as follows according to BS 5837 (2005) Trees In Relation To Construction Sites: Recommendations. Category R Trees: Those in such a condition that any existing value would be lost within the next ten years and which should in the current context, be removed for reasons of sound arboricultural management: Category C Trees: Those of low quality and value: Currently in adequate condition to remain until new planting could be established or young trees with a stem diameter below 150mm. These trees although of some value should not be allowed to affect the design of the site layout as they can easily be replaced. Category B Trees: Those of moderate quality and value: those in such a condition as to make a significant contribution for a minimum of twenty years. Site design should where practicable retain these specimens. Category A Trees: Those of high quality and value: in such a condition as to be able to make a substantial contribution for a minimum of forty years. Site design should seek to retain these trees wherever it is practicable to do so. BS5837.AIA.JT.04.2012.V2 24 II. Protective Fencing Details 25 BS5837.AIA.JT.04.2012.V2 BS5837.AIA.JT.04.2012.V2 26 (T63) (T17) KEY (T18) Tree Root Protection Area (RPA) (T64) 'No-dig' road/footpath construction (Porous construction detail) T61 (T66) T60 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction (T65) Existing hard standing replaced by soft landscaping (T27) Non-porous footpath construction (replacing existing non-porous construction) (T16) Existing wearing course refurbished Proposed increase T13 in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained PLOTS 49 G2 Tree to be removed Tree protection barrier G1 T12 (G4) T11 PLOT 1 Rev. Date Description - - - (G4) Client Shepherd Offshore Project Jesmond Towers Title Tree Protection Plan No13 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.13 (T28) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk Scale@A3 1:250 Revision 10/05/2012- (13) PLOTS 43 - 48 KEY (11) 8 Tree Root Protection Area (RPA) G6 'No-dig' road/footpath construction (Porous construction detail) 7 (16) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained T5 Tree to be removed Tree protection barrier T4 T6 (T7) T3 T8 Rev. Date Description - - - T2 Client Shepherd Offshore T13 Project T1 Jesmond Towers Title (T10) PLOTS 49 (T9) Tree Protection Plan No12 Drawn Checked JR Date 26-04-12 Drawing No. G2 G1 JT.TPP.12 T12 T11 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk Scale@A3 1:250 Revision 10/05/2012- 12 (G6) KEY Tree Root Protection Area (RPA) 9 'No-dig' road/footpath construction (Porous construction detail) 15 (13) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction 3600 (11) 8 Existing hard standing replaced by soft landscaping (16) G6 7 Non-porous footpath construction (replacing existing non-porous construction) Existing wearing course refurbished Proposed increase in levels in mm above existing 1300 1000 (subject to further detailed design/survey information) Tree to be retained Tree to be removed Tree protection barrier T5 T4 Rev. Date 10 Apartments - Description - T6 (T7) Client Shepherd Offshore T3 Project T2 Jesmond Towers T8 Title Tree Protection Plan No11 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.11 T1 (T10) (T9) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk Scale@A3 1:250 Revision 10/05/2012- KEY Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction 29 Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) (36) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) 30 Tree to be retained 34 Tree to be removed 35 Tree protection barrier 33 32 Rev. Date Description - - - Client G6 Shepherd Offshore Project Jesmond Towers Title 31 Tree Protection Plan No10 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.10 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk Scale@A3 1:250 Revision 10/05/2012- 19 KEY 18 21 14 22 23 24 Tree Root Protection Area (RPA) 25 'No-dig' road/footpath construction (Porous construction detail) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) 15 Tree to be retained 3600 Tree to be removed Tree protection barrier 1300 1000 Rev. Date Description - - - Client Shepherd Offshore Project Jesmond Towers Title (36) Tree Protection Plan No9 Drawn Checked JR 10 Apartments Date 26-04-12 Scale@A3 1:250 Revision Drawing No. JT.TPP.09 10/05/2012- 34 35 33 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk KEY (2no. Ash) G6 Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) 18 Existing wearing course refurbished 14 10 Proposed increase in levels in mm above existing (subject to further detailed design/survey information) North Lodge Tree to be retained Tree to be removed 12 Tree protection barrier (G6) 9 15 (13) Rev. Date Description - - - 3600 (11) 8 (16) G6 Client Shepherd Offshore 7 Project Jesmond Towers Title Tree Protection Plan No8 1300 Drawn Checked JR 1000 Date 26-04-12 JT.TPP.08 T4 1:250 Revision Drawing No. T5 Scale@A3 10/05/2012- 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk 10 Apartments KEY Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction 4 Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) 3 Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) (2) G6 Tree to be retained Tree to be removed 1 Tree protection barrier 10 5 North Lodge Rev. Date Description - - - 9 Client Shepherd Offshore Project PLOTS 43 - 48 Jesmond Towers Title Tree Protection Plan No7 Drawn 8 Checked JR Date 26-04-12 G6 JT.TPP.07 (T26) 10/05/2012- 7 (T24) (T22) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk (T21) T20 1:250 Revision Drawing No. (T25) Scale@A3 PLOTS 33 - 36 KEY Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) PLOTS 43 - 48 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping (T25) (T26) Non-porous footpath construction (replacing existing non-porous construction) (T24) PLOTS 37 - 42 (T23) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) (T22) (T21) Tree to be retained Tree to be removed (T62) T20 Tree protection barrier (T19) (T63) (T17) (T18) (T64) T61 (T66) Rev. Date Description - - - (T65) Client Shepherd Offshore Project (T27) Jesmond Towers Title (T16) Tree Protection Plan No6 Drawn Checked JR Date 26-04-12 T13 Drawing No. JT.TPP.06 (G4) 1:250 Revision 10/05/2012- (T1 PLOTS 49 G2 Scale@A3 G1 T12 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk T11 (T17) KEY (T18) Tree Root Protection Area (RPA) (T64) 'No-dig' road/footpath construction (Porous construction detail) T61 (T66) T60 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction (T65) Existing hard standing replaced by soft landscaping (T27) Non-porous footpath construction (replacing existing non-porous construction) (T16) Existing wearing course refurbished T13 Proposed increase in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained PLOTS 49 G2 (G4) Tree to be removed G1Tree protection barrierT12 T11 PLOT 1 (G4) Rev. Date Description - - - Client Shepherd Offshore Project Jesmond Towers Title Tree Protection Plan No5 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.05 (T28) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk Scale@A3 1:250 Revision 10/05/2012- KEY Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping Non-porous footpath construction (replacing existing non-porous construction) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained Tree to be removed Tree protection barrier +0 +0 PLOT 19 T80 +0 T81 + 120 550+ + 150 PLOT 20 T78 T82 +0 T79 +0 PLOT 26 Rev. Date Description - - - 4 Client Shepherd Offshore Project + 50 Jesmond Towers 3 Title Tree Protection Plan No4 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.04 PLOT 21 - 25 PLOTS 27 - 32 PLOTS 10 - 18 1) Please refer to the Designer's Risk Assessments within the health and Safety File / Construction Phase Plan and the relevant Contractor's Construction Method Statements prior to construction / maintenance of the designs illustrated. (2) 1:250 Revision 10/05/2012- 1 HEALTH & SAFETY NOTES: The Designers responsible for producing this document draw the reader's attention to the following residual health and safety risks associated with the design which have not been eliminated by the design process: Scale@A3 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk T36 T50 KEY T38 (T47) Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) T51 (T39) (T35) (T46) (T40) T52 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction (T53) PLOT 7 Existing hard standing replaced by soft landscaping T45 T41 (T42) (T44) Non-porous footpath construction (replacing existing non-porous construction) (T55) (T54) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) T57 T56 Tree to be retained Tree to be removed Tree protection barrier PLOT 6 Rev. Date Description - - - Client Shepherd Offshore PLOT 5 PLOT 4 Project Jesmond Towers Title PLOT 3 Tree Protection Plan No3 Drawn Checked JR Date 26-04-12 Drawing No. T31 (T32) JT.TPP.03 (T30) (T29) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk PLOT 2 Scale@A3 1:250 Revision 10/05/2012- PLOTS 27 - 32 KEY T69 Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction detail) T68 PLOTS 10 - 18 T67 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction Existing hard standing replaced by soft landscaping G5 Non-porous footpath construction (replacing existing PLOTS non-porous construction) 33 - 36 Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained Tree to be removed T48 Tree protection barrier T37 (T25) (T26) T49 T36 (T24) T50 T38 PLOTS 37 - 42 T59 (T47) (T39) (T35) Description - - - (T22) (T21) T51 (T46) (T40) Rev. Date (T23) T52 (T62) T20 Client (T19) Shepherd Offshore (T53) (T63) Project (T17) Jesmond Towers T45 Title T41 Tree Protection Plan No2 (T42) (T44) Drawn (T55) (T54) JR (T64) Date (T18) 26-04-12 1:250 10/05/2012- (T66) T60 Scale@A3 Revision Drawing No. JT.TPP.02 T61 T57 T56 Checked (T65) (T27) 0191 2092392 07773991474 [email protected] www.woodsman-arb.co.uk KEY Tree Root Protection Area (RPA) 'No-dig' road/footpath construction (Porous construction +0 T80 detail) PLOT 19 + 120 550+ T74 T79 PLOT 9 Existing tarmacadam surface to be raised to tie in with levels to new 'no dig' construction PLOT 20 Existing hard standing replaced by soft landscaping T78 + 150 +0 + 50 Non-porous footpath construction (replacing existing +0 non-porous construction) Existing wearing course refurbished Proposed increase in levels in mm above existing (subject to further detailed design/survey information) Tree to be retained T75 T73 Tree to be removed T70 Tree protection barrier T77 PLOT 21 - 25 T69 T76 T68 PLOTS 10 - 18 T67 (T72) Rev. Date Description - - - G5 Client Shepherd Offshore Project Jesmond Towers Title Tree Protection Plan No1 Drawn Checked JR Date 26-04-12 Drawing No. JT.TPP.01 Scale@A3 1:250 Revision 10/05/2012- T48 PLOT 8 T37 T49 0191 2092392 07773991474 T36 T50 [email protected] T38 (T47) www.woodsman-arb.co.uk T59 +
© Copyright 2026 Paperzz