Update on FCPS Construction/Renovation Projects

Deep Springs Elementary -- Renovation

Architect:
EOP Architects

General Contractor:

GC Contract Sum:
$12,152,800

Total Project Cost:
$15,082,114

Change Orders to Date (7):

Scheduled Contract Completion Date:

% of Contract Completed:

Revised Completion Date per GC:
Griggs Enterprises
$172,716
December 2014
30.91%
February 2015
December 2013
Deep Springs Elementary -- Renovation
Rendering of Final Façade
December 2013
Deep Springs Elementary -- Renovation
Work

Completed to Date:

Continued metal stud work in Decagon area.

Completed CMU in Phase 1 area.

Completed brick in Phase 1 area.

Started painting in the gym and Decagon areas.

Installed windows / storefronts in the Decagon.

Started CMU walls at the Area A addition.
Current Work Effort (December):

Continue painting in the Gym and Decagon.

Install spray-on insulation in the Gym.

Install gym equipment in the Gym.

Start ceiling grid.

Start installing lights, grilles, and cut off sprinkler lines.

Start terrazzo in the Decagon.
December 2013
Deep Springs Elementary -- Renovation
Brick & Stone Sills at Decagon
Area A Addition
Decagon - Drywall
Gym Ductwork
December 2013
Deep Springs Elementary -- Renovation
Decagon – Storefront Windows
Ramp – Storefront Windows
Computer Room
Resource Room Corridor
December 2013