Completion Report Project Number: 37041-013 Loan Number: 2261 April 2016 Cambodia: Second Power Transmission and Distribution Project This document is being disclosed to the public in accordance with ADB’s Public Communications Policy 2011. CURRENCY EQUIVALENTS Currency Unit At Appraisal (2 August 2006) KR1.00 = = $1.00 – riel/s (KR) At Project Completion (30 November 2014) $0.00025 KR4,063 $0.00024 KR4,133 ABBREVIATIONS ADB EDC EIRR FIRR GMS JICA – – – – – – MEF SDR VAT – – – Asian Development Bank Electricité du Cambodge economic internal rate of return financial internal rate of return Greater Mekong Subregion Japan International Cooperation Agency Ministry of Economy and Finance special drawing right value-added tax WEIGHTS AND MEASURES km kV kWh m2 – – – – kilometer kilovolt kilowatt-hour square meter NOTES (i) The fiscal year (FY) of the government ends on 31 December. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2009 ends on 31 December 2009. (ii) In this report, “$” refers to US dollars. Vice President Director General Director S. Groff, Operations 2 J. Nugent, Southeast Asia Department (SERD) S. Tukuafu, SERD/Cambodia Resident Mission (CARM) Team leader Team members N. Ouk, Senior Project Officer, SERD/CARM S. Hel, Associate Project Analyst, SERD/CARM M. Ouk, Associate Operations Coordinator, SERD/CARM In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. CONTENTS Page BASIC DATA i I. PROJECT DESCRIPTION 1 II. EVALUATION OF DESIGN AND IMPLEMENTATION A. Relevance of Design and Formulation B. Project Outputs C. Project Costs D. Disbursements E. Project Schedule F. Implementation Arrangements G. Conditions and Covenants H. Consultant Recruitment and Procurement I. Performance of Consultants, Contractors, and Suppliers J. Performance of the Borrower and the Executing Agency K. Performance of the Asian Development Bank 2 2 3 4 5 5 5 6 7 8 9 9 III. EVALUATION OF PERFORMANCE A. Relevance B. Effectiveness in Achieving Outcome C. Efficiency in Achieving Outcome and Outputs D. Preliminary Assessment of Sustainability E. Impact 9 9 10 11 11 12 IV. OVERALL ASSESSMENT AND RECOMMENDATIONS A. Overall Assessment B. Lessons C. Recommendations 13 13 14 14 APPENDIXES 1. Design and Monitoring Framework 2. Appraisal and Actual Project Costs 3. Currency Equivalents 4. Projected and Actual Disbursements 5. Project Implementation Schedule 6. Project Organization Chart 7. Status of Compliance with Loan Covenants 8. Financial and Economic Reevaluation 9. Resettlement Activities 16 20 21 22 23 24 25 34 37 BASIC DATA A. B. Loan Identification 1. 2. 3. Country Loan Number Project Title 4. 5. 6. 7. Borrower Executing Agency Amount of Loan Project Completion Report Number Loan Data 1. Appraisal – Date Started – Date Completed 2. Kingdom of Cambodia 2261-CAM(SF) Second Power Transmission and Distribution Project Kingdom of Cambodia Electricité du Cambodge SDR13.519 million ($20.0 million equivalent) CAM 1556 25 April 2006 28 April 2006 Loan Negotiations – Date Started – Date Completed 11 July 2006 13 July 2006 3. Date of Board Approval 4 October 2006 4. Date of Loan Agreement 1 December 2006 5. Date of Loan Effectiveness – In Loan Agreement – Actual – Number of extensions 1 March 2007 29 January 2008 3 Closing Date – In Loan Agreement – Actual – Number of Extensions 31 December 2010 10 March 2015 2 Terms of Loan – Interest Rate – Maturity – Grace Period 1.0% during grace period, 1.5% thereafter 32 years 8 years Terms of Relending – Interest Rate – Maturity – Grace Period – Second-Step Borrower 4.2% 20 years 5 years Electricité du Cambodge 6. 7. 8. 9. Disbursements a. Dates Initial Disbursement 10 March 2009 Effective Date 29 January 2008 Final Disbursement 10 March 2015 Original Closing Date 31 December 2010 Time Interval 72 months Time Interval 35 months ii b. Amount (SDR million) Category or Original Subloan Allocation Category Number 1 2 Civil Works-Substations Consulting Services for Project Implementation Environmental Management and Monitoring Improvement of EDC Data System Social, Resettlement and Environment Training Interest Charge Unallocated 3 4 5 6 7 Total (SDR) Total ($) C. Amount Disbursed Undisbursed a Balance 8.861 1.555 11.242 1.677 11.247 1.675 (0.005) 0.002 0.338 0 0 0 0.338 0.335 0.335 0 0.203 0.071 0.068 0.003 0.223 2.001 0.193 0 0.194 0 0 0 a 13.519 0 20.000 20.618 0 13.519 20.000 ( ) = negative. a Numbers may not sum precisely because of rounding. 10. Last Revised Allocation 13.519 Local costs (Financed) - Amount ($ million) - Percent of Local Costs - Percent of Total Cost 4.15 27.88% 6.27% Project Data 1. Project Cost ($ million) Cost Appraisal Estimate Foreign Exchange Cost Local Currency Cost Total 2. 31.27 20.76 52.03 Actual 50.55 14.88 65.43 Financing Plan ($ million) Cost Appraisal Estimate Implementation Costs Borrower Financed ADB Financed Other External Financing JICA Subtotal IDC Costs Borrower financed ADB Financed Other External Financing JICA Subtotal Total Actual 10.06 19.68 16.84 20.32 22.28 52.03 28.27 65.43 0.00 0.33 0.00 0.29 0.00 0.33 0.47 0.76 52.36 66.19 ADB = Asian Development Bank, IDC = interest during construction, JICA = Japan International Cooperation Agency. iii 3. Cost Breakdown by Project Component ($ million) Component 1 2 3 4 5 6 7 6 7 8 9 10 11 12 13 Appraisal Estimate 230 kV Line Bay, Kampot Substation 230 kV Line, Kampot to Sihanoukville (Stung Hav) 230 kV Substation, Veal Renh 230 kV Substation, Stung Hav MLV Distribution System 115 kV Substation, Sihanoukville and 115kV extension (Stung Hav) 115kV Line, Stung Hav to Sihanoukville Consulting Services Project Management and Monitoring Land Acquisition Strengthening of EDC Provincial Branches Improvement of EDC Information System EDC Training in High-Voltage Systems EDC Training in Social, Resettlement, and Environmental Management Interest During Construction 2.67 22.12 12.68 5.20 3.36 3.53 26.35 0 7.61 3.21 0 12.50 0 2.66 1.50 0.34 0.13 0.54 0.50 2.31 2.59 2.41 3.64 0.15 0.57 0.46 0.32 0.10 0.33 0.76 Total 52.36 EDC = Electricité du Cambodge, kV = kilovolt, MLV = medium and low voltage. 4. 66.19 Project Schedule Item Date of Contract with Consultants Completion of Engineering Designs Civil Works Contracts Date of Award (Transmission and Distribution Lines) Completion of Work (Transmission and Distribution Lines) Date of Award (Substations) Completion of Work (Substations) Dates First Procurement Last Procurement Completion of Equipment Installation Start of Operations Completion of Tests and Commissioning Beginning of start-up a Other Milestones a Actual Appraisal Estimate Actual March 2007 June 2007 December 2008 February 2009 June 2008 December 2009 February 2011 February 2014 June 2008 December 2009 30 December 2010 25 August 2014 July 2007 June 2009 December 2009 30 December 2010 3 May 2012 31 May 2014 September 2010 January 2010 25 August 2014 March 2013 The first extension of the loan closing date (from 30 December 2010 to 31 December 2013) was approved on 8 October 2010. The second extension of the loan closing date (from 31 December 2013 to 30 November 2014) was approved on 13 January 2014 (including reallocation of loan proceeds). iv 5. Project Performance Report Ratings a Ratings Development Objectives Implementation Period From From From From From From From From From From From From From From From From a January 2008 to June 2011 July–September 2011 October– December 2011 January–March 2012 April–June 2012 July-September 2012 October–December 2012 January–March 2013 April–June 2013 July–September 2013 October–December 2013 January–March 2014 April–June 2014 July–September 2014 October–December 2014 January–March 2015 Potential Problem Potential Problem Potential Problem Actual Problem Potential Problem On Track On Track On Track On Track On Track On Track On Track On Track On Track On Track On Track Implementation Progress Potential Problem Potential Problem Potential Problem Actual Problem Potential Problem On Track On Track On Track On Track On Track On Track On Track On Track On Track On Track On Track Effective 1 January 2011, the Lotus Notes-based Project Performance Reporting system was replaced with an Oracle-based eOperations Projects database. The new system does not rate development objectives and implementation progress separately, but provides overall project ratings such as “On Track”, “Potential Problem”, and “Actual Problem”. D. Data on Asian Development Bank Missions Name of Mission Fact-finding Consultation Appraisal Project inception Special review Review 1 Review 2 Review 3 Review 4 Midterm review Review 5 Special administration Review 6 Review 7 Review 8 Review 9 Review 10 Project completion review a Date 22 Nov–1 Dec 2005 6–9 Feb 2006 25–28 Apr 2006 28–30 Apr 2008 27 May–3 Jun 2008 8–10 Dec 2008 25–29 May 2009 8–12 Feb 2010 10–13 Aug 2010 14–16 Feb 2011 16–18 Aug 2011 3–10 July 2012 14–22 Nov 2012 2–10 May 2013 26 Sep–8 Oct 2013 19–26 Mar 2014 11–18 Nov 2014 12–13 Nov 2015 No. of Persons No. of Person-Days Specialization a of Members 4 2 5 3 4 4 4 5 4 5 3 5 6 3 3 3 3 3 40 8 20 9 32 12 20 25 16 15 9 20 18 12 9 9 9 12 c,d,g,h a,d a,b,d,g,h d,f,j d,f,j d,f,i,j a,d,g,i a,d,f,i d,f,g,i d,e,f,g,i d,i f,g,i,k f,g,I,k f,g,i f,j,i f,j,i f,j,i f,j,i a = financial analysis specialist, b = counsel, c = project economist, d = senior energy specialist, e = environment specialist, f = senior project officer, g = project analyst, h = senior social development specialist, i = social safeguard officer, j = operations officer, k = senior procurement officer. I. PROJECT DESCRIPTION 1. Until 2012, Cambodia’s power sector was fragmented, with only 10 of 24 provinces connected to the national grid and the remaining 14 operated as isolated power systems centered in various provincial cities. The lack of an integrated high-voltage transmission system, coupled with the high cost of imported diesel fuel, had made electricity in Cambodia among the costliest in the world1. The government recognizes that the high cost and inadequate supply of electricity significantly limits economic growth and poses a hindrance in attracting investment and stimulating economic activity. To address this issue, the Asian Development Bank (ADB), the Nordic Development Fund and the World Bank provided assistance to Cambodia in building 230-kilovolt (kV) backbone transmission lines2 in the southern part of the country, originating at a substation on the border with Viet Nam and passing through Takeo to Kampot in the south before heading north to Phnom Penh. These facilities have allowed Electricité du Cambodge (EDC), a state-owned utility, to import lower-cost electricity from Viet Nam to meet the power demand in Phnom Penh, Takeo, and Kampot.3 2. Sihanoukville is a fast-growing city with major developments to expand its port facilities, upgrade the existing airport, and set up a special economic zone, thus making it an import gateway to Cambodia’s southern economic corridor. Prior to the Second Power Transmission and Distribution Project,4 there were no power transmission facilities connecting Sihanoukville to the national grid; the city obtained its power from a small, isolated power system based on diesel generators. This mode of power generation is expensive and inefficient, and was incapable of meeting the rapidly growing demand for electricity in the city. The main objective of the project was therefore to complement previous investments in power transmission and distribution facilities, in particular the extension of the national grid from Kampot to Sihanoukville to meet growing demand and to provide distribution capacity for the proposed bulk electricity generating facilities in Sihanoukville and adjacent areas along the transmission corridor. 3. The project, which was appraised during 25–28 April 2006, had two major components: (i) infrastructure, and (ii) institutional strengthening and capacity building. The project comprised four outputs: (i) construction of a 230 kV transmission line from Kampot to Sihanoukville, (ii) construction of 230kV substations and expansion of an existing 230 kV substation, (iii) construction of a medium- and low-voltage distribution system, and (iv) capacity building programs to improve EDC’s performance. The project had a regional cooperation focus, with its outputs forming part of the transmission backbone between Cambodia and Viet Nam. The project has enabled EDC to provide the southern provinces with reliable and affordable electricity from the lowest-cost source of power. The project has also contributed to the economic development of the Greater Mekong Subregion (GMS) Southern Economic Corridor by providing basic economic infrastructure. The provision of firm and reliable supply of electricity to Sihanoukville has therefore replaced the low-efficiency and high-cost diesel generating plants. 1 Commercial and industrial users were charged $0.21/kWh, and residential users $0.10/kWh. In comparison, the average retail tariffs in the Lao People’s Democratic Republic, Thailand, and Viet Nam were around $0.04/kWh, $0.07/ kWh, and $0.06/ kWh, respectively. 2 ADB. 2003. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Kingdom of Cambodia for the Second Power Transmission and Distribution Project. Manila (Loan 2052-CAM). 3 The cost, which was originally as low as $0.05 per kilowatt-hour (kWh), is currently $0.09 per kWh. 4 ADB. 2006. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Kingdom of Cambodia for the Second Power Transmission and Distribution Project. Manila (Loan 2261-CAM). 2 II. A. EVALUATION OF DESIGN AND IMPLEMENTATION Relevance of Design and Formulation 4. The project was formulated to address the power sector issues identified during appraisal while meeting the government’s development objectives. In its National Strategic Development Plan, 2006–2010, the government recognized the importance of developing the energy sector and electricity network to promote socioeconomic development and reduce poverty.5 One of the most important aspects of the government’s economic policy as outlined in the development plan was developing the energy sector to respond effectively to the increasing needs for low-cost electricity. Energy sector development remains an important component of the Rectangular Strategy for Growth, Employment, Equity and Efficiency: Phase III, 2013–2018, the government’s current development strategy. 6 In particular, the government prioritizes increasing electricity supply capacity, reducing tariffs to an appropriate level, and expanding the national grid electricity infrastructure into rural areas while strengthening institutional mechanisms and management capability. The government’s power sector development strategy aims to provide adequate, reliable, and stable power supply at affordable prices throughout the country, and it sets two goals for rural electrification: (i) all villages have access to electricity of some type by 2020, and (ii) at least 70% of all households have access to grid-quality electricity by 2030.7 5. At the time of appraisal, the project was in line with ADB’s country strategy and program for Cambodia, 2005–2009, which indicated that adequate supply of reliable and affordable power is a prerequisite for private sector-led economic growth.8 ADB assistance during 2005– 2009 focused on expanding power generation and transmission and distribution systems as well as improving sector performance and operational efficiency through institutional strengthening and capacity building. The project was included in ADB’s lending pipeline for 2006. The country partnership strategy, 2014–2018 supports the government’s economic reform priorities and embeds Strategy 2020’s three strategic agendas of inclusive economic growth, environmentally sustainable growth, and regional integration into ADB operations in Cambodia.9 6. ADB approved a project preparatory technical assistance in 2003 to assist the government in preparing a feasibility study for the expansion of Cambodia’s power transmission network in the southern part of the country, including constructing a new 230 kV transmission line linking Cambodia and Viet Nam to allow Cambodia to import reliable low-cost power.10 The first component of this technical assistance entailed a feasibility study of the GMS Transmission Project,11 and the second component was a feasibility study of the Second Power Transmission and Distribution Project. 12 The technical assistance was rated satisfactory. In 2010, the 5 Government of Cambodia, Ministry of Planning. 2005. National Strategic Development Plan, 2006–2010. Phnom Penh. 6 Government of Cambodia, Ministry of Planning. 2013. Rectangular Strategy for Growth, Employment, Equity and Efficiency: Phase III, 2013–2018. Phnom Penh. 7 Government of Cambodia. 2011. Strategy and Plan for Development of Rural Electrification in the Kingdom of Cambodia. Phnom Penh. 8 ADB. 2005. Country Strategy and Program: Cambodia, 2005–2009. Manila. 9 ADB. 2014. Country Partnership Strategy: Cambodia, 2014–2018. Manila; ADB. 2008. Strategy 2020: The LongTerm Strategic Framework of the Asian Development Bank, 2008–2020. Manila. 10 ADB. 2003. Technical Assistance to Cambodia for Preparing the Power Distribution and Greater Mekong Subregion Transmission Project. Manila (TA 4078-CAM). 11 ADB. 2003. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Kingdom of Cambodia for the Greater Mekong Subregion Transmission Project. Manila (Loan 2052-CAM). 12 ADB. 2006. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Kingdom of Cambodia for the Second Power Transmission and Distribution Project. Manila (Loan 2261-CAM). 3 electrical load in Sihanoukville was growing fast due to several economic development projects such as an industrial zone, a special economic zone, and increased activities related to the expansion of Sihanoukville port. A feasibility study conducted in 2010 by EDC found that a voltage level of 115 kV was more economical than 22 kV for bulk supply to Sihanoukville to meet power demand; ADB subsequently approved a change in scope to the project to reflect this. B. Project Outputs Transmission line. At appraisal, it was envisaged that the Japan International 7. Cooperation Agency (JICA) would finance the 88-kilometer (km), 230 kV double-circuit transmission line from Kampot to the proposed 230 kV substations at Veal Renh and Sihanoukville (Stung Hav commune). Two changes were made to this transmission line subsequent to appraisal: (i) the proposed 230 kV Veal Renh substation was dropped, as forecasted demand growth in Veal Renh area did not warrant construction of 230 kV of capacity; and (ii) the transmission line route was modified in some locations due to difficulties in acquiring the necessary land. As built, the total length of the 230 kV transmission line is about 82 km. 8. At appraisal, it was assumed that 22 kV distribution lines would be constructed from the proposed 230 kV Stung Hav substation to Sihanoukville city and beyond. Subsequent analysis by EDC indicated that forecasted demand growth in and around the city and the port supported construction of a 115 kV substation close to the center of demand growth. A feasibility study was commissioned in 2010 under the loan (conducted by the project implementation consultants), and a decision was made to use 115 kV as a sub-transmission voltage level at a new substation in Sihanoukville. JICA agreed to finance the 12 km double-circuit 115 kV line from the Stung Hav 230 kV substation to this new 115 kV substation. 9. Substations. At appraisal, it was planned to (i) extend the Kampot 230 kV substation (by adding two 230 kV line bays to cater for the new transmission line to Sihanoukville), (ii) construct a new 230 kV substation at Veal Renh, and (iii) construct a new 230 kV substation at Stung Hav. However, as earlier mentioned, two modifications were subsequently made to this investment program: (i) the proposed Veal Renh substation was dropped (para. 7); and (ii) the revised projection of demand growth in Sihanoukville supported the introduction of 115 kV as a sub-transmission voltage, with the concomitant requirement to build a 115 kV substation close to the load center in Sihanoukville (para. 8). 10. Medium-voltage distribution system. At appraisal, only broad conceptual designs for medium- and low-voltage distribution systems were prepared. At that time, it was envisaged that all areas along the corridor of the 230 kV transmission line would be supplied at 22 kV and that connections would be made to the existing 22 kV networks in the area. Approximately 40 km of 22 kV transmission lines were constructed under the contract. EDC used its own funds to connect all people living along the transmission line route to the grid. 11. Consultants. Consulting services covered detailed design; implementation supervision costs; project management and monitoring, land acquisition, resettlement, environmental mitigation, monitoring, training for EDC staff in environmental management, and resettlement implementation. 12. Capacity building programs. Four distinct capacity building programs were included at appraisal: (i) strengthening of EDC’s provisional operational capability (primarily to improve the technical skill base so that more autonomy from EDC’s head office would be possible); (ii) 4 training in maintenance and operation of high-voltage transmission systems; (iii) improvement in EDC’s data management system through the procurement of hardware and software to establish a consolidated data platform, including reliable backup systems and improved communication systems between headquarters and branches; and (iv) training of EDC staff in the management of social, resettlement, and environmental issues by financing higher-level education for two social and environmental specialists from existing EDC staff. 13. These four capacity building programs were all delivered. Staff members at EDC’s Kampot and Sihanoukville branches attended routine training programs on operation and maintenance at EDC’s training center as part of its annual cycle of professional development. Two EDC staff members completed master’s degrees in social and environmental fields at the Asian Institute of Technology in Thailand. JICA loan financed training programs in operations and maintenance of high-voltage systems for about 70 EDC staff. A consolidated data platform including reliable backup systems was established to improve communication systems between EDC headquarters and branches. C. Project Costs 14. At appraisal, the project was estimated to cost $52.36 million. Foreign exchange cost accounted for $31.59 million (approximately 60% of the estimated total), including $0.33 million for interest during construction. Local currency cost was estimated at $20.77 million (40% of the estimated cost). ADB was to provide a loan for the equivalent of $20.0 million from its Special Funds resources to finance 38% of the project cost. A loan from the Japan Bank for International Cooperation (JBIC), which was called Japan International Cooperation Agency (JICA) loan after JBIC and JICA merged to form JICA, was planned to cofinance the equivalent of $22.3 million (43% of the project cost). The government and EDC were to fund the balance of $10.06 million of domestic currency costs (representing 19% of total project costs). 15. At project completion, the project cost totaled $66.2 million, of which ADB financed $20.6 million (31%), JICA $28.8 million (43%), and EDC and the government the balance of $16.8 million (26%). The government’s contribution was for taxes and duties, and EDC funded land acquisition. The major differences between appraisal cost estimates and actual costs were (i) the dropping of the Veal Renh 230 kV substation (with an estimated cost at appraisal of $12.7 million); (ii) the addition of a 115 kV sub-transmission in Sihanoukville (with an actual additional cost of approximately $14.9 million, including the substation and line works); and (iii) a significant increase in land acquisition costs ($3.3 million), which was due to the high land cost for the new 115 kV substation in Sihanoukville city. 16. Comparisons of contract costs at appraisal versus actual costs were made difficult due to significant variations that were made to the scope of work. For example, at appraisal it was envisaged that separate turnkey contracts would be awarded for the 230 kV lines and for the 22 kV and 0.4 kV lines. Appraisal cost estimates also considered that the 230 kV line would loop into and out of the substation to be constructed at Veal Renh, but this substation was dropped (after appraisal but prior to a contract being signed for the 230 kV lines). A single contract was ultimately awarded to cover both the 230 kV lines and 22 kV lines. When the decision was made to introduce 115 kV as a sub-transmission voltage in Sihanoukville, construction of a 12 km, 115 kV line was added to the contractor’s scope of work. The total cost of line construction for the 230 kV, 115 kV, and 22 kV transmission lines was $31.9 million, against $25.5 million estimated at appraisal. However, it can be estimated that implementation delays increased the cost of the transmission and distribution lines by approximately $4 million, and of the 230 kV substation by approximately $3 million. 5 D. Disbursements Loan proceeds were disbursed in accordance with ADB’s Loan Disbursement Handbook 17. (2015, as amended from time to time). However, loan proceeds were disbursed more slowly than envisaged at appraisal, when it had been assumed that disbursements would be completed in 2010.13 In practice, due to delays brought about by delayed loan effectiveness, late recruitment of project implementation consultants, and delayed engagement of main contractors and execution of works, no disbursement was made until March 2009, and none until 2011 for civil works. An imprest fund was not used. ADB canceled the loan balance of SDR0.33 on the closing date of 10 March 2015, reducing the size of the loan to SDR13,518,999.67. E. Project Schedule 18. The ADB loan was approved by the Board on 4 October 2006. The loan agreement was signed on 1 December 2006. However, the loan did not become effective until 29 January 2008 after two extensions (a 13-month delay from the original schedule) due to noncompliance with two conditions of loan effectiveness (para. 23). Based on reasonable progress toward achieving these conditions, the Board approved on a no-objection basis the request for waiver of these loan effectiveness conditions on 14 January 2008. The original loan closing date of 31 December 2010 was also extended two times, finally closing on 30 November 2014. 19. At appraisal, the project was estimated to be implemented over 4 years from the date of loan effectiveness (which was expected to be the first quarter of 2007). Advance recruitment of project implementation consultants was anticipated in the schedule, which planned for the consultants to be ready to commence preparation of detailed designs and bidding documents by the start of the second quarter of 2007. Procurement was expected to commence in mid-2007, with construction starting in the second quarter of 2008 and concluding at the end of 2009. Testing and commissioning was scheduled for the first half of 2010, with all project assets in service by the middle of that year. 20. The actual project schedule differed materially. Advance action for procurement and recruitment of consultants was not implemented to the extent envisaged at appraisal; project implementation consultant proposals were not submitted to ADB until December 2007, and the technical evaluation report was not submitted until June 2008. A contract was finally signed with the project implementation consultants in December 2008, 21 months later than anticipated at appraisal. Procurement of turnkey contracts was also delayed by the need to acquire additional supporting documents on bidders’ qualifications and experiences, as well as the processing of numerous representations from bidders.14 The completion of construction of transmission lines was delayed due to the additional works related to the 115 kV line, and the construction of substations was delayed by slow land acquisition for the 115 kV substation at Sihanoukville. F. Implementation Arrangements 21. As envisaged at appraisal, the project was implemented by EDC, the project’s executing agency. Project management capacity and permanent institutional arrangements established 13 14 The projected and actual disbursements are shown in Appendix 4. The contract award for the transmission and distribution lines took 30 months, and the contract award for substations took 30 months. 6 during the GMS Transmission Project loan (footnote 10) were adopted and worked well. The director of EDC’s Corporate Planning and Projects Department headed EDC’s two permanent project management offices. The first project management office undertook daily project management activities with the support of the project implementation consultants, while the second managed other projects financed by bilateral development partners. The first project management office, which was headed by a senior engineer and supported by a number of experienced engineers and construction site supervisors, was responsible for coordinating implementation activities with relevant departments and offices within EDC. EDC’s Social, Environment and Public Relations Office was responsible for implementing environmental and social safeguards aspects. Financial management arrangements were implemented as planned, and the minor change in project scope did not cause any change in implementation arrangements. G. Conditions and Covenants In addition to the usual loan effectiveness conditions,15 there were two other conditions: 22. (i) the government should allocate additional funds from the budget to the Ministry of Economy and Finance (MEF) to enable it to offset the past-due input value-added tax (VAT) owed by EDC to the government’s Customs and Tax Department; and (ii) the government should allocate additional funds from the budget to the MEF to offset accounts receivable from government institutions and agencies, and local authorities. The MEF confirmed that these two budget items would be submitted by the government to the National Assembly in early 2008. Based on this rationale, the Board approved on a no-objection basis the request for waiver of loan effectiveness conditions on 14 January 2008. 23. Major loan covenants were generally complied with, and the following key financial covenants were complied with: (i) minimum debt service coverage ratio, (ii) debt–equity ratio, (iii) revenue breakeven, and (iv) accounts receivable. Submission of the (i) audited financial statements for the project account, (ii) auditor’s opinion on compliance with financial covenants, (iii) management letter, and (iv) audited financial statements for EDC operations was also complied with. However, one financial covenant (offset of the input VAT owed by EDC to the government) and one sector covenant (annual submission of power development plans) were only partially complied with. The MEF had offset all past-due input VAT owed by EDC to the government against EDC’s liability on VAT, but EDC was unable to pass on the newly imposed VAT to its customers. However, this partial compliance did not affect EDC’s financial performance. Similarly, the partial compliance with a sector covenant did not affect power sector planning, as EDC submitted power development plans when updates were required, although not annually. For consistency with financial loan covenants as required in the loan and project agreements for the other two ongoing projects,16 the MEF, EDC, and ADB agreed to amend several financial covenants in the loan and project agreements for the Second Power Transmission and Distribution Project loan.17 The amendments, which were effective from 26 November 2014, did not affect EDC’s financial performance until the project completion date. Details of compliance with the key loan covenants are in Appendix 7. 15 Conditions covering the cofinancing arrangement, subsidiary loan agreement, and legal opinions. ADB. 2012. Report and Recommendation of the President to the Board of Directors: Proposed Loan to the Kingdom of Cambodia for the Medium-Voltage Sub-Transmission Expansion Sector Project. Manila (Loan 2979CAM); ADB. 2013. Report and Recommendation of the President to the Board of Directors: Proposed Administration of Grant to the Kingdom of Cambodia: Rural Energy Project. Manila (Grant 0336-CAM). 17 These financial covenants includes those related to EDC’s net revenues, EDC’s funds from internal sources, EDC’s debt–equity ratio, and EDC’s accounts receivable. 16 7 H. Consultant Recruitment and Procurement 1. Consultant Recruitment 24. Project implementation consultants were financed under the ADB loan and were recruited in accordance with ADB’s Guidelines on the Use of Consultants (2013, as amended from time to time) to assist EDC with the engineering design, procurement, construction supervision, final testing, and commissioning of the works. The quality- and cost-based selection method with full technical proposal was used and found to be appropriate for this consulting services contract. At appraisal, the consultants were expected to be fielded by March 2007. Although advance procurement action was approved by ADB, the contract was not signed with a consultant until December 2008. This was mainly due to a delay in submission of an evaluation report to ADB, which had resulted from the executing agency’s unfamiliarity with ADB’s consultant recruitment procedures and the process of preparing an evaluation report. At appraisal, approximately 40 person-months of international and 45 person-months of national consultant inputs were envisaged. Actual project implementation consultant inputs totaled 69 person-months of international and 64 person-months of domestic consultant inputs. The increase in project implementation consultants’ inputs was mainly due to additional design works and implementation delays. 2. Procurement 25. The procurement of goods and services under the ADB-funded project components was carried out in accordance with ADB’s Procurement Guidelines (2015, as amended from time to time), while procurement of goods and services under the JICA-funded components was carried out in accordance with JICA’s own procurement procedures. At appraisal, procurement of works under the ADB-funded project components was planned to be covered by a single turnkey contract for new 230 kV substations at Veal Renh and Stung Hav and extension of the existing 230 kV Kampot substation. As requested by EDC, the Veal Renh substation was dropped during the preliminary design stage and was not included in the turnkey contract. ADB loan proceeds were also used to procure hardware and software for EDC’s data management system. 26. Turnkey contract for ADB-funded 230-kilovolt substations. Preparation of bidding documents started later than expected at appraisal as a consequence of delayed recruitment of the implementation consultants. The pre-bid meeting was held for this contract in late November 2009, and the deadline for submission of bids was set for 9 February 2009 (after one extension). While 10 bids were received, four bidders failed to submit the proper bid security and had their bids rejected. Only six technical bids were therefore opened. Bid evaluation for this turnkey contract package was time-consuming due to a need to seek bidders’ clarifications and additional supporting documents on bidders’ qualifications and experience, resulting in only one bid being deemed responsive. The financial proposal for the only responsive bid was opened on 22 October 2010, and a contract was awarded on 30 December 2010, 30 months later than the time envisaged at appraisal. 27. Turnkey contract for Japan International Cooperation Agency-funded 230-kilovolt transmission line and 22-kilovolt distribution lines (later amended to include 115-kilovolt transmission line). The bidding process for this package also started late due to the late engagement of the implementation consultants. A pre-bid meeting was held in January 2010 and was attended by 13 firms, of which 12 firms submitted bids. The bid evaluation committee ultimately deemed that only two bids were substantially responsive, and the financial proposals 8 of the two responsive bidders were opened. A letter of acceptance was issued to the selected bidder on 11 February 2011 and a contract was signed soon thereafter, some 32 months later than envisaged at appraisal. 28. The need to provide 115 kV transmission facilities into Sihanoukville from Stung Hav substation was discussed and agreed with ADB in August 2011. The preference to contract directly with the contractor for the 230 kV transmission and distribution lines was also agreed, and the contractor was requested to submit a price proposal in December 2011. The contractor’s price was accepted and a contract amendment to cover 115 kV line works was signed on 4 June 2012. 29. Turkey contract for ADB-funded 115-kilovolt substations. The addition of 115 kV facilities was agreed with ADB in August 2011 (para. 29). Funds previously earmarked for the canceled Veal Renh 230 kV substation were made available for a new 115 kV substation in Sihanoukville and for a 115 kV extension at the Stung Hav 230 kV substation. A pre-bid meeting was held on 15 November 2011 and bids were received and opened on 16 December 2011. Six bids were received, but ultimately only two bids were deemed substantially responsive. A bid evaluation report was submitted to ADB on 13 March 2012 and a contract was signed with the successful bidder on 3 May 2012. 30. Electricité du Cambodge’s data management system. A contract for the delivery and installment of EDC’s data management system was signed on 21 March 2012. Due to the delay in the construction of EDC's branch in the Russey Keo district—the location for data recovery as defined in the contract—installment of the equipment was also delayed and only completed in March 2014. I. Performance of Consultants, Contractors, and Suppliers Consultants. Consulting services covered engineering design, preparation and 31. evaluation of bidding documents, supervision of project implementation, and technical support and training of EDC staff. The project implementation consultants followed their terms of reference and provided all staff inputs as required in their contract. EDC used the services of the consultants judiciously (particularly for works supervision, which EDC felt that it had the capacity and competency to handle), which reserved consultants’ resources for tasks that required expertise outside of EDC’s skill set. EDC was satisfied with the consultants’ performance. 32. Contractors. JICA-funded transmission and distribution lines constructed under the project were in service by April 2013 (230 kV and 22 kV) and August 2014 (115 kV). EDC and the implementation consultants considered the contractors’ work and performance to be good. The major delay in contract implementation was caused by the need to alter the 230 kV line route, a process that added almost 12 months to the implementation time frame but was outside of the contractor’s control. The delays in paying compensation to the affected persons also caused delays in construction of the transmission and distribution lines. The transmission and bulk distribution lines are of an acceptable quality and meet the technical specifications. Overall, the performance of the contractors was rated satisfactory. 33. The overall performance of both the 230 kV substation contractor and the 115 kV contractor was also rated satisfactory. EDC noted good cooperation and responsiveness from both contractors, and no major design issues were encountered. Again, delays were largely outside of the contractors’ control; in the case of the 115 kV Sihanoukville substation, the need 9 to change the location after the original site proved to have poor soil conditions delayed the start of construction by more than 6 months while the new site was acquired. Otherwise, work programs were generally on schedule and issues were resolved in a timely manner with adequate resourcing from both contractors. 34. Suppliers. Supply and installation of a data recovery system was straightforward and was rated satisfactory. J. Performance of the Borrower and the Executing Agency 35. EDC successfully implemented the project with support and advisory services from the implementation consultants. EDC acted as both employer and as project manager of the three main turnkey contracts and mobilized its own engineers to monitor work progress at the project sites on a daily basis. Project implementation consultants’ inputs were used only when critical engineering supervising works were required. This highlighted a marked increase in EDC’s confidence to supervise construction works, which is a positive indicator of EDC’s improved technical capacity compared to EDC’s works on previous ADB-financed projects. Government and EDC counterpart funds were made available on a timely basis and resettlement activities were carried out in accordance with the resettlement plan. The performance of the borrower and executing agency is rated satisfactory. K. Performance of the Asian Development Bank 36. The project was originally administered from ADB headquarters, but administration was transferred to the Cambodia Resident Mission in April 2012 to allow for closer monitoring and timely follow-up actions and necessary assistance. ADB had four project officers involved during project implementation and conducted 13 review missions and special loan administration missions. The missions included site visits and meetings in Phnom Penh, Kampot, and Sihanoukville with project stakeholders. The government and EDC recognized the positive role that the ADB missions played in providing (i) advice on technical issues; (ii) assistance with the preparation and evaluation of bid documents; and (iii) close monitoring by ADB, including participation in a number of monthly progress meetings after the project administration was delegated to the resident mission. Overall, the performance of ADB is rated satisfactory. III. A. EVALUATION OF PERFORMANCE Relevance As appraised, the project was consistent with the government’s development goals for 37. the energy sector, in particular the desire to (i) provide access to electricity to all villages by 2020, and (ii) provide at least 70% of all households with access to grid-quality electricity by 2030. As Cambodia’s only deepwater port, Sihanoukville is significant to the country’s economy, and provision of high-voltage transmission capacity to the city should catalyze further investment and economic growth in Sihanoukville. Demand for electricity in the city has already increased sharply over the last ten years, even though a few large electricity consumers still choose to generate their own power rather than take supply from EDC. Once EDC demonstrates that it is able to continue to provide high-quality and secure supply to the city, there will likely be further rapid growth in electricity demand. 38. The primary function of the transmission facilities built under the project is now materially different to that envisaged at appraisal. Instead of delivering grid electricity to Sihanoukville, 10 which was the main project rationale articulated at appraisal, the 230 kV transmission line and substation are now mainly used to export coal-fired electricity to Phnom Penh via Kampot. Arguably, this is even more relevant to the government’s development goals for the energy sector, particularly the desire to provide an adequate supply of energy throughout the country. To date, 360 megawatts of privately owned base-load plant have been commissioned in Sihanoukville, representing around 20% of the country’s available generating capacity. Almost 500 megawatts are expected to be in service by the end of 2017. This capacity will underpin EDC’s and the government’s plans for grid expansion. It will also allow the country to reduce its dependence on importation of electricity from Viet Nam during the dry season and to replace old and inefficient diesel and fuel-oil plants. The project is therefore rated relevant. B. Effectiveness in Achieving Outcome 39. The project substantially achieved the outcome18 envisaged at appraisal. However, the performance indicators for the project’s outcome and purpose set low performance targets. The first outcome indicator was that there would be an increase in 230 kV transmission lines, substations, and distribution facilities in Sihanoukville. However, this outcome indicator lacked a quantitative baseline and the desired increase was not realized, making a meaningful and objective assessment impossible. The second outcome indicator was that there would be a 125% increase in EDC’s energy sales in the project area from project appraisal (2006) to project completion (2010). The project was not completed until 2014, by which time EDC’s annual electricity sales were 600% higher than in 2006. Assessing this performance on the basis of annual demand growth indicates that the target was easily surpassed. The third outcome indicator referred to the number of customer connections, but no baseline was provided and the target was rather ambiguous, with reference only given to the number of customers served by the “power grid.” The fourth indicator referred to EDC’s performance against covenanted financial ratios and against a distribution loss cap of 16%. However, because the financial ratios and distribution losses relate to EDC as a whole, there is no apparent link between the outcome and the fourth outcome indicator. Therefore, even though the performance targets were met, no inference of project effectiveness can be drawn. 40. Given that the desired outcome was strengthening of the power grid and distribution facilities and improved operational efficiency, peak demand served and a measure of network reliability performance for Sihanoukville would have provided more meaningful performance targets. In light of the substantially different primary function of the transmission facilities than that identified at appraisal (para. 39), indicators related to transmission capacity, availability, stability, and losses are more relevant to effectiveness of the new transmission assets. The project are effectively delivering desired outcome by increasing the energy consumption in Sihanoukville from 20 GWh in 2005 to 141 GWh in 2014. Since 2009, there has been continuous improvement in all of EDC’s operational and financial performance indicators. Currently, EDC readily exceeds the requirements of the financial covenants and distribution loss is kept at less than 16%. EDC’s ongoing training program has continually improved the mediumand low-voltage operation and maintenance capacity of branch staff. The project is therefore rated effective. 18 The national backbone 230 kV power grid and associated distribution facilities in the southern region are expanded and strengthened, and EDC’s operation efficiency and performance are improved. 11 C. Efficiency in Achieving Outcome and Outputs 41. The project was assessed as providing adequate financial returns to EDC, with a financial internal rate of return (FIRR) of 13.2% at appraisal. The change in primary function of the transmission assets constructed by the project, from importation of electricity to Sihanoukville to export of electricity to Phnom Penh, has materially increased the project’s returns. At appraisal, the project’s financial benefits were taken to be an increase in electricity sales due to load growth in Sihanoukville and savings due to electricity loss reduction in the project area. However, the commissioning of new base-load generation in Sihanoukville has meant that the new transmission facilities have enabled EDC to increase electricity sales in Phnom Penh in addition to increasing sales in Sihanoukville. On this basis, the project’s FIRR at project completion is estimated to be 25.9%, which is well above the project’s weighted average cost of capital (estimated at appraisal to be 4.3%). 42. At appraisal, an investment time-slice approach was used to estimate the economic return for the project, with an assumption that a small-scale diesel plant would be constructed in Sihanoukville to meet demand in the “without project” case. This approach is invalid for two reasons: (i) the development of base-load generation in Sihanoukville appears not to have been considered, even though this is identified as likely in the power sector assessment that was prepared during appraisal; and (ii) the use of an alternative “next best” scenario in the “without project” case means that an equalizing discount rate rather than an internal rate of return was calculated. Therefore, the project’s economic performance has been reevaluated using a simplified approach and recognizing the following benefits: (i) displacement of electricity importation from Viet Nam (a resource cost saving), (ii) displacement of output from inefficient diesel and heavy fuel oil generating stations in Sihanoukville and Phnom Penh and a fuel oil plant in Phnom Penh (a resource cost saving), and (iii) induced consumption from newly connected and existing customers in Phnom Penh and Sihanoukville (incremental output). A high economic internal rate of return (EIRR) of 61% has been estimated, because connecting Sihanoukville to the national grid allows for the dispatch of relatively cheap base-load coal-fired electricity to the Phnom Penh load center. 43. The project’s FIRR and EIRR are substantially higher than hurdle rates, and the project had achieved its outcome and outputs. This is despite actual capital costs being 26% higher than estimated at appraisal (an increase partially attributable to a change in project scope and partially attributable to a material increase in land acquisition costs). Appendix 8 provides details of the methodology and assumptions underlying the FIRR and EIRR calculations. The project is therefore rated efficient. D. Preliminary Assessment of Sustainability 44. At the asset level, during and after the project, EDC’s ability to maintain its transmission and distribution assets and to operate them efficiently has improved significantly, and many new head office and regional staff have gained invaluable experience in this area. The construction of three base-load power stations in Sihanoukville means that the transmission facilities have a somewhat diversified customer base. Rapid demand growth in Sihanoukville over the last ten years, far outstripping demand forecasts prepared at appraisal, indicates that the transmission and distribution capacity provided will be fully utilized. 45. At the system level, the project forms an important network link that materially improves system stability and operational flexibility. EDC’s financial performance and position are relatively strong, and the increase in profitable electricity sales enabled by the project is 12 expected to provide further improvements. At the country level, the connection of the new baseload generation in Sihanoukville has relieved Cambodia’s dependence of electricity imports from Viet Nam, particularly during the dry season. Although the primary fuel for the new generation (coal) is imported, a degree of increased energy independence has been achieved as a consequence of the new transmission capacity. The import of electricity from Viet Nam is expected to continue to be required, particularly during the dry season, when the output from Cambodia’s run-of-river hydropower stations is reduced. At a regional level, ongoing transmission projects will further strengthen the national grid across the country, thereby enhancing prospects for meaningful GMS power trade and further underpinning the sustainability of the project. EDC staff members who received training under this project have contributed to enhancing EDC’s operations and maintenance capabilities. The ongoing MediumVoltage Sub-Transmission Expansion Sector Project (footnote 15) will support the operational integration of the Department of Rural Electrification Fund, which was established in 2012, and strengthen the institutional capacity of EDC’s provincial branches. The project is rated likely sustainable. E. Impact 46. The project impacts identified at appraisal were (i) extension of the national power grid; (ii) provision of reliable, adequate, and affordable electricity; and (iii) improvement in quality of power supply in the southern region. The indicators for these impacts were (i) an increase in the household electrification ratio from 17% in 2005 to 30% in 2010, (ii) a decrease in the average tariff in the Sihanoukville from $0.13/kWh–$0.20/kWh in 2005 to $0.08/kWh by 2010; and (iii) all towns and villages along the transmission line have access to electricity from the national power grid. The first indicator was achieved by 2010 even though the project was not completed until 2014, suggesting that this was not a suitable indicator for the project’s impact. The second indicator has not been and is very unlikely to be achieved; the basis for such a low tariff expectation was not provided at appraisal and appears to reflect an aspirational tariff target rather than one reflective of costs of supply and the need to provide for EDC’s ongoing financial viability. The third indicator has been achieved, but given that provision of medium- and lowvoltage circuits along the transmission line route was part of the project design, this appears to be a poor choice as an indicator of the project’s impact. 47. The impacts identified at appraisal have been achieved. Connection to the national grid has meant that consumers in and around Sihanoukville now have access to electricity procured and dispatched on a least-cost basis, resulting in a significant decline in end-use tariffs by as much as $0.05/kWh. Supply is more reliable and of a higher quality as well, benefiting from grid generation reserves and abundant transmission capacity. Confidence in EDC’s ability to maintain supply is expected to encourage a number of large commercial and industrial electricity consumers to cease self-generating and instead connect to EDC’s network, which will enhance EDC’s revenues to the ultimate benefit of all customers. Operational efficiency has increased across EDC’s network as a consequence of the new base-load generation in Sihanoukville, and the cost of supply in Sihanoukville has decreased significantly now that inefficient diesel generators have been taken out of service. 48. The project was classified as category B for environmental impacts. ADB’s Environment Policy (2002) was applied and an adequate summary initial environmental examination was disclosed at the time of approval. The initial environmental assessment noted that special attention was given to the assessment of the project alignment, which was expected to traverse the buffer zone of Bokor National Park. Detailed planning of the 230 kV route along the narrow coastal strip between the steep mountain slopes in Bokor National Park and the Gulf of Thailand 13 resulted in the selection of a low-impact transmission line route with minimal biophysical and social impacts, despite a 20.3 km section crossing the edge of the Bokor National Park buffer zone. The route through the national park was selected over alternatives across the coastal plain because it would (i) create the least visual impact, (ii) cross fewer tidal areas, (iii) involve the resettlement of the fewest households, and (iv) provide greater line reliability due to lower salt pollution of the line. To minimize adverse environmental impacts, the transmission line route was actually constructed to traverse across orchard land and paddy fields, instead of traversing across the degraded and regrowth forest in the park buffer zone as planned at appraisal. Visual impact was minimized by locating the route close to the change of slope at the rear of the coastal plains and by avoiding ridgelines whenever possible. 49. Although the transmission line route was selected to minimize resettlement impacts, 445 households were affected along the route, with 12 requiring resettlement. A comprehensive resettlement plan that fulfilled government requirements to finalize resettlement and compensation arrangements prior to project implementation was prepared and updated during project implementation when detailed design was completed. EDC’s ongoing recognition of and commitment to its resettlement activities under this and other projects are reflected in the strengthening of its internal resources to manage the process. A total of 887,000 square meters of land was acquired for the project, and approximately 1,658 square meters of structures and around 53,000 trees were affected. All affected persons were compensated according to the entitlements provided for in the resettlement plan, and adequate consultations took place during preparation of the resettlement plan and throughout implementation. The resettlement and compensation process was independently monitored by an external monitoring agency. There were some complaints raised during implementation of the resettlement plan as reported by the external monitoring agency, but the complaints were satisfactorily addressed in accordance with the grievance redress mechanism. The resettlement cost increased sharply mainly because EDC used its counterpart budget to purchase land for the 115 kV substation in Sihanoukville since the government land originally reserved for this substation was not technically suitable. The project did not affect any indigenous peoples or ethnic minorities. IV. A. OVERALL ASSESSMENT AND RECOMMENDATIONS Overall Assessment 50. The project was generally implemented in accordance with arrangements identified during appraisal and, with the exception of initial implementation delays, has generally performed beyond expectations identified at appraisal. Visits to project sites during the project completion review noted that the project facilities are of high quality, are being well maintained, and are functioning without interruption. The adequacy of project design, implementation arrangements, and the performance of the borrower and ADB were also assessed and discussed with EDC, the MEF, the Ministry of Mines and Energy, the Electricity Authority of Cambodia, and JICA. The addition of a 115 kV transmission line and substation late in project implementation was a minor change in scope, yet the project’s design was sufficiently flexible to accommodate this change. 51. Although forming only one link in Cambodia’s national grid, the impact of the project on the country’s economy is expected to be very significant. Provision of a reliable and cheaper electricity supply in Sihanoukville stands to catalyze much needed investment in Sihanoukville, including the special economic zone. The city has great importance as the country’s only deepwater port, and further development of the port is very likely now that the prerequisite reliable power supply is in place. The extent to which electricity sales have already increased in 14 Sihanoukville provides an indication of the suppressed demand for electricity in the city, and demand growth rates will possibly further accelerate as EDC demonstrates that the improved electricity supply is permanent. In Phnom Penh, the project’s impact is also evident in the sharp increase in electricity sales seen subsequent to the project’s commissioning in 2014. Given that this demand was either not being met or was being met from expensive alternative fuel sources, the economic impact of this increase in electricity consumption is significant, with the estimated EIRR providing evidence of this economic impact (para. 42). Based on the review of its relevance, effectiveness, efficiency, and sustainability, the project is rated successful. B. Lessons 52. There were implementation delays during the initial period of the project, especially in achieving loan effectiveness, recruiting implementation consultants, and awarding contracts. These delays occurred even though advance procurement action had been approved. To minimize delays in achieving loan effectiveness, it is recommended that the practicalities of achieving all proposed loan effectiveness conditions are reviewed and discussed with the borrower and the executing agency during appraisal. To address start-up issues, ADB should assist the executing agency with the implementation of project start-up tasks such as consultant recruitment and the preparation of comprehensive feasibility studies and detailed engineering designs. 53. The delegation of project administration responsibilities to the resident mission during the project helped facilitate close working relationships between ADB staff and key government and EDC officials. The experience EDC gained from this project and the relationships that have developed between the resident mission and government counterparts should greatly benefit any future project. C. Recommendations 1. Project Related 54. Context of investment. There was an apparent disconnect between the sector assessment undertaken during appraisal, which identifies the likely development of base-load generation in Sihanoukville, and the project rationale and design (and in the appraisal documents), which do not reflect this (para. 42). It is recommended that for future electricity transmission investments, the short- and long-term planning contexts of the project are fully articulated, and realistic alternatives to the project are explored. 55. Project financial reports. The audited project accounts that are part of the financial reporting requirements disclose sources of funds (ADB, JICA, and counterpart) and expenditures by disbursement category (civil works, consultants, etc.). The project accounts are prepared in US dollars, but they do not account for such relevant MEF transactions as interest charges and debt service. They also do not include information on cofunded project expenditures. Rather, the expenditure details mirror ADB’s own internal disbursement record rather than detailing investments made by asset or type of asset. This complicates calculation of actual expenditures on a component-by-component basis. It is recommended that EDC detail all project transactions and reconcile them against the asset values in local currency in EDC’s asset register. This would provide ADB with a more complete financial report on the project and show what assets and expenses have been funded by the disbursements. The requirements of ADB should have been explained to EDC during project preparation to clarify the scope of the audited project financial statements. 15 56. Prequalification of bidders. Evaluation of bids took far longer than expected and delayed subsequent activities. To reduce the likelihood of delays, it is recommended that prequalification activities include strict verification of the certificates such as the completion and operational acceptance certificates submitted by the bidders, authentication of the references submitted by the bidders, and evaluation of the complete list of key personnel. 57. Bid evaluation. To reduce the bid evaluation time frame, it is recommended that substantial technical documents such as technical data sheets, drawings, process descriptions, and manuals be scrutinized in parallel to the formal checks regarding bid completeness. 58. Design process. The lengthy detailed engineering design process was the source of significant implementation delays. To reduce delays, the following measures are recommended: (i) establish a regular meeting cycle between the employer, the contractor, and the implementation consultant; (ii) agree and fix dates for the submission of comments from the employer and the consultant, and the resubmission of designs from the contractor; and (iii) insist that the contractor's designers are present for technical discussions with the employer to avoid miscommunication and a fragmented approval process. 2. General 59. Evaluation of capacity building. The project succeeded in improving EDC’s ability to design and implement a major project. EDC’s judicious use of the project implementation consultants is also worthy of recognition (para. 31). Capacity building of the executing agency is often identified as a desired outcome from investment projects, but objective targets and indicators to measure the extent of capacity building are seldom adopted. It is therefore recommended that capacity building impacts and outcomes are given greater consideration in project design and monitoring frameworks, particularly following project implementation and in follow-on projects. 60. Design and monitoring framework. A number of indicators were not measurable, as data were either not available or not regularly updated by relevant government agencies. In addition, some targets were either too high or too low and used absolute dates rather than relative time frames, making objective evaluation of project performance difficult. It is therefore suggested that during appraisal missions, a group of key stakeholders—particularly technical specialists and those whose performance will be measured by the design and monitoring framework—be convened to arrive at a consensus on the appropriate indicators, realistic targets, and data sources. Project delays should be taken into account so they do not invalidate indicators and targets, and project performance and the selected indicators and targets should be correlated. 16 Appendix 1 DESIGN AND MONITORING FRAMEWORK Design Summary Impact The national power grid in the region is extended, and provides reliable, adequate, and affordable electricity The quality of power supply in the southern region improves Outcome The national backbone 230 kV power grid and associated distribution facilities in the southern region are expanded and strengthened, and EDC’s operation efficiency and performance are improved Performance Indicators/ Targets 5 years after project completion • Electrification ratio by population increases from 17% in 2005 to 30% in 2010 • The average tariff in Sihanoukville is reduced from the current $0.13/kWh– $0.20/kWh to $0.08/kWh by 2010 • All towns and villages along the transmission line have access to the national power grid After project completion • There is an increase in 230 kV transmission lines, substations, and distribution facilities in project area • EDC energy sales and consumption in the project area increase from 20 GWh to 45 GWh • About 25,000 people are served by the power grid • EDC’s financial ratios targets are fully met, and Data Sources/Reporti ng Mechanisms Assumptions and Risks Achievements Assumptions • Country economic and power sector analysis reports • Socioeconomic statistics of provinces and districts • Project inception, progress, and completion reports • Consultants’ survey reports • The government will implement other committed infrastructure projects as planned. • Electricity supply is available from Viet Nam and large generation sources. • Tariff set for electricity is affordable and financially and economically viable. • Electrification ratio (households) was 31.1% by the end of 2010 and 51.0% by the end of 2013. • Tariffs for gridconnected customers in Sihanoukville are currently $0.18/kWh– $0.26/kWh. An average tariff of $0.08/kWh is not credible and has no stated basis. • All towns and villages along the transmission line route have access to grid electricity. Assumptions • EDC annual report, financial statements, and project accounts • Project inception and completion reports • Project performance monitoring and evaluation system • Consumers are willing to connect to the power grid and pay the grid connection charges. • Adequate power supply is available from associated generation sources. • EDC has adequate institutional capacity. • The government comprehensively implements the EDC financial action plan. The • 82 km of 230 kV transmission line were constructed along with a new 230 kV substation at Stung Hav and an extension to the 230 kV substation at Kampot. • In 2014, EDC sold 141 GWh of electricity to 14,000 customers in Sihanoukville. The number of customers had increased to 15,500 by Appendix 1 Design Summary Performance Indicators/ Targets Data Sources/Reporti ng Mechanisms distribution loss is kept at less than 16% Outputs 1. 230 kV transmission lines from Kampot to Sihanoukville are fully operational 2. Three new substations are fully functional 3. Associated medium- and lowvoltage distributions system are established along the 230 kV transmission corridor 4. Capacity building to improve EDC’s performance is fully implemented • 230 kV doublecircuit transmission lines are extended by 78 km. • New 230 kV substations are erected at Veal Renh and Sihanoukville, and the Kampot substation is expanded. • Medium- and low-voltage distribution facilities are erected in vicinity of the transmission corridor • All affected households have been compensated, resettled, and rehabilitated according to approved resettlement plans • Recommended environmental mitigation Assumptions and Risks cumulative arrears from government agencies are fully paid by the government, and other sector improvement measures are implemented as committed. • EDC annual report, financial statements, and project accounts • Project inception and completion reports • Project administration memorandum • Project progress reports • Project review missions • Training manuals • Audited financial reports of EDC Assumption • Counterpart funds are available on time. Risks • There are delays in the approval of loan documents and procurement. • Implementation of social and environmental mitigation measures is delayed. 17 Achievements October 2015. • All loan financial ratio covenants have been met. EDC has consistently lowered distribution losses and achieved overall losses of less than 15% at project completion. • 82 km of 230 kV transmission line were constructed. • A 230 kV substation was erected at Sihanoukville and the Kampot 230 kV substation was extended, but the Veal Renh substation was dropped from the investment due to insufficient electricity demand in the Veal Renh area. • Medium-voltage lines (40 km) were erected areas along the transmission corridor using loan proceeds. EDC constructed low-voltage circuits using proceeds from other projects and its own funds. Rural electricity enterprises also constructed some 18 Appendix 1 Design Summary Performance Indicators/ Targets Data Sources/Reporti ng Mechanisms Assumptions and Risks measures are well implemented • The operation and maintenance capacity of EDC’s branches at Kampot and Sihanoukville is strengthened • Training programs for EDC staff are fully implemented Activities with Milestones • Consulting services for project implementation: commenced from January 2007 • Detailed design and bidding documents: completed by September 2007 • Resettlement implementation: completed by June 2008 • Civil works on 230 kV transmission line and substations: contract awarded by March 2008 and works completed by December 2009 • Civil works on distribution system: contract awarded by January 2009 and works completed by December 2009 • EDC capacity-building activities and training: completed by December 2009 • Capacity-building training to improve awareness of social, resettlement, and environmental safeguards: completed by 2007 • Awareness training in sexually transmitted diseases and/or HIV/AIDS and trafficking among contractors and local communities: before contractors are mobilized Achievements low-voltage lines. • 445 households were affected by the project and a total of $1.85 million was paid out in compensation. • Environmental mitigation measures were well implemented. • EDC’s ongoing training program has continually improved the medium- and low-voltage operation and maintenance capacity of branch staff. • Project implementation consultant commenced services in January 2009. • Bidding documents for 230 kV works were completed in late 2009. Bidding documents for 115 kV works (which replaced the canceled 230 kV Veal Renh substation) were completed in late 2011. • Resettlement implementation was completed by the end of 2011 for the 230 kV line and by the end of 2013 Appendix 1 Design Summary Performance Indicators/ Targets Data Sources/Reporti ng Mechanisms Assumptions and Risks 19 Achievements for the 115 kV line. • A turnkey contract for 230 kV substations was awarded in late December 2010, and the turnkey contract for the 230 kV and 22 kV lines (later extended to include the 115 kV line) was awarded in early February 2011. 230 kV line works were completed by February 2013, 115 kV line works by February 2014, and 230 kV substation works by January 2013. A contract for 115 kV substations was awarded in mid-2012 and works were completed by December 2013. • Training and capacity-building activities were completed satisfactorily by the end of 2013. Inputs • ADB loan of $20 million • Government counterpart funds of $10.06 million • JICA loan of $22.3 million • ADB loan amount was $20.61 million. • Government and EDC counterpart funding was $16.84 million. • JICA loan amount was $28.74 million. ADB = Asian Development Bank, EDC = Electricité du Cambodge, GWh = gigawatt-hour, JICA = Japan International Cooperation Agency, km = kilometer, kV = kilovolt, kWh = kilowatt-hour. Source: ADB. 20 Appendix 2 APPRAISAL AND ACTUAL PROJECT COSTS ($ million) Item Appraisal Estimate Actual Foreign Exchange Local Currency Total Foreign Exchange Local Currency Total 2.27 0.40 2.67 3.12 0.41 3.53 14.81 7.31 22.12 22.95 3.40 26.35 3. Substation at Veal Renh 6.91 5.77 12.68 0 0 0 4. Terminal substation (Stung Hav) 2.83 2.37 5.20 6.08 1.53 7.61 5. MLV distribution system 0.63 2.73 3.36 2.77 0.44 3.21 6. Consulting services 2.32 0.34 2.66 2.56 0.03 2.59 a. Resettlement 0 0.65 0.65 0 1.85 1.85 A. Infrastructure Components 1. Line bay (Kampot substation) 2. 220 kV line, Kampot to Sihanoukville 7. Project management and monitoring b. Land acquisition 0 0.34 0.34 0 3.64 3.64 c. Environmental management and monitoring 0 0.56 0.56 0 0.56 0.56 d. Other monitoring activities 0 0.28 0.28 0 0 0 8. 115 kV Sihanoukville substation and extension at Stung Hav 0 0 0 9.78 2.73 12.51 9. 115k V line (terminal substation– Sihanoukville 115 kV Substation) 0 0 0 2.02 0.29 2.31 29.77 20.76 50.53 49.28 14.88 64.16 1. Strengthening of EDC provincial branches 0.13 0 0.13 0.25 0 0.25 2. Improvement of EDC information system 0.54 0 0.54 0.57 0 0.57 3. EDC training in high-voltage systems 0.50 0 0.50 0.46 0 0.46 4. EDC training in social, resettlement, and environmental management issues 0.32 0 0.32 0 0 0 1.49 0 1.49 1.27 0.00 1.27 31.26 20.76 52.02 50.55 14.88 65.43 0.33 0 0.33 0.76 0 0.76 31.59 20.76 52.36 EDC = Electricité du Cambodge, kV = kilovolt, MLV = medium and low voltage. Note: Numbers may not sum precisely because of rounding. Source: EDC and Asian Development Bank. 51.31 14.88 66.19 Additional Infrastructure Components (Not Included at Appraisal) Subtotal (A) B. Capacity-Building Components Subtotal (B) Total Project Costs Interest during construction Total Costs to be Financed Appendix 3 CURRENCY EQUIVALENTS (Annual averages) Year 2008 2009 2010 2011 2012 2013 2014 2015 Source: Asian Development Bank. KRs = $1.00 4,081.00 4,169.00 4,056.00 4,036.83 3,995.00 3,995.00 4,068.00 4,053.95 21 22 Appendix 4 PROJECTED AND ACTUAL DISBURSEMENTS ($ million) Year Projected Actual 2006 0.000 0.000 2007 0.370 0.000 2008 2.058 0.000 2009 6.507 0.280 2010 7.533 0.671 2011 2.230 1.108 2012 0.000 5.838 2013 0.000 4.887 2014 0.000 7.042 2015 0.000 0.792 Total 18.698 20.618 Source: Asian Development Bank. Appendix 5 PROJECT IMPLEMENTATION SCHEDULE ID Task 2006 2007 2008 2009 2010 2011 2012 2013 2014 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 A. Loan Approval O A B. Loan Effectiveness O A C. Advance Procurement of Consultants O A D. Appoint Implementation Consultants O A E. Detailed Design O A F. Prepare and Approve Bid Documents O A G. Resettlement Implementation and Monitoring O A H. Civil Works 1. Transmission line bidding and contract award O A a. RP updated and approval O A b. Construction O A 2. Substations Bidding and contract award O A a. RP updated and approval O b. Construction O A O A O A O A O A O A 3. 22 kV distribution system 4. Tests/commissioning 5. Completion of installation I. Capacity-Building Activities J. Loan Closing Date A = actual, O = original, kV = kilovolt, RP = resettlement plan. Sources: Asian Development Bank and Electricité du Cambodge. 23 24 Appendix 6 PROJECT ORGANIZATION CHART Government of Cambodia Delegate in Charge of Managing Electricité du Cambodge Deputy Managing Director of Finance and Business Deputy Managing Director of Planning and Technique In-House Adviser Executive Director, Corporate Planning and Projects Department Executive Director, Finance and Accounting Department Financial Controller Deputy Managing Director of Administration Project Implementation Consultants Head, Project Management Unit 1 and Project Manager Accounting Office Deputy Project Manager General Management Unit Administration Unit Procurement Unit Head, Environmental and Public Relations Office Resettlement and Environmental Unit Transmission Line and Substation Unit Supervisor, Resettlement Project Engineering Unit Supervisor, Environment Supervisor, Medium-voltage Line Site Supervisor, Transmission Line Site Supervisor, Transmission Line Site Supervisor, Transmission Line Appendix 7 25 STATUS OF COMPLIANCE WITH LOAN COVENANTS Covenant Sector No later than three (3) months prior to the commencement of each fiscal year, beginning with FY 2007, the Borrower shall cause EDC to furnish to ADB a draft Power Development Plan setting forth EDC’s power development plans and investment requirements for the subsequent ten (10) years, and which plan(s) demonstrate to the reasonable satisfaction of ADB, inter alia, that (i) investments are economically and technically justified and constitute a part of the least-cost power expansion program; (ii) EDC has adequate financial and managerial capacity to undertake each investment without adversely affecting its current work program, including timely implementation of the Project; and (iii) EDC is carrying out the Project in a timely manner. Reference in Loan/ Project Agreements Loan Agreement (LA), Schedule 5, Para. 10 Status of Compliance Party complied with. Power development plans were updated regularly when required, but not annually. Financial The Borrower shall promptly notify ADB of any LA, Schedule Complied with. proposal to amend, suspend or repeal any 5, Para. 4 provision of the Governing Laws that would have a material effect on the operations of EDC and EDC's ability to comply with the provisions under this Loan Agreement and the Project Agreement, and shall afford ADB an adequate opportunity to comment on such proposal prior to taking any action thereon. A minimum debt service coverage ratio of 1.3 is LA, Schedule Complied with. The lowest achieved in FY 2007 and maintained thereafter. 5, Para. 5(a) debt service ratio during the entire 2007-2014 project implementation period was 2.46 (in FY2008). A maximum debt to equity ratio (as those terms LA, Schedule Complied with. The highest are defined in the Project Agreement) of 70:30 5, Para. 5(b) debt–equity ratio during the shall be maintained through fiscal year 2010. entire 2007-2014 project implementation period was 48:52 (in FY2012). EDC shall produce a revenue breakeven for FY LA, Schedule Complied with. EDC made 2007, and maintain the revenue breakeven 5, Para. 5(c) operational benefits during 26 Appendix 7 Covenant Reference in Loan/ Project Agreements thereafter, such that total operating revenues are equivalent to or not less than the sum of total operating expenses less depreciation costs. Status of Compliance the entire 2007-2014 project implementation period. Total accounts receivable shall be maintained at LA, Schedule Complied with. The highest a level that does not exceed the equivalent of 5, Para. 5(d) accounts receivable during three (3) months' average sales revenue. the entire 2007-2014 project implementation period was 2.53 months (in FY2013). Beginning with the proposed Budget Law for LA, Schedule 2007, and for every fiscal year thereafter, unless 5, Para. 6 otherwise agreed by the Borrower and ADB, the Borrower shall earmark an estimated expenditure, in the contingency line items (Chapter 40) of the draft Budget Law, equivalent to input VAT chargeable to EDC as recorded by the Custom Department against an estimated amount that the Customs Department would record as revenue in from VAT. Pursuant to such budget allocation, the Borrower shall annually offset against the input VAT owed by EDC to Customs Department. Complied with late. The borrower started earmarking funds from the budget to offset the VAT in 2008. Beginning with the proposed Budget Law for LA, Schedule 2007, and for every fiscal year thereafter, unless 5, Para. 7 otherwise agreed by the Borrower and ADB, the Borrower shall earmark an estimated expenditure, in the contingency line items (Chapter 40) of the draft Budget Law, equivalent to the amount levied by Taxation Department for input VAT against EDC’s liability on interest and principal payments due the Borrower under subsidiary loans to EDC using funds provided by ADB and the World Bank. Pursuant to such budget allocation, the Borrower shall annually offset against the input VAT owed by EDC to Taxation Department. Partly complied with. The MEF had offset all past-due input VAT owed by EDC to the government against EDC’s liability on VAT, but EDC was unable to pass on the newly imposed VAT to its customers. Beginning with the proposed Budget Law for LA, Schedule Complied with. 2007, and every fiscal year thereafter, unless 5, Para. 8 otherwise agreed by the Borrower and ADB, the Borrower shall make a budget estimate for each fiscal year of the electricity consumption of the Borrower’s agencies, institutions and local authorities, taking into account their respective actual electricity consumption of the previous Appendix 7 Covenant Reference in Loan/ Project Agreements 27 Status of Compliance year as calculated by EDC. Using this calculation, the Borrower shall, three months prior to the end of the fiscal year, earmark from a total budget for each agency, institution and local authority a sufficient amount to meet expected electricity consumption, and shall deduct such amount from the respective budgets for direct payment or credit to EDC. By 30 June 2007 the Borrower shall have used a similar procedure to pay or credit in full to EDC the past due arrears of the Borrower’s agencies, institutions and local authorities for the fiscal year 2006. Operational The Borrower shall ensure that EDC takes all LA, Schedule necessary action to maintain transmission and 6, Para. 9 distribution losses at a level not exceeding 16% in FY 2006 and in each subsequent fiscal year. Complied with. The overall transmission and distribution losses during the entire 20072014 project implementation period were less than 15%. Social The Government should ensure that land LA, Schedule Complied with. acquisition, compensation, relocation, 5, Para. 15 resettlement and rehabilitation is carried out in accordance with the Resettlement Plan (as updated upon completion of the detailed measurement survey and a sugar palm/income restoration study with the study's findings incorporated into the Resettlement Plan) agreed upon between the Borrower and the Bank, the Borrower's laws, regulations, and procedures and the Bank's requirements as defined in the Bank's Policy on Involuntary Resettlement and the Handbook on Resettlement. Prior to commencement of any resettlement LA, Schedule Complied with. activities, including the detailed measurement 5, Para. 16 survey, EDC shall engage and mobilize (a) resettlement specialist consultants (as part of the Project implementation consultants) to assist in preparing and implementing the RPs, and (b) an independent monitoring organization (IMO). EDC shall appoint at least one full-time resettlement staff who is a recent social science graduate (as described in para. 2 of this 28 Appendix 7 Covenant Reference in Loan/ Project Agreements Status of Compliance Schedule) and ensure, through its PMU, that provincial and district resettlement committee authorities are appointed. The Borrower shall ensure that EDC has taken LA, Schedule Complied with. all needed actions to ensure that (a) the 5, Para. 17 resettlement planning and implementation is carried out promptly and efficiently in accordance with all Government laws and regulations, ADB’s Policy on Involuntary Resettlement, and the approved RPs and RF, specifically including those special measures specified in the RP and RF for complementary mitigation and enhancement activities to assist socially and economically vulnerable groups, such as women-headed families, children and elderly people without support structures, people living in extreme poverty, and indigenous and ethnic minorities; (b) all affected people are given adequate opportunity to participate in resettlement planning and implementation; (c) all affected people are compensated and assisted prior to displacement from their houses, land, and assets such that they will be at least as well off as they would have been in the absence of the Project and the poorest and vulnerable are assisted to improve their socio-economic status; (d) implementation of the RPs is monitored by EDC and provincial resettlement committees, and by the IMO, and related reports are submitted to ADB and EDC through the quarterly monitoring reports as stipulated in the RP and RF; (e) the RP for the distribution system is prepared in accordance with the RF, and disclosed to the affected people before being submitted to ADB for review and approval; and (f) each final and updated RP, including compensation rates, is translated into Khmer and placed in commune and district offices, and summaries, in the form of information booklets, including compensation rates, are distributed to all affected people. The Borrower shall ensure that EDC: (a) LA, Schedule Complied with. allocates and disburses funds needed for land 5, Para. 18 acquisition and resettlement in a timely manner; (b) the RP is updated and submitted to ADB Appendix 7 Covenant Reference in Loan/ Project Agreements 29 Status of Compliance after completing the detailed measurement surveys and detailed design, and approved by ADB before it is implemented; and (c) ADB is promptly advised of any changes in the resettlement impacts, and if necessary, a revised RP is submitted to ADB for concurrence. The Borrower shall ensure timely provision of LA, Schedule Complied with. counterpart funds to EDC for land acquisition, 5, Para. 19 resettlement and monitoring activities specified in the RPs, and will meet any unforeseen obligations in excess of the RP budget estimate in order to satisfy resettlement objectives. The Borrower shall ensure that counterpart funds for compensation and entitlements under the RPs are fully provided directly to affected people prior to their displacement from housing and prior to loss of land, livelihood, income or other assets or both. No construction civil works shall commence in a LA, Schedule Complied with. specified geographic area prior to EDC having 5, Para. 20 satisfactorily completed in that area, and in accordance with the approved RP, compensation payment and relocation, if any, and having ensured that all rehabilitation assistance to Project affected persons is in place and that the specified geographic area required for civil works is free of all encumbrances. The Borrower shall provide to the IMO, at no LA, Schedule Complied with. cost, all documents required to monitor the 5, Para. 21 resettlement process, specifically including the RPs, RF, Detailed Measurement Survey documents, signed agreements with affected people, and all associated documents which may be requested by the IMO. The Borrower shall ensure that EDC includes LA, Schedule Complied with. the following conditions in the civil works 5, Para. 21 contract documents: (i) mandatory provisions on health, sanitation and appropriate working conditions, including accommodation, for construction workers at campsites during the construction period; (ii) requirements that the contractor comply with all applicable labor laws, 30 Appendix 7 Covenant Reference in Loan/ Project Agreements Status of Compliance including elimination of gender differentiated employment conditions, wages or food rations, and that it will not employ child labor in construction activities; (iii) employment targets for women; (iv) appropriate child care facilities in campsites with women employees will be provided; and (v) requirements that the contractor will carry out, through a budgeted line item for a qualified NGO or other appropriate body, a dissemination campaign or campaigns on the risks of sexually transmitted diseases (including HIV/AIDS), and on the risks of trafficking women and children, to (a) those employed during Project implementation and (b) communities in the Project area. Environmental The Borrower shall ensure that its laws and LA, Schedule Complied with. regulations governing environmental impact 5, Para. 11 assessments, as well as ADB's Environment Policy (2002), are followed. If there is any discrepancy between the Borrower’s laws and regulations, and ADB's Environment Policy, then the ADB Policy requirements shall apply. The Borrower shall ensure that the contract LA, Schedule Complied with. documents for all civil works under the Project 5, Para. 12 include specific measures in accordance with ADB's Environment Policy to mitigate negative environmental impacts caused by the construction and to give due consideration to prevention of damage to the natural environment in the design, construction, operation and maintenance of Project facilities. The Borrower shall ensure that EDC implements LA, Schedule Complied with. the Environmental Management Plan (EMP) for 5, Para. 12 the Project, based on the IEE, ensuring that there are adequate budget and staff resources. The Borrower shall ensure that the Project complies with best environmental practices and meets the mitigation and monitoring requirements in a timely manner as described in the IEE and prevents damage to the natural environment as a result of the design, construction, operation and maintenance of Project facilities. The Borrower and EDC shall Appendix 7 Covenant Reference in Loan/ Project Agreements Status of Compliance cause (i) the contractors engaged under the civil works contracts to comply strictly with all environmental impact mitigation and monitoring requirements set out in the contract documents, and (ii) the consultants engaged for construction supervision to monitor closely the compliance by the contractors with the environmental impact mitigation and monitoring requirements. Monitoring The Borrower shall ensure that EDC conducts LA, Schedule Complied with. performance monitoring using agreed upon and 5, Para. 23 measurable performance targets utilizing EDC’s customer database, with a separate category for poor consumers (defined as those utilizing 50 kilowatt hours of electricity per month or less). Efficiencies in utilities operations shall be measured by data on distribution losses, energy sales, employee-customer ratio, and average cost of service. Monitoring of EDC’s Sihanoukville branch shall include an assessment of the effectiveness of demand management and consumer services. Project Implementation EDC shall ensure that throughout Project LA, Schedule Complied with. implementation the PMU shall be headed by a 5, Para. 1 senior staff member with experience and qualifications acceptable to ADB as Project Manager, and shall further include an adequate number of suitably qualified and experienced administrative and technical staff assigned on a full-time basis who are experienced in previous ADB-financed transmission line projects. EDC will assign at least three experienced and qualified engineers on a full-time basis to liaise and work with Project implementation consultants. By 30 June 2007 EDC shall have appointed two LA, Schedule Complied with. recent graduates in environmental and social 5, Para. 2 science (or other disciplinary area as agreed by ADB) assigned to the EDC social and environment unit. The PMU shall manage and supervise the 31 LA, Schedule Complied with. 32 Appendix 7 Reference in Loan/ Covenant Project Agreements Project and shall assign appropriate qualified 5, Para. 3 resettlement staff for the periods necessary and with responsibilities for social issues, including (i) resettlement planning and management, (ii) HIV/AIDS awareness program, (iii) poverty and social impact assessments, and (iv) labor practices. Status of Compliance EDC simultaneously submits within six (6) LA, Schedule Complied with. months after the end of the fiscal year: (i) 5, Para. 29(a) audited annual Project accounts (APA) which provide a detailed description of source of funds and expenditures made; and (ii) audited corporate financial statements (CFS) which include statements of income and expenditures, assets and liabilities with notes to the accounts and cash flows. The auditors shall be required to provide an LA, Schedule Complied with. opinion on EDC's compliance with the financial 5, Para. 29(d) covenants in [the] Loan Agreement and the Project Agreement. The Borrower shall ensure that EDC prepares LA, Schedule Complied with. regular progress reports for submission to ADB 5, Para. 30 on a quarterly basis. The Borrower shall establish committees on LA, Schedule Complied with. procurement in accordance with the Borrower’s 5, Para. 26 Procurement Manual (2005), which shall supervise the entire procurement process. The Major Committee on Procurement, as defined by the Procurement Manual, shall be established by 31 March 2007 and chaired by a representative from EDC. Particular In the carrying out of the Project and operation of the Project facilities, the Borrower shall perform, or cause to be performed, all obligations set forth in Schedule 5 to this Loan Agreement. The Borrower shall enable ADB’s representatives to inspect the Project, the Goods or Works financed out of the proceeds of the Loan, and any relevant records and LA, Article IV, Complied with. Section 4.01 LA, Article IV, Complied with. Section 4.02 Appendix 7 Covenant Reference in Loan/ Project Agreements 33 Status of Compliance documents. The Borrower shall take all action which shall be necessary on its part to enable EDC to perform its obligations under the Project Agreement and shall not take or permit any action which would interfere with the performance of such obligations. LA, Article IV, Complied with. Section 4.03 The Borrower shall exercise its rights under the Subsidiary Loan Agreement in such a manner as to protect the interests of the Borrower and ADB and to accomplish the purposes of the Loan. LA, Article IV, Complied with. Section 4.04. (a) No rights or obligations under the Subsidiary Loan Agreement shall be assigned, amended, or waived without the prior concurrence of ADB. LA, Article IV, Complied with. Section 4.04. (b) EDC = Electricité du Cambodge, MEF = Ministry of Economy and Finance, VAT = value-added tax. Source: EDC and MEF. 34 Appendix 8 FINANCIAL AND ECONOMIC REEVALUATION A. General 1. This financial and economic reevaluation considers the total project investment as a whole. The reevaluation is based on estimated cost and benefit streams expressed in constant 2014 dollars. Figures from the appraisal, which were expressed in 2006 values, have been adjusted to 2014 values for the purpose of comparison. Financial and economic evaluation models from appraisal were not available in a useable form, requiring new models to be created for this reevaluation. 2. All investment funded by the project has been completed and the facilities have been in operation since mid-2014. The bulk of the investment (68%) is in electricity transmission facilities connecting Sihanoukville to the national grid via existing 230-kilovolt (kV) facilities at Kampot. The balance of the investment (32%) relates to enhancing sub-transmission capacity into Sihanoukville and building new medium-voltage lines along the transmission line route. 3. The most significant component of the investment from a financial and economic viewpoint is the connection of Sihanoukville to Cambodia’s national grid. At appraisal, it was considered that electricity would be imported into Sihanoukville through the new transmission facilities, and analysis was undertaken on that basis. In practice, the construction of new largescale coal-fired generation facilities in Sihanoukville (to date, 360 megawatts of privately owned base-load plant have been commissioned in Sihanoukville, increasing to around 500 megawatts by mid-2017) means that electricity is being exported from Sihanoukville to the national grid, necessitating a substantially different approach to conducting financial and economic analysis. B. Financial Evaluation 4. At appraisal, the project’s benefits were taken to be an increase in electricity sales due to load growth in Sihanoukville and savings due to electricity loss reduction in the project area. However, because of the development of large-scale generation in Sihnoukville that was not envisaged at appraisal (para. 3), actual financial benefits from the investment vary significantly from those estimated at appraisal. In particular, the investment in transmission facilities means that Electricité du Cambodge (EDC) can increase its electricity sales in Phnom Penh in addition to increasing sales in Sihanoukville.1 These increases in sales were quantified on the basis of a revised demand forecast, derived from existing demand and the growth rates estimate at appraisal, and valued at the prevailing tariffs for Sihanoukville and Phnom Penh. The basis on which loss reduction was quantified and valued at appraisal is unclear; because this benefit is expected to be small relative to other benefits, it was excluded from this reevaluation. The project also allows for substitution of expensive diesel and heavy fuel oil generation with cheaper generation from Sihanoukville coal plant. However, because end-use tariffs are adjusted to reflect EDC’s cost of supply, limited financial benefit will accrue to EDC from this reduction in generation cost and it has therefore been excluded from the financial reevaluation. 5. As at appraisal, financial costs were taken to be capital and operating costs of the project facilities, the costs of electricity purchases, and allowance for the capital cost of the distribution system in Sihanoukville required to meet the forecast demand. 1 It is not required that the transmission capacity constructed under the project be devoted to allowing EDC to increase sales in Sihanoukville. In practice, however, if not for EDC committing to construct the Kampot– Sihanoukville transmission connection under the project, the new coal-fired generating plant in Sihanoukville would not have been financially viable and would therefore have not been built. Appendix 8 35 6. The reevaluated financial internal rate of return increased from 13.2% at appraisal to 25.9% at project completion (Table A8.1). The increase is unsurprising given the fundamental change in the use of the project transmission facilities (from import of electricity into Sihanoukville to export of electricity from Sihanoukville) between appraisal and project completion. The increase in financial internal rate of return occurred even though the project capital cost increased from an estimate of $52.4 million at appraisal to $66.2 million at completion (a 26% increase due to changes in scope, delays, and higher than expected resettlement and land acquisition costs). Table A8.1: Project Financial Performance Item At Appraisal Project financial internal rate of return (%) Project financial net present value ($ million, 2014) 13.2 96.3 At Project Completion 25.9 1,102 Source: Asian Development Bank estimates. C. Project Economic Evaluation 7. At appraisal, an investment time-slice approach was used to estimate the economic return for the project, with an assumption that a small-scale diesel plant would be constructed in Sihanoukville to meet demand in the “without project” case. This approach has not been repeated for the purpose of this reevaluation because (i) insufficient detail was available in appraisal documentation to allow replication; (ii) the use of the alternative (small-scale diesels) case to represent the “without project” scenario means that the economic internal rate of return reported at appraisal is actually an equalizing discount rate; and (iii) given the material change in use of the project facilities between appraisal and completion, a simpler and more transparent approach to economic analysis is justified. 8. For this reevaluation, the project’s benefits are (i) displacement of electricity importation from Viet Nam (a resource cost saving), (ii) displacement of output from inefficient diesel and heavy fuel oil generating stations in Sihanoukville and Phnom Penh and a fuel oil plant in Phnom Penh (a resource cost saving), and (iii) induced consumption from newly connected and existing customers in Phnom Penh and Sihanoukville (incremental output). These benefits were quantified by developing a simple generation dispatch model for the national grid based on estimated generation costs. Demand forecasts for Phnom Penh and Sihanoukville were updated using growth rates assessed at appraisal and actual demand in 2010-2014 (demand forecasts for Phnom Penh used at appraisal significantly underestimated present day demand). Induced demand was valued at prevailing tariffs (an average of around $0.15 per kilowatt-hour), which is a minimum estimate of willingness to pay. Costs include (i) the full project investment of $54.96 million (expressed in economic terms using the world price numeraire and adopting the shadow exchange rate factor of 1.1 used at appraisal), (ii) operation and maintenance costs at 2% of capital costs, (iii) the incremental cost of generation (at the estimated economic unit cost of supply from the Sihanoukville coal-fired plant), and (iv) other costs incurred in serving the increased sales volume. The project’s economic performance is presented in Table A8.2. 36 Appendix 8 Table A8.2: Project Economic Performance Item Project economic internal rate of return (%) Project economic net present value ($ million, 2014) At Appraisal 20.9a At Project Completion 61.0 740 a Although not correctly identified at appraisal, this was an equalizing discount rate (between two alternative development scenarios) rather than an economic internal rate of return. As such, it is not directly comparable with the economic internal rate of return calculated at project completion. Source: Asian Development Bank estimates. 9. The project’s robust economic return of 61% derives from the fact that connection of Sihanoukville to the national grid allows for the dispatch of relatively cheap base-load coal-fired electricity to the Phnom Penh load center (as opposed to simply delivering electricity to Sihanoukville, as was assumed at appraisal). Other investments that have previously been made in transmission and distribution networks have facilitated this dispatch, even though they have been treated as sunk costs for the purpose of this analysis. A comprehensive time-slice analysis of network development over the past 10 years, which is beyond the scope of this report, would present a more complete and accurate picture of the overall economic performance of investments in the sector. However, it is clear that the decision to construct the project facilities was correct from a financial and economic perspective, and will be a critical component in the development of the national grid over the next 10 years. Appendix 9 37 RESETTLEMENT ACTIVITIES A. Resettlement Plan 1. Analysis undertaken as part at project appraisal indicated the need for a short resettlement plan for the 230-kilovolt (kV) transmission line and substations because fewer than 200 persons were then expected to experience major impacts. According to the resettlement plan prepared in 2006, 731 households are expected to experience either minor or major impacts as result of land acquisition for right-of-way (ROW). Of these, it was anticipated that only 12 households would need to move out of the line’s 30-meter right-of-way, of which seven households could move back on their remaining land outside the right-of-way and five could relocate within their own villages. It was anticipated that 14 households would also have to relocate their temporary field huts on their remaining land outside the right-of-way. Only two households were expected to lose land to the two new substations. Of the rest of the 703 households, 220 were expected to be marginally affected by a loss of 100 square meters (m2) of land for the transmission line towers. A total of 3.92 hectares of land was anticipated to be permanently acquired. It was also estimated that 3,000 trees would have to be removed to allow for sufficient vertical clearance for the 230 kV line. For the medium- and low-voltage facilities, a resettlement framework was prepared at appraisal to guide the preparation of a short resettlement plan during loan implementation. The project did not affect any indigenous peoples, ethnic minorities, or cultural sites. 2. As required under loan covenants, the updated resettlement plan for the Kampot– Sihanoukville 230 kV transmission line and Sihanoukville (Stung Hav) 230 kV substation was prepared by Electricité du Cambodge (EDC) and submitted to the Asian Development Bank (ADB) in July 2012 during project implementation. This updated resettlement plan reflected the modification of the transmission line route from Kampot to the Stung Hav substation agreed by EDC in November 2011, which was necessitated due to difficulties in acquiring land and agreeing on compensation along the original line route. The updated resettlement plan was based on a detailed technical design and detailed measurement survey (DMS) of losses by the affected households. Prior to DMS assessment, extensive consultation was carried out by the EDC resettlement plan working group dedicated to this project. The consultation meetings, which included question and answer sessions, were attended by affected persons, commune and village leaders. Key questions raised included replacement costs of affected land or structures, relocation along the right-of-way, and options for resettlement. Following the public meetings, EDC staff carried out house-to-house measurements of assets to be lost and updated the DMS database. Members of EDC’s Provincial Resettlement Sub-Committee actively participated in the DMS and consultation meetings. EDC assured the affected persons that they would be paid at replacement or market value and as per the entitlement matrix, which was disclosed to the affected persons. There were no grievances lodged during the DMS. EDC has established its Provincial Resettlement Sub-Committees and Grievance Redress Committee in all project provinces. EDC also conducted short orientation training for field staff at the provincial level to facilitate the implementation of resettlement work. The EDC working group conducted regular monitoring of all resettlement implementation work. The DMS resulted in a database that formed the basis for monitoring of resettlement work. As constructed, the 230 kV transmission line cuts across 2 provinces, 4 districts, 13 communes, and 34 villages. Land acquired for each of the 240 transmission line towers was 225 m2. Land acquired for the Stung Hav 230 kV substation was 62,236 m2. Ultimately, 415 households were affected by the transmission line. 3. The short resettlement plan for the 115 kV line from Stung Hav substation to the new 115 kV substation in Sihanoukville was prepared by EDC and submitted to ADB in July 2013, and a revised and final resettlement plan was submitted in March 2014. The total constructed length of the 115 kV transmission line was 12 kilometers, cutting across one district and one municipality of 38 Appendix 9 Sihanoukville province, two communes, and two villages. Land acquired for each of 32 transmission line towers was 144 m2. Land acquired for the Stung Hav 230 kV substation was 14,500 m2. Ultimately, 30 households were affected by the line and substation. Of the acquired land, 41% is public and the remaining 59% is private and mainly used for farming (12.5%), village activities (34.0%), and forest (12.5%). 4. The project entitlement matrix was designed to comply with ADB’s Policy on Involuntary Resettlement (1995) and relevant laws and regulations of Cambodia. Resettlement plans detailed processes and procedures for assessing eligibility and entitlements, consultation, grievance redress and participation, relocation and rehabilitation, income restoration strategies, and the institutional framework for implementation. In response to notification from the Prime Minister’s Office, from December 2010, responsibility for implementation of resettlement activities was passed from the Inter-Ministerial Resettlement Committee led by the Ministry of Economy and Finance to EDC. The resettlement process has been independently monitored by an independent monitoring agency. B. Resettlement Impacts 5. Upon completion of the project, total resettlement impacts were as follows: Table A9: Resettlement Impacts Item Affected households (number) Area of land acquisition (m2) - for towers and poles - in right-of-way - at substation site Area of affected structures (m2) - Type 1a - Type 2b Affected trees (number) 2 Transmission Lines 230 kV 115 kV 415 30 53,920 426,079 4,608 325,323 Substations 230 kV Total 115 kV 0 0 445 62,236 14,500 58,528 751,402 76,736 75 1,393 0 190 0 0 0 0 75 1,583 52,209 1,155 0 0 53,364 kV = kilovolt, m = square meter. a Type 1 structure has thatched, leaf, and/or plastic roof. b Type 2 structure has metal and/or fiber cement roof. c Type 3 structure has tile roof. Source: Project implementation consultant’s final report.
© Copyright 2026 Paperzz