EXECUTIVE SUMMARIES FOR THE PRACTITIONER A Langdon & Seah Consultancy Information Sheet Volume 14 Issue 3: June 2014 Langdon & Seah Singapore Pte Ltd Global Construction Consultants Further Updates on the Building and Construction Industry Security of Payment Act Introduction In the light of the recent Court cases and adjudication determinations under the SOP Act in 2013, I would like to provide a summary of the key issues so that we are aware of the vigilance needed. 1) Both contractual obligations & SOP Act requirements need to be considered The SOP Act sits on the construction contract and is the legislative regime that entitles the Contractor to payment for work done. The SOP Act will take precedence if the contract is drafted such that the payment requirements and regime under the Act is not complied with e.g. where maximum timeframes under the SOP Act are breached, or pay when paid clauses incorporated in contravention of s. 9 of the SOP Act, as no contracting out is permitted. Preliminaries have been carefully drafted to take into account the requirements of the SOP Act, e.g. under the standard L&S REDAS PCs, Interim Payment Certificates (issued within 14 days under PC cl. 22.3) are §deemed¨ the Payment Response, if the Employer does not subsequently provide a Payment Response (within 21 days from the date of the Payment Claim, being the maximum period permitted under s. 11(1)(a) of the SOP Act). It does not automatically follow that an employer does not need to pay the contractor if the quantity surveyor did not produce an interim valuation, or the architect an interim payment certificate. If the contractor makes a payment claim, there must be a payment response, supported by adequate reasons where there is a difference in amounts or amounts are withheld (s. 11(3)(c) of the SOP Act). Also in the event of termination, and even if there is a termination certificate, employers must still pay the contractor for work done up to termination. If the payment claim is made after termination, employers must still value the work done, less any deductions e.g. for defects and LD. 2) Draft payment claims It is clear from cases like Lee Wee Lick Terence v Chua Say Eng [2012] SGCA 63 that a payment claim does not have to specify that it was made pursuant to the SOP Act. In such context, where “draft” payment claims are requested, these must clearly indicate that it is for discussion only and they do not constitute a payment claim under the SOP Act, to avoid it being treated as such. If the Contractor subsequently attempts to treat the payment claim as one under the SOP Act, the Employer can avail themselves of a defence of estoppel. Copyright Volume 14 Issue 3: June 2014 MCI (P) 063/06/2014 …@Langdon & Seah Consultancy Executive Summaries for the Practitioner Page 2 Further Updates on the Building and Construction Industry Security of Payment Act 3) Date of submission of payment claims Given the uncertainty regarding the treatment of §month¨ arising from cases like Chua Say Eng and the effect on the date for submission of payment claims, it shall be clarified that the submission date shall be based on calendar month. For example, under the standard L&S REDAS PC cl. 22.2.1, the payment claims are to be submitted within 7 days from the end of the calendar month following the month in which the contract is made. 4) No basis to pay when certified The fact there is no certification, or SOI, ERI or AI, under the contract is not a reason for not making payment, given the purposes of the SOP Act and that it entitles the contractor to payment for work done. Certification is just a contract administration mechanism under the contract and if work has been done, the contractor must be paid. We need to ensure that proper assessment of the work done and variations are carried out timeously and clear the RVO process efficaciously, so that the necessary instructions can be issued. Unfortunately, the RVO process instituted by our clients is not part of the SOP Act and if a contractor is claims conscious, he still can make a payment claim and succeed in adjudication, notwithstanding a proper RVO approval process and absence of SOI, ERI or AI. Therefore, a good working relationship with the contractor is important due to the dichotomy of the requirements based on the SOP Act and what is needed for good change management. 5) Be especially vigilant for no payment response by the M&E Engineers It has come to our attention that there are many SOP determinations in 2013 against the Employer because of no reasons given. As valuation is carried out by us and the M&E Engineer, all should at least have the principle: i) Valuations must have reasons for the difference in amount; ii) “Nil”, or “0.00”, or “-“ entry is not acceptable as a reason; iii) To be sensitive to the timelines. Essentially, good reasons should be given whenever the response amount is less than the claimed amount. Section 11 (3)(c) of the SOP Act mandates this, so it is not that we are imposing unnecessary demands. Practically, it is still the case that failure to serve a payment response is usually fatal and likely means full payment will be allowed by adjudicators. The implications of s15 (3) are draconian. We must have these instituted, so as to protect our clients and Langdon & Seah in this SOP process. Copyright Volume 14 Issue 3: June 2014 MCI (P) 063/06/2014 …@Langdon & Seah Consultancy Executive Summaries for the Practitioner Page 3 Further Updates on the Building and Construction Industry Security of Payment Act 6) For ¨Nil¨, good reasons must also be given If there is “Nil” payment e.g. because the contractor has not come to that part of the work yet and is claiming in advance, we need to clearly state “Nil” Payment and the reasons for this. Just stating “Nil” payment is not a valid reason at all. 7) No Maintenance Certificate is not a reason Even if we are using the SIA form, the fact there is no maintenance certificate is not a good enough reason to withhold monies on claims for release of retention e.g. under clause 31(10) of SIA Lump Sum Conditions of Contract, 9th Ed. This can be challenged by the contractor again on the basis that he is entitled to payment for work done regardless of certification process. It is better to explain why the maintenance certificate was not issued, e.g. works were not completed, defects have not been rectified, indemnities or warranties were not provided, or no proper as-built drawings submitted. And if proper as built drawings are not submitted, it is harsh to hold back all the retention monies just on account of this. There should still be some payment for work done, even if some drawings are not submitted. 8) Definition of Work Done to include Drawings etc If shop drawings submissions are to be approved before contractor is entitled to payment, it has to be clearly worded that these submissions shall be part of the works. If the clauses are drafted as though they are condition precedents, or that payment will be made only when these are approved, then there is a chance that non-payment due to non-submission of the shop drawings, will be subject to challenge under the SOP Act. These documentations, including the need to submit the conforming documents prior to the release of the retention, shall be described as part of the works in order for full payment to be released and paid. If they are not submitted, then it is deemed that the works are not completed and payment can’t be made in full. We may need to go one more step to say that if all documents are not submitted, a percentage can be paid. Once approved, the remaining monies can be paid, in order to show reasonableness of approach. Eugene Seah Group Managing Director Copyright Volume 14 Issue 3: June 2014 MCI (P) 063/06/2014 …@Langdon & Seah Consultancy Executive Summaries for the Practitioner Page 4 Further Updates on the Building and Construction Industry Security of Payment Act L&S TPI is a measure of the comparative tender price movements based on the projects handled by Langdon & Seah Singapore Pte Ltd. The TPI reflects the tender price level of contracts let out over the years. Other than material and labour costs, it takes into account the elements of competition, risk and profits. /6 7HQGHU3ULFH,QGH[%DVH<HDUDW %&$ A A A A A 4 Source: * Building and Construction Authority as at 19 May 2014 Note: With effect from the 1st Quarter of 2009, BCA has implemented the new TPI series with Base Year 2005 = 100. The TPI chart shown above has been amended accordingly to reflect the Base Year as Year 2005. ^ L&S TPI is based on 4th Quarter index Langdon & Seah Singapore Pte Ltd (L&S) in addition to providing traditional quantity surveying has developed a range of specialist integrated management services for construction projects comprising of cost management, project management, contract advisory & dispute management, cost engineering services, loan monitoring, insurance valuations and loss adjusters assessment, sustainable construction, construction supervision services and investment appraisals. L&S Contract Advisory & Dispute Management Services Pte Ltd: Eugene Seah, Amos Teo and Kua Moon Yin Professionally qualified and experienced construction professionals providing the following within Singapore, the Region and the International arena: x Front End Contract Advisory work including Contract Administration, Procurement Strategy, incorporation of Conditions of Contract x Claims Assessment x Legal and Litigation Support x Expert Technical Advice and Witness x Dispute Management towards Avoidance and Resolution x Evaluator, Mediator, Arbitrators and Adjudicator x Research, Publication, Seminars, Short Courses and In-house Training for Staff, Clients and Consultant Organisations L&S x x x x Consultancy: Eugene Seah and Amos Teo Construction Innovation Sustainability and Green Issue Bank Technical Advisory Management Facilities Cost Consultancy Capital Allowance x Technical Due Diligence x Market Intelligence and Research x Management Consultancy / Development Landgon & Seah Consultancy includes the following services through the following departments: Cost Research Department: Eugene Seah, Ho Kong Mo, Cheryl Lum and Christine Chan x Cost Analysis & Research of tenders and its price indexing x Value Management & Engineering exploring schemes, architectural forms and constructions methods towards achieving efficiency and buildability x Benchmarking – Generic, Competitive, External and Internal x Reinstatement Cost Assessment x Due Diligence Reporting Mechanical & Electrical Quantity Surveying Department: Goh Chok Sin and Lorimer Doig x Budget and Detailed Cost Estimating x Tender and Contract Documentation x Financial Management of Contract x Value Engineering x Life Cycle Costing x Capital Allowances Taxation Assistance x Dispute Resolution and Expert Witness Reports x Cost Audit Contact us at our Email: [email protected]; [email protected]; M&[email protected]; Tel: (65) 6222 3888 or Visit our website at www.langdonseah.com …@Langdon & Seah Consultancy’s Executive Summaries for the Practitioner provides a synopsis of legal and/or professional practice issues in the construction industry and is intended for information purposes only. While L&S Consultancy endeavours to ensure the accuracy and completeness of the information sheet, specific professional legal advice should be obtained and L&S Consultancy shall bear no liability whatsoever for any part of its contents. All rights reserved. Copying in any form or by any means (electronic, photocopying or otherwise) is strictly prohibited without the written permission of L&S Consultancy. Printed by Kairos Design Copyright Volume 14 Issue 3: June 2014 MCI (P) 063/06/2014
© Copyright 2026 Paperzz