Construction Contracts Act 2015 case review Greg Nairn 22 July 2015 HAMERSLEY IRON PTY LTD -VJAMES [2015] WASC 10 (16 January 2015) – – Sheds further light on what will constitute reviewable jurisdictional error Confirms test for leave to enforce 2 Reminder: section 31(2)(a) and (b) Section 31(2)(a): adjudicator must dismiss without a determination on merits if he/she finds one or more of identified criteria exist (eg not a construction contract) Section 31(2)(b): if not dismissed, adjudicator must determine on BoP whether any party to the payment dispute is liable to make a payment 3 Question is not whether or not criteria actually exist SECTION 31(2)(a) CRITERIA Focus is on adjudicator’s reasoning and conclusion Unreasonableness, manifest illogicality or irrationality Misconstruction of the CCA Misconception of nature of function Irrelevant considerations involved Mandatory relevant considerations ignored 4 SECTION 31(2)(b) MERITS DETERMINATION Also amenable to judicial review Various grounds will suffice eg Misunderstands nature or limits of powers eg Misconception of nature of function eg Decision in bad faith eg Denial of natural justice 5 No jurisdictional error on the facts of Hamersley Attack on adjudicator’s treatment of a set-off claim, specifically how principal’s “costs to complete” were to be calculated No error, let alone jurisdictional error, established 6 However, leave to enforce was refused Accepted “pay now, argue later” object of the Act Mere arguable counterclaim not enough to deny leave to enforce However, additional factor motivating refusal of leave was contractor’s insolvency S 553C of the Corporations Act requires an account to be taken of the parties’ mutual dealings S 553C would be frustrated if determination enforced 7 GRC GROUP PTY LTD and KESTELL [2015] WASAT 11 (6 February 2015) – – An adjudicator is not entitled to dismiss an application under section 31(2)(a) on the basis that the adjudicator found that the payment claim was not “bona fide”. Bona fides of the claim was relevant only to the determination on the merits under section 31(2)(b). 8 LEND LEASE BUILDING CONTRACTORS PTY LTD T/AS SITZLER BAULDERSTONE JOINT VENTURE V HONEYWELL LIMITED T/AS HONEYWELL BUILDING SOLUTIONS & ANOR [2015] NTSC 10 (9 February 2015) – – Determination that applicant contractor was entitled to a sum of money, but deferring obligation of respondent to pay until applicant provided replacement guarantees, survived judicial review The deferral component of the determination depended on a reading of the contract and any error made was not jurisdictional in error 9 FIELD DEPLOYMENT SOLUTIONS PTY LTD -v- SC PROJECTS AUSTRALIA PTY LTD [2015] WASC 60 (16 February 2015) – – Sheds light on scope of SAT review of adjudicator’s decision to dismiss Sheds further light on what constitutes a “construction contract” 10 SCOPE OF SAT REVIEW “De novo” review SAT to consider matter afresh SAT can uphold a decision to dismiss for different reasons to adjudicator SAT can have regard to evidence/arguments not before the adjudicator Touchstone is what is the “correct and preferable” decision 11 “CONSTRUCTION CONTRACT” Construction of a gas pipeline is construction work Rehabilitation work on land on which a pipeline is constructed is construction work Hauling, moving earth to pipeline and at the site for use in rehabilitation is construction work Processing plant exception not applicable as pipe function was merely to transport, not process, gas 12 FIELD DEPLOYMENT SOLUTIONS PTY LTD -v- JONES [2015] WASC 136 (20 April 2015) – – – Contractor sought in Supreme Court to quash two adjudication decisions to dismiss Mitchell J refused on basis it was (1) futile (contractor out of time to recommence); (2) alternative remedy available, namely s46 CCA review to SAT SAT recently rejected Field Deployment’s attempt to lodge its review out of time: SC Projects and Field Deployment [2015] WASAT 69. 13 DELMERE HOLDINGS PTY LTD -v- GREEN [2015] WASC 148 (24 April 2015) – – Sheds light on what will/will not constitute a “payment claim” and that adjudicator’s failure to properly deal with the evidence about whether a payment claim exists will be a jurisdictional error Strong support (obiter) for view that CCA for contractual entitlements only; no claims “outside the contract” 14 RATIO: PAYMENT CLAIM AND ERROR Revolved around VC17 VC17 stated: In accordance with … clause 34(d), we submit the costs of this Variation to the contract. Cl 34 was variation clause; provided for submission of variation costing information Clause 34 was separate to payment claim provisions which provided mechanism for how a variation was to be claimed K Martin J found mere submission of a document under GC34 could not be, and was not, a payment claim 15 RATIO: PAYMENT CLAIM AND ERROR (cont’d) Rejected contractor’s attempt to paint VC17 as a payment claim Further noted that contractor issued a formal invoice for VC17 after adjudication was lodged – that was the payment claim Adjudicator’s failure to have regard to that invoice was a jurisdictional error Adjudicator had misconceived his function by proceeding on erroneous basis that payment dispute existed 16 KUREDALE PTY LTD -v- JOHN HOLLAND PTY LTD [2015] WADC 61 (21 May 2015) – – – Leave to enforce case JHG made a payment before adjudication determination was handed down – it was argued that this was in partial satisfaction of the determination (related to the same head of claim) Keen DCJ accepted that was arguably the case but still granted leave to enforce based on the “pay now, argue later” purpose of the CCA 17 LAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD -v- SAMSUNG C & T CORPORATION [2015] WASC 237 – – – – Confirms Blackadder test for when a “payment dispute arises” (payment dispute can arise via a dispute before due date for payment passes) Extensive commentary/guidance on the role of the adjudicator under s31(2)(b) and when jurisdictional error can be established Also sheds further light on leave to enforce applications Appeal has been lodged 18 Samsung: s31(2)(b) and jurisdictional error Detailed commentary on adjudicator’s duties under s31(2)(b) Core duty is to determine CONTRACTUAL liability on BoP There must be, as an objective fact a PAYMENT CLAIM and a PAYMENT DISPUTE, each UNDER a construction contract Adjudicator’s opinion on those core matters is not conclusive and is open to review – matters must be objectively present If determination cannot be readily supported by analysis of contract, court will likely infer a jurisdictional error has occurred 19 FIRST DETERMINATION IN SAMSUNG Two adjudications. First was for ordinary progress claim which was never certified as contract was terminated. Second was for value of works up to date of termination. Mitchell J: contract did not support liability of Samsun to pay the progress claim. Contract had been terminated including progress claim/certification provisions (cl 37). Only contractual entitlement to payment then arose under a different clause (cl 39A). No other available conclusion. Adjudicator’s refusal to so find in accordance with contract supported inference that adjudicator was determining claim other than in accordance with the contract 20 SECOND DETERMINATION IN SAMSUNG This time adjudicator did have regard to clause 39A which provided for payments to LORAC where termination occurred Mitchell J: adjudicator nevertheless failed to go on and determine the meaning and operation of that provision Cl 39A required adjudicator to consider (1) whether LORAC’s payment claim exceeded the contract sum when aggregated with earlier payments (2) whether Samsung had any applicable set-off entitlements Adjudicator failed to make findings on those critical issues. This indicated adjudicator failed to comply with s31(2)(b) duty to make a contractual liability determination on BoP 21 Samsung: leave to enforce No leave to enforce as jurisdictional error established Further, no leave to enforce as His Honour was satisfied that the payment required to be made by the determination had in fact been made by Samsung 22 MODULAR FORMS PTY LTD and CECICH [2015] WASAT 76 (6 July 2015) – – – Confirms adjudicator’s ability to dismiss an application in part and determine the balance Confirms dismissed portion can be reviewed under s46 CCA Confirms SAT, on a review, cannot substitute its decision for the adjudicator 23 The take-away points from the 2015 cases Expansion of case law on (1) nature of adjudicator’s role in merits determination (2) ability to review a merits determination (3) leave to enforce Contractor’s entitlements must be rationally tied back to the contract Take care to fully consider and explore relevant contractual provisions Failure to do so will leave determination exposed to review Expect even closer scrutiny of merits determinations 24
© Copyright 2026 Paperzz