Milton E. Proby Parkway Construction Project Final Traffic Movement Ramp A Traffic Movement: Northbound Academy Blvd. Traffic to Eastbound Milton E. Proby Parkway. Ramp B Traffic Movement: Westbound Milton E. Proby Parkway Traffic to Southbound Academy Boulevard. E N RAMP A RAMP B RAMP E RAMP C Ramp D Traffic Movement: Westbound Milton E. Proby Parkway Traffic to Northbound Academy Boulevard and Drennan Road west of Academy Boulevard. Ramp E Traffic Movement: Eastbound Drennan Road to Eastbound Milton E. Proby Parkway April 2011 | BuildProby.com Ramp C Bridge is 85% Complete W RAMP D Ramp C Traffic Movement: Southbound Academy Blvd. Traffic to Eastbound Milton E. Proby Parkway. S Newsletter Know before you go ACADEMY BRIDGE Artist rendering of completed project. Your voice matters. Ramp C Bridge looking West PPRTA •Clyde Pikkaraine Project Manager City of Colorado Springs •Robin Kidder Acting City Engineer Ames Construction, Inc. •Sheryl Machado Project Information Manager Atkins •Jeff Klimek Senior Construction Manager Project Information Line 719-268-7430 Project Website BuildProby.com Construction crews are making great progress on the highly visible flyover bridge that will eventually take motorists traveling south bound on Academy Boulevard to east bound Milton E. Proby Parkway. The bridge will be completed this summer with all roadways open in late fall of this year. The bridge deck for the Ramp C bridge was poured on two separate dates. The first pour on March 29th took approximately 8.5 hours. Approximately 445 cubic yards of concrete were used to pour the first portion of the driving surface for the new bridge. The second pour took place on April 16th, taking 5 hours to complete, utilizing another 445 cubic yards of concrete. Now that the deck has been poured the next phase of constructing the bridge will begin. What Is Next? Ames will post-tension the bridge superstructure, which will strengthen the bridge to be selfsupporting. This will facilitate the removal of the temporary support structures that include the steel beams and wood posts that currently exist on Academy Boulevard and Drennan Road. At that time the height restrictions and narrowed lanes will be eliminated. This will help to ease traffic constraints currently in place. Work remaining to complete the bridge includes installing bridge rails, street lights, signs, striping and painting. Soffit excavation Proby Update Completed Winter Work: • Ramp E bridge deck has been poured • Traffic has been moved onto the new Academy Boulevard bridge • The FMIC siphon box and channel is complete and water is flowing • 85% of the concrete on the Ramp C bridge is poured • The south portion of Academy Boulevard is paved Anticipated Spring Work: • Construction of Ramp B under Ramp C will begin • Storm drain work on Ramp B will begin • Ramps A, B and C will be paved connecting to Milton E. Proby Parkway • Completion of the MSE walls on all bridges • Completion of the north and south Academy storm drainage ponds • Continue topsoil placement and seeding throughout the project • Continue Drennan Road Improvements • Complete work on Hancock Expressway • Build traffic signals at Hancock Expressway and Milton E. Proby Parkway • Utility relocations under Drennan Road Keep It Safe! The first week of April ushered in National Work Zone Awareness week. What can you do to keep it safe in our local work zones? • Never use a cell phone or text while driving • Stay Alert! Expect the unexpected • Slow down and don’t tailgate • Pay attention to signs • Obey the flaggers • Be patient and stay calm • Know the road rules for work zones Unfortunately, we have had several trucks attempt to maneuver the truck closure at Academy Boulevard and Drennan Road potentially jeopardizing the project, the safety of the structure, and the crews working above ground. The vertical clearance during this closure is 14 feet. Lanes were also narrowed to 9.5 feet. All truck traffic is being detoured to Hancock Expressway and Astrozon Boulevard during this closure. Your patience and cooperation is greatly appreciated as we finish this portion of the project. The Statistics • In 2009, 667 people were killed in motor vehicle crashes in highway work zones and more than 30,000 were injured. • About 85 percent of those killed in work zones are drivers and their passengers. • Distracted driving causes 25% of all traffic accidents. Local Cub Scouts Pack #110 Visit the Milton E. Proby Parkway Project Pipe Installation Almost Complete Pipe installation on the Milton E. Proby Parkway Project is almost complete. To date, 12,144 lineal feet, or 2.3 miles of storm sewer pipe has been installed from Powers Boulevard through Academy Boulevard. With only 1100 feet left to lay, the installation is now over 90% complete. Pipe installation is anticipated to be complete by the Fall of 2011. March 15, 2011 Jeff Klimek, Atkins Project Manager, Steve Lange, Ames Construction Superintendent, Ed French, Ames Construction Structures Superintendent, Gordon Lindvall, Atkins Inspector Pack #110 Members: Jackson Alston, Dane Birkeness, Lucas Debiase, Noah Desort, Christopher Haworth, Aidan Keenan, Will Louis, Dillon McElroy, Alex North, Hayden O’haver, Josh Suslow, Collin Tiemens, and Aidan Todorov. Hancock Pond and Drainage Structure Know Before You Go “Thank you for hosting a fabulous learning experience for our Cub Ames Construction is committed to keeping you informed Scouts on last Tuesday. The boys appreciate having all their questions Project Website: BuildProby.com | Project Hotline: 719-268-7430 | Project Email: [email protected] answered, and I know they liked talking with real engineers. The Scouts thoroughly enjoyed going outside and climbing on the bridge. The explanations given the boys while actually standing on the If you would like to be added to the project’s e-newsletter distribution list, sign up at the project website. No internet? Call the project hotline to request a copy via U.S. Mail.719.268.7430. structure made the complicated bridge planning process, as shown by the 1-inch thick sheaves of bridge plans you gave us, come to life. Through the kindnesses shown our boys by you and your team of experts, I am certain we also realized an increase in each Scout’s confidence in trying to understand complicated enterprises such as yours. Thank you for a great experience.” Lloyd M. Alston Cubmaster Pack #110 Interesting Milton E. Proby Parkway Factoids •To date, 1.8 million pounds of steel has been placed on the Milton E. Proby Parkway Project. This equates to same weight as 500 average passenger cars that will eventually travel over the new bridge. •To date, 7,370 cubic yards of concrete has been poured on the project. This equates to 30 miles of a 4 foot wide sidewalk. •To date, 1 million cubic yards of dirt has been moved. This equates to a 10 foot by 10 foot trench from Colorado Springs to Denver. The Fountain Mutual Irrigation Channel The Fountain Mutual Irrigation Channel (FMIC) relocation under S. Academy Blvd. was completed March 16th. Fountain Mutual provides water to fill the Big Johnson Reservoir which in turn services many different local shareholders. As part of the Milton E. Proby Parkway Project an agreement was developed between FMIC and the City of Colorado Springs to relocate a portion of the open channel and pipe crossing of Academy Boulevard. Ames Construction constructed the 25 feet deep siphon box in three phases while maintaining full traffic movements on north and southbound Academy Blvd. In all, Ames Construction crews placed 662 cubic yards of concrete to build the new channel and siphon box. FMIC tested the construction of the channel and siphon on April 7th. The relocation was a success and the water can now flow through this newly constructed portion of the channel. New FMIC Structure
© Copyright 2025 Paperzz