Update on FCPS Construction/Renovation Projects

Deep Springs Elementary -- Renovation

Architect:
EOP Architects

General Contractor:

GC Contract Sum:
$12,152,800

Total Project Cost:
$15,082,114

Change Orders to Date (3):

Scheduled Contract Completion Date:

% of Contract Completed:

Revised Completion Date per GC:
Griggs Enterprises
$60,916
December 2014
17%
January 2015
September 2013
Deep Springs Elementary -- Renovation
Rendering of Final Façade
September 2013
Deep Springs Elementary -- Renovation
Work
Completed to Date:

Continued with footings and foundation walls in the Phase 1 area.

Poured the slab in the gym and in the majority of the Decagon area.

Continued with masonry walls in the Phase 1 area.

Continued with underground storm line installation.

Installed gravel and concrete curbs at the new road and parking lot.
Current Work Effort (September):


Complete pouring the slab and installing CMU in the Phase 1 area.

Start brick installation in the Phase 1 area.

Install bar joists and decking in the Phase 1 area.

Start roofing the Decagon area.

Install the base course of asphalt for the new road and parking area.

Start footings and foundations at the Area A addition.
September 2013
Deep Springs Elementary -- Renovation
CMU on Decagon
Decagon – Slab
Decagon Mechanical Room
Gym – CMU & Door Frames
September 2013
Deep Springs Elementary -- Renovation
New Parking Lot
New Rear Entry
Retaining Wall
Area A Addition Graded
September 2013