Bridging the Gap Tedd Schoch, vice president of Technical Services, Aggregate Industries Mid Atlantic, and the rest of the WWBP consortium are proud of the tremendous work they’ve done over the past several months. Exceptional partnering and ingenuity conquer tough concrete pours over the Potomac. B for a total clearance of 70 feet at its highest point. This, according to the Woodrow Wilson Bridge Project, will allow for 70% fewer bridge openings. The deck will consist of 12 lanes, which accommodate eight general-purpose lanes, high-occupancy vehicle lanes, and merge lanes after the interchanges are built. Building the massive concrete foundations beneath the bridge deck is, of course, where the project started after the first contract to dredge 340,000 cubic yards of material was completed on Feb. 14, 2001. The second contract included the majority of foundation work for the bridge. The foundations include steel pipe piles that have a diameter range of 48 to 72 inches for river piers and Pier V-2, the first pier on the Virginia shore. The other Virginia piers include 24-square-foot prestressed concrete piles. The lengths of the piles vary from about 40 feet for the concrete piles to about 200 feet for larger steel pipe piles. Concrete pile caps were also included in the contract. Concrete production and placement logistics Tidewater Construction Corp./Kiewit Construction Co./Clark Construction (TKC) won the second contract as a joint venture. After numerous planning meetings, a joint venture consisting of TKC, Waldorf, Md.-based Chaney Enterprises, and Aggregate Industries Mid Atlantic division, Greenbelt, Md., was formed. Called Woodrow Wilson Bridge LLC, the group set about to make the plan for concrete production and placement a functional reality. The plan consisted of conveying material from an onsite plant to two barges, which then feed concrete to a rough-terrain Creter Crane equipped with a telescopic placement conveyor that extended 75 to150 feet. The onsite plant, a 12-cubic-yard Con-E-Co portable central mix plant rated at about 400 cubic yards per hour, was purchased by the joint venture. After the partnership ends, Aggregate Industries will purchase the plant from the group. Permitting the plant was relatively snag-free, EDWIN REMSBERG / GETTY IMAGES BY BILL WELGOSS y any measure, the construction of a new Woodrow Wilson Memorial Bridge to replace the older Wilson Bridge, built in 1961, marks one of the most important transportation projects in the country. The old bridge, originally four lanes, was designed to carry 75,000 vehicles a day over 20 years. Today, the 71⁄2 mile bridge carries nearly three times the traffic volume—nearly 200,000 vehicles a day on six lanes. The six-lane bridge connects Virginia and Maryland over the Potomac River via Interstate 95/Interstate 495 (the Washington, D.C., Beltway), which is an eight-lane highway. The narrower Wilson Bridge causes one of the worst bottlenecks in the United States. Goals of the new Woodrow Wilson Bridge Project, which also consists of new surrounding interchanges, are to ease congestion as well as to address community and environmental concerns and to represent a fitting tribute to President Woodrow Wilson. The final structure will be a drawbridge that stands 20 feet higher than the existing bridge, WOODROW WILSON BRIDGE PROJECT Material for the bridge was conveyed from an onsite plant to two barges to feed concrete to a rough-terrain Creter Crane. From there a telescopic placement conveyor extends 75 to 150 feet. as no building permit was required since the plant is portable and the land has been set aside by the state of Maryland. The environmental permitting, which included air and water, was essentially a formality as the plant discharged no process water. “The plant could certainly do 300some yards per hour, and we needed at least 250 cubic yards per hour. We never had a problem throughout the project,” says Tedd Schoch, vice president of Technical Services, Aggregate Industries Mid Atlantic. To stockpile cement, the group used five blimp storage systems, which each held as much as five loads of cement. Area around the plant allowed for stockpiling 3500 tons of the three necessary aggregate sizes—sand from Chaney Enterprises’ operation and gravel and stone from nearby Aggregate Industries operations. From the onsite plant, concrete is dumped into a 20-cubic-yard hopper, which feeds an inclined 30-foot conveyor that drops concrete to another 50-foot inclined conveyor to a transfer point. At the transfer point, the concrete flow changes direction nearly 45 degrees to a 100-foot conveyor, which feeds a 125-cubic-yard coneshaped hopper equipped with vibrators and agitators located at the shoreline. “We also set up separate backup conveyors for each hopper in case of a breakdown,” says Schoch. The shoreline hopper fed a 250-foot conveyor, which fed hoppers on two barges, which transported concrete to the pour (about 1 mile). These transfer barges were each equipped with 60-foot conveyors to feed the third barge equipped with a 125cubic-yard hopper, which supplied the crane equipped with the telescopic placement conveyor. Concrete temperature challenge Concrete placement was not the only challenge requiring a unique approach. Demanding concrete specifications, such as a placement temperature limit of 160° F, put quality control in the forefront. “It was very difficult to reach 160° F, as most large pours allow temperatures up to 170° F. Also, considering concrete can peak at 240 to 250° F in a solid mass, the specification required a sizeable temperature reduction,” says Schoch. Several strategies were incorporated to keep concrete temperature down, especially in the summer months when ambient temperatures would reach the mid-90s or higher. Starting at the concrete plant, Aggregate Industries tried to keep concrete temperature at 70° F. On the hottest days, that required as much as 1200 pounds of ice for each 10cubic-yard batch. Chillers were also installed on the plant to keep water at 40° F. The concrete mix also incorporated 75% Newcem slag cement to help control temperature. Other key admixtures used were a Type II high-range water reducer and retarders applied in hot weather to help to keep set times low and maintain slump. At point of placement, specifications required the center of the concrete placement to remain within 35° F of the concrete at the edge of the form. Cooling tubes were inserted to pump water through placed concrete to control temperatures. Insulation was also applied to the outside of the forms to keep the placed concrete within the 35° F range in cold weather. Air entrainment challenge Maintaining the specified 6% air in the concrete at the point of placement was another challenge given the concrete transport system. “The number of transfer points, with the concrete hitting a plate then falling a few feet into a hopper, really took the air out of the concrete,” says Schoch. In order to achieve concrete that met specifications at point of placement, Aggregate Industries needed to use an air entrainment admixture to add 2 to 21⁄2 times the amount of air (14 to 16% air) at point of production. “It was a scary ordeal because if too much air stayed in the concrete, strengths wouldn’t be very good,” says Schoch. Strength requirements for concrete were 6500 psi for the pedestal concrete, which provided the base for precast concrete placement for the superstructure; 4000 psi for the pilecaps; and 3500 psi for the tremies. Continuous pour challenge In all, 17 piers (each of consisting of a pedestal, pile cap, and tremie) have been built—11 in the river and six in Jones Point Park in Virginia. Pedestal pours for the bridge averaged 300 to 650 cubic yards as the bridge rose to the bascule—the drawbridge section. The pilecaps beneath the pedestals are 700 to 1500 cubic yards. The major challenge was providing continuous pours for the four massive foundations supporting the bascule. “Each large foundation required about 2000 cubic yards for the tremie, about 6000 EDWIN REMSBERG / GETTY IMAGES The Con-E-Co portable central mix plant, rated at about 400 cubic yards per hour, originally was purchased by the joint venture and will be bought by Aggregate Industries at the completion of the project. cubic yards for the pilecap, and 8000 to 8500 cubic yards of formwork,” says Schoch. Pours for the small foundations—each 300 to 400 cubic yards—took 3–6 hours. For the large pours, times were measured in days. “The last big pour for a pilecap for the bascule required almost 7000 cubic yards. We started on a Friday and finished Sunday morning,” says Schoch. In all, the bascule foundations required about 45,000 cubic yards of concrete. For the big continuous pours, keeping a steady supply of aggregate and cement was a concern. For the last 7000-cubic-yard pour, the plant beefed up aggregate stockpiles on Friday. On Saturday morning an independent trucking company replenished the stockpiles, which provided enough aggregate to complete the pour. Cement was also stockpiled as much as possible prior to the pour, and five cement tankers also parked onsite to replenish cement supplies in an emergency. Weather, especially wind, was always an unknown during the pours. A few times during the project, operations were stopped because of high winds. Because all the transfer hoppers were open, rain was also a concern. Pours were scheduled around weather forecasts, and in this respect, the group was relatively fortunate. Although the crews faced tough, wintry weather on some days, conditions never reached a point of compromising the large continuous pours. About a week before the project’s end, the onsite plant was dismantled, and the rest of the concrete supply duties were handled from offsite sources. Along with sampling concrete quality at the plant and at the point of placement, Aggregate Industries also periodically inspected concrete samples at each transfer point. A certain number of samples of hardened concrete were taken to a lab for petrographic analysis to ensure the concrete had the proper air entrainment. Given the number of variables, the number of rejected concrete loads was miniscule. “We had one barge rejected by the state, and it wasn’t even full,” says Schoch. “Our own group rejected other concrete loads, and we rebatched it ourselves. Because of time delays or slump concerns, we may have lost about 100 cubic yards of concrete throughout the whole job.” The smoothness of the operation prompted the project team to invite representatives from The Washington Post and The Baltimore Sun to observe two separate foundation pours, which resulted in positive press coverage. Attention to detail, cooperation from all parties, and great communication were the keys to the project’s success. Schoch is quick to say, “Everybody did a great job.” Meetings vital to success Key to the smooth operations, as well as the timely completion of the project, according to Schoch, were the continuous meetings throughout the project. State officials from Maryland and Potomac Crossing Consultants strongly promoted regular and frequent meetings among all parties involved—local, state, and federal transportation and environmental agencies as well as contractors and subcontractors. “These partnering meetings proved to be very valuable,” says Schoch. Representatives of all parties met twice at the beginning of the project, putting all concerns and grievances on the table before the project began. Meetings were then held every month in the early stages of the project, then every two months. “Before every foundation pour, a meeting was held,” says Schoch. “Even when the first foundation pour went well, the partnership still met to discuss issues concerning the next pour. Issues were put on the table immediately and resolved.” Initially the project was delayed a few months, so the partnering group expected to fall behind schedule. Now, as the job draws to completion, it will likely finish ahead of schedule. Additionally, milestones for the completion of each foundation were built into the contract with financial disincentives for missing these time markers. No milestones were missed throughout the project. Open communication fostered frequent meetings that likely played a big part in the overall efficiency of the project. For instance, the meetings, with all necessary parties in attendance, expedited blueprint approvals for each part of the project—an aspect of any large project that is notorious for causing delays. Success of Woodrow Wilson Bridge LLC bodes well for each partner for the subsequent bids to complete the other phases of this ambitious project. —WELGOSS is a freelance writer based in Frederick, Md. He has more than 10 years of experience covering the aggregates and construction materials supply industries. Publication #J03G028, Copyright © 2003 Hanley-Wood, LLC. All rights reserved
© Copyright 2026 Paperzz