FAQs – Neptune Transmission Interconnection Last

955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
FAQs – Neptune Transmission Interconnection
Last Updated 11/30/05
NOTE: This FAQ is a work in progress and will be updated when additional questions are
received or when answers are clarified or corrected. Please check for updates regularly for
the most up to date information. The latest updates are highlighted in red.
If you would like to have a question added to this list, please e-mail your questions to
[email protected]
1. What is a PJM Merchant Transmission Interconnection Request?
A. The PJM Transmission Grid provides the means for delivering the output of
interconnected generators to the load centers of the PJM energy and capacity markets.
As the Regional Transmission Organization (RTO), PJM administers the connection of
generators and new transmission facilities to the PJM Transmission Grid. In this role,
PJM coordinates the planning process for connection of new generation and/or new
transmission facilities, coordinates the reliability studies for operation of new generation
and/or new transmission facilities and oversees the construction of the required
Interconnection Facilities. As specified in Part IV, Subpart B, Section 41.1 of the PJM
Open Access Transmission Tariff (OATT), a party wishing “to interconnect or add
Merchant Transmission Facilities to the Transmission System, or to increase the capacity
of existing Merchant Transmission Facilities interconnected with the Transmission
System shall submit to the Transmission Provider a Transmission Interconnection
Request.” The Transmission Interconnection Request provides PJM with information
about the proposed Merchant Transmission Facility that is required to initiate appropriate
system reliability studies for connection of the new transmission facilities.
2. Who is required to request Interconnection with PJM?
A. All new generation and/or transmission facilities that plan to interconnect and operate in
parallel with the PJM Transmission Grid and participate in the PJM capacity and/or
energy markets (new generation or transmission and any existing generation or
transmission that is increasing capability to inject and/or withdraw by more than 1 MW
above that specified in its existing ISA or any Energy Only resources requesting Capacity
Interconnection Rights) must submit an Interconnection Request to PJM.
3. How is a Transmission Interconnection Request submitted to PJM?
A. To initiate an interconnection request, the project developer/owner must submit an
Interconnection Request to PJM in the form of a completed, executed Transmission
Interconnection Feasibility Study Agreement (OATT Attachment S) and a nonrefundable $10,000 study fee. Refer to PJM Manuals M-14-A & B for further details
about the Interconnection Request process.
DOC #312225
610.666.8980 | www.pjm.com
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
4. Why must developers of new Merchant Transmission and owners that are
upgrading existing Merchant Transmission facilities submit an Interconnection
Request to PJM?
A. The PJM RTO has the responsibility for planning the expansion and enhancement of the
PJM Transmission Grid on a regional basis. To ensure that the PJM Transmission Grid is
adequate to serve the PJM System load under all levels of load-serving conditions
requires planning for necessary and timely expansion of the PJM Transmission Grid. The
planned interconnection of new generating units and new Merchant Transmission
facilities and any changes (increases or decreases) in the output capability of existing
generating units or capability of existing Merchant Transmission facilities are among the
critical inputs to expansion planning for the PJM Transmission Grid. Based on all of the
requirements for firm transmission service on the PJM Transmission Grid, PJM annually
develops a Regional Transmission Expansion Plan (RTEPlan) to meet those
requirements. Thus, any entity that proposes to interconnect a generating unit or a
Merchant Transmission facility within any PJM region or proposes to change the capacity
of an existing generating unit or Merchant Transmission facility must request
interconnection rights from PJM.
5. What is the purpose of the Regional Transmission Expansion Plan (RTEPlan)?
A. The continuing evolution and growth of PJM’s robust and competitive regional market
rests on a foundation of bulk power delivery system reliability, ensuring PJM’s ongoing
ability to meet all of the regional load-serving obligations. PJM’s FERC-approved
Regional Transmission Expansion Planning Process (“RTEPProcess”) preserves this
foundation through independent analysis and recommendation, supported by broad
stakeholder input and approval by an independent RTO Board in order to produce a
single Regional Transmission Expansion Plan (“RTEPlan”). Refer to PJM Manual M14-B for further details about the RTEPProcess.
6. How long is the process to obtain PJM Interconnection approval for a Merchant
Transmission project?
A. Part IV of the PJM OATT describes the procedures used to process all requests for
interconnections with the PJM Transmission system. Part IV, Subpart B describes the
specific procedures used to process requests for Merchant Transmission facility
interconnections with the PJM bulk power transmission system. The OATT establishes
the business rules for the Merchant Transmission facility interconnection process. These
business rules include three analytical steps – Transmission Interconnection Feasibility
Study, System Impact Study and Transmission Interconnection Facilities Study. Each
step imposes its own financial obligations on the requesting party and establishes PJM
610.666.8980 | www.pjm.com
2
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
milestone responsibilities. Refer to PJM Manual M-14-B and its Attachment A flow
diagram for details and timeline of the study stages described below.
As the Transmission Provider, PJM, in coordination with any affected Transmission
Owner(s), conducts first stage Transmission Interconnection Feasibility Studies twice
each year (OATT at 41.2) for completion by:
• March 31, for requests received during the six-month period ending January 31, and
• September 30, for requests received during the six-month period ending July 31.
Thus, the initial Transmission Interconnection Feasibility Study stage could have a total
duration of as long as 8 months for requests submitted at the beginning of a particular
interconnection request cycle.
After reviewing the results of the Transmission Interconnection Feasibility Study, the
applicant must decide whether or not to pursue the second stage study, the System
Impact Study. To maintain its assigned priority, the applicant must execute and return
the System Impact Study Agreement within 30 days of receiving it. The System Impact
Studies are also conducted by the Transmission Provider twice each year (OATT at
41.4.1), commencing on:
• May 1, for requests received during the six-month period ending January 31, and
• November 1, for requests received during the six-month period ending July 31.
In general, System Impact Studies will be completed within 120 days of the date the
study begins. Thus, completion of the System Impact Studies could have a total duration
of as long as 5 months beyond the issue of the Transmission Interconnection Feasibility
Study results.
Upon completion of the System Impact Study, the Transmission Provider will furnish a
Transmission Interconnection Facilities Study Agreement to the applicant, along with the
estimated cost of the study and the estimated time of completion. After reviewing the
results of the System Impact Study, the applicant must decide whether or not to pursue
the third and final stage study, the Transmission Interconnection Facilities Study. For
an interconnection request to maintain its assigned priority, the applicant must execute
and return the Transmission Interconnection Facilities Study Agreement within 30 days
of receiving it. Thus, the total duration for completing the PJM Interconnection approval
process could be as long as 14 months plus the time required to complete the
Transmission Interconnection Facilities Study.
7. Are there any procedures or conditions available to expedite the process for
approval of a Merchant Transmission project?
A. Under certain circumstances, an applicant for a Transmission Interconnection Service
Agreement may wish to initiate project construction activities on an expedited basis prior
to completion of the Transmission Interconnection Facilities Study. One example of such
a circumstance is to request that orders be placed for equipment or materials that have a
610.666.8980 | www.pjm.com
3
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
long lead time for delivery. To initiate such an advance of construction activities, the
applicant may request execution of an Interim Interconnection Service Agreement (ISA)
for those construction activities being advanced. Such an Interim ISA would bind the
applicant for all costs incurred for the construction activities being advanced pursuant to
the terms of the PJM Tariff.
8. What information is developed and provided in the results of a Transmission
Interconnection Feasibility Study?
A. The Transmission Interconnection Feasibility Study assesses the potential reliability
impacts for new Merchant Transmission facilities connecting to the PJM system. The
study results provide a description of the exposures for network upgrade requirements,
define the general scope and duration of work needed to complete any identified system
upgrade projects and provide magnitude cost estimates for the identified system upgrade
projects. If applicable, the Transmission Interconnection Feasibility Study shall include a
preliminary estimate of the Incremental Deliverability Rights associated with the
proposed Merchant Transmission Facilities.
9. What are Incremental Deliverability Rights?
A. Incremental Deliverability Rights are the rights to the incremental ability, resulting from
the addition of a Merchant Transmission Facility, to inject energy and capacity at a point
on the Transmission System, such that the injection satisfies the deliverability
requirements of a Capacity Resource. Refer to PJM Manual M-14-E, Section 2 for
further details about Incremental Deliverability Rights.
10. What information is developed and provided in the results of a System Impact
Study?
A. The System Impact Study provides a thorough evaluation of the reliability impacts for
new Merchant Transmission Facilities connecting to the PJM system. The study reviews
both direct connection requirements and network impacts for the Transmission Rights
requested for interconnection of the new Merchant Transmission Facilities. The potential
impacts of interconnecting the new Merchant Transmission Facilities with the PJM
system are evaluated for compliance with various reliability criteria including operation
during Normal System, Single Contingency and Second Contingency conditions; System
Stability Analysis; Short Circuit Analysis; Generator Deliverabilty Analysis and
CETO/CETL Criteria Analysis. The study results include a project description and the
estimated cost for both the direct connection facilities and the network upgrade facilities
required for interconnection of the new Merchant Transmission Facilities with the PJM
system. When appropriate, the System Impact Study Report also defines the cost
allocation for the network upgrade work.
610.666.8980 | www.pjm.com
4
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
11. Is thirty days sufficient time to have all developers respond to the System Impact
Study results?
A. The timing of the studies and the decision windows were chosen as a compromise to
allow for information to be provided to the developer in a timely fashion, to proceed to
the design of facilities and the execution of Interconnection Service Agreements as
quickly as possible, and to develop the best possible regional plan that will meet the
needs that have been identified. The decisions that are made at the end of a System
Impact Study cycle will affect the start of the design phase for that cycle as well as the
start of the System Impact Study phase for the subsequent queue. If the decision window
is extended, the entire process must be stretched out to accommodate the additional time.
By receiving the Transmission Interconnection Feasibility Study results, the developer
should be in a position to begin to evaluate the viability of a project before the
completion of the System Impact Study. The thirty day window is a compromise that is
necessary to meet the varied objectives of the process.
12. What information is developed and provided in the results of a Transmission
Interconnection Facilities Study?
A. The Transmission Interconnection Facilities Study provides complete details of the
requirements for interconnecting a new Merchant Transmission project to the PJM
system. The study includes a general description of the new Merchant Transmission
interconnection project, indicates any changes from the System Impact Study Report,
describes the scope of both Direct Connection work and Network Upgrade work and sets
a schedule of major project milestone dates. The Transmission Facilities Study Report
also provides Design Descriptions of the facilities to be installed and a detailed cost
estimate of the work. The assignment of Transmission Injection and Withdrawal Rights
associated with new Merchant D.C. or Fully Controllable A.C. Transmission Facilities
will be made in accordance with Section 47 of the PJM Tariff and may depend upon the
capabilities of facilities and upgrades necessary to accommodate other Interconnection
Customers’ Interconnection Requests.
13. What are Transmission Injection Rights and Transmission Withdrawal Rights?
A. Transmission Injection Rights are the rights to schedule capacity and/or energy deliveries
at a defined Point of Interconnection between a Merchant Transmission Facility and the
PJM Transmission System. Capacity and/or Energy Transmission Injection Rights may
be awarded only to a Merchant D.C. or Fully Controllable A.C. Transmission Facility
that connects the Transmission System to another control area outside of the combined
PJM Region. Deliveries scheduled using Capacity Transmission Injection Rights have
rights similar to those under Firm Point-to-Point Transmission Service or, if coupled with
a generating unit external to the combined PJM Region that satisfies all applicable
criteria specified in the PJM Manuals, similar to Capacity Interconnection Rights.
Deliveries scheduled using Energy Transmission Injection Rights have rights similar to
those under Non-Firm Point-to-Point Transmission Service.
610.666.8980 | www.pjm.com
5
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
Firm Transmission Withdrawal Rights are the rights to schedule capacity and energy
withdrawals from the PJM Transmission System at a defined Point of Interconnection
between a Merchant Transmission Facility and the PJM Transmission System.
Withdrawals scheduled using Firm Transmission Withdrawal Rights have rights similar
to those under Firm Point-to-Point Transmission Service. Non-Firm Transmission
Withdrawal Rights are the rights to schedule energy withdrawals from a specified point
on the Transmission System. Withdrawals scheduled using Non-Firm Transmission
Withdrawal Rights have rights similar to those under Non-Firm Point-to-Point
Transmission Service. Firm and Non-Firm Transmission Withdrawal Rights may be
awarded only to a Merchant D.C. or Fully Controllable A.C. Transmission Facility that
connects the Transmission System with another control area outside the combined PJM
Region.
Transmission Injection Rights and Transmission Withdrawal Rights are available to
developers of Merchant D.C. or Fully Controllable A.C. transmission facilities only if the
developer has elected, pursuant to Section 41.1 of the PJM Tariff, to receive
Transmission Injection Rights and Transmission Withdrawal Rights in lieu of
Incremental Deliverability Rights, Incremental Auction Revenue Rights and Incremental
Available Transfer Capability Revenue Rights. Refer to PJM Manual M-14-E, Section 2
for further details about Transmission Injection Rights and Transmission Withdrawal
Rights.
14. What are Incremental Auction Revenue Rights?
A. Incremental Auction Revenue rights are the additional Auction Revenue Rights (as
defined in Section 1.3.1 of Attachment K to the PJM Tariff), not previously feasible,
created by the addition of new Merchant Transmission Facilities, or a new transmission
facility or upgrade resulting from the accommodation of an Interconnection Request
pursuant to Part IV of the PJM Tariff. Refer to PJM Manual M-14-E, Section 2 for
further details about Incremental Auction Revenue Rights.
15. What are Incremental Available Transfer Capability Revenue Rights?
A. Available Transfer Capability Revenue Rights (ATCRRs) are the rights of a
Transmission Owner to the revenues for Available Transfer Capability that is made
possible by the Transmission Facilities installed by the Transmission Owner.
Incremental ATCRRs are those additional ATCRRs, not previously feasible, created by
the addition of Merchant Transmission facilities, or a new transmission facility or
upgrade resulting from the accommodation of an Interconnection Request pursuant to
Part IV of the PJM Tariff. Refer to PJM Manual M-14-E, Section 2 for further details
about Incremental ATCRRs.
16. How are the increases and decreases in MW values for projects handled?
610.666.8980 | www.pjm.com
6
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
A. Any increase in the MW size of a project will not be accepted within the scope of the
existing queue position. Such changes must be submitted with a new Transmission
Interconnection Feasibility Study request.
Decreases in MW size for projects can be accepted in response to the results of either the
Transmission Interconnection Feasibility Study or the System Impact Study. Decreases
identified during the performance of either study will be accepted at the discretion of
PJM based on the impact to the work in progress.
17. When (time frame) will a Merchant Transmission project no longer be allowed to
reduce the size of its project?
A. Currently, we allow limited project reductions at all phases of the interconnection
process. A total reduction of up to 50% of the original project size is allowed after the
Transmission Interconnection Feasibility Study is issued but before the System Impact
Study Agreement is executed. A total reduction of up to the greater of 20% of the project
size considered in the impact study or 50 MW will be allowed after the Impact Study is
issued (PJM OATT, Part IV, Article 41.2A.2).
18. Is there a limit on the amount of MW increase that a project in the queue may
request?
A. Any increase to the MW size of a project will not be accepted within the scope of the
existing queue position. Such changes must be submitted with a new Transmission
Interconnection Feasibility Study request.
19. When will a complete dollar estimate for connection of each project be determined?
A. At the end of the System Impact Study, each of the projects in an equivalent queue will
know their cost responsibility (estimates) for interconnection to the transmission system.
These estimates will be based on the projects recommended by the RTEPP and the cost
allocations for each project. However, each project is ultimately responsible for costs
actually incurred to construct the necessary transmission upgrades.
20. For cost allocation, is money reimbursed to the first project by later projects in the
queue when they both impact the same facility? After a network facility is built for
a previous generator and/or Merchant Transmission developer, can a new generator
or Merchant Transmission project jump on the excess transmission capability
without expenditure?
A. When multiple projects in the same queue impact a facility, the cost allocation will assign
a portion of the upgrade responsibility to each project. This would not involve
reimbursement, per se. If a project in a later queue impacts a facility already identified as
requiring an upgrade, cost responsibility may be assigned to the later project. Refer to
PJM Manual M-14-B, Attachment B, for details about PJM Generation and Transmission
Interconnection Cost Allocation Methodologies.
610.666.8980 | www.pjm.com
7
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
21. How will the cancellation of projects that occur during the Transmission
Interconnection Facilities Study or even during construction of facilities be handled
as far as cost allocation and moving ahead with construction?
A. It is expected that some projects will drop from the queue during or after the Generation
and/or Transmission Interconnection Facilities Study phase. Depending on the progress
of construction of regional plan upgrades, significant costs may remain that must be
assigned to some party. Prior to construction, needs and cost responsibility will be
redetermined per section 41.7.3 (c) of the PJM Tariff. After the start of construction,
PJM will evaluate each situation, on a case by case basis, and make a determination as to
the most appropriate course of action.
22. Can a Merchant Transmission project be connected to more than one voltage at a
substation or more than one substation allowing the developer to decide which bus
to sell energy and capacity?
A. A Merchant Transmission project can be connected to more than one voltage level or to
more than one substation. However, if a parallel path is created for the system, that path
must be under the control of the Transmission Provider. The Merchant Transmission
developer cannot be in a position to create congestion on the system by opening facilities
under its control and then benefiting from that congestion through sales of transmission
service to bypass that congestion.
23. Can projects be in more than one cluster?
A. Yes, it is possible that a project can have impacts on two clusters based on a single
interconnection option while it does not make sense to combine all of the related
generators into one large cluster.
24. What is the definition of minimal upgrade costs?
A. A minimal upgrade is the next logical upgrade for a specific facility that would satisfy the
appropriate criteria tests imposed under the process.
25. What is an Interconnection Service Agreement for Merchant Transmission
Facilities?
A. After the Transmission Interconnection Facilities Study is completed, the Transmission
Provider (PJM) will furnish an Interconnection Service Agreement (ISA) to be executed
by the applicant and any affected Interconnection Transmission Owner(s). The ISA
defines the obligation of the Merchant Transmission developer regarding cost
responsibility and the expected dollar flows for required transmission system upgrades.
These dollar flows may be related to cost responsibility for facilities constructed for the
Merchant Transmission project or lower voltage transmission charges for projects
connected below the voltage level of the facilities recovered through the PJM Tariff. The
ISA also identifies the rights associated with the interconnection of the Merchant
610.666.8980 | www.pjm.com
8
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
Transmission Facility and any operational responsibilities, restrictions or other limitations
on which those rights depend. The ISA defines the Transmission Injection and/or
Withdrawal Rights of the Merchant Transmission project and quantifies the dollar flows
related to interconnection service. The ISA also defines the physical interconnection
between the Merchant Transmission facilities and the Transmission System and the
operational responsibilities associated with the interconnection. The ISA further
identifies any changes in construction responsibility from the Standard Option for
Transmission Owner Interconnection Facilities due to the Interconnection Customer
exercising the Negotiated Contract Option or the Option to Build. Further information on
all terms and conditions to be incorporated and made part of an ISA may be found in Part
IV of the PJM Open Access Transmission Tariff (Subpart B at 41.7, Subpart E and
Attachment O) available on the PJM website http://www.pjm.com/
26. What is a Construction Service Agreement for Merchant Transmission Facilities?
A. A Construction Service Agreement specifies the Terms and Conditions for the
construction of any Interconnection Facilities required to interconnect a Merchant
Transmission Facility with the PJM Transmission Grid. The Construction Service
Agreement is executed among the applicant for Transmission Service (Transmission
Interconnection Customer), the Transmission Provider and the affected Interconnection
Transmission Owner(s). The form of a Construction Service Agreement may be found in
the PJM Open Access Transmission Tariff as Attachment P. Further information on all
terms and conditions to be incorporated and made part of a Construction Service
Agreement may be found in Part IV of the PJM Open Access Transmission Tariff
(Subpart F and Attachment P) available on the PJM website http://www.pjm.com/
27. When will realistic time frames be developed for construction schedules?
A. During the System Impact Study, construction schedules will be evaluated considering
the scope of the regional plan. The schedules included in the System Impact Study
results should provide a more realistic view of the construction requirements for the
entire regional plan. The schedules will be more accurately defined in the Transmission
Interconnection Facilities Study.
28. How is a Schedule of Work developed to meet the in service date specified by the
Transmission Interconnection Customer?
A. The party(ies) responsible for installing the Transmission Interconnection Facilities
and/or Network Upgrade Facilities shall use reasonable efforts to install those facilities in
accordance with an agreed Schedule of Work. In the event that the responsible Parties
are unable to agree upon the terms of a Construction Service Agreement, the
Transmission Interconnection Customer shall have the right, but not the obligation
(“Option to Build”), to design, procure, construct and install all or any portion of the
Transmission Owner Interconnection Facilities.
610.666.8980 | www.pjm.com
9
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
29. What is the Option to Build?
A. The Transmission Interconnection Customer may choose to design and install all or any
portion of the Transmission Owner Interconnection Facilities if the Transmission
Interconnection Customer and the Interconnected Transmission Owner are unable to
agree upon the terms of a Construction Service Agreement. If the Transmission
Interconnection Customer chooses to exercise the Option to Build, the Interconnection
Parties must adhere to a timeline for various activities that require coordination among
the Interconnection Parties.
30. How does a Transmission Interconnection Customer exercise the Option to Build?
A. In order to exercise the Option to Build, the Transmission Interconnection Customer must
provide the Transmission Provider and the Interconnected Transmission Owner with
written notice of its election to exercise the option by no later than seven days after the
date that is 30 days after Transmission Interconnection Customer’s execution of the
Interconnection Service Agreement, provided, however, that the Transmission
Interconnection Customer and the Interconnected Transmission Owner may by mutual
agreement extend the time period for exercise of the option. Refer to Part IV, Subpart F,
Section 83.2.3 of the PJM OATT for further details about the manner and conditions
associated with the Option to Build.
31. At what point are dollars for system reinforcements due? How will the mechanism
for payment be established in the Interconnection Service Agreement?
A. In accordance with PJM OATT Section 41.5.2.1, PJM will invoice the Merchant
Transmission Developer on a quarterly basis for work to be conducted on the
Interconnection Facilities Study during the subsequent three months. The initial invoice
will be delivered prior to the start of work and shall be for the cost of work scheduled to
be completed during the first three months after work commences. However, alternative
arrangements may be negotiated between the Merchant Transmission Developer and the
Transmission Owner(s) responsible for the construction and such arrangements are
included in the Interconnection Service Agreement.
32. If projects further back in the queue are ready to come on line ahead of projects
sooner in the queue, when will it be determined whether those earlier queued
projects will stay on course or not be built?
A. Milestones will be included in Transmission Interconnection Facilities Study Agreements
and Interconnection Service Agreements to ensure that projects continue to demonstrate
progress toward their ultimate completion. There are no guarantees that any project will
ultimately be completed, regardless of how far they have proceeded in the process.
33. What if a project is delayed? What are the obligations of the project?
A. Milestones will be negotiated in both the Transmission Interconnection Facilities Study
Agreement and the Interconnection Service Agreement. If a project is delayed, the tariff
610.666.8980 | www.pjm.com
10
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
allows the Transmission Provider to extend milestone dates in the event of delays not
caused by the Interconnection Customer. Other failures to meet milestone dates will
result in the removal of the associated project from the interconnection queue. Any
project so removed from the queue is still responsible, under the tariff, for costs incurred
prior to removal from the queue.
34. Who will schedule outages for construction?
A. Scheduling of transmission outages for construction will be coordinated through PJM.
35. Can a "regulated utility" build a Merchant Transmission project in the service
territory of another "regulated utility"?
A. That determination is primarily a regulatory one. We believe that any entity can initiate a
Merchant Transmission project, including another "regulated utility", however that
regulated utility could not include the cost of such a Merchant Transmission project in its
regulated rates for its "home" service area. Such cost treatment must be treated
independently, possibly through an unregulated subsidiary.
36. Does a "regulated utility" have the right of "first refusal" if another entity wants to
build a Merchant Transmission project within the service territory of the
"regulated utility"?
A. We believe that the initiator of a Merchant Transmission project owns the "right of first
refusal". However, for economic expansion projects defined by PJM, if no Merchant
party has come forward to initiate such reinforcement, it is expected that the "home"
regulated utility would be offered the "right of first refusal”.
37. What if a Merchant transmission project, in addition to providing the intended
economic benefit, also provides a "reliability" benefit? How is the cost of the
"reliability benefit" allocated? Does it matter whether or not the Merchant
transmission project functionally replaces a "planned" or an "unplanned"
reliability project?
A. We believe that the value of the reliability benefit would be allocated as a "credit" to the
developer of the Merchant project for reliability projects included in the regional
transmission expansion plan as approved by the PJM Board. For unplanned reliability
projects, no "credit" would be allocated to the developer.
38. What type of transmission service do I need to schedule transactions over a
merchant transmission HVDC facility?
A. PJM presently sees the transmission service requirements unfolding in two components:
1)
Subscription for transmission service over a HVDC merchant facility itself.
Assuming that the facility developer/owner has elected transmission injection
and withdrawal rights instead of possible ATC rights, the 'transmission
610.666.8980 | www.pjm.com
11
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
service' over the facility would be scheduled according to the
developer/operator’s "open season" subscription, regardless of which RTO
retains operational control of the HVDC merchant facility.
2)
Transmission service from the source(s) in PJM to the HVDC terminal in
PJM. The transmission customer can choose either point-to-point
transmission service or network transmission service, depending on their
respective circumstances. See response to 44 below regarding those
circumstances under which network service may be used to serve external
load.
39. PJM has indicated that once TWRs are granted for a HVDC cable project, the cable
becomes eligible for either Network Service or Point-to-Point (PtP) Service. What
are the requirements to utilize network service for capacity and energy sales from
PJM to an external region in the context of HVDC cable project(s)?
A. Only Point-to-Point Service is available for service or sales to non-designated loads. The
only exception that provides for use of Network Service is for a Network Customer that
requests transmission service for load outside of PJM and elects to include its entire load
as Network Load for all purposes (PJM OATT, Part III, Article 31.3). Also, see response
to question 44.
40. Strictly in terms of reliability, what are the tradeoffs between Firm PtP and
Network Service? Does Firm PtP offer additional reliability benefits for the
entitlement holder of the cable’s TWRs?
A. There are no reliability differences between Firm Point-to-Point and Network Service.
41. What, if anything, needs to be done to “match” PtP service with the TWRs obtained
by the merchant HVDC project?
A. To “match” PtP transmission service with the TWRs, PtP service must be requested
between each source node and the TWR sink node terminal of the HVDC project.
42. If an entity were to hold Firm PtP to a generator with whom a bilateral
arrangement were in place but the generator were unavailable, would that entity be
permitted to transport energy from a PJM Spot Market Hub to the cable injection
point on a firm basis? If not, why not?
A. Yes, the seller of the bilateral arrangement has inherent spot market back-up. In the case
of a PJM Maximum Emergency (capacity deficiency), exports using firm transmission
service may be curtailed unless sourced from a de-listed generator (a generator from
which the capacity is not designated to serve PJM load).
If the service was intended to serve PJM non-zonal load, it would be Network Integration
Transmission Service (NITS) subject to load deliverability requirements.
610.666.8980 | www.pjm.com
12
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
This service has equivalent priority to Firm Point-to-Point transmission.
43. Is Firm PtP service applicable when more than one source of energy is contemplated
under a bilateral contract?
A. Yes, if Point-to-Point service is used to deliver from resources designated to serve
external non-PJM load, a Point-to-Point reservation with a source of the designated
resource is required for each resource.
44. Which type of service (Network vs. Firm PtP) would be applicable in the case where
an entity enters into a call option arrangement under a defined indexed value with a
generator in PJM, thereby providing that entity with the ability to procure energy
from the bulk power market during lower cost hours and/or when the unit is
unavailable?
A. A customer can use network service for external load that is included as PJM network
load. In this case, the customer must designate network resources to support the load. A
customer must use firm point-to-point service for load that is excluded from PJM
network load. Section 31.3 of the OATT, Network Load Not Physically Interconnected
with the Transmission Provider states:
This section applies to both initial designation pursuant to Section 31.1 and the
subsequent addition of new Network Load not physically interconnected with the
Transmission Provider. To the extent that the Network Customer desires to obtain
transmission service for a load outside the Transmission Provider’s Transmission
System, the Network Customer shall have the option of (1) electing to include the
entire load as Network Load for all purposes under Part III of the Tariff and
designating Network Resources in connection with such additional Network Load, or
(2) excluding that entire load from its Network Load and purchasing Point-To-Point
Transmission Service under Part II of the Tariff. To the extent that the Network
Customer gives notice of its intent to add a new Network Load as part of its Network
Load pursuant to this section the request must be made through a modification of
service pursuant to a new Application.
45. For a scenario where a party pays to reinforce the PJM System to fulfill the TWR
requested in the System Impact Study (SIS) and also procures Firm PtP, is it correct
that such party pays the greater of the annualized cost of the system improvements
or the Firm PtP charge, but not both. Also, does this provision apply if the party
elects Firm PtP rather than Network Service?
A. The above interpretation is correct with respect to the upgrades required for PtP or
Network Service, but doesn’t apply to the upgrades required for the TWR . The test
applies to both Firm Point-to-Point Service and Network Service, to the extent that
Network Service is applicable (See response to 38 and 44 above regarding applicability
of Network Service).
610.666.8980 | www.pjm.com
13
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
46. If a merchant HVDC project obtains TWRs and not TIRs, can energy be imported
into PJM on a non-firm basis when market conditions warrant?
A. No. PJM’s business practices allow Firm service to be rescheduled on any other path on
a non-firm basis (non-firm secondary service). However, the Neptune tie is
unidirectional out of PJM.
47. What has been the historical frequency and duration of curtailments for
transmission customers who have contracted for Non-Firm PtP Service in PJM?
Can an entity obtain historical information regarding the quality of Non-Firm PtP
service? Are there any forecasts or other analysis regarding quality of non-firm
transmission service in PJM?
A. PJM Performance Department can gather statistics, that can, by Transmission type,
provide the capacity reserved, the amount scheduled, and the amount curtailed on an
hourly basis. These statistics could be processed for something a little less granular. It
will take 2-3 days to gather and process the data. PJM may charge for the service to
provide historical data. There are no forecasts regarding the future quality of non-firm
transmission service in PJM.
48. What is the procedure for interrupting customers with Non-Firm PtP Service?
What are PJM’s notice requirements for curtailments? What is the procedure and
service classification priority for interrupting or curtailing transmission customers?
Are all Non-Firm transmission holders interrupted or curtailed on an equiproportional basis? If no, how are such interruptions or curtailments performed?
Is duration of service a factor? If so, how? Does shorter term Firm PtP have the
same status as monthly or annual Firm PtP? Are affected shippers interrupted or
curtailed on a coincident basis?
A. A full description of curtailment priority can be found in Chapter 2, Energy Scheduling,
of the PJM Regional Practices and Business rules located at
http://oasis.pjm.com/rpdoc.html. Notice requirements are a function of system conditions
and the urgency to curtail. The curtailment would occur at the next practical schedule
change point. Only service that adversely affects the system constraint would be
considered as a candidate for curtailment by service type, willingness to pay congestion,
duration and timestamp.
For FIRM, curtail schedules that effectively relieve the constraint, proportionally among
Native Load customers, Network customers and customers taking Firm Point-to-Point
transmission service. (NERC Transmission Bucket 7). (Chapter 2, Energy Scheduling,
of the PJM Regional Practices and Business rules located at
http://oasis.pjm.com/rpdoc.html).
49. Along a specific transmission path, there may be multiple parties that are
transporting through a constrained flow gate, but only a single entity using a
610.666.8980 | www.pjm.com
14
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
specific transmission path. Is the curtailment performed on all paths through the
constrained flowgate?
A. Curtailments are flowgate based. Any transaction adversely impacting the constrained
flowgate or system element is a candidate for curtailment regardless of the path being
utilized.
50. What are the differences in scheduling protocols / requirements between Firm PtP,
Non-Firm PtP, and Network Service?
A. Table 1.6 of the Regional Practices and Business Rules. – Transmission Service
Submittals, (located at http://oasis.pjm.com/rpdoc.html) defines the submittal times and
response times for reservation types. Energy scheduling is done on a first come first
serve basis.
51. We understand that hourly Non-firm PtP is currently offered at a discounted rate of
$0.67/MWh. Please confirm. How is the discounted Non-Firm PtP rate derived?
A. The current discounted rate for all Non-Firm service is $0.67/MWh. For rate
determination, see PJM Tariff, Schedule 8, Non-Firm Point-to-Point Transmission
Service (http://www.pjm.com/documents/downloads/agreements/tariff.pdf) and PJM
Regional Practices and Business Rules, Section 1.13, PJM Non-Firm Pricing and
Discounting Policy (http://oasis.pjm.com/rpdoc.html). Additionally, there is an
Allegheny Power transitional market expansion charge (TMEC) with a rate of
$0.33/MWh collected for each reservation. See PJM Tariff, Schedule 8, Item 7 Transitional Revenue Neutrality Charge.
52. Is the discounted Non-firm PtP applied on a reservation basis or volumetrically?
A. The discounted Non-Firm Point-to-Point is assessed on a reservation basis according to
the MW of capacity reserved (excluding PJM curtailments). There is no additional
discounting for volume considerations.
53. How does the expansion of the PJM “footprint” affect the pricing of Non-Firm PtP?
Under what circumstances would the pricing of Non-firm PtP significantly change
over the next two years?
A. It was expected that the non-firm rate would increase after Market Integration, but to date
the non-firm rate remains at $0.67.
54. To the extent requests for Firm PtP increase so that the Available Transmission
Capability (ATC) declines to zero, can any change in the Non-Firm PtP rate
discount be expected?
A. No discount change would be expected. Participants can continue to purchase non-firm
point-to-point willing to pay congestion service if ATC is zero. See question 58.
610.666.8980 | www.pjm.com
15
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
55. Are transmission rights tradable / assignable? Does OASIS facilitate a secondary
market for transmission rights? For example, if an entity procured long-term Firm
PtP, could that entity repost its transmission rights for specific hours for assignment
to a third party? If yes, could the entity procure Firm / Non-Firm PtP service as
available on a secondary market?
A. Transmission rights are tradable / assignable. PJM would not act as an agent, but would
facilitate the entity’s arrangements with a third party. The entity could procure
transmission service on a secondary market. OASIS does not currently facilitate a
secondary market, but any resulting resales will be posted on the OASIS.
56. Once firm service is purchased, can PJM’s ATC calculations alter service
availability?
A. Section 2.2 of the PJM OATT discusses reservation priority for existing firm service
requests. Requests for long term service (one year or longer) have rollover rights.
Section 2.3 of the PJM OATT describes the procedures for exercising transmission
reservation priority rights. Customers with long term service have the right of first
refusal (2.2.a). Rollover rights are assumed to be exercised for the purpose of ATC
calculations.
Section 13.2 of the PJM OATT discusses reservation priority for new firm service
requests. If the Transmission System becomes oversubscribed, Long-Term Firm PointTo-Point Transmission Service or Network Integration Transmission Service may
preempt requests for monthly transmission service up to two months before the
commencement of monthly service. Otherwise, requests for longer term service will not
preempt requests for shorter term service.
57. Does PJM sell firm transmission rights up to the TTC of a specific pathway?
A. PJM does not sell transmission service rights up to TTC. TRM and CBM margins, where
appropriate, are maintained for system reliability - See PJM Manual for Transmission
Service Requests (http://www.pjm.com/contributions/pjm-manuals/pdf/m02v07.pdf).
58. Can Non-Firm PtP be made available even if ATC = 0 MW? How is the quantity of
Non-Firm PtP available service determined? Specifically, is the amount of NonFirm PtP a margin above the TTC, or, a derived % of the TTC that is not available
to Firm PtP and/or Network service requests?
A. Non-Firm Point-to-Point is available even if ATC is zero, as long as the willing to pay
congestion flag is set to yes. The amount of Non-Firm Point-to-Point willing to pay
congestion is not determined. Non-Firm Point-to-Point is curtailable under Emergency
Procedures for reliability, until that point additional charges associated with redispatch
are used to manage congestion and maintain schedules. The customer can curtail the
transaction at any time to avoid the congestion charges associated with continued
redispatch for delivery. See section 2, Available Transfer Capability of PJM Manual 2:
610.666.8980 | www.pjm.com
16
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
Transmission Service Requests (http://www.pjm.com/contributions/pjmmanuals/pdf/m02v07.pdf).
59. Can PJM provide a history of the ATC for a given pathway or flowgate?
A. PJM Performance Department may be able to provide some statistics on Path ATC. PJM
may charge for the services to gather the data, if not readily available.
60. Can PJM provide a history of Non-Firm service made available and/or
approved/disapproved?
A. PJM Performance Department can gather statistics, that can, by Transmission type,
provide the capacity reserved, the amount scheduled, and the amount curtailed on an
hourly basis. These statistics could be processed for something a little less granular.
There may be a charge to the customer to obtain this information.
61. The System Impact Study (SIS) process can represent a maximum of 105 days to
receive PJM’s response to the SIS request. What is the average turnaround?
A. You should plan on response within tariff requirements.
62. ARRs are provided upon request to entities seeking Firm PtP or Network Service.
Is there any reason not to request ARRs?
A. An ARR is defined by a source point, a sink point and a MW quantity. The economic
value of an ARR is the ARR MW amount times the difference between the ARR Sink
LMP minus the ARR Source LMP where the LMPs are clearing prices derived from the
Annual FTR Auction. If the Sink LMP is less than the Source LMP, then the ARR is an
economic liability to the ARR holder.
63. Please explain the process for allocation of FTR revenues among ARR holders.
A. An ARR is defined by a source point, a sink point and a MW quantity. The economic
value of an ARR is the ARR MW amount times the difference between the ARR Sink
LMP minus the ARR Source LMP where the LMPs are clearing prices derived from the
Annual FTR Auction. Annual FTR Auction revenues are distributed to ARR holders in
proportion to each ARRs economic value.
64. Can the holders of FTRs bid in the associated FTR auctions? If so, does PJM’s
market mitigation enforcement restrict bidding parameters?
A. FTR holders can bid into the Annual FTR Auction. There are no bidding parameter
restrictions, but the Market Monitor Unit does monitor for market manipulation.
65. The PJM Billing Manual (M-29), p. 10, under the Transmission Congestion Charges
bullet, references “explicit” and “implicit.” Please define “explicit” and “implicit”
transmission congestion charges.
610.666.8980 | www.pjm.com
17
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
A. Explicit congestion charges apply to the buyer of a bilateral energy transaction where the
source differs from the sink. They are calculated as transaction MWh times the
difference in price between the sink and the source. Implicit congestion charges reflect
the moving of energy generated or purchased to where it was consumed or sold within
each customer account. It is calculated by subtracting the amount already paid for spot
market energy at an average rate from a locational net energy bill where all energy
injections and withdrawals are priced at the applicable bus price. More information on
this can be found in the PJM Operating Agreement Accounting Manual.
66. In order to complete their due diligence effort, can an entity have access to PJM’s
eTools that are available to PJM members through the PJM site? If so, what
administrative requirements are needed to facilitate data exchange?
A. PJM Transmission Customers have access to the PJM OASIS for the purpose of
requesting transmission service. PJM membership is required for access to other PJM
eTools for participation in the PJM market. Instruction for use of eTools is provided at
the time membership or transmission service is approved.
67. Is the selection of Incremental Deliverability Rights (IDRs), Incremental Auction
Revenue Rights (IARRs), and Incremental Available Transfer Capability Revenue
Rights (IATCRRs) over TIRs and TWRs an actual option if an entity were to inject
power into the proposed PJM node for a HVDC cable?
A. In accordance with PJM OATT Section 48.1.1, an Interconnection Customer (a) that
interconnects Merchant D.C. Transmission Facilities with the Transmission System, one
terminus of which is located outside the PJM Region and the other terminus of which is
located within the PJM Region, and (b) that will be a Merchant Transmission Provider,
shall not receive any IATCRRs with respect to its Merchant D.C. Transmission Facilities.
Thus, there are no IATCRRs available to the Neptune project.
68. Are IATCRRs valued based on PtP service or Network service?
A. See response to question 67. There are no IATCRRs available to the Neptune project.
69. Can the IATCRRs be sold through the PJM OASIS, or are they sold through a
separate open-access system?
A. See response to question 67. There are no IATCRRs available to the Neptune project.
70. The IARRs are rights to the revenues with incremental FTRs associated with the
system improvement. Which zones or nodes are represented in the relevant FTRs?
A. Incremental ARRs may be requested between any two points for which PJM calculates a
price.
610.666.8980 | www.pjm.com
18
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
71. Are the IDRs specific as to the location of the deliverability right? That is, we
assume that IDRs could not be resold to a generator interconnecting at another
node. Is that accurate?
A. Yes, IDRs are for a specific location. They could be resold to a generator interconnecting
at another node; however the amount of IDRs could be decreased based on the injection
impact at the new site relative to the original location.
72. How do the ARRs provided through ownership of Firm PtP service and IARRs
offered through system build-out interact? Are they additive?
A. ARRs are allocated annually, subject to feasibility, to firm transmission service
customers through a two-stage Annual ARR Allocation process. Incremental ARRs are
allocated to those paying for system upgrades. Incremental ARRs have a life-span of 30
years or the life of the upgrade whichever is less.
73. Does PJM have a projection of ancillary charges, including transition charges, going
forward?
A. PJM has no such projection. Historic ancillary rates are posted on the PJM Website
under Market Settlements.
74. How are Transitional Revenue Neutrality Charges calculated?
A. Transitional charges are derived at the discretion of the entities responsible for their
determination. There is no set procedure. Typically, the transmission owners calculate
the amount of revenues being lost due to integrating with PJM and allocating it monthly
to network load customers.
75. If an entity were to resell the energy procured at the generator bus – before carriage
across transmission wires – do the transmission charges, losses, and ancillary
charges apply?
A. The party responsible for the transmission charges is subject to the agreement of sale. If
not specified, the default party for the transmission service charges would be the party
taking delivery (load).
76. PJM currently calculates losses based on 3% of system prices during peak hours
and 2.5% of system prices during off-peak hours. Our understanding is that PJM is
contemplating changing that mechanism to a marginal loss-based system. Please
comment on the likelihood and timing of a change in the loss calculation
mechanism.
A. Losses are 3% and 2.5% of scheduled energy, respectively, and billed at the system price
at the time of occurrence. The earliest possible date to implement marginal losses is
June, 2006. See response to question 91.
77. What Transmission Paths will be offered?
610.666.8980 | www.pjm.com
19
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
A. The POR will be PJM, and the POD will be NYIS.NEPTUNE or something similar. The
POD would be restricted to only those market participants eligible to schedule across the
Neptune Line. It has not been determined as of yet when this POD would be created.
The source can be any pricing point within the PJM market and the sink will be
Sayerville.
78. How will transactions across the Neptune Line be Tagged?
A. The format of the NERC Tag across the Neptune Line will be dependant on whether
Neptune acts on its own behalf as a transmission provider or not. The two examples
below reflect the possible tag scenarios.
CA
PJM
TP
POR
POD
SE
PJM
“Neptune”
NYIS
PJM
PJM
“Neptune”
PJM.Neptune
NYIS
NYIS
NYIS
NYIS
Example 1: Tag Example with Neptune as its own TP
CA
PJM
TP
POR
POD
SE
PJM
NYIS
PJM
PJM
NYIS.Neptune
NYIS
NYIS
NYIS
Example 2: Tag Example with Neptune NOT its own TP
In both examples, the POD on the PJM TP line would identify the transaction as a “Neptune”
transaction for appropriate validations.
Note: (CA = Control Area, TP = Transmission Provider, POR = Point of Receipt, POD =
Point of Delivery, SE = Scheduling Entity).
79. Who will PJM verify transactions with?
A. PJM will verify transactions with the NYISO.
80. How will transmission across the Neptune Line be procured?
A. Purchase of transmission on the PJM OASIS, Neptune OASIS (if Neptune facilitates its
own OASIS node, otherwise, transmission would be procured on the node of the entity
with which Neptune contracts for this service) and the NYISO OASIS (via HAM/DAM
bid).
610.666.8980 | www.pjm.com
20
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
81. Will there be any additional charges to customers based on the operation of a DC
Tie?
A. As of this time, we are not aware of any additional premiums that would be charged for
using the line beyond what is included in the Neptune Tariff.
82. When is the actual construction date? When is the completion date?
A. Estimated in service date is June, 2007.
In accordance with PJM OATT Section 80.1, the Effective Date of a Construction
Service Agreement shall occur upon the latest of the following: (i) the execution of an
Interconnection Service Agreement among the Construction Parties; (ii) the execution of
the appropriate Construction Service Agreement by the Construction Parties; (iii)
acceptance by the FERC of such Construction Service Agreement; and (iv) the
Interconnection Customer’s delivery of Security to the Transmission Provider, provided,
however, that if the Construction Service Agreement is filed unexecuted, the Effective
Date shall be the date specified by the FERC.
For construction to be performed by the Interconnection Customer in accordance with
PJM OATT Section 82.3, Construction by the Interconnection Customer may begin prior
to execution of a Construction Service Agreement at the Interconnection Customer’s sole
risk, cost and expense.
The Construction Service Agreement shall continue in full force and effect from the
Effective Date until termination thereof pursuant to PJM OATT Section 94. In
accordance with PJM OATT Section 94.1.1, The Construction Service Agreement shall
terminate upon the later of the following: (i) completion of construction of all
Interconnection Facilities and/or Merchant Network Upgrades; (ii) transfer of title under
Section 85 of the PJM OATT; (iii) final payment of all Costs due and owing; and (iv) the
delivery to the Interconnected Transmission Owner of final “as-built” drawings of any
Interconnection Facilities and/or Merchant Network Upgrades built by the
Interconnection Customer.
83. Who at PJM can be contacted regarding the Neptune Project? In other words, who
is the PJM Client Manager?
A. PJM Client Manager Lauren Andersen is the contact person for this project (610-6668867).
84. Does or will the Sayerville Terminal have a POD on the PJM OASIS?
A. No, but PJM will create a Sayerville Sink.
85. If PJM and NY create a RTOR agreement that would eliminate transmission costs,
would this agreement apply to the use of the Neptune Line?
610.666.8980 | www.pjm.com
21
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
A. This information is not available at this time.
86. Which ISO – NY ISO or PJM -- will control the operation of Neptune, including
transmission reservation - OASIS, energy scheduling/tagging, energy dispatch etc.)?
• What are the applicable rules?
• Has PJM confirmed the operational rules with the NY ISO?
• If the rules are not “final”, what is the process for finalizing them?
A. It has not been determined as of yet which entity will control operation of the Neptune
Line. An operating protocol will be developed between the NYISO and PJM on how the
operation of Neptune will be handled. Standardized rules in NERC policy will determine
the procedures.
87. It is our understanding that LIPA will only hold transmission rights from PJM to
NYISO (one-directional) on the Neptune Cable, is this correct? Are there open
rights in the opposite direction, and what are proposed tariff rates for such rights?
A. Neptune has requested withdrawal rights. No injection rights have been requested and,
therefore, there are no open rights in the opposite direction. A DC line can operate in
both directions but only one direction at a given time.
88. Please confirm that the Sayreville, NJ interconnect point will be a separate price
point for transfers into NY ISO (i.e., this point will not be averaged with the existing
interface pricing point for transactions that go into NY ISO).
A. Yes, this will need to be a separate price point and not aggregated with the existing NYIS
point.
89. We understand that the Retail Access Working Group is analyzing potential
implications of including marginal losses in the LMP calculation.
• Is there any available analysis available at this time?
• Also, are we correct that the RAWG intends to request a go/no go
direction from the Market Implementation Committee in September
2005, and that the earliest date for implementation would be June
2006?
A. All available analysis is posted on the MIC Website. The earliest possible date is June,
2006, and this date is subject to MIC and EMC approval. See response to question 76.
90. What is the status of PJM's approval of Neptune's interconnection request?
A. In accordance with the FERC Order issued on February 10, 2005 in Docket EL05-48000, Neptune has been provided with an Interconnection Service Agreement for the
Neptune project. The Facilities Study work has been initiated with an expected
completion date of April 8, 2005.
91. What concerns does PJM have regarding the Neptune project?
610.666.8980 | www.pjm.com
22
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
A. Those concerns that the interconnection will satisfy all of the applicable reliability
criteria.
92. What concerns does PJM have regarding the interface with NY ISO?
A. PJM has not operated a DC tie line with any neighboring control areas to this point. Any
concerns that PJM has regarding the interface with the NYISO will be addressed during
the joint operating committee on this subject. See answer to question 86.
93. The responses to questions 38 and 44 seem to apply to load serving entities. If the
capacity in question would be de-listed from the PJM market; for the bilateral sale
of de-listed installed capacity from the owner of generators located in XXX territory
and XXX territory to a wholesale counter-party located in New York, over
the Neptune cable, would any PJM Transmission Service be required?
A. The responses to questions 38 and 44 apply to any entity for the delivery of energy from
source(s) within PJM to the Neptune terminal in PJM.
94. If PJM Transmission Service is not currently required for such capacity
transactions over the Neptune Cable, will it be required in the future if Locational
ICAP is implemented in PJM?
A. PJM Transmission Service is required for all energy transactions from source(s) within
PJM to the Neptune terminal in PJM, with or without Locational ICAP.
95. If PJM Transmission Service is required for such capacity transactions over the
Neptune Cable, why are these transactions treated differently than current capacity
sales between PJM and rest-of-state New York, for which no PJM Transmission
Service must be purchased?
A. The above statement is not correct about transactions being treated differently. Current
capacity sales between PJM and rest-of-state New York do require PJM Transmission
Service for deliveries from the capacity source(s) within PJM to the PJM Border. There
is no difference in the treatment of deliveries to the PJM Border and deliveries to the
Neptune terminal in PJM.
96. If Point-to-Point Transmission service is required, would it be the rate for the
"Border of PJM" Point of Delivery, or the rate for the applicable Zonal Point of
Delivery?
A. The Point-to-Point Transmission Service rate is the same for deliveries to the PJM
Border and to the Neptune terminal in PJM. The applicable Zonal Network Rate (the rate
for the PJM Zone in which the Neptune terminal is located) would only apply for the
specific circumstance described in the response to question 44 (a Network Customer that
elects to include its entire load, including the sale, as Network Load for all purposes).
610.666.8980 | www.pjm.com
23
955 Jefferson Ave.
Valley Forge Corporate Center
Norristown, PA 19403-2497
97. Considering that the Neptune Cable has requested and will receive firm
transmission withdrawal rights (TWRs) from PJM, which are the rights to schedule
energy and capacity withdrawals from its point of interconnection with the PJM
transmission system (ref. PJM Tariff paragraph 1.13 A), if an energy transaction is
scheduled over the cable utilizing the PJM spot energy market at the Sayreville
terminus as the source and the sink, must any additional transmission service to the
PJM Border be purchased from PJM? In other words, is the Sayreville terminus
already at the PJM Border?
A. Yes, additional transmission is still required to remove Spot Energy from the PJM
Market. While the Sayreville bus is considered the border of PJM and the Neptune line,
it is still inside the PJM footprint, so additional transmission is needed to get the energy
out of PJM. This is no different than any other export transaction sold from PJM from
any other interface.
98. IS PJM currently accepting requests for transmission service to Neptune on its
OASIS?
A. PJM will start accepting requests for transmission service for delivery to Neptune starting
Friday, November 11, 2005 at 0800. PJM will study the transmission requests, but will
not approve the requests until the final rights to use the Neptune Cable have been granted
through the Neptune RFP process. The normal approval process will be followed in
studying and approving Neptune requests (i.e. queuing order, study costs etc. as per the
PJM OATT). To submit a transmission request, the OASIS path “PJM – NEPTUNE”
and a Sink of “Neptune” should be used when making a reservation.
99. How will the LMP be calculated for the Neptune Interface?
A. The exact bus name will be publicly posted in the first quarter of 2006 for informational
gathering of historical prices.
100. How will PJM process transmission requests for Neptune delivery?
A. PJM started accepting requests for transmission service on Friday, November 11, 2005 at
0800. PJM will conduct studies of the transmission requests on a first come, first serve
basis and will approve requests up to a cumulative maximum delivery of 685 MW firm to
the Neptune Cable. The approved service will be contingent on their receipt of a Neptune
contract for service on the cable. Transmission service requests queued after the initial
approved requests will be conditional on the "original requests" ability to deliver the
contracts, otherwise the service will be awarded in queue order. This approval status is
necessary to hold the ATC. To submit a transmission request, the OASIS path "PJM NEPTUNE" and a Sink of "Neptune" should be used when making a reservation.
PJM is reviewing the recent FERC Order in Docket No. ER05-1010-003 to determine the
appropriate mechanism for assigning transmission upgrade costs to transmission
customers using the Neptune cable. This may impact the transmission customer's rate for
transmission service
610.666.8980 | www.pjm.com
24