Process for building over or building within 3 meters of a sewer, for

Process for building over or building within 3 meters of a sewer,
for sewer pipe over 375mm (15”) in diameter.
For more detailed information on each process step please view the page below or visit the
building over page on our website (www.thameswater.co.uk/buildover).
Timeframe
21 Calendar days
Submit
Application
You
Technical
assessment,
CCTV &
easement
Us
Approval to
begin
building
works
21 Calendar days
Confirm
works
complete
You
Post
construction
CCTV survey
Build over
agreement
issued
Us
Who the activity needs to be completed by
Page 1 of 2
(subject to all required information
and once payment has been received)
(subject to all required information and
once payment has been received)
Us
21 Calendar days
You
Us
21 Calendar days
You
Process for building over or building within 3 meters of a sewer, for sewer
pipe over 375mm (15”) in diameter.
Submit
Application
•You will need to submit your application on-line for building over or building within 3 meters of a sewer agreement
and pay fee of £1300. VAT is not applicable to this service. (You can also do this by post). Please refer to your application
form for costs relating to a disabled applicant.
•We will do a technical assessment of your application. We will request further information and work with you to achieve
approval if we are unable to consent your application at this time.
Technical •Once we have agreed your design, we will order a pre-construction CCTV survey to check the condition of the sewer.
assessment •We will instruct our solicitors to draft the legal Deed of Easement once the sewers condition has been confirmed
& CCTV
acceptable.
•Additional information may be required at this stage, if this is not provided and/or the Deed of Easement is not completed
we will be unable to give consent for you to start works.
•In certain circumstances where it is not possible to approve your application, we will then issue a full refund.
Approval to
begin
building
works
•Once the Deed of easement is registered and the proposed works have been approved, we will then issue you with a letter
to commence the approved works.
•You will need to advise us once your building works are completed.
Confirm
works
completed
Post
construction
CCTV
•We will then order a post construction CCTV survey to check the condition of the sewer after your works are
completed.
•Once we have approved the CCTV survey we will send you a buildover agreement.
Buildover
agreement
issued