SHIPPING NEWSLETTER – JUNE 2008, ISSUE 24 IN THIS ISSUE: • Loss of earnings after collision • Four eyes are better than two • Wrongful maintenance of arrest • FOB contracts: shipment/delivery periods • Nairobi wreck removal convention • A life less frustrating? • Bunker Wars: the burden of proof strikes back! • “Elli” and “Frixos” 2 Shipping Newsletter – JUNE 2008 LOSS OF EARNINGS AFTER COLLISION Ron Clark, an Admiralty Manager in our Hong Kong office, considers the points of interest arising from the recent judgment of The Owners of the ship “FRONT ACE” v. the owners of the “VICKY 1” [2008] EWCA Civ 101. In this case, the Defendants’ feeder tanker “VICKY 1” came into collision with the Ron Clark [email protected] Claimants’ VLCC “FRONT ACE”, whilst manoeuvring alongside for a lightening operation, causing significant damage to the “FRONT ACE”. The Defendants admitted liability for the collision and the issue before the Admiralty Registrar was the assessment of the quantum of damages. The issues between the parties arose out of the loss of a fixture which had been entered into before the collision and which the Claimants said that they were unable to perform as a result of the collision. Two questions were considered:1. Whether the loss of the fixture was caused by the collision and 2. If it was, how the loss should be calculated. The charter the “FRONT ACE” missed was a Chevron voyage charter from “1/3 ports Arabian Gulf” to “1/2 ports Singapore, Thailand, Philippines” In explaining the effect of this deviation, and holding that the Claimants and their various agents acted reasonably in taking the steps that they did, and that there was no evidence of any failure on their part to take reasonable steps to mitigate their loss as a result of losing the Chevron fixture, the judgment demonstrates the Court’s reluctance in such circumstances to entertain submissions based on the benefit of hindsight. Accordingly, provided a party can be seen to have been acting reasonably in its attempts to mitigate losses, the opposing party has an onerous task in discharging the burden of proof that matters should have been handled differently. This approach has long been recognised and accepted by admiralty practitioners and it is the exception where the Registrar will uphold an opposing party’s arguments that have been developed with hindsight. The lesson to be learned, therefore, is for a party seeking to recover losses for detention to ensure that it records contemporaneously any reasons or decisions taken in response to the deprivation of earning capacity. As long as they are reasonable in the circumstances, they should have a relatively comfortable ride in the recovery process. Having determined that the loss of the fixture was caused by the collision, the Registrar then proceeded to determine how that loss should be calculated. In his judgment, Sir Anthony Clarke MR outlined the methods concerned. at a freight rate of WS125, whilst the substitute charter she took up was The time equalisation method is “… based upon the earnings of which a Vitol voyage charter from “1/2 ports West Africa” for discharge at “1/2 the vessel could expect to make in the 57 days between 20 January ports Singapore, Japan” at a freight rate of WS90. 2003, which was the projected end of the Chevron fixture and 18 March The critical issue before the Registrar was whether the loss of the Chevron fixture was caused by the collision. The Claimants said that it was, whereas the Defendants said that it was not, but that it was caused by the Claimants’ failure to take reasonable steps to mitigate their loss by proceeding to a repair port with reasonable expedition, so as to avoid cancellation of the charterparty. Following the collision, “FRONT ACE” discharged part of her cargo at an Indonesian port, and then proceeded to another Indonesian port to discharge the remaining part of her cargo before proceeding to Karimun for permanent repairs, which were necessary to carry out the Chevron fixture. A striking feature of this case, however, was that whilst en route to Karimun the master, for reasons unbeknown at the time to the Claimants, turned the ship on to a reciprocal course for some hours, before again turning round and resuming his original course. This involved a deviation of some 12 hours, which, it was alleged by the Defendants, broke the chain of causation between the collision and the loss of the Chevron fixture. It was only a day before the trial that this fact became known, upon disclosure of the ship’s GPS log, which, effectively, 2003, which was the actual end of the Vitol fixture. Since the loss of the Vitol fixture was caused by the collision, this seems to me to have been a logical period to have taken. During that time it would have been possible to complete either one voyage from the Arabian Gulf (“AG”) to North West Europe or two voyages from the AG to Singapore and in both cases leave the vessel approximately the same distance from her primary loading area as she was following her discharge at Cilacap. In this way it was possible to compare like with like”. With regard to the ballast/laden method – “both the theoretical Chevron voyage and the actual Vitol voyage are defined as starting on completion of discharge at Cilacap and finishing on discharge of the Chevron cargo. In this way each voyage has a ballast leg followed by a laden leg and (as set out above) the time charter equivalent is calculated for the Chevron voyage and then compared to the actual time charter equivalent achieved on the Vitol fixture for the period over which the voyage dates coincide.” The main flaws identified in the ballast/laden method were that: 1. It is unsuitable for VLCC’s which have one major loading area supported the Registrar’s previously held conclusion that, on balance, (i.e. the Arabian Gulf) because it does not reflect the commercial the deviation was most probably for purposes of tank cleaning and gas importance to an owner of discharging cargo as closely as possible freeing prior to the ship’s arrival at Karimun. to the Arabian Gulf; and 3 Shipping Newsletter – JUNE 2008 2. It does not take account of different voyage lengths so in the instant case it was not possible to compare satisfactorily the Chevron voyage with the Vitol voyage that ended 57 days later than the Chevron one would have. Accordingly, the losses calculated by reference to the time equalisation method were held to be payable by the owner of “VICKY 1” to the owners of “FRONT ACE”. It is clear that there is a lack of binding authority on such matters. This is almost certainly due to the fact that admiralty practitioners have The time equalisation method could be contrasted with that, in that it been settling these cases over many years and accepted practices in took into account the overall position until the end of the substitute the calculation of detention losses have been developed between them, fixture, which was entered into as a direct consequence of the meaning that, only where the specific or unusual facts of a case dictate collision. (as here), will the Courts be called upon to decide these issues. Four Eyes are Better than Two owner to limit its liability for property or personal injury claims if it can Oliver Beiersdorf and Joe Teig, Associates in our New York office, comment on the recent decision in re City of New York v. Agni, No. 07-12521, decided March 27, 2008 in which the Second Circuit rejected New York City’s attempt to limit liability in Oliver Beiersdorf [email protected] knowledge. The Act also provides that a single forum may determine: (a) whether the vessel owner is liable; (b) whether the owner may limit its liability; (c) the total amount of claims; and (d) how the funds should be distributed. Over 175 claimants asserted wrongful death or personal injury claims against the City in the limitation action. a ferry crash. The district court denied the City’s petition, and the City appealed to A U.S. federal appeals court recently On appeal, beginning from the agreed premise that a ship in navigable denied the City of New York a limitation waters owes a duty to its passengers to exercise reasonable care of liability under the Limitation of Liability under the circumstances, the City argued that reasonable care did not Act in a lawsuit arising from the crash of require the presence of two pilots in the pilothouse at all times, and a Staten Island Ferry into a pier when the that, therefore, Ryan’s failure to enforce the City’s two-pilot policy was captain lost consciousness. Eleven people insufficient to establish negligence within the City’s privity or knowledge. were killed, dozens were injured and the The Claimants countered that the City was indeed negligent because it impact tore a 210 foot long gash into the took no other steps to mitigate the risk of sudden pilot incapacitation. hull of the 310 foot long ferry. Joe Teig [email protected] establish that the fault that caused the loss was not within its privity or the United States Court of Appeals for the Second Circuit (“the Court”). Neither precedent nor industry custom provided the Court with a ready The ferry, the M/V “Barberi”, was a large answer with respect to the applicable standard of reasonable care. U.S. passenger vessel owned and operated courts, however, often look to governmental safety regulations to help by the City of New York, which shuttled determine an appropriate standard of care. The Court, therefore, looked passengers between Manhattan and Staten to the agency charged with establishing maritime safety regulations – Island. 1,500 passengers were on board on the U.S. Coast Guard. The Coast Guard issued a regulation, 46 C.F.R. October 15, 2003, when Assistant Captain §78.30-5, which although not technically applicable, required that for Richard Smith, the single pilot in the passenger vessels of the size and passenger capacity of the pilothouse at the time of the accident, “lost consciousness or situational M/V “Barberi”, in addition to the pilot, there should be at least one other awareness.” The calamity that ensued made national headlines. member of the crew on watch in or near the pilothouse at all times when Smith, who had concealed that he was taking prescription medication for the vessel is being navigated. chronic health conditions, pleaded guilty to multiple counts of seaman’s The Court held that this regulation accurately reflected the minimum manslaughter. Patrick Ryan, the City’s director of ferry operations, standard of care under these circumstances. Because Ryan not only pleaded guilty to criminal negligence due to his failure to enforce the failed to enforce the two-pilot rule, but any policy that would meet this City’s internal “two-pilot” rule, which generally requires that the Captain standard of care, the City was guilty of negligence within its privity or and an Assistant Captain both be present in the pilothouse when the knowledge, and the district court’s denial of the City’s petition for a vessel is underway. limitation of liability was affirmed. The City filed a petition in the United States District Court for the Eastern Unless successfully appealed to the United States Supreme Court, this District of New York, seeking to limit its liability to U.S. $14.4 million, decision essentially opens the door to unlimited liability for the fifty-nine the value of the vessel less the cost of repairs, under the Limitation claims that have not yet settled. The City has paid approximately U.S. $ of Liability Act, 46 U.S.C. §183 (“the Act”). The Act permits a vessel 35.5 million in settlements to date. 4 Shipping Newsletter – JUNE 2008 Wrongful maintenance of arrest Alan Curran, an Associate in our Dry Shipping Group, considers the position of a shipowner who finds that the release of his vessel from arrest is delayed for some reason. Alan Curran [email protected] cases coming before the courts. As far back as 1864, in the case of the “Cheshire Witch” 167 E.R. 402, (1867) Br. & L. 362, it was recognised by the courts that damages for such detention could be recovered. In that case the arrest suit had been dismissed; this should ordinarily have allowed the vessel to sail. However the arrestors were allowed to detain the vessel for a further 12 days whilst they considered whether to appeal. That further detention was for the claimant’s convenience It is well settled law that an action for alone and he was obliged to pay damages to the ship owner accordingly. wrongful arrest will only be successful The argument, which clearly failed, against the recovery of damages in if the ship owners can prove mala fides that case was on the basis that the detention was not improper since (bad faith) or crassa neglegntia (gross there was a lack of malice. When it comes to wrongful maintenance of negligence). In order to show bad faith, an arrest, the test would therefore not appear to be set as high as when the ship owner would need to demonstrate considering the wrongfulness of the arrest itself, which, as mentioned that the arresting claimant had no honest belief in a right to arrest. Alternatively, to show gross negligence, the shipowner would need to above, would require malice or gross negligence. show that there was so little basis for the claim that the arresting party is The report of the “Cheshire Witch” case is very brief and does not taken to have had no belief in its entitlement to arrest. In addition, gross disclose the full strength of the two sides’ cases. That decision should negligence could be shown by a lack of serious regard to the adequacy therefore be treated with caution since it will not follow that in every case of the grounds for arrest – The “Evangelismos” (1858) 12 Moore, 352; The “Kommunar” (No.3) [1997] 1 Lloyd’s Rep. 22. These are very high thresholds and, unless these are met, an innocent ship owner is left without any way to recover damages for an unjustified arrest. This is quite a harsh rule for ship owners, and it may leave them with no recourse despite incurring potentially very large losses in such a situation. Thankfully, the practice of the shipping industry is such that an arrested vessel is often released after a short period of time once security is provided by her owners, or their Club. This practice operates to minimise the losses that may be incurred by an owner whose vessel is under arrest and therefore goes some way to mitigate the effect of the difficulties in recovering damages following an arrest that turns out to be unjustified. What, then, of the ship owner who finds that the release of his vessel is delayed for some reason? of delay after the time when an arrest should have been released, even in similar circumstances pending appeal, the ship owner will be able to recover damages ( The “Kommunar” (No.3), above, p.30, per Colman J.) Indeed in the case of The “Kommunar” (No.3), the judge found that a delay of six days following judgment whilst an appeal was considered was not so unreasonable as to render the arrestor liable in damages. The test thus appears to contain a requirement of reasonableness. From comments made by the Judge in the case of The “Kommunar” (applying “Cheshire Witch”) it is submitted that there may be scope for a ship owner to recover damages for the wrongful maintenance of an arrest where an arrestor is deprived of all reasonable grounds for continuing the arrest. Although both those cases related to the continuance of an arrest pending a decision to appeal, it is highly arguable that they are applicable by analogy to any situation where an arrest is maintained past It would appear odd that an arresting party, having offered security, its sell-by date. It is apparent that each case will need to be assessed or who has had their arrest set aside, would wish to continue the individually and the reasonableness of the arresting party’s actions detention of the vessel. However, this does, on occasion, happen. The considered. There is, nonetheless, clearly scope for a ship owner to rarity of such a situation is demonstrated by the infrequency of such pursue an arresting party who acts unreasonably. Reed Smith With effect from 1 May 2008, Reed Smith Richards Butler (the trading name of Reed Smith in Europe and the Middle East) will trade simply as Reed Smith. The change in Europe and the Middle East complements the firm’s position in the rest of the US and in Germany. In accordance with Hong Kong regulatory issues, the firm’s Hong Kong practice will continue to trade as Richards Butler in Association with Reed Smith for the foreseeable future. Nick Shaw, head of the firm’s shipping practice, commented: “Since the Reed Smith Richards Butler merger, which took place on 1 January 2007, most of our clients and market contacts already accept and are aware of our merger. This is a logical step which reflects the growth and global reach of our shipping practice for which we have ambitious expansion plans.” years in the shipping business 5 Shipping Newsletter – JUNE 2008 Q&As with ALAN CURRAN Alan Curran is an associate in the Shipping Group. He has a broad experience and handles a wide range of shipping matters acting for P&I Clubs, Owners and Charterers. He is primarily focussed on dry shipping and works in particular on P&I and FD&D matters and bill of lading and charter disputes. Alan also has experience of admiralty and wet shipping matters. Alan is qualified as a Solicitor-Advocate. What is your full name: How do you get into work? Alan Curran Slowly, by train and tube. Mother/father’s nationality? What podcast did you last download? Irish Radio 1 Introducing... Where were you born? Most played song on your i-pod? Hammersmith It is usually on shuffle but Bon Jovi: “Its my life” is currently the most played. Any lawyers in family before? One of my cousins is a lawyer in California. What jobs, other than the law, did you consider? As a child I always wanted to be a chef. When I went to university I also looked into studying psychology. Last concert you went to? The Prodigy. Last item of clothing you bought? A t-shirt for a friend. What other jobs did you do in your summer hols etc? Last five things on credit card? Waiter, night club door supervisor, barman, cashier, shelf-stacker, mini bus driver, photo processor… Kit for my Jeep Cookery books Indian meal Case of wine Interest How does working at Reed Smith compare to them? Very different. What has been your favourite holiday destination to date? Swat Valley, Northern Pakistan. Have you been anywhere of particular interest on business? Unfortunately not. If you could go to one place in the world where would it be? At the moment, probably Japan. Why? It is one of the few places that I have always wanted to visit but haven’t managed to get to yet. Are you married? No. Last film you went to see? The Other Boleyn Girl. Favourite actor / actress? Julia Roberts. Favourite sport? Rugby. How do you relax? Bottle of wine and a video, or out with friends. Do you have a personal role model – either at work or for life generally? If so, who? No. Car? We are meant to learn from our mistakes – what will you never forget? Jeep Wrangler (TJ). Avoid “Reply to All” in emails… Where do you live in London? I don’t. 6 Shipping Newsletter – JUNE 2008 FOB Contracts: Shipment/Delivery Periods Diane Galloway, a partner, and Iulia Ispas, a paralegal, both in our Energy, Trade and Commodities Group, look at the difficulties which can arise when charterparty terms are used in sale contracts. Commercial trends have changed over the Diane Galloway [email protected] A Seller is not in breach of condition for failing to load promptly on arrival of the vessel. A vessel arriving very early in the shipment period can often therefore be kept waiting by Sellers on payment of demurrage and the Buyer cannot withdraw the vessel. Delivery Period/“Laycan”: Summary Laycan traditionally is a charterparty term; giving a spread of dates. The short date is the earliest laytime will commence (even if the vessel arrives earlier); and the charterer is entitled to cancel the charter if years, creating more sophisticated FOB the vessel does not tender NOR by the end date (but without any right contract clauses which are meant to satisfy to claim damages for the non-arrival without some other breach by the traders’ needs and requirements. shipowners). Although these changes have some The translation into an FOB contract would initially seem benefits and merits, they can also create straightforward: the “lay” earliest date is the earliest date at which confusion among the contractual parties in laytime commences against the Seller at the loadport and so the start of case of dispute. The confusion arises when the Seller’s loading obligation; the “can” is the last date the Buyer can there are no clear provisions in respect present a vessel otherwise the Seller can refuse to load and cancel the of all of the relevant time limits. This can shipment. arise, for example, where time provisions apply to one party only or where charterparty terminology (particularly “laycan”) is lifted into sale contracts. Iulia Ispas [email protected] • What then are the obligations if the FOB contract does not provide for a shipment period? The “Delivery Period” in an FOB sale can be a period for presentation by Traditional v Modern Approach the Buyer of the vessel – see for example, GAFTA FOB contracts: The traditional approach was to use “Provided the vessel is presented at the loading port in readiness to load “shipment period” in an FOB contract to create obligations on the Seller within the delivery period, Seller shall, if necessary, complete loading to ship the goods during a specific period, i.e. by the end of the period. after the delivery period ….” The Buyer had to nominate and present for loading a vessel in good time before the end of the shipment period to enable the Seller to ship in time. Alternatively, many traders use “shipment” and “delivery” periods interchangeably to mean the same thing. As a result, the various other The more modern approach is to use “delivery period” and “laycan” or terms of the contract must be scrutinized to see what the intention of the “laydays” to create tight obligations on the Buyer to make the vessel parties was. available for loading at the loading installation within a particular (usually short) time. Shipment period: Summary • It is the duty of an FOB Seller to put the goods on board a ship nominated or designated by the Buyer. • The Buyer must nominate and present a suitable vessel which is capable of loading within the shipment period. • The shipment period is usually a condition of the contract. Failure to load within the contractual shipment period gives the Buyer the opportunity to reject the goods and documents. One way in which traders have made clear that the period is for presentation of vessel, not completion of loading, is the adoption of charterparty wording “laycan” or “laydays” in the sale contract e.g. “Delivery within period February 2008, buyer will narrow such period to a two day laycan…”. See also, for example, BP GTCs 2007, Section 5 “The Buyer shall ensure that by no later than 2400 hrs on the last day of the Laydays the vessel has arrived and tendered NOR”. The problem The danger of the FOB contract specifying a period for arrival of the vessel is that there is then the unanswered question of when exactly does the Seller have to load? • The timing obligations of the Buyer to give “effective” shipping instructions to the Seller – usually to nominate and present a vessel The quick answer is at the agreed loading rate, otherwise the Seller will - are usually conditions. Instructions which are too late are not pay demurrage for late loading. The more difficult issue is when is the “effective”: the Buyer is in breach of condition and the Seller may LATEST the Seller must load? When can the Buyer withdraw his ship for refuse to load and claim damages for the Buyer’s breach. failure to load? 7 Shipping Newsletter – JUNE 2008 It is this issue that demonstrates a potential problem with this method of • defining FOB obligations. Buyer for the failure of the Seller to load promptly. Demurrage is usually the only remedy; It was held in a recent Court of Appeal judgment ERG Raffinerie Mediterranee Spa v Chevron USA Inc [2007] All ER 364 and in SHV Other losses (e.g. market losses) would not be recoverable by the • The Buyer would only be entitled to terminate for non-loading and Gass v Naftomar [2006] 2 All ER 515 that a laycan provision in an FOB remove his vessel after a “frustrating time” based on charterparty contract gave the FOB seller a right to bring the contract to an end in cases. “Frustrating period” is ill defined and unhelpful to most circumstances in which, without a cancelling provision, he might well Buyers seeking a clear date when they may withdraw the vessel. have no right to do so. • Sellers’ late loading may have substantial consequences for Buyers, The concomitant of that right was that the buyer was entitled to present particularly if pricing is bill of lading date dependent, but demurrage the vessel at any time up to 2400 hours on the last day of the laycan is usually the Buyer’s only recovery. spread, which was 30 May in the instant case. If he was entitled to present the vessel at any time up to and including 2359 on 30 May, the contract could not be interpreted to mean that the seller had to have completed loading by 2400 on that day, i.e. the time for presentation of the vessel by the Buyer was a condition of the contract, meaning the Seller could terminate for non-arrival of the vessel. There was no similar absolute deadline for Sellers’ performance. The result of these decisions is: • “Laycan” or “laydays” does not mean the same as shipment period; • This wording makes the contract a “non-traditional” FOB contract; • The Buyer runs the risk of the contract being terminated if the vessel does not arrive in time; • • We have had a number of cases recently where the Buyer was keen to withdraw a vessel for non loading by the Seller but contract terms did not permit this, so the Buyer then runs the risk of himself being in default. The simple question “How long do I have to wait?” had no simple answer. We have also had cases where Traders assume that they have made back to back FOB sales where, on analysis, one is a traditional FOB sale, and one is a contract providing for delivery of the vessel not loading within the contract period, giving a serious mismatch of obligation. Care must therefore be taken to look at which type of FOB contract is made. Ideally, a latest date for loading should be inserted, even on these non-traditional FOB contracts. For example, the Exxon Mobil FOB terms provide for time of delivery of the vessel not to be a condition but permit The Buyer is entitled to present the vessel at any time up to 2400 the Buyer to withdraw and cancel if there is no completion of loading hours on the last day of the laycan spread; within 10 days of NOR or 10 days of the end of the “Accepted Date Range”. The Seller would be in breach giving rise to damages (usually Traders’ checklist for all FOB contracts should therefore include demurrage) if he did not load within the laydays but would not be in identifying what type of FOB contract they are making and consideration breach of condition; of insertion of a final date for loading. 8 Shipping Newsletter – JUNE 2008 Nairobi Wreck Removal Convention The UK Government has indicated that it proposes to ratify the Nairobi International Convention on the Removal of Wrecks 2007 (ICRW) as soon as practicable. Ratification will be effected by inserting new Sections 255A-U in the Merchant Shipping Act 1995. The UK’s ratification of the Convention will be of interest to all those who own and operate sea-going ships, and will be important to owners of ships exceeding 300 GT, insurers, and public bodies likely to incur wreck for such costs. This will only apply to vessels in excess of 300 GT. The Government will be required to certify insurance for all eligible UK flagged ships (comparable to the position under the CLC, and Bunker Convention, which will be coming into force on 21.11.08.). Further, non-UK registered ships of 300 GT or more will not be allowed to enter or leave UK ports or terminals without a State certificate. 4. State parties will be able to recover from shipowners the costs associated with wreck removal. Although at the moment the UK arrangements for maritime casualties removal costs. The Convention will come into force 12 months after it has been ratified by ten countries. At the moment only Estonia has ratified it, and so its implementation is some way off. include wrecked ships in the UK territory and territorial waters, and in the Pollution Control Zone, (as provided for in the Merchant Shipping Act 1995, as amended by the Maritime Security Act 1997 and Marine Safety Act 2003), the Convention fills the gap in the international However, once it applies, it will have the following effect: liability framework. It means that the UK will be able to act in respect 1. The registered owner of a vessel will be required to remove its wreck as providing a system of insurance and the ability to claim costs. There from the UK’s Pollution Control Zone (equivalent to an exclusive economic zone under the United Nations Convention on the Law of the Sea 1982). 2. Strict liability will be imposed on registered owners of all ships in UK ports, harbours or terminals, or operating in UK waters in respect of the cost of locating, marking and removing a wreck, unless the wreck was caused by force majeure or the actual omission of a third party. 3. Registered owners of a ship registered in or entering a port or terminal of a State party will be required to maintain insurance cover A life Less Frustrating? Mark O’Neil, a Partner, and Antonia Panayides, an Associate (Legal Assistant), both in our Dry Shipping Group, review the impact of two recent decisions on the law of frustration of all wrecks, whatever the flag, in the Pollution Control Zone, as well is also an option available to the UK to apply the Convention in both its territory and territorial seas. The Convention does not set out the penalties for breach, but allows each State to determine what the appropriate penalties should be. The effectiveness of the Convention is likely, therefore, to be dependent on the consistency and deterring effect of the penalties imposed. In the UK this is likely to be criminal liability and fines for the master and operator, and detention of any vessel that fails to comply with the insurance provisions. the contractual obligation. Force majeure clauses are often present in contracts which reduce the significance of the doctrine of frustration. That said, frustration is often nevertheless pleaded as a primary or alternative defence by a party seeking to avoid its contractual obligations and remains an argument which is extremely difficult to deal with, and of uncertain results. In a maritime context, frustration can arguably arise when an event Antonia Panayides [email protected] A contract may be discharged on the ground occurs without due fault of either party, whether it be the total loss or of frustration when something occurs after commercial destruction of the ship under the charter, or requisition the formation of the contract which renders or detention of the ship for an inordinate period of time, or whether it it physically or commercially impossible be that the performance of the charter becomes illegal or impossible to fulfil or transforms the obligation to because of the destruction or discontinuance of something essential to perform into a radically different obligation its performance. The contract will be terminated by operation of law if from that undertaken at the moment of entry into the contract (Chitty). Established as a legal concept in 1863 in Taylor v. Caldwell 122 ER 309, the effect of the event is such that it destroys the identity of the charter service or makes it as a matter of business a totally different thing, which the terms of the contract are not wide enough to encompass. Time frustration today operates within narrow confines. In general the courts charters, for long periods of time, are less likely to be found frustrated by do not like using the doctrine of frustration which (potentially) allows the courts, as it is much more likely that the fundamental purpose of the a party to escape from a bad bargain. Such an approach is perhaps charter will and can be performed within the period agreed. Such a result justified in circumstances in which commercial contracts increasingly obviously depends upon the length of the time charter concerned and the make provision for the various possible catastrophic events which nature of the potentially frustrating event. Voyage charters, on the other may occur during the life of the contract and which may impact on hand, are much more susceptible to frustrating events in circumstances 9 Shipping Newsletter – JUNE 2008 that no cargo could be provided in Taiwan. The cement was subsequently supplied by alternative sellers at a higher price and the cargo was shipped to Mexico although never delivered owing to blocking by Cemex. Buyers claimed that the original sellers were in breach of the contract and claimed damages. The original sellers’ defence was that the contract had become frustrated by virtue of the fact that they were unable to secure a supplier. The High Court found in favour of buyers, reversing an earlier Tribunal’s finding, in the alternative, that there was no frustrating event in sellers not being able to supply cement from the Far East. The Court found the sellers had assumed the risk of being unable to provide a supplier under the contract and that the sellers could not be excused from in which it is usually imperative that both cargo and vessel leave on time without delay. The purpose of this article is not to provide a comprehensive recital on the law on frustration, but to consider two recent cases which impose further restrictions on the application of the doctrine and require a much more multi-factorial and, most importantly, equitable, approach in considering whether the doctrine should apply at all. The “Sea Angel” [2007] 2 Lloyd’s Rep. 517 involved the grounding of a crude oil tanker on 7th July 2003 as the vessel approached the port of Karachi. The “Sea Angel” was the vessel chartered in by the salvors, Tsavliris, the initial time charter period being for only 20 days. After completion of the vessel’s final voyage, charterers were unable to redeliver her for over 3 months owing to the Karachi Port Trust’s refusal to issue the necessary clearance certification which is a pre-requisite to obtain port clearance. The Court of Appeal upheld the High Court’s finding that there was no frustrating event, insofar as the risk of being detained by the Port Authority was part and parcel of the matrix of the their obligation by frustration. There was always a risk of supplier failure and, as between the seller and the buyer, it was the seller who was in a position to guard against the risk by making a binding and enforceable contract with the supplier. This case represents a major shift by the Courts away from the doctrine of frustration, insofar as it prioritises the consideration of the whole factual matrix and the equity of the parties’ respective positions over and above consideration of whether the underlying and most immediate contracts are capable of performance. By way of conclusion, courts are now much more likely to look at the overall justice to be served than the simple question of the background facts and/or trying to identify a frustrating event. Furthermore, the onus is now much more on the contracting parties to consider and provide for those events and circumstances which may or might allow them to avoid their contractual obligations. As Lord Denning stated in Intertradex SA v. Lesieur-Tourteaux Sarl [1978] 2 Lloyd’s Rep. 509 “such events are commonplace in the world of affairs. If a party desires to avoid such consequences, he must insert a stipulation to excuse him. He cannot avoid them by a plea of frustration.” charterparty, and should have been foreseeable by Tsavliris and the salvage industry. Gross J., at first instance, held the risk of any delay resulting from the lack of port clearance rested with charterers. In the Court of Appeal, Lord Justice Rix said “the application of the doctrine of frustration requires a multi-factorial approach. Among the factors which have to be considered are the terms of the contract itself, its matrix or context, the parties’ knowledge, expectations, assumptions, contemplations, in particular as to risk, as at the time of the contract.” Most importantly, the Court of Appeal felt that “greater injustice” would have been caused to the ship-owner had he not received hire due to no fault of his own than to Tsavliris in paying hire for the extended period. This concept of a multi-factorial approach and finding the equitable solution constitutes a further development of the Court’s previous reluctance to make a finding of frustration and thereby allow a party to escape a bad bargain. In the “Mary Nour” [2008] 1 Lloyd’s Rep. 250 CTI, as buyers of cement, entered into a sale contract with Transclear SA as sellers, for the sale of 27,000 m.t. of cement for shipment and sale to Mexico. The objective of the contract was to try to break the cartel operated by Cemex in Mexico. The seller’s suppliers pulled out and the sellers gave notice to the buyers In February 2008, Reed Smith LLP announced the continuation of its growth in China with the addition of two partners and a team of lawyers and legal professionals from the former Dewey Ballantine’s Beijing office. The enlarged Beijing practice will complement that of the firm’s Hong Kong operation. Already one of the 15 largest law firms in the world, Reed Smith officially began operations in Asia when its merger with Richards Butler Hong Kong became effective at the start of this year. The partners joining Reed Smith in Beijing are Sharon Mann and Hugh Scrogin. Sharon is a former senior director of the Trade Facilitation Office at the U.S. Embassy in Beijing. Her practice covers Chinese investment, capital markets and trade issues. Hugh is a corporate partner focusing on investment, M&A, other corporate transactions and dispute resolution. Michael Dardzinski is also joining Reed Smith as Counsel. He handles M&A, other transactions and dispute resolution. A number of other lawyers and professionals will also join the team. 10 Shipping Newsletter – JUNE 2008 Bunker Wars: The Burden of Proof Strikes Back! Mark O’Neil, a partner in our Dry Shipping Group, considers the burden of proof in bunker quality disputes Mark O’Neil [email protected] held that, on a balance of probabilities, the main engine damage must have been caused by some aspect of the bunkers supplied and that, on the balance of probabilities, that aspect was the poor ignition quality of such bunkers. Whilst the above mentioned arbitral decision was welcomed by the author of this article and his clients, it did rather drive a coach Bunker quality disputes have traditionally and horses through the standard burden of proof tests and checks focused on whether or not the bunkers established under English law. Claimants had not been rigorously supplied to a vessel accorded with the required to prove that a specific quality of the bunkers (be it ignition contractual charterparty specification. quality or anything else) had caused the specific damage concerned, as Claimants in such disputes would have the Tribunal focused on ignition quality as the likely cause absent any the dual burden of proof to show, not other more likely explanation. This arbitral decision was followed by only that the respondent suppliers of the many others in owners’ favour focusing on ignition quality and unfitness bunkers (normally the charterers) had for purpose as the battleground and encouraged owners to attribute supplied bunkers outside of the contractual any and all engine damage to alleged poor quality of bunkers. Bunker specification, but also (often a more difficult burden to overcome) that the disputes are notoriously expensive and complicated to run which, in off-spec quality of the bunkers supplied actually caused the damage to the turn, encouraged charterers and/or bunker suppliers to settle these vessel’s main engine. Whilst the first burden of proof was often easy to claims rather than risk an adverse finding as a matter of fact (never establish through ever more sophisticated sample collection at the vessel appealable) in arbitration. An American style litigation culture was or barge manifold and sampling procedures, the second burden of proof therefore initiated. would almost inevitably require extremely complicated expert evidence of both an engineering and chemical nature. With a less than perfectly maintained and regularly overhauled main engine and component parts, it was often easy for the bunker supplier (be it charterers or the ultimate physical supplier of the bunkers) to raise alternative possibilities as to the cause of the damage (e.g. improperly maintained purifiers, improper bunker management through co-mingling of bunkers, cylinder liners exceeding their life expectancy/running hours). The burden of proof was a “burden” in a very real sense and this dissuaded “have a go” litigants from proceeding with less than cast iron cases. Recent bunker quality disputes have become ever more complicated and the focus has very much been on the dual obligation of bunker suppliers/ charterers not only to supply bunkers which are on spec, but also fit for the purpose intended (and for the specific engine onboard the vessel supplied). The “fitness for purpose test” was brought to the fore in an arbitration successfully pursued by the author of this article, the basis of the allegation of lack of fitness for purpose being the poor ignition quality of the fuel supplied. In that particular arbitration, the Tribunal In a recent arbitral decision involving the author of this article (but this time on charterers’ behalf) the floodgates were firmly closed by a very sensible Tribunal adopting an extremely rigorous approach on burden of proof. In that particular arbitration, owners thought to claim huge damages for physical damage to the main engine and consequential loss of time on an extremely scant and dubious evidential basis. Hoping to ride the fitness for purpose wave created by previous arbitral decisions, they were abruptly stopped in their tracks, after a lengthy hearing, by an Award which found that they had failed to discharge the burden of proof. The above development is a welcome one and will cause owners and/ or disponent owners to think again before they embark on costly bunker claims without the necessary evidence to succeed and discharge the burdens of proof placed upon them. Furthermore, and importantly, it will also encourage claimants’ insurers to take a much more cautious approach to the question of cover of these disputes or face potentially huge exposure on costs in the event that the claim should fail. This article first appeared in the 15th August 2007 edition of Lloyd’s List. The Reed Smith Corporate Group has prepared a Guide to doing Business in the UK: About UK Business summarises the main legal requirements for doing business in the UK, the different ways in which those requirements can be met, and some of the more significant legal considerations which the business will have to deal with. It is aimed to be of relevance particularly to companies based abroad. For more details, or to request a copy, please contact Allison Mitchell, [email protected] 11 Shipping Newsletter – JUNE 2008 “elli” and “frixos” New Joiners In Newsletter 23 Alan Curran reviewed the decision in the case of the Amy Dominguez has recently joined ELLI” and the “FRIXOS”. That decision was appealed and Alan now the Shipping team from Stephenson reviews the appellate decision Harwood, where she trained and qualified as a solicitor in September 2006. Amy The claims in this matter concerned two “double sided” sister-ships has experience of handling dry shipping chartered on the Shelltime 4 form. When the MARPOL regulations litigation cases, including cargo claims on double-hulls came into force both vessels were defined by their and charterparty disputes. Amy will be classification society as being only partially double sided. The primarily working for David Semark, consequence of this was that the vessels could no longer be used to carry fuel oil. At first instance the court held that the fitness of a vessel for service Mark O’Neil and Charlie Weller. Amy Dominguez [email protected] was an obligation that extended to physical and legal fitness. The vessels could not obtain the appropriate MARPOL certification and Nick Barber is an Associate in the Shipping were therefore not fit for the service required of them. The Owners had Group specialising in both Dry and Wet a continuing obligation to maintain or restore that fitness if it was lost. matters. He served in the Merchant Owners were therefore obliged to do whatever was necessary to restore Navy for six years on a range of vessels the vessels’ fitness for the service required of them regardless of the including offshore supply vessels and costs of doing so. anchor handlers, Capesize bulkers and On appeal, the Owners argued that the nature of Owners’ obligations as freight and passenger ro-ros. After serving to seaworthiness, which includes cargoworthiness, are tied to the time as a chief officer Nick studied Law at of delivery into Charterers’ service. Owners also stressed that there was Southampton University and qualified no breach in the description of the vessels. Nick Barber [email protected] The judgment turned on the precise wording of the charter, in particular: i) Clause 1, which began with the words “At the date of delivery of the vessel …”, and continued in sub-clause (g) to say that the vessel “shall have on board all certificates, documents… required from time to time by any applicable law to enable her to perform the charter service without delay”. It was held that the particular should prevail over the as a solicitor. Since qualifying, Nick has assisted in various charterparty disputes including unsafe port disputes and late redelivery of a drillship after a long term charter, as well as undertaking casualty investigations. Nick has also assisted in MOA disputes and has advised on long term offshore charter and service agreements. Nick is a member of the Firm’s Casualty Response Team. general, and so the specific words of the sub-clause (g) prevailed over the general phrase at the beginning of clause 1. Luca Salerno is an English and Italian qualified lawyer and has worked as a ii) Clause 52, which warranted that ‘the vessel is in all respects eligible commodities derivatives lawyer in London under applic[able] convention, laws, and regulations for trading to and for the last seven years. His experience from the ports and places specified in… the Charter Party’ and that ‘she derives from in house positions in a shall have on board… all certificates… and other documents required trading company (Sempra Energy Europe for such services…’. This covered the requirement to have a MARPOL Limited now part of the RBS Group) and exemption and the later words of the clause resolved all doubt as to subsequently in an investment bank (J P future applicability of the warranty since it was warranted that the vessel “does, and will, fully comply with all applicable conventions…including …. MARPOL 1973/1978 as amended and extended.” The Court of Appeal held that the terms of the charter were clear and there was therefore a continuing obligation on Owners to restore the ability of the vessels to carry out the service required of them when the MARPOL regulations came into force. Morgan Chase Bank N.A.) where he was Luca Salerno [email protected] Assistant General Counsel. He joined Reed Smith’s Energy Trade & Commodities Group in May 2008. Luca’s expertise encompasses physically and financially settled transactions having energy commodities, base metals, emission allowances as underlying and complements both the Shipping and Financial Institutions Group capabilities. Luca is also a regular speaker on, and has expertise in, It is not yet known whether the Owners will pursue this point any further regulatory capital and financial regulation. Luca contributed to the and seek to appeal to the House of Lords. drafting of the MIFID Guide for Commodity Traders. The information contained in this Newsletter was compiled for its clients by Reed Smith as a summary of the subject matter covered and is intended to be a general guide only and not to be comprehensive, nor to provide legal advice. Reed Smith Richards Butler LLP accepts no responsibility whatsoever for loss which may arise on information contained in this Newsletter. This Newsletter was compiled up to and including May 2008. ©Reed Smith 2008. Reed Smith Richards Butler LLP is a limited liability partnership registered in England and Wales with registered number OC303620 and registered office at Beaufort House, Tenth Floor, 15 St Botolph Street, London EC3A 7EE, England. The term ‘partner’ is used to refer to a member of Reed Smith Richards Butler LLP. A list of partners of Reed Smith Richards Butler LLP, and their professional qualifications, is available at the registered office. Reed Smith Richards Butler LLP, or a separate but affiliated entity, has an office or an association in each of the places listed below. Reed Smith Richards Butler is regulated by the Solicitors Regulation Authority. For further information on any topic in this Newsletter, please contact Jane Peaston, ([email protected]) or your usual contact at Reed Smith.
© Copyright 2026 Paperzz