CSU’s Multi-Purpose Stadium Report – December 2016 Construction Budget and Schedule Budget Stadium Fixed Limit of Construction Construction Management General Contractor Guaranteed Maximum Price (CMGC GMP) Other Hard Costs (miscellaneous construction, furniture, fixtures, equipment, technology, testing, inspections, utilities) Design and Professional Services Owner Contingency Total Stadium Budget Contingency Status* Project Owner Contingency CMGC Bidding Contingency (in CMGC GMP) CMGC Construction Contingency (in CMGC GMP) $172,701,598 Academic & Alumni $14,125,790 $22,372,951 $2,228,932 $17,730,775 $7,533,821 $220,339,145 $1,693,439 $451,839 $18,500,000 Original $8,462,045 $1,118,380 $5,591,902 Remaining $7,985,660 $96,970 $2,076,500 *Cost evaluation of project alternated and presented risk ongoing will not exceed remaining budgets. Project is currently within budget Schedule Substantial Completion Date June 2017 (stadium), July (A/A) Seating benches and metal railing installation ongoing. Permanent Power within stadium complete. Precast Stadia complete. Interior wall installation in progress. CMU walls substantially complete. Drywall, tape, finish and paint being installed on all levels. Extensive Mechanical, Plumbing, Fire Protection and Electrical rough-in installed. Work is ongoing and will continue through project completion. Stadium tower dry-in scheduled for November 2016. Full enclosure anticipated in February 2017. Field Installation to begin December 2016 with anticipated completion in May 2017 Project is currently on schedule CSU Multi-Purpose Stadium on Main Campus Less Than One Year to Go: Milestones December 2016: Academic & Alumni Dry in; Level 500- Club Level; Level 600- Suite Level; Level 700- Indoor Club; Field Installation (December 2016 - May 2017); Install Signage & Graphics (December 2016 - February 2017) January 2017: Site work (January 2017 - May 2017), Kitchen Equipment Installation (January 2017 - April 2017) February 2017: Enclosure Completion; Functional MEP Systems Testing (February 2017 - May 2017); Punchlist Kick-off- (February 2017) March 2017: Install Athletic & Training Equipment (March 2017 – April 2017) April 2017: Big Flush (April 4, 2017); Fire Alarm & Life Safety Testing May 2017: Punch list certification for Substantial Completion; June 2017: Opening of Meridian Ave; Date of Substantial Completion: Stadium (June 9, 2017); Furniture and Equipment Installation (June - July 2017) Administrative Closeout and Punch List completion for Stadium Final Acceptance (June 12, 2017- August 3, 2017); Move-in: All departments (June – August, 2017) July 2017: Date of Substantial Completion: Alumni Center, CASA, Classrooms August 2017: Final Acceptance Stadium (August 10, 2017) September 2017: Soft Opening Event (Pending September 2, 2017) First Home Football Game (September 9, 2017) Stadium Advisory Group (SAG) Colorado State University and the City of Fort Collins formed a Stadium Advisory Group (SAG), per the terms of the IGA. The jointly appointed members are: • Danielle Clark, Executive Director of Communications, PSD • Gary Buffington, Larimer County Natural Resources Department Director • Bob Herrfeldt, Director, The Ranch Events Complex • Steve Taylor, Owner, Hot Corner Concepts • Per Hogestad, City of FOCO Landmark Preservation Comm. Member and Ret. CSU Architect • Colin Gerety, Owner, Momo Lolo Coffee House • Mitch Majeski, Pastor, Summitview Community Church • Ben Manvel, Former City Councilmember and Retired CSU Professor • Carol Reed, Sheely Neighborhood Resident SAG has now completed 12 meetings since October 2015. The most recent meeting was held November 14, 2016. The meeting began with Doug Wilson with ICON and Fred Haberecht with CSU Facilities providing an update on the stadium and other construction projects on campus. Athletics Director Joe Parker and Gary Ozzello, CSU Director of Community Outreach and Engagement, then facilitated a discussion with SAG members on designing and managing a grant application process for allocation of the Good Neighbor Fund. Under the terms of the Intergovernmental Agreement (IGA) between CSU and the City of Fort Collins, the purpose of Good Neighbor Fund is to support efforts to lessen undesirable or unanticipated effects on neighborhoods from an on-campus stadium. CSU has committed up to $37,500 annually to the Good Neighbor Fund to be allocated and disbursed at CSU’s discretion based on recommendations made by the SAG. At their October and November meetings, SAG discussed establishing core values to guide the grant submission and selection process. For example, SAG discussed these possible core values: 1) Community Character – a commitment to uphold and enhance the unique identities of the neighborhoods and larger Fort Collins communities; 2) Goodwill – a commitment to promote relationships of trust between adjacent neighborhoods and the CSU community; 3) Responsible Citizenship – a commitment to positively shape and improve neighborhoods for the benefit of all residents; 4) Impact – a commitment to offset or mitigate any identified or potential negative impacts to neighborhoods from an on-campus stadium, and to enhance, strengthen and protect the beauty, serenity, and security of neighborhoods directly impacted by the stadium; and 5) Leveraging – a commitment to multiply the impact of the grant by leveraging financial support of other sources or through collaboration and partnerships, when possible. SAG also discussed the proposed timeline for accepting and making recommendations to the CSU Vice President of Operations for prioritizing and allocation of the fund: July 1 – November 1, make application available to public November 1-30, SAG hears applicant presentations and reviews grant applications December – SAG presents it recommendations to CSU and City January – Final approval/rejection of grant applications January – March – Design and funding request/approval March – June 30 – Implementation (unless already completed in prior months) SAG will meet again in January 2017, but will continue (via email) to finalize grant criteria, core values and an application/selection process, and develop a plan for community outreach for soliciting grant submissions. Additionally, SAG members will attend internal/external open houses tentatively planned for January/February to be hosted by CSU and the City to inform the campus and Fort Collins communities about the final framework for game day operations. At those open houses, SAG members will discuss the Good Neighbor Fund, the IGA and their work-to-date on behalf of neighborhoods adjacent to CSU. Game Day Experience Committee The university formed a Game Day Experience (GDE) committee operating under Vice President Blanche Hughes. The jointly appointed co-chairs are: Blanche Hughes, Vice President for Student Affairs, Tom Milligan, Vice President for External Relations, and Joe Parker, Athletic Director. Approximately 20 other committee members represent a broad crosssection of university stakeholders including ASCSU, University Advancement, Parking and Transportation Services, the Faculty, AP and State Classified Employee councils, Athletics, CSU PD, Facilities, CSU Health Network and Housing and Dining. The Game Day Experience Committee continues to meet regularly to address the following topics in preparation for the opening of the on-campus stadium in August 2017: Game Day Operations Framework (Parking/Transportation) Law Enforcement – CSUPD, Landmark Yellow Jackets Tailgating Programming and Marketing Logistics for Spirit/Support Groups Communications Update – Open Forums with Community and Campus Partners The Game Day Operations Framework was presented in multiple open forum meetings with community and campus constituents soliciting feedback and suggestions. This feedback was incorporated this summer into more detailed executable plans (e.g., specific parking numbers per lot, final traffic patterns, tailgating policies, location of bike carrels, etc.) and has been presented at additional public forums during Fall 2016 (including a presentation to student government, the Deans, Cabinet, and the University Physical Development Committee). The Committee was asked by Dr. Frank to select a number of universities with on-campus stadiums to get more detail about their operations and what we can learn from them. A number of areas on campus (Alumni, External Relations, Student Affairs, Campus Police, Off-Campus Programs, Athletics, Student Government, New student orientation programs) contacted their colleagues to get more information focused on tailgating (students, alumni, and guests), alcohol policies, reparking policies, facilities, safety, and impact on campus (residence halls, recreation, conferences, etc.). The co-chairs are scheduled to meet in December to review the results of the survey and share this with the larger committee. This information will assist in finalizing Game Day events and procedures to be presented for approval to the Executive Stadium Committee and Dr. Frank by Feb. 1. IGA (Intergovernmental Agreement) with City of Fort Collins Twenty-six projects were identified in the original IGA. Since April 2015, fifteen have been built and or are nearing completion, five are ready for construction or actively under construction, and six are in the design stage. The projects not currently complete are scheduled to be delivered late summer or early Fall 2017, pending funding allocations and desire to move forward with the Lake and Center Avenue Traffic Management Improvements. The Shields and Elizabeth Underpass is moving forward. Property acquisitions and entitlements are in place and the Design-Build team has mobilized to the project site and began construction activities the last week of November. Concurrently, they will continue to advance the design and engineering work, ultimately aiming to deliver the project in Fall 2017. Neighborhood outreach meetings will continue to occur to with the City of Fort Collins and the immediate community affected by the construction of this improvement. Hughes Stadium ICON Venue Group, working on behalf of the University, has acquired and reviewed all existing information and documentation relating to the Hughes Stadium property. ICON has also commissioned and completed due diligence reports to evaluate the title, survey, geotechnical and environmental conditions associated with the property. Currently, ICON is working with Cameron Gloss, Ft. Collins City Planner, to coordinate communications with the Neighborhood Organizations proximate to the Hughes Stadium property. Tim Romani with ICON is in direct contact with the leaders of the respective Neighborhood Organizations and working with the City on a mailing to adjacent property owners. Neighborhood meetings will be organized and conducted by ICON and the City starting in January. Also in January, ICON will be assimilating all of the property information, due diligence reports and neighborhood input to prepare the RFP document to review with the University for release to potential developers in early March. Proposals will be received and reviewed in late April. Candidates will be shortlisted and interviewed in May with a final ranking to be prepared in June. Stadium: Naming Rights + Sponsorships toward Pro Forma 100.0% 90.0% 80.0% 70.0% 60.0% 50.0% 40.0% 30.0% 20.0% 10.0% 0.0% 1 167.8% FY18 $ Pro Forma % Met Naming Rights 1,060,167 500,000 212.0% Sponsorships 2,700,000 1,741,162 155.1% 3,760,167 2,241,162 167.8% *The sponsorship pro forma amount used on this chart is the net amount of sponsorship revenue less sponsorship expense from the 2012 CSL study. Earlier versions of this chart used the 2012 CSL study gross revenue number for the sponsorship pro forma amount. The CSL study pro forma also included a sponsorship expense line equal to approximately 50% of gross revenue that accurately reflected the revenue share contract then in place with Nelligan Sports. CSU’s recent contract extension with Learfield moved the sponsorship model from a revenue share model to a guaranteed rights fee model. As a result, the full guaranteed rights payment is comparable to the CSL net number now set forth on this chart as the sponsorship pro forma amount. Stadium: Naming Rights + Sponsorships toward CSL High 100.0% 90.0% 80.0% 70.0% 60.0% 50.0% 40.0% 30.0% 20.0% 10.0% 0.0% 1 110.6% 73.1% FY18 $ CSL High % Met Naming Rights 1,060,167 750,000 141.4% Sponsorships 2,700,000 2,650,000 101.9% 3,760,167 3,400,000 110.6% *The sponsorship CSL High amount used on this chart is the net amount of sponsorship revenue less sponsorship expense from the 2012 CSL study. Earlier versions of this chart used the 2012 CSL study gross revenue number for the sponsorship CSL High amount. The CSL study pro forma also included a sponsorship expense line equal to approximately 50% of gross revenue that accurately reflected the revenue share contract then in place with Nelligan Sports. CSU’s recent contract extension with Learfield moved the sponsorship model from a revenue share model to a guaranteed rights fee model. As a result, the full guaranteed rights payment is comparable to the CSL High net number now set forth on this chart as the sponsorship CSL High amount. Stadium Total: Naming Rights + Sponsorships + Philanthropy Naming Rights Sponsorships Philanthropy 100,000,000 90,000,000 80,900,000 80,000,000 70,000,000 60,000,000 86,400,000 86,400,000 86,975,000 41,600,000 41,600,000 42,175,000 34,400,000 34,400,000 34,400,000 10,400,000 10,400,000 10,400,000 Jul 2016 Sep 2016 Nov 2016 40,300,000 50,000,000 40,000,000 30,000,000 36,000,000 21,000,000 20,000,000 10,000,000 34,400,000 15,000,000 6,200,000 0 Dec 2015 May 2016 *Note: Donations for naming rights for fiscal years 2018-2027 are included in "Naming Rights" total. Donations for naming rights receivable for fiscal years 2028+ are included in "Philanthropy" total. The Philanthropy total represents the philanthropic reserve coverage to service the stadium bonds, if needed. Stadium Total: Naming Rights + Sponsorships + Philanthropy $86,975,000 Incremental 575,000 36,000,000 44,900,000 Dec 2015 0% 10% May 2016 Jul/Sep 2016 5,500,000 Nov 2016 *Note: Donations rights for fiscal years 2018-2027 20% 30%for naming 40% 50% 60% are included 70% in "Naming 80%Rights" total. 90% Donations for naming rights receivable for fiscal years 2028+ are included in "Philanthropy" total. 100% STADIUM PREMIUM SEATING #'s SOLD OF TOTAL CAPACITY SUITES INDOOR CLUB LOGE OUTDOOR CLUB COMBINED 100% 100% 100% 100% 100% 90% 90% 90% 90% 90% 80% 80% 80% 80% 80% 70% 70% 70% 70% 70% 60% 60% 60% 60% 60% 50% 50% 50% 50% 50% 40% 40% 40% 40% 40% 30% 30% 30% 30% 30% 20% 20% 20% 20% 20% 10% 10% 3% 10% 10% 10% 0% 0% 0% 1 100% Note: One suite held for naming rights partner 1 100% 0% 0% 1 100% 1 100% 100% 1 100% Income Statement Pro Forma as of November 2015 Revenues Premium Seat Donations Priority Seat Donations Tickets and Parking Advertising/Sponsorship Naming Rights Miscellaneous Revenue FY 16 Hughes FY 17 Hughes FY 18 FY 19 FY 20 FY 16 Hughes FY 17 Hughes FY 18 FY 19 FY 20 Total Revenue Expenses Salaries and Benefits Supplies General Operating Services Professional Services Repairs & Maintenance Utilities Game-Day Expenses Total Expenses Net Income CSL Feasability Study Low Case 2012 Revenues Premium Seat Donations Priority Seat Donations Tickets and Parking Advertising/Sponsorship Naming Rights Miscellaneous Revenue Total Revenue Expenses Salaries and Benefits Supplies General Operating Services Professional Services Repairs & Maintenance Utilities Game-Day Expenses Total Expenses Net Income Projected Pro Forma Net Income Variance Versus CSL Feasability Low Case (Line 18-Line 36) Positive (Negative) Projected Bond Debt Service Coverage Net Income from Line 18 Contribution to Athletics from CSL Model Bond Payments Surplus(Shortfall) Stadium Donations from CSUF as needed Net General Fund Allocation Philanthropic Coverage Beginning Reserve Balance New Funds Raised Reserve Deployed (= line 42) Ending Reserve Balance
© Copyright 2026 Paperzz