STATE OF MICHIGAN BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION ***** In the matter of the complaint of NORDIC MARKETING, L.L.C., against THE DETROIT EDISON COMPANY for failure to comply with enrollment processing requirements. ) ) ) ) ) Case No. U-14208 At the October 18, 2005 meeting of the Michigan Public Service Commission in Lansing, Michigan. PRESENT: Hon. J. Peter Lark, Chairman Hon. Laura Chappelle, Commissioner Hon. Monica Martinez, Commissioner OPINION AND ORDER I. HISTORY OF PROCEEDINGS On July 23, 2004, Nordic Marketing, L.L.C. (Nordic), filed a complaint against The Detroit Edison Company (Detroit Edison), alleging that Detroit Edison failed to complete open access enrollment activities within 45 days for Nordic’s customers as required by Detroit Edison’s retail access service tariff (RAST), its alternative electric supplier (AES) agreement with Nordic, and the Customer Choice and Electricity Reliability Act, 2000 PA 141 (Act 141),1 MCL 460.10 et seq. Nordic requested that the Commission (1) find that Detroit Edison violated its RAST and AES agreement with Nordic, (2) order Detroit Edison to cease and desist from further noncompliance, 1 Act 141 took effect on June 5, 2000, and authorizes the Commission to establish the rates, terms, and conditions under which all retail customers of an electric utility would be permitted to choose an AES. (3) fine Detroit Edison for each Nordic customer whose enrollment was delayed, (4) order Detroit Edison to refund to Nordic customers the additional monies they expended on bundled rates because of Detroit Edison’s untimely enrollments, and (5) award costs, attorney fees, and damages. On January 20, 2005, Administrative Law Judge James N. Rigas (ALJ) conducted an evidentiary hearing at which testimony was bound into the record and witnesses were crossexamined. The Commission Staff (Staff) also participated in the proceedings. The evidentiary record consists of 85 pages of transcript and 18 exhibits. On April 7, 2005, the ALJ issued a Proposal for Decision (PFD). Nordic, Detroit Edison, and the Staff filed exceptions on April 21, 2005, and replies to exceptions on May 2, 2005. II. PROPOSAL FOR DECISION The ALJ found that from October 2003 through April 2004, Detroit Edison failed to meet the 45-day enrollment requirement for at least 175 Nordic customers, thereby violating Act 141, the RAST, and the AES agreement. The ALJ concluded that the Commission mandated in its December 20, 2001 order in Case No. U-12489 (December 20 order) that the 45-day enrollment requirement was absolute and, therefore, rejected Detroit Edison’s argument that a rule of reason should be applied because of mitigating circumstances or because it acted in good faith. The ALJ agreed with the Staff and Nordic that Detroit Edison should pay a fine2 and Nordic’s attorney fees, and further recommended that the Commission issue a cease and desist order because of Detroit Edison’s history of problems with untimely customer enrollments. 2 The ALJ recommended a fine of $1,000 for the first offense, $2,000 for the second offense, and $5,000 for the third and 172 subsequent offenses. Page 2 U-14208 However, the ALJ found that the record did not support a reliable computation of damages with respect to lost gross margin or losses attributed to the cost of excess power pre-purchases. The ALJ concluded that the AES agreement precludes recovery of consequential, incidental, and indirect damages, which he determined included costs for personnel and benefits, depreciation, leases, cost of capital, supplies, utilities, taxes, and profit. Further, the ALJ found that Detroit Edison’s testimony and exhibits critically undermined and raised serious doubt as to the validity of Nordic’s claimed loss attributable to excess power pre-purchases. Finally, the ALJ noted that because Nordic requested that its damage claim be heard in this proceeding, he does not agree with the Staff that this case should be reopened for further consideration of damages. III. POSITIONS OF THE PARTIES Nordic Nordic complains that from October 2003 through April 2004, Detroit Edison failed to enroll at least 175 Nordic customers3 within 45 days as required by Detroit Edison’s RAST, which provides for no excuses for failure to comply with the standard. Therefore, Nordic says, it is undisputed that Detroit Edison violated the RAST. Nordic argues that regardless of the enormity of the challenges in implementing choice, the complexity of installation of interval demand meters, or the enrollment spikes, none of these reasons justify the enrollment delays. Nordic proposes that the problems were foreseeable. See, Exhibit C-14, p. 4, where Detroit Edison’s witness, William J. Newbold, Jr., its Manager of 3 Nordic specifically claims that between October 2003 and July 2004, Detroit Edison failed to comply with the 45-day enrollment requirement for 187 of its customers (2 Tr., pp. 13, 22), although Detroit Edison’s witness testified that it failed to meet the standard in only 175 instances (2 Tr., p. 72). Page 3 U-14208 Electric Choice Strategy, admitted in Case No. U-14025 that Detroit Edison foresaw problems in installing interval demand meters as far back as 2000. Nordic further maintains that until February 2004, Detroit Edison actually reduced resources devoted to completing enrollment activities rather than increasing resources, as logic would dictate with the increased enrollment requests. Nordic maintains that site visits to install meters dropped significantly in November and December 2003 from the September and October level because overtime at Detroit Edison stopped (Exhibit C-14, p. 6), and the facility that tested and programmed meters was shorthanded. Nordic complains that the Allen Road Facility normally had six employees, yet during this time period, Detroit Edison’s personnel at this facility was reduced from three employees to one, and were not replaced until the new budget year. Exhibit C-14, pp. 7-8, 10-11. Despite the fact that meter testing was a critical bottleneck in processing applications, the number of meter testers went down to one and overtime was abolished. Therefore, Nordic concludes, Detroit Edison not only violated the RAST, but took no reasonable steps to correct the problem. Indeed, Nordic says, Detroit Edison’s compliance with the 45-day standard only occurred after the February 20, 2004 interim order in Case No. U-13808, that increased fees for choice customers thereby drastically reducing enrollments and Detroit Edison’s workload. Because of Detroit Edison’s persistent violations and refusal to take effective measures to correct the violations, Nordic urges the Commission to (1) issue a cease and desist order prohibiting Detroit Edison from future violations, (2) assess fines, and (3) order Detroit Edison to compensate Nordic for attorney fees, lost gross margin due to delays in commencing service, and losses on delivery of power that could not be used by its customers due to Detroit Edison’s delay. Nordic says it incurred (1) $88,262 in losses due to the cost of excess power it purchased that was Page 4 U-14208 not used by the customers because they were not site ready within 45 days, (2) $43,800 in losses of gross margin,4 and (3) $21,600 in costs for legal expenses. Nordic disputes Detroit Edison’s calculations because the utility’s witness, Kenneth D. Johnston, Principal Project Manager in Regulatory Affairs, did not include any accounts in his calculations with margins less than zero. Even if the AES agreement precludes recovery of lost profits, Nordic says it incurred the remainder of the costs, despite its customers not receiving service as anticipated. Further, using Detroit Edison’s methodology, it calculates its imbalance payments at $88,262. Nordic further explains that while Detroit Edison said Nordic was in an imbalance situation, Detroit Edison offered no proof of the alleged imbalances, therefore, Mr. Johnston’s testimony consists of mere speculation and challenges Detroit Edison’s position on this point. Finally, Nordic points out that its witness testified that Nordic’s estimated cost of power was $48 per megawatt-hour (MWh), based on actual forward curves used by Nordic’s power supplier during the times of delayed enrollment, whereas Detroit Edison merely opined that Nordic could have purchased power at a lower cost. Nordic construes that its AES agreement does not preclude recovery of direct out-of-pocket damages such as attorney fees, costs of undeliverable power, or lost gross margin (other than profit). Nordic says it had already incurred $21,600 in attorney fees up until the time of the hearing, and requests that this amount be amended to include additional expenses incurred since that time. Nordic refutes Detroit Edison’s contention that it was in an imbalance situation, maintains that it was never assessed penalties for imbalances or purchased power at a penalty rate, and challenges Detroit Edison to produce evidence to the contrary. 4 Nordic says gross margin is costs incurred to deliver power and consists of personnel and benefits, depreciation, leases, cost of capital, supplies, utilities, taxes, and profit (which makes up 40% of gross margin calculations). Nordic calculated lost gross margin at $73,004, of which $29,200 was profit. Page 5 U-14208 Detroit Edison Detroit Edison suggests that the Commission should find that Detroit Edison’s actions were reasonable and, because the backlog has been resolved, reject the ALJ’s recommendations regarding the proposed penalty, cease and desist order, and payment of attorney fees. It does, however, agree with the ALJ that the record fails to support a reliable computation of damages. Nordic failed to carry its burden of proof, Detroit Edison concludes, with respect to the cost of excess power purchases and agrees that lost gross margin is barred by the AES agreement. Detroit Edison says that beginning in September 2003, it received an extraordinary number of enrollments, in excess of any previously received in the history of customer choice. Detroit Edison opines that this was caused by supplier hoarding of enrollments, but readily admits the enrollment spike was a result of the Commission’s July 31, 2003 order in Case No. U-13350 (July 31 order) “which denied Detroit Edison transition costs and also reaffirmed the credits being provided to customers who take Electric Choice service.” 2 Tr., p. 47. The flood of new enrollments, it says, placed a unique burden on Detroit Edison, and overwhelmed its resources. However, despite this volume, Detroit Edison argues, it allocated reasonable resources to the problem and managed to resolve the backlog. Therefore, it concludes, the proposed penalty is unwarranted and unjustified. Detroit Edison complains that the ALJ erred in recommending fines and payment of attorney fees. Act 141 requires proof of damages, it says, to justify fines, penalties, and other monetary remedies. Relying on the language of the statute that provides that “the commission shall order such remedies and penalties as necessary to make whole a customer or other person who has suffered damages as a result of the violation” (emphasis added), Detroit Edison construes the Page 6 U-14208 statute to require proof of actual damage as a prerequisite to the imposition of fines or the award of costs and attorney fees. Because Nordic has not proven damages, Detroit Edison concludes, there is no basis to fine it. Even if there were a basis for the fine, this case involves mitigating circumstances that justify the Commission not imposing a fine. Further, Detroit Edison asserts, the ALJ’s recommended fine of $868,000 for 175 violations is not justified because this case involves a one-time deviation that has been corrected, not 175 independent violations. A fine is unjustified, Detroit Edison claims, because it has taken action to fully comply with the 45-day requirement. A warning, it proposes, would be more reasonable and sufficient to address any remaining concerns about future conduct. This is not an enforcement action because the problem has been resolved; rather, Detroit Edison says, this is a case of first impression that poses the policy question of what level of resources Detroit Edison should dedicate to account for extreme volatility in choice enrollments. Finally, Detroit Edison argues that the Commission should not impose additional fines because it has already paid fines for the same time period as a result of the April 28, 2005 order in Case Nos. U-14025, U-14054, and U-14070 (Consolidated Order). See, Consolidated Order, p. 21. The Staff The Staff agrees with the ALJ that Detroit Edison failed to enroll Nordic’s customers in a timely manner, but takes exception with the ALJ’s finding that Detroit Edison committed only 175 violations of the RAST during the time period that is the subject of this complaint. The Staff points out that the Commission found in the Consolidated Order that Detroit Edison violated its RAST in over three thousand other instances for three additional AESs, which is an egregious violation, and Detroit Edison has, in the past, had problems with timeliness. The Staff agrees with the Commission’s computation of damages in the Consolidated Order, that each day Detroit Page 7 U-14208 Edison was out of compliance with its RAST should constitute a separate violation. The Staff further agrees with the ALJ that there is no good faith exception for failure to comply with its tariff. However, because the Commission has already imposed a fine in the Consolidated Order that covers the same facts and time period as this case, the Staff does not recommend that Detroit Edison be assessed an additional fine. However, the Staff does urge the Commission to issue a cease and desist order and reject Detroit Edison’s argument that a cease and desist order is not necessary. Detroit Edison has a history of failing to enroll choice customers in a timely manner, and there is no guarantee, the Staff says, that Detroit Edison will keep staffing at an appropriate level in the future. Finally, the Staff encourages the Commission to open a docket addendum in this case so that Nordic may prove damages consistent with the Consolidated Order. IV. DISCUSSION Detroit Edison does not deny that it failed to enroll Nordic’s customers within 45 days as required by its tariff. Therefore, the Commission finds that the evidence is undisputed that Detroit Edison failed to complete enrollment activities within 45 days for at least 175 of Nordic’s customers as required by Section 2.5 of the RAST. Detroit Edison’s unlawful conduct and flagrant disregard for Commission orders is inexcusable in light of the Commission’s December 20 order that established the 45-day enrollment requirement. Further, the Commission has previously determined in the Consolidated Order that Detroit Edison had knowledge that its enrollments were likely to increase following the July 31 order, yet chose to allow its choice meter-installing personnel to dwindle throughout 2003 from six to two persons and made a management decision not to hire replacements until well into 2004. Page 8 U-14208 Because the Commission adopted the RAST under Section 10a of Act 141, a violation of the tariff is a violation of Act 141 and subjects the utility to the remedies provided in the statute. Moreover, Act 141 specifically allows the Commission to order remedies and penalties if a utility has not complied with a Commission order. Section 10c(1) of Act 141 provides that the Commission, after finding that an electric utility has not complied with a provision or order issued under Sections 10 through 10bb: ….shall order such remedies and penalties as necessary to make whole a customer or other person who has suffered damages as a result of the violation, including, but not limited to, 1 or more of the following: (a) (b) (c) (d) (e) Order the electric utility or alternative electric supplier to pay a fine for the first offense of not less than $1,000.00 or more than $20,000.00. For a second offense, the commission shall order the person to pay a fine of not less than $2,000.00 or more than $40,000.00. For a third and any subsequent offense, the commission shall order the person to pay a fine of not less than $5,000.00 or more than $50,000.000. Order a refund to the customer of any excess charges. Order any other remedies that would make whole a person harmed, including, but not limited to, payment of reasonable attorney fees. Revoke the license of the alternative electric supplier if the commission finds a pattern of violations. Issue cease and desist orders. MCL 460.10c(1). Based upon the statute, Nordic and the Staff request that the Commission (1) issue cease and desist orders, (2) impose fines, (3) award attorney fees, and (4) order Detroit Edison to pay damages for gross margin (minus profit) and losses incurred on excess deliveries of power that were never used. Cease and Desist Order Nordic requested that the Commission issue a cease and desist order requiring Detroit Edison to cease and desist from all delays in processing enrollments within 45 days. The ALJ agreed, Page 9 U-14208 citing Detroit Edison’s history of problems with timely customer enrollments and failure to meet the deadline in such a significant number of instances. The Commission agrees with the ALJ and Nordic that Detroit Edison should be ordered to cease and desist from violating the 45-day enrollment requirement of the RAST. The Commission is not persuaded by Detroit Edison’s argument that a cease and desist order is not needed because of its efforts to resolve the backlog, its performance over the duration of the electric choice program, and the ongoing collaborative process. Costs and Attorney Fees Section 10c(1)(c) of Act 141 allows the Commission to “[o]rder any other remedies that would make whole a person harmed, including, but not limited to, payment of reasonable attorney fees.” Nordic has requested that Detroit Edison be ordered to pay its reasonable attorney fees spent in prosecuting this matter and the ALJ agreed. The Commission agrees that Nordic should be fully compensated for bringing these violations to the Commission’s attention and orders Detroit Edison to pay Nordic, within 30 days, $21,600 for attorney fees and expenses. 2 Tr., p. 26. Following issuance of this order, Nordic shall present to Detroit Edison, within 10 days, a fully itemized, final bill for its reasonable attorney fees and costs in this case, that must be paid within 30 days of issuance of this order unless contested by Detroit Edison. Damages Consistent with Section 10c(1)(c) of Act 141 that allows the Commission to order “any other remedies that would make whole the person harmed,” Nordic requests that the Commission order Detroit Edison to pay Nordic for damages sustained for lost gross margin and excess power prepurchases, whereas the Staff urges the Commission to convene a subsequent proceeding to Page 10 U-14208 determine damages that Nordic incurred because of Detroit Edison’s violation of the RAST. The ALJ found that the record in this case does not support a reliable computation of damages with respect to either lost gross margin or losses attributed to the cost of excess power pre-purchases. The ALJ said that Nordic’s claim for lost gross margin is barred by the AES agreement that prohibits recovery of consequential, incidental, and indirect damages, such as Nordic’s costs for personnel and benefits, depreciation, leases, cost of capital, supplies, utilities, taxes, and profit. Although Nordic did not ask for lost profits, it failed to demonstrate, the ALJ found, that the AES agreement does not bar recovery of these other items as well. Although Nordic claimed it suffered losses attributable to the cost of excess power prepurchases that were never used, the ALJ found that Detroit Edison’s testimony and exhibits raised serious doubt as to the validity of Nordic’s claimed loss. Detroit Edison endeavored to show that Nordic’s scheduled power was insufficient to meet its existing load, and, therefore, it had not purchased excess power to cover new customers who were not enrolled in a timely manner. Further, the ALJ found that Detroit Edison cast serious doubt on Nordic’s calculations for its cost of power per MWh, and, therefore, concluded that Nordic failed to carry its burden of proof with respect to its claim for the cost of excess power pre-purchases. Although the Staff recommended that the Commission open a docket addendum in this case to allow Nordic to present evidence regarding damages using the same methodology used in the similar consolidated case, the ALJ found that the recommendation was unjustified in this case. Nordic opposed the Staff’s recommendation and asked that the damage claim be heard and was given an opportunity to present its case for damages in this proceeding. The ALJ concluded that it would be inequitable and unreasonable to provide Nordic a second opportunity to show damages. Page 11 U-14208 The Commission finds, as the ALJ did, that Nordic failed in its burden of proof regarding losses attributable to the cost of excess power pre-purchases. Fines Nordic requested that the Commission fine Detroit Edison at least $1,000 for the first violation, $2,000 for the second violation, and $5,000 for subsequent violations, pursuant to Section 10c(1)(a) of Act 141, for the 187 Nordic customers Detroit Edison failed to enroll within 45 days as required by the RAST. The ALJ found that Detroit Edison failed to enroll at least 175 of Nordic’s customers in a timely manner and recommended that Detroit Edison be fined pursuant to the statute. The Commission agrees with Nordic and the ALJ that a fine is warranted in this case. The Commission finds that Detroit Edison engaged in anti-competitive behavior and thwarted customer choice and the intent of the Legislature in passing Act 141, by failing to complete enrollment activities for choice customers within 45 days as mandated by the RAST. Detroit Edison, by its actions, has managed to delay, or deny altogether, choice for thousands of AES customers. The Commission agrees with Michael Carosio, Nordic’s Vice President of Sales, that Detroit “Edison’s failure to meet the 45 day meter installation period prevented the Nordic Electric Choice customers from being able to begin enjoying the savings offered by becoming a Nordic customer. The customers paid a higher cost to remain a bundled electricity customer and were prohibited from saving money on their electricity bill.” 2 Tr., p. 23. Although the Commission agrees with Nordic and the ALJ that a fine is appropriate in this case, it also agrees with the Staff and Detroit Edison that it has already paid a fine for most of the days that are the subject of this complaint. See, Consolidated Order, pp. 18-20, where the Commission fined Detroit Edison $5,000 for each of the 195 days from October 20, 2003 through Page 12 U-14208 May 2, 2004, that Detroit Edison was not in compliance with the 45-day enrollment requirement of its RAST. However, the Commission does not agree with Detroit Edison’s argument that Nordic must prove damages prior to the Commission imposing a fine. The complainants in Case Nos. U-14025, U-14054, and U-14070 had not proven damages before the Commission imposed a fine (see, Consolidated Order, pp. 17-20), a fine that Detroit Edison has paid. Exhibit C-2 shows that of the Nordic accounts documented at the hearing, account number 50312270014 took 210 days for enrollment to be complete from October 24, 2003 until May 21, 2004. For the account information available at the hearing, this was the last account that Detroit Edison failed to enroll within 45 days. Detroit Edison was only noncompliant for an additional 19 days beyond what was found in the Consolidated Order. Therefore, the Commission will fine Detroit Edison $95,000, $5,000 for each of the additional 19 days it was in further noncompliance with its RAST. The Commission FINDS that: a. Jurisdiction is pursuant to 1909 PA 106, as amended, MCL 460.551 et seq.; 1919 PA 419, as amended, MCL 460.51 et seq.; 1939 PA 3, as amended, MCL 460.1 et seq.; 1969 PA 306, as amended, MCL 24.201 et seq.; and the Commission’s Rules of Practice and Procedure, as amended, 1999 AC, R 460.17101 et seq. b. Detroit Edison has violated the RAST and the Commission’s December 20 order, and should be ordered to: (1) cease and desist from future violations of the RAST, and (2) pay costs, attorney fees, and fines, as described in this order. Page 13 U-14208 THEREFORE, IT IS ORDERED that: A. The Detroit Edison Company shall cease and desist from violating its retail access service tariff. B. The Detroit Edison Company shall pay to Nordic Marketing, L.L.C., within 30 days of issuance of this order, $21,600 for its reasonable costs and attorney fees. Any additional reasonable attorney fees and costs in the final bill must be paid, within 30 days, unless contested by The Detroit Edison Company. C. The Detroit Edison Company shall pay a fine of $95,000 for its violation of its retail access service tariff and shall deliver to the Commission’s Executive Secretary a cashier’s check for that amount within 30 days of the issuance of this order. The Commission reserves jurisdiction and may issue further orders as necessary. Any party desiring to appeal this order must do so in the appropriate court within 30 days after issuance and notice of this order, pursuant to MCL 462.26. MICHIGAN PUBLIC SERVICE COMMISSION (SEAL) /s/ J. Peter Lark Chairman By its action of October 18, 2005. /s/ Laura Chappelle Commissioner /s/ Mary Jo Kunkle Its Executive Secretary /s/ Monica Martinez Commissioner Page 14 U-14208 THEREFORE, IT IS ORDERED that: A. The Detroit Edison Company shall cease and desist from violating its retail access service tariff. B. The Detroit Edison Company shall pay to Nordic Marketing, L.L.C., within 30 days of issuance of this order, $21,600 for its reasonable costs and attorney fees. Any additional reasonable attorney fees and costs in the final bill must be paid, within 30 days, unless contested by The Detroit Edison Company. C. The Detroit Edison Company shall pay a fine of $95,000 for its violation of its retail access service tariff and shall deliver to the Commission’s Executive Secretary a cashier’s check for that amount within 30 days of the issuance of this order. The Commission reserves jurisdiction and may issue further orders as necessary. Any party desiring to appeal this order must do so in the appropriate court within 30 days after issuance and notice of this order, pursuant to MCL 462.26. MICHIGAN PUBLIC SERVICE COMMISSION _______________________________________ Chairman By its action of October 18, 2005. ________________________________________ Commissioner _____________________________ Its Executive Secretary ________________________________________ Commissioner Page 15 U-14208
© Copyright 2026 Paperzz