APPENDIX F: DRAINAGE AND STORMWATER MANAGEMENT Downtown Ottawa Transit Tunnel: Tunney’s Pasture to Blair Station via a Downtown LRT Tunnel Prepared for: City of Ottawa 110 Laurier Avenue West Ottawa, ON K1P 1J1 Prepared by: Delcan Corporation 1223 Michael Street Suite 100 Ottawa, ON K1J 7T2 January 2010 Table of Contents List of Tables 1.0 DRAINAGE IMPACTS ................................................. 1 1.1 Water Quantity..................................................... 1 1.2 Water Quality ....................................................... 1 Table 1: Conceptual Tunnel Drainage Plan Summary .............. 2 Table 2: Maintenance and Storage Site SWM Facility.............. 3 Table 3: Major Pipe Relocation Requirements ......................... 3 Table 4: Potential Infrastructure Risk and Issue Locations ....... 4 2.0 DRAINAGE DESIGN CRITERIA ................................. 1 2.1 Level of Service ...................................................... 1 2.2 Water Quality ....................................................... 1 3.0 REQUIREMENTS OF THE NETWORK...................... 2 3.1 Ballasted Track ..................................................... 2 3.2 Tunnel Drainage ................................................... 2 3.3 East Portal to Rideau River .................................... 2 3.4 St. Laurent Station to Blair Station ........................ 3 3.5 Maintenance and Storage Facility .......................... 3 3.6 Maintenance and Storage Facility Connecting Tracks ................................................................... 3 4.0 INFRASTRUCTURE RISKS AND RELOCATION REQUIREMENTS ......................................................... 3 4.1 Major Pipe Relocations .......................................... 3 4.2 Potential Infrastructure Risks and Issues ................ 4 4.3 Tunnel Stations Shafts ........................................... 4 5.0 INFRASTRUCTURE DATA GAPS ............................... 4 6.0 IMPACT MITIGATION PLAN .................................... 4 1.0 DRAINAGE IMPACTS 1.1 Water Quantity The LRT track will be supported by ballast and an impervious sub-grade involving the existing paved surface of the Transitway. Typically, the track structure will be built up from the existing Transitway surface, using the existing curbs to retain the ballast. While the ballast will provide flow attenuation and storage, the impervious sub-grade will ensure that runoff volumes will be essentially the same as the existing Transitway. conditions. Thus the redevelopment of the site is expected to have a beneficial impact from a water quantity perspective. Notwithstanding the limited impacts identified above, major system drainage will need be given careful consideration for each element of the system to ensure that the level of service criteria are met under future conditions, the potential impacts on adjacent properties are properly evaluated, and appropriate mitigation measures identified. Particular issues related to major system drainage include: • The existing Transitway infrastructure will be removed where the preferred LRT alignment departs from the Transitway, and will be typically reinstated with a pervious surface. Generally speaking, in terms of water quantity, no negative drainage impacts are anticipated as a result of the project. In fact, the attenuation provided by the ballast is likely to result in a positive impact due to the reduction in existing peak flows.1 In the vicinity of the tunnel portals there will be a significant increase in grade, and the LRT surface will transition from ballast to concrete slab. In these sections, an increase in peak flow rates over existing conditions is anticipated as a result of the project. At some transit stations, new building structures will be required, but most will be integrated with existing Transitway stations or be constructed below ground for the tunnel stations. However, for the sections addressed by this report, the change in imperviousness at transit stations will be small, and can be ignored for the purposes of functional design. For the proposed maintenance and storage facility site, the future imperviousness is expected to be lower than existing 1 Available storage in the order of 1,500 m3/ha of flat rail corridor, whereas the storage needed to manage excess flow resulting from a 100 year storm is only about 200 m3/ha assuming just a 5 year minor system. • Vertical curb extensions to contain rail ballast will impact major system drainage Redevelopment of Transit Stations and the development of the Maintenance and Storage Facility 1.2 Water Quality The conversion from diesel buses to electric LRT is expected to have positive impact in terms of the quality of the runoff from the transit surface. Furthermore, given the lack of any significant increase in impervious area, no significant water quality impacts area anticipated. Based on preliminary discussions with the Ministry of the Environment (MOE), there will, in general, be no need for water quality control facilities. Nonetheless, some water quality control has been proposed for specific locations to improve on existing conditions, address specific issues, and contribute to the overall mitigation plan for the DOTT project. The proposed approach is discussed in the following section on drainage criteria. 2.0 DRAINAGE DESIGN CRITERIA 2.1 Level of Service For planning purposes, the level of service to be provided is based on the Transitway Drainage Guidelines, as documented in the City’s Sewer Design Guidelines. Current practice would require a minimum ten (10) year level of service for the transit corridor and the Transit stations. However, the project characteristics allow for a much higher level of service due to the introduction of a ballasted track surface, and it is proposed that the drainage system be designed to avoid ponding on the ballast up to the 100 year frequency. The actual level of service to be provided in critical areas such as the toe of slopes, and where the track will be fixed to a concrete slab surface, should be based on operational and cost-benefit considerations at the preliminary design stage. Appropriate major system design must be provided for the 100 year event to avoid negative impacts on operations and adjacent properties. Guidelines suggest a 25 year level of service for depressed areas. This event frequency is proposed as the basis of design for the portal pump stations to limit surface drainage into the tunnel. (Excess drainage that reaches the tunnel low point will be combined with tunnel infiltration and pumped to an appropriate outlet). For the Maintenance and Storage Facility, a five (5) year level of service is proposed with an engineered major system as described above. 2.2 Water Quality The future drainage system should maintain or improve on the quality of runoff draining from the existing surfaces. As described in the previous section, the nature of the project is such that no significant impacts on water quality are anticipated, in general. Conversion from diesel buses to electric trains would be expected to result in somewhat improved runoff quality. Nonetheless, the following approach to water quality control is proposed: • Tunnel portals: Pumping facilities will be required at the portals to manage runoff that would otherwise drain into the tunnel. As described in a subsequent section of this report, new outlets are anticipated for the station discharges, and treatment to MOE guideline levels is proposed for these small areas. The proposed outlet 1 • • 3.0 2 locations would require Level 1 protection (80% TSS removal). Maintenance and Storage Facility (MSF): This 12 ha site is highly impervious under existing conditions, and the future use is expected to reduce imperviousness somewhat. However, given that it is a practical location to provide water quality control, a SWM facility has been proposed for this site to improve on existing conditions. Conceptual level sizing is based on Level 1 protection. Maintenance and Storage Facility Connecting Tracks: Roughly 1 km or 1.7 ha of new transit corridor is required to link the Maintenance and Storage Facility to the LRT corridor. Drainage from this corridor will be treated in the proposed MSF SWF described above. REQUIREMENTS OF THE NETWORK For the purposes of functional design of the DOTT project, a conceptual drainage plan has been prepared and is described in this section. Given the limited drainage related impacts, drainage infrastructure needs will be driven by the need to relocate infrastructure to accommodate the project, and identify alternative outlets and/or pumping infrastructure where the profile of the transit system is lowered to the extent that the existing gravity outlet is no longer available. Specific drainage infrastructure needs are addressed for various sections of the project as follows. 3.1 Ballasted Track As noted previously, the existing Transitway sewer system is expected to be sufficient for most sections of the project. However, existing inlets are expected to be insufficient to convey runoff to the sewer system because the ballast which will overlay the catchbasins will effectively reduce inlet capacities. On flat and mild grades, the storage provided by the ballast will compensate for the reduced inlet capacity. However, on steep grades, additional capture capacity will be required. A continuous grate-covered rectangular drainage channel located under the ballast is proposed to interconnect the catchbasins to provide the necessary inlet capacity. 3.2 Tunnel Drainage Portals The West and East Tunnel Portals are located below grade, as they provide access and egress to the proposed tunnel by the LRT vehicles. Thus existing grades will be substantially increased in the vicinity of the portals. The general concept is that the LRT corridor will transition from a ballasted track to a concrete slab surface at the top of slope descending to each portal. There are significant lengths of transit corridor that will drain towards each portal. The drainage approaching the portals must be managed appropriately to maintain the required level of service and avoid negative impacts on transit operations. A pumping station will be required at each portal to intercept and pump drainage from the slope leading to the portal.2 The pump station capacity is based on a 25 year storm. Excess flow from very large storms will be routed through the tunnel in drainage channels to the tunnel low point to be located at the Downtown East transit station. Tunnel The International Tunneling Association (ITA)3 recommends a maximum infiltration allowance of 0.082 L/m2/day (0.002 gal/ft2/day). For planning purposes, a design infiltration rate of 0.15 L/m2/day was selected. Based on a rough estimate for the total tunnel surface area (two tunnels and four stations) of 165,000 m2, the design infiltration rate would be less than 1 L/s for the entire tunnel. 2 There may be an opportunity to provide a gravity outlet for the West Portal, requiring the construction of a very deep sewer discharging to the Tailrace. This option should be given further consideration at the preliminary design stage. 3 http://www.fhwa.dot.gov/bridge/tunnel/pubs/nhi09010/01a.cfm Key parameter estimates associated with the conceptual drainage plan for the tunnel are summarized in Table 1. The total dynamic head (TDH) given in Table 1 is based on the assumption that a suitable outlet sewer is available (or will be provided) a horizontal distance of 20 m from the station for the West Portal and Tunnel Low Point stations. Due to a number of constraints related to flooding issues in adjacent drainage systems (Sandy Hill), topographic constraints, and nearby contaminated soil conditions, this is unlikely to be the case for the East Portal. For the East Portal, a 800m forcemain is estimated to be required to a new gravity outlet sewer east of Lees/Chapel. Table 1: Conceptual Tunnel Drainage Plan Summary Parameter Drainage Area (ha) Pump Station Capacity (L/s) Active Wet Well (m3) Forcemain Size (mm) Forcemain Length (m) Total Dynamic Head (m) West Portal 0.35 50 East Portal 0.90 125 Tunnel Low Point 25 50 250 30 10 130 400 800 12 25 200 60 40 3.3 East Portal to Rideau River Drainage from about 425m beyond the East Portal along the track alignment will drain to the East Portal Pump Station, which is discussed in the previous section. This section covers the area from 425m south of the East Portal to the high point on the bridge crossing the Rideau River. Given the short, rising grade from the East Portal to the Rideau River Bridge, it has been assumed that the rail will be fixed directly to concrete throughout the section. Drainage will be provided by the existing Transitway drainage system. However, to limit carryover flows to the East Portal, an increase in storm capture in this section is anticipated, with associated storm pipes oversized to provide the storage necessary to avoid downstream impacts. With grades ranging from 0.5% to 5%, ballasted track would be of limited benefit from a surface storage perspective. 3.4 St. Laurent Station to Blair Station This section is expected to be dominated by ballasted track, and no change in imperviousness is anticipated. Thus the existing Transitway drainage system would be expected to meet the future LRT needs in this section of the project. However, the profile of the system will drop several metres, starting from roughly 350m west of Blair Station. The existing storm sewer that serves the Transitway will need to be relocated. In order to provide drainage for the new profile, the sewer will need to be lowered. Preliminary investigations indicate that sufficient grade is available to serve the area with the same outlet location at the Cyrville Drain. However, more detailed analysis will be required to verify that the required level of service can be provided, considering flow levels in the Drain at critical frequencies. While the proposed drainage plan does not include provisions for introducing upgraded SWM to this section of the project, the feasibility of upgrading the existing Gloucester City Centre Dry Pond (incorporating practical water quality management features) and diverting the lowered sewer to the pond should be investigated. (The design report for this pond is unavailable.) 3.5 Maintenance and Storage Facility The Maintenance and Storage Facility will cover an area of approximately 12 ha. Under existing conditions, the total imperviousness of the site is about 85%, whereas a future imperviousness in the order of 50% is anticipated. The site development is expected to improve on existing conditions with respect to runoff quality and quantity. Nonetheless, as discussed in the section on drainage criteria, a SWM facility (wet pond) is proposed for the site to manage runoff from the site, and contribute to the mitigation of overall DOTT project impacts. The ultimate outlet for the drainage area is the Rideau River, and Level 1 protection was assumed for the basis for the treatment volume. Any major system issues associated with the existing site, and the impact of the development on major system drainage will need to be investigated at the preliminary design stage. To account for additional SWM needs associated with major drainage, the conceptual sizing of the SWM facility is based on attenuation of the peak 100 year runoff from the site to the existing 5 year rate, in addition to the water quality storage. The estimated SWM facility characteristics are summarized in Table 2. Table 2: Maintenance and Storage Site SWM Facility Parameter Value Surface Area 0.4 ha Quality Storage Volume 3,600 m3 Total Storage Volume 5,800 m3 Peak 100 Year Outflow 2.6 cms 3.6 Maintenance and Storage Facility Connecting Tracks The tracks that link the Maintenance and Storage Facility to the LRT corridor east of Train Station will curve away from the corridor and pass down through two tunnel portals located east and west of Belfast Road, merging about 50 m south of Tremblay Road, and rising back to existing ground elevation about 575 m south of Tremblay at the west end of the Maintenance and Storage Facility. Approximately 0.6 ha of fully impervious area will drain to two low points located on the east and west branches of the connecting tracks. These two low points are located within about 30m of each other. A single pumping facility and forcemain is proposed to drain the connecting track low points, and discharge to a new sewer draining to the proposed Maintenance and Storage Facility SWM facility described in the previous section. For planning purposes a pump station with capacity in the order of 150 L/s (assuming a wet well of roughly 65 m3 of active storage), and a 400 mm forcemain, roughly 600 m in length will be required to handle a 100 year storm, plus any adjustments to the Maintenance and Storage Facility sewer system. The sizing of the Maintenance and Storage Facility SWM facility will also need to be adjusted to accommodate the forcemain discharge so that treatment objectives and the estimated existing peak site discharge rate of 2.6 cms can be maintained. 4.0 INFRASTRUCTURE RISKS AND RELOCATION REQUIREMENTS Potential infrastructure conflicts for the entire project corridor were determined (considering pipes 400 mm and larger) based on information provided by the City of Ottawa including GIS databases for water and sewer, in addition to available as-built drawings for pipes located in the study area. A number of data gaps were identified as summarized later in this section of the report. Further investigations will be required to confirm the relocation and risk areas identified in this section. 4.1 Major Pipe Relocations Major pipe relocation requirements are summarized in Table 3. Only one known conflict has been identified, but several other major pipes have been identified for reconstruction to carry the proposed embankment loads in the vicinity of Hurdman Station. Several other major pipes are within 2 m of the tunnel or LRT surface. These latter pipes are described in the following section. Table 3: Major Pipe Relocation Requirements Service Pipe Diameter (mm) Blair Station to Cyrville Drain Storm 750, 900, 1050 Hurdman Station Storm 1650 Hurdman Station Storm 1200 Hurdman Station Sanitary 1350 Hurdman Water Pumping Station Storm 1200 Location Comment ~1km of sewer must be lowered to drain new profile in vicinity of Blair Station. Further investigation to verify level of service possible. To be reconstructed to carry embankment load To be reconstructed to carry embankment load To be reconstructed to carry embankment load (Rideau River Collector) To be reconstructed to carry embankment load 3 4.2 Potential Infrastructure Risks and Issues Potential infrastructure risks are identified in Table 4. Known major infrastructure is identified where it intersects the corridor and is within about 5 vertical metres from the tunnel or LRT surface. Infrastructure 400mm and larger is highlighted where it is within 2 m of the tunnel/LRT surface. Infrastructure that must be relocated is excluded from Table 4 (see previous section). It should be noted that the conversion from bus to rail on the West Transitway, west of Bayview, may conflict with existing access points to the twin 3800 mm x 2000 mm box storm sewers. Construction of new access points (e.g. offset maintenance holes) to these sewers may be required. Further investigation will be required at the preliminary design stage. Table 4: Potential Infrastructure Risk and Issue Locations Location 4 Service Pipe Diameter (mm) Twin 3800 x 2000 Tunney’s Pasture Station to West Side of Bayswater Bridge West Side of Bayswater Bridge Bayswater Water 2100, 2100, 750 1950 East of Bayswater City Centre City Centre Broad Street Broad to Booth East of Booth Commissioner Templeton Combined Combined Storm Sanitary Combined Sanitary Water Sanitary 1200 1200 1800 950 1500 1800 1500 1800 Greenfield Storm 750 Lees Water 1200 Rideau Canal Colonel By Drive at Rideau Rideau River Combined Storm 2300 1350 x 2025 1500 Storm Storm Sanitary Comment Existing box storm sewers are less than 1m below LRT grade Three storm sewers crossing corridor near west end of bridge Major high pressure transmission main (HPTM) from Lemieux Island Plant Cave Creek Collector Cave Creek Collector Nepean Bay Storm Trunk Sewer Status of pipe to be confirmed Cave Creek Collector Ottawa Interceptor Sewer Fleet Street PS discharge main Status of pipe to be confirmed. Pipe is less than 0.5 m above tunnel Pipe is less than 1 m above tunnel Main transmission line to 1E and 2E Pressure Zones Rideau Canal Interceptor DPW Tunnel Rideau River Interceptor Location Interceptor Hurdman Water Pumping Station East of Riverside East of Riverside East of Train Station East of Train Station Tremblay, East of Train Station Tremblay from East of Train Station to St. Laurent Tremblay East of Belfast Maintenance and Storage Facility Connecting Tracks at Tremblay Maintenance and Storage Facility Connecting Tracks at Tremblay Maintenance and Storage Facility Connecting Tracks at Tremblay West end of HWY 417 Underpass St. Laurent Station St. Laurent Station Service Pipe Diameter (mm) Water 1200 Storm Storm Sanitary Storm Water 1950 1500 600 1050 1200 Storm 1650 Water 1050 Water 1200 Storm 900 Comment Two discharge transmission mains serving pressure zones 1E and 2E. East side of bridge embankment East side of bridge embankment Pipe is within 1m of LRT grade Status of pipe to be confirmed Main transmission main through Zone 1E Storm sewer serving existing Transitway Major transmission main serving Zone 1E Main transmission main through Zone 1E Pipe is within 2 m of top of MSF tunnel Sanitary 600 Pipe is within 2 m of top of Maintenance and Storage Facility tunnel Water 1050 Storm 1650 Major transmission main serving Zone 1E Drains Transitway. Obvert less than 1 m below LRT grade (350 m length) Siphon less than 1 m below LRT grade Sanitary 525 4.3 Tunnel Stations Shafts A number of watermain and sewer relocations will be required to accommodate construction of the tunnel station shafts. In general, worst case locations were assumed for these shafts, or it was confirmed that major infrastructure could be avoided. It has been concluded that no major pipes are associated with these shafts. However, relocation of minor infrastructure will be required. 5.0 INFRASTRUCTURE DATA GAPS A number of data gaps exist and require further investigation to confirm complete scope of drainage and infrastructure risks associated with the project. In general, current as-built drawings and/or field investigations are needed. Gaps for the project include: • • • • • Infrastructure in the vicinity of the West Portal. While no conflict with the DOTT project is apparent, further investigation is needed to confirm the alignment of pipes that are of critical importance to the City’s water distribution and wastewater collection systems. Infrastructure in the vicinity of Rideau Station. While no conflict with DOTT project is apparent, further information is needed to confirm inverts of the Rideau Canal Interceptor and the DPW Tunnel. 750 mm Storm Sewer at east end of Hurdman Station. Storm outlet and main sewers to Rideau River from St. Laurent to Train Station. Transitway drainage infrastructure. No information on transitway drainage infrastructure has been provided for several sections of the project including: Lees Station to Rideau River; St. Laurent to east of Cyrville Drain. 6.0 IMPACT MITIGATION PLAN From a drainage perspective, the project is expected to have very limited impacts. Stormwater Management Facilities are proposed for specific drainage areas (tunnel portals and Maintenance and Storage Facility) to improve on existing conditions. Surface storage provided by the introduction of ballast to the existing Transitway surface is also expected to attenuate sewer flows in several areas. The detailed design phase must include specifications for sediment and erosion control to be complied with during construction. These specifications will be prepared in accordance with relevant Provincial and Regional legislation, guidelines and by-laws.
© Copyright 2024 Paperzz