Project Record Version 1 – 11/15/2016 Returning Meter 2.0: Field Meters Troubleshooting Testing Energy Monitoring and Management Systems Nathaniel Pardoe Paul Tajiri Project Record: Version 1 11/15/2016 ABSTRACT Returning from the field in Burkina Faso were two of our Meter 2.0 meters. According to our client, these two meters failed during operation and it was our task to determine the reason for their failure. After testing the functionality of different sections of each meter it was determined that the display box of the Rad House meter failed in its operation, causing the rest of the meter to fail. On the other hand, the Team Hut meter functioned as desired and appeared to have no problems. VERSION HISTORY Version 1 Author(s) Nathaniel Pardoe, Paul Tajiri Date 11/15/2016 Description Troubleshooting faulty returning 2.0 meters from the field Page 2 of 5 File Name Returning Meter 2.0 Project Record Project Record: Version 1 11/15/2016 Goal of Study The primary goal of this MVP was to troubleshoot the returning 2.0 meters (Team Hut meter and Rad House meter) from Burkina Faso in order to determine what causes their failures. Then once the failures were identified, the secondary goal was to implement fixes in order to restore the functionality of the meters. Background Returning from the field in Burkina Faso were two of our Meter 2.0 meters. These meters were installed in Burkina Faso for our client Matt Walsh in the summer of 2014. One meter was installed at the facility called Team Hut, while the other meter was installed at the facility called Rad House. Over the course of time the individuals at these facilities came to the conclusion that for unspecified reasons these two meters failed in operation. In the summer of 2016, Tom Austin removed these meters from their facilities in order to be troubleshooted back in the states by the rest of our team. In addition, while out in Burkina Faso Tom Austin needed to remove some of the capacitors on the command board and display board of the Rad House meter. This needed to be taken into account when troubleshooting issues with the Rad House meter. Procedure In order to properly troubleshoot the meters and attempt to identify the reasons for their assumed failure, we needed to approach the meters in distinct parts. This means testing different parts of the meter to see whether or not each individual part functioned as expected. In order to do this, we looked at the meter in three separate test sections, the power supply, display box, and command board. Figure 1: Two 2.0 meters from Burkina Faso We first started to test the power supply section of both meters. We did this by powering the meter with 120V AC as the meter normally would be when powering a facility. The power supply board should then take this 120V AC input and provide two different outputs: 12V DC and 640mV peak to peak AC. The power supply sections for both the Rad House and Team Hut meters worked as expected. The next section that we tested was the display box for each meter. This was done by Page 3 of 5 Project Record: Version 1 11/15/2016 powering on the meters and connecting the display box via ethernet cable to the command board. The display board for the Team Hut meter worked as expected, as all functions were operational and the information displayed was what was expected. The display box for the Rad House meter however did not work as expected, as the display would not even energize. With further analysis it was found that some of the capacitors were missing from the Rad House display box, and one of the soldered on jumper wires broke off. Overall, it appeared that only the Rad House display box was not functioning properly. Figure 2: In the red box is the jumper wire that needed to be resoldered for the Rad House display board. A broken capacitor on the Rad House display board is shown in the green box. Moving on from the display box, we looked at both command boards by using the functional Team Hut display box for both meters. When we put 120V AC through the Team Hut meter and connected a load to simulate energy usage (basic lamp), it appeared that the Team Hut meter worked as expected. We were able to allocate a specific amount of power to the meter and saw the power allocation bar graph on the display box decrease over time when the load was connected. Then once the allocated power amount was reached and the power allocation bar graph on the display box reached 0%, power to the load was cut off (turning off lamp). On the other hand, it appeared that the Rad House meter did not function as expected. When the meter would be connected to 120V AC, the meter would energize and the display box (using the functional Team Hut display box) would work as expected. However, after about one minute, a “link connection error” message would appear on the display box, and the meter would power cycle. After further analysis, it was found that additional capacitors were also missing from this board as well. Page 4 of 5 Project Record: Version 1 11/15/2016 Figure 3: These photos show the Team Hut meter working as expected. The left photos show the meter when power is first allocated (lamp is ON). The right photos show the meter when power allocation has been used up (lamp is OFF). Results After testing the functionality of the two meters, we determined that the Team Hut meter worked without any issues, while the Rad House meter did have issues. We were able to narrow down the Rad House failures to the following two issues: 1) the display box not energizing and missing capacitors & a wire lead 2) the command board power cycling every minute and missing capacitors (note: the missing capacitors as mentioned before were due to Tom attempting to use these capacitors on the newly installed meters while in Burkina Faso). We then transitioned to our secondary goal of attempting to fix the Rad House meter. The first step to do this was to try and fix the Rad House display board by adding the correct capacitors to the board and re-soldering the loose wire lead. Upon doing this, the display board still would not energize and a fix for the display board was not reached. Since fixing the meters was not our primary objective, we decided to stop our attempt to further fix the Rad House meter and move on to a different task for the EMMS project. Conclusion In conclusion, after the testing the meters everything seemed to be working as expected on the team hut meter. In the future, the project might try to perform long term testing to see if any errors show up. On the other hand, the rad house meter was not functional. The display board would not energize and the power cycle would reset every minute on the command board. The project determined that the display board failed in Burkina Faso most likely due to a broken connection, with the command board errors coming from when Tom took the capacitors off of it. The version 2.1 meters had the same problems with the command board and were missing these capacitors. With this information the project can conclude that the the errors were just a durability problem and not any flaw in the electrical design. The project is currently working on a new display box enclosure that should hopefully increase its durability. Page 5 of 5
© Copyright 2026 Paperzz