A ‘PERFECT STORM’ WILL HIT UK POWER GENERATION UNLESS GOVERNMENT ACTS NOW April 2016 A combination of circumstances, due partly to economic conditions but predominantly government policy, is holding up necessary investment in capital power plants in the UK. The recently confirmed closure of all of our large coal fired plants by 2025, along with the planned closure of older and less efficient gas fired plants, means we should be investing in large scale replacement capital power. Yet the ongoing delay in constructing the new nuclear power plants that will replace the Advanced Gas Reactor (AGR) nuclear power plant fleet, which is nearing its end life, means we will become more and more reliant on building additional modern and efficient Combined Cycle Gas Turbine (CCGT) power plants to provide us with our electricity needs. Lack of certainty in the regulated power market has meant that private developers, including the big six utilities, are currently struggling to build new large scale gas fired power plants. Meanwhile existing coal plants and some gas plants must close in order that the Government meets its commitments to environmental targets. Urgent Government intervention is required to ensure that the current uncertainty in the market is replaced by developer confidence, and that a realistic timeline is established that will deliver the necessary construction of new build capital generating capacity in time to prevent the lights going out. A recent paper by the Institution of Mechanical Engineers (IMechE) points to a potential UK electricity shortfall, as existing coal fired power plants are phased out by 2025, existing nuclear plant is decommissioned and new build nuclear continues to be delayed. We potentially need up to 30 new CCGT power plants to fill the gap, but the problems in achieving this target are numerous. ISSUES WITH THE CAPACITY MARKET AUCTIONS The governments’ ongoing strategy for Electricity Market Reform has a number of mechanisms to drive reform. One of these places National Grid in the role as the Delivery Body administering the Capacity Mechanism (auction) which was first introduced in 2014. The annual Capacity Market Auctions of 2014 and 2015 were each designed to ensure that adequate generating capacity will be available four years from the auction date, by awarding agreements to existing and refurbished power plant operators and new build power plant developers. The mechanism is designed to help balance supply and demand, and maintain adequate reserve capacity for periods of high demand, for example during severe winters. The viability of investment in new CCGT plants is dependent upon obtaining agreement through the Capacity Market Auction at a clearing price which provides an acceptable return on the investment for developers and lenders. However, the results of the 2014/15 and 2015/16 Capacity Market Auctions provided little encouragement to developers of large CCGT power plants. According to National Grid’s Transmission Entry Capacity (TEC) Register, there are 13 large Urgent Government intervention is required to ensure that the current uncertainty in the market is replaced by developer confidence new-build CCGT projects that have been consented and have a grid connection agreement, which is the minimum entry requirement to the Capacity Market Auction, with a combined capacity of around 12 GW. Another two large CCGT projects are in the scoping and consenting phase with a combined capacity of 3 GW. The fact is, there are only two large scale new-build CCGT’s that have got through the Capacity Market Auction to date. In the 2014 Capacity Market Auction, Wainstones Energy Ltd (1656 MW) was awarded a 15 year agreement at a clearing price of £19.4/kW/year, and in the 2015 auction Carrington Power Ltd (810 MW) was awarded a 15 year agreement at a clearing price of £18/kW/year. In 2014, a total of 15.7 GW of capacity exited the Capacity Market Auction above the clearing price; only electricity the plant will be required to produce in its working life (Load Factor). Typically developers require a payback period of at least 15 years at a relatively high Load Factor. When added to other uncertainties, including the future cost of fuel, electricity price and demand, and environmental legislation, there is great uncertainty for developers and lenders wishing to make a viable long term investment. CAPACITY CONSTRAINTS DEMONSTRATE NEED FOR CHANGE Worryingly, the 2014 and 2015 capacity agreements for coal fired generation showed a drop in capacity from 9.2 GW for 2018/19 to 4.6 GW for 2019/20. This is going to be further exacerbated by the impact of the Industrial Emissions Directive (IED), which came into force on 1 January 2016 and will force the closure of virtually all existing coal and a number of gas plants on or before 31 December 2023 under the ‘Limited Life Derogation’ option. The total capacity of coal fired generation with agreements for 2019/20 is just 7 GW approximately. As a result, we need many more new build CCGT developments to replace this capacity. Given a typical four year period to design and construct a CCGT power plant, these new build projects must start now if they are to be completed in advance of the coal station shutdowns. ADDRESSING THE SHORTFALL 8.8 GW (35%) of which was new build CCGT capacity. In 2015 the figure was slightly better at 11.4 GW, of which 5.5 GW (47%) was related to new build CCGT. Coal fired generation set to lose 50% of capacity between 2018/19 – 2019/20 The story isn’t much better if we look solely at new build capacity, rather than CCGT. The 2014 Capacity Market Auction resulted in 2.6 GW of new-build capacity awarded; just 5% of the total awarded capacity. 2015 was slightly worse, with 1.9 GW of newbuild capacity awarded, equating to around 4% of the total. The two new-build CCGT plants with capacity agreements make up more than half (approximately 55%) of the total awarded new-build capacity to date. The remaining awarded capacity was made up mostly of a large number of sub 20 MW diesel and gas plants. UNCERTAINTY FOR DEVELOPERS AND LENDERS The Capacity Market Auction of 2014 and 2015 clearly favoured existing generation, refurbishments and relatively low CAPEX plants, such as small scale diesel and gas plants. This provides limited headroom for new-build large scale capital plant until existing coal and nuclear plants are scheduled to shut down. The clearing price is currently too low to make large newbuild CCGT plants viable. Additionally the Capacity Mechanism currently offers no guarantee to developers on the amount of To ensure security of supply beyond the next few winters, the Department for Energy and Climate Change (DECC) stated in its Single Departmental Plan for 2015 to 2020 that it intends to review the operation of the Capacity Mechanism to ensure it provides the right investment incentives for new gas plants to be built in the UK. The urgency for action was exacerbated in February 2016 when SSE announced that it is proposing to end commercial operations at three of the four units at its coal fired power plant at Fiddlers Ferry from April 2016. This is despite SSE having secured a capacity agreement for 2018/19 under the 2014 Capacity Market Auction. This leaves a potential generating shortfall that the government will need to address. An additional factor is the timing of the shutdown of existing AGR nuclear plants, and their replacement by new nuclear capacity. The timing of the new nuclear capacity coming on line will be key to determining how much new CCGT capacity will ultimately be required. There is currently approximately 9 GW of existing nuclear capacity in the system, with approximately 17 GW nuclear new-build planned. It is uncertain when existing capacity will drop off and when new replacement capacity will be connected, but currently we don’t expect new nuclear capacity to be connected until at least 2025. However, positive news came in February when EDF announced it planned to extend the life of some of its existing nuclear plants beyond 2025. If this is achieved it would mitigate the scale of the potential energy gap. Which CCGT plants go ahead and when they start is wholly dependent on the individual project economics related to the clearing price at future Capacity Market Auctions, along with the cost of risk associated with the uncertainties. There is broad industry anticipation that government will make the necessary changes to the Capacity Mechanism to remove some of this uncertainty and to encourage new-build CCGT. THE FUTURE FOR UK POWER A revitalised power plant construction sector in the UK would generate significant employment but may be constrained in the short to medium term. As a result of the prolonged lack of investment, multiple simultaneous CCGT projects underway in the UK would be required to compete for the same scarce design and construction resources. Similarly, the numbers of original equipment manufacturing organisations active in this market have reduced and the manufacturing capacity of their plants has fallen. The pace of new-build CCGT implementation is currently being driven by supply and demand economics through the Capacity Market Auction the lowest price wins – as opposed to designing a balanced mix of technologies as was done in the past. The Capacity Mechanism has been designed with the intention of helping to ensure ‘the lights don’t go out’, and new-build CCGT should play an important part in that. However, the buffer provided by the infrastructure that was previously built in the main by the nationalised Central Electricity Generating Board (CEGB) has all but come to an end. This and the other factors have combined to create ‘a perfect storm’ of uncertainty for developers of and investors in large CCGT projects. The Capacity Market Auction needs to change to support CCGT, and it needs to change now. CONTACT Paul Webber Partner T +44(0)7887 626 575 E [email protected]
© Copyright 2025 Paperzz