DRAFT Internal Audit Report Computer Recycling Document Details: Reference: Senior Manager, Internal Audit & Assurance: Engagement Manager: Auditor: 2.7/2013.14 ext. 6567 ext. 6572 ext. 6244 Date: 4th August 2015 1. EXECUTIVE SUMMARY 1.1 INTRODUCTION This report is not for reproduction publication or disclosure by any means to unauthorised persons. Page 1 Internal Audit Report – Computer Recycling As part of the 2013/14 Internal Audit Plan an audit of computer recycling was carried out. It is important that appropriate processes are in place with regards to computer recycling and that they are in line with agreed procedures. Worcestershire County Council produces an appreciable amount of ICT waste each year, mainly comprising of PC's, Laptops, Printers and Servers. The Council currently replaces approximately 1000 PCs per year. The equipment disposed of is normally 4 to 5 years old; the proportion of desk tops to laptops is 50/50. The Council also disposes of a number of servers and these are normally 4 to 8 years old. The introduction of the Public Services Social Value Act 2012 requires Local Authorities to consider how scarce resources are allocated and used. Social Value has been defined as "A process whereby organisations meet their needs for goods, services, works and utilities in a way that achieves value for money on a whole life basis in terms of generating benefits to society and the economy, whilst minimising damage to the environment." The Council has entered into contracts to provide a disposal service for its obsolete ICT equipment in accordance with the European Waste Electrical and Electronic Equipment Directive (ICT WEEE) and has looked to contract with businesses that will provide opportunities for people with learning disabilities in order to meet social value requirements. 1.2 OVERALL OPINION The audit work has identified a clear management commitment to ensuring that personal data is disposed of in a secure manner. Whilst there are a number of good practices in place, the concerns identified around procedures, contractual arrangements and security have led to a limited assurance audit opinion. Officers responsible for computer recycling were unable to provide copies of contracts with either Lifestyles or Newstart for the recycling of the Council's computers. There is a requirement to update procedural documents to reflect current procedures. Consideration should also be given to a more detailed Asset Disposal Strategy that addresses the process of IT asset disposal and personal data deletion. The Council has a computerised inventory system. However, the system requires the Business Support Assistant to manually update the status of computers at each stage of the recycling process. There was evidence to suggest that the computerised inventory is not updated in a timely basis. Moreover, computer recycling progress sheets produced by recycling companies have not been checked and updated on the inventory for three months at the time of audit testing. Consideration should be given to whether there are more efficient and timely ways to process this information. Page 2 Internal Audit Report – Computer Recycling Computers are authorised for disposal by the Business Support Assistant. However, the Business Support Assistant is not on the Directorate's scheme of delegation and is therefore not authorised to release the computers to the recycling companies. Examination of the Council's computerised inventory record revealed that 5 computers that had been sent to Lifestyles for recycling, have been classed on the inventory as missing. Full investigations should be undertaken into any missing computers. The Council has not carried out any inspection of the companies who recycle the Council's computers to ensure that they are operating in accordance with WEEE standards. Overall Audit Opinion Full assurance Full assurance that the system of internal control meets the organisation’s objectives and controls are consistently applied. Significant assurance Significant assurance that there is a generally sound system of control designed to meet the organisation’s objectives. However, some weaknesses in the design or inconsistent application of controls put the achievement of some objectives at some risk. Limited assurance Limited assurance as weaknesses in the design or inconsistent application of controls put the achievement of the organisation’s objectives at risk in some of the areas reviewed. No assurance No assurance can be given on the system of internal control as weaknesses in the design and/or operation of key control could result or have resulted in failure(s) to achieve the organisation’s objectives in the area(s) reviewed. 2. SUMMARY OF CONCLUSIONS 2.1 The conclusion for each control objective evaluated as part of this audit was as follows: Page 3 Internal Audit Report – Computer Recycling Control Objective Full CO1: Ensure that Policies and Procedures are available and appropriately approved. CO2: Ensure that the disposal of computer equipment for recycling is in accordance with the approved policies and procedures. CO3: Confirm the Security of computer equipment prior to disposal and that all data has been fully removed. CO4: Ensure that the disposal of computer equipment is in accordance with the contracted arrangements in accordance with the specified targets. Assurance Significant Limited None 2.2 The recommendations arising from the review are ranked according to their level of priority as detailed at the end of the report within the detailed audit findings. Recommendations are also colour coded according to their level of priority with the highest priorities highlighted in red, medium priorities in amber and lower priorities in green. In addition, the detailed audit findings include columns for the management response, the responsible officer and the time scale for implementation of all agreed recommendations. 2.3 Where high recommendations are made within this report it would be expected that they should be implemented within three months from the date of the report to ensure that the major areas of risk have either been resolved or that mitigating controls have been put in place and that medium and low recommendations will be implemented within six and nine months respectively. 3. LIMITATIONS REGARDING THE SCOPE OF THE AUDIT The following areas did not form part of this audit: The auditor only looked at a random sample of items processed on the inventory and did not carry out any checks on equipment that had been sent to the recycling companies. 4. ACKNOWLEDGEMENTS Audit would like to thank all involved for their assistance during this review. Page 4 Internal Audit Report – Computer Recycling 5. DETAILED AUDIT FINDINGS Ref. Priority Findings Risk Arising/ Consequence Recommendation CO1: Ensure that Policies and Procedures are available and appropriately approved. 1 Medium The Council has a computer The computer The Council should review recycling procedure. However, recycling procedures the current policies and there is no indication of the used by the Council procedures to ensure that date when this was written, are out of data and do they reflect the risks reviewed or an expected not reflect the current associated with redundant review date. controls and hardware recycling and procedures within the ensure that data is cleansed Appendix one refers to data Council. to Government standards removal. However, there no by the individual recycling longer appears to be a companies. requirement for this to be completed by staff as data removal is now carried out by The procedures should be recycling Companies. reviewed on a regular basis. 2 Medium The computer recycling procedure only refers to one of the two recycling company that the Council uses. There is no detailed Asset Disposal Strategy that addresses the process of IT asset disposal and personal data deletion. If personal data is compromised during the disposal process, the council may be responsible for breaching the Data Protection Act (DPA). The Information Commissioners Office has produced an IT asset disposal for organisation document. The Council should ensure that this is referred to when drafting a computer recycling procedure. This refers to various Management Response Agreed that the current recycling processes are not incorporated into the Inventory Procedures that state actions and responsibilities during the lifecycle of ICT assets. Responsibility Recommendation and Timescale Implemented (Officer & Date) ICT Service Operations Manager to update by end of November 2014. This will need to be updated. The Council allows reasonable personal use of ICT equipment and services and there is opportunity for personal data to be found on the PC as copies of documents or emails. It is the responsibility of the user that they handle the personal data that may be ICT Service Operations Manager to update by end of November 2014. Internal Audit Report – Computer Recycling Ref. Priority Findings Risk Arising/ Consequence Recommendation aspects including a consideration of how personal data will be disposed of, conducting a risk assessment of the disposal process and categorising personal data. 3 High Officers responsible for recycling could not provide copies of contracts with either of the current providers, Lifestyles or Newstart for the recycling of computers. There is a lack of a formal agreement between the Council and the recycling companies to determine individual responsibilities. Data may not be cleansed to Government standards. There is also a potential breach of There is also a requirement to identify devices containing personal data. Whilst a significant amount of data may be stored on laptops and PCs there also needs to be consideration of other devices such as faxes, printers, servers, smartphones, tablets and USB backups or storage. The Council should ensure that there is a contract in place with individual recycling companies reflecting responsibilities regarding the recycling process. The contracts should include: • explicit direction on the services to be undertaken and that it may only act in accordance with the Council's instructions; Management Response Responsibility Recommendation and Timescale Implemented (Officer & Date) present on their devices to be handled appropriately. This responsibility needs to be emphasised strongly via computer sage policy. S&CA will review the process to derive a formal agreement between WCC and the Recyclers. ICT Service Operations Manager and ICT Contracts Manager to derive a formal agreement that will cover statement if responsibilities by end December 2014. Internal Audit Report – Computer Recycling Ref. Priority Findings Risk Arising/ Consequence Recommendation Management Response • an approved specification for IT asset disposal which is aligned to the Council's disposal/security policy; CO2: Ensure that the disposal of computer equipment for recycling is in accordance with the approved policies and procedures. 4 High The Business Support Computer equipment The recycling of computer The recycling process will be Assistant is responsible for is being authorised to equipment should be changed to ensure that authorising the disposal of the be recycled by a nonapproved by a senior scheme of delegation is not items of equipment recorded authorised member of member of staff in undermined. This role will on the computer recycling staff. accordance with the have to be performed by sheets, which are then signed Directorate's Scheme of senior members of ICT by a member of staff from the Delegation. management team. recycling company on collection of the equipment. The Information This will also add an extra Commissioners Office layer of validation to those The Business Support recommends that there is devices being recycled. Assistant is not an authorised an asset disposal champion officer and is not on the with a sufficient level of Authority's Scheme of authority. Delegation. 5 Medium A sample of nine laptops and The Council's When computers are placed It would be good to provide one tower PC held in the inventory is not kept in the recycling cage the automation for the recycling recycling cage were checked up to date. inventory should be process. This automation is against the inventory. automatically updated to present when taking reflect the change in status. allocating stock. The nine laptops were still showing on the inventory as S&CA will investigate located with their previous user opportunities to provide that and had not been updated to form of automation at the reflect the current status. recycling stage. Responsibility Recommendation and Timescale Implemented (Officer & Date) the DPA. If automation is not possible, the manual update to inventory will be expedited. ICT Service Operations Manager to update by end of November 2014. ICT Service Operations Manager to schedule a review of the automation process for recycling, and implement, by end of December 2014. Internal Audit Report – Computer Recycling Ref. 6 Priority Findings Risk Arising/ Consequence Recommendation Management Response Low A Dell tower PC did not have a WCC sticker and the serial number could not be found on the asset register. There is no audit trail back to the inventory. All items placed in the recycling cages should have a WCC sticker so that the item can be traced through to the inventory. S&CA does not offer a service to recycle other user equipment however it sometimes does have nonWCC equipment presented to it for recycling, (either personal or schools equipment). Responsibility Recommendation and Timescale Implemented (Officer & Date) ICT Service Operations Manager to update by end of November 2014. Where this is the case, there will not be a WCC sticker present, and therefore not on the WCC inventory. This is invalid in the recycle process. Where such situations are found, S&CA will issue a WCC asset tag and associate the device on Hardware Inventory as 'not supported' and release for recycling in the normal fashion. 7 Medium The Council should receive reports from both recycling companies to show that the hard drives of recycled computers have been cleansed. However, at the time of the audit there was a back log of three months progress reports that have yet to be checked and processed on to There is a risk that items being sent for recycling might not have been recycled in line with the required standards and that the inventory is not kept up to date in a timely basis. Progress reports should be checked and processed on a timely basis, thus ensuring that computers have been cleansed and recycled and the inventory record is accurate. S&CA will look to adopt automation to speed the otherwise paper-based process. Where the process will rely on manual processes, this will be expedited with greater time allocated or inventory updates. ICT Service Operations Manager to update by end of November 2014. Internal Audit Report – Computer Recycling Ref. Priority Findings Risk Arising/ Consequence Recommendation Management Response the inventory. CO3: Confirm the security of computer equipment prior to disposal and that all data has been fully removed. 8 High For the sample of Recycling Sensitive data may be A full investigation should The existing recycling forms viewed one of the accessed by an be undertaken in respect of procedure should handle this computers listed (Serial No unauthorised user. any missing computers. correctly. G3BZM3J) was not received by the recycling firm. It is When the computers are What needs to change here unclear at which stage of the collected by the recycling is the timeliness of process that the computer There is a concern company it is conducting the checks went missing or the current that potentially items recommended that the between what was taken by location of the computer as the maybe mislaid or computers are physically the recycling company and status on the inventory is misappropriated. checked against the what they have said has missing. computer cage list by a been recycled by reference member of the Council staff to the certificates received The auditor was told that the and a member of the back. Business Support Assistant will recycling company to certify notify senior member of staff that the list is correct. A shorter time between that a computer has gone recycling and checking will missing. be implemented. Further research shows that a total of five Notebooks sent to Lifestyles Recycling in the last year and a half have been classed as missing on the inventory Following further discussions, the Service Delivery Manager found that one of the laptops was reissued. However the other four still remain missing. One of the missing laptops had The inventory is not updated to reflect the current location of the laptop. The Council should confirm the current location of the laptop and update the inventory accordingly. It is important that the reports from the recycling companies are checked in a Responsibility Recommendation and Timescale Implemented (Officer & Date) ICT Service Operations Manager to update by end of November 2014. Internal Audit Report – Computer Recycling Ref. 9 Priority Low Findings Risk Arising/ Consequence Recommendation not been updated on the system as missing until nine months after the machine was due to be collected by Lifestyles. It is unclear if the delay in updating the system is with Lifestyles or as previously mentioned in finding No 6 that the reports are not checked and processed against the records held in a timely basis. It was noticed that the Lifestyles Computer Re-cycling progress sheets (CRPS) reports appear to have the Lifestyles I.T Technicians typescript signature and that these reports are emailed to the Council by a colleague of his at Lifestyles. There is a risk that items that go missing are not being investigated in a timely manner. timely basis and that any missing computers are promptly brought to the attention of senior management so that they can be investigated. There is a lack of assurance that all the work carried out on each computer has been completed by the I.T Technician, as the signature could be pasted on the documents by any member of staff within Lifestyles. The Computer Re-cycling progress sheets should either be physically signed or emailed to the Authority by the I.T Technician to ensure that the work has been carried out as stated on the documents. Management Response S&CA will work the recyclers to arrive at a process that gives a more verifiable process that each certificate is being handled appropriately, and signatures used in an automated process. Responsibility Recommendation and Timescale Implemented (Officer & Date) ICT Service Operations Manager to update by end of December 2014. It was also noticed that the progress sheets from Newstart are not signed although they are emailed to the Council by the person who has carried out the checks. CO 4: Ensure that the disposal of computer equipment is in accordance with the contracted arrangements in accordance with the specified targets. 10 Medium The Council holds copies of The Council has not The Council should ensure Agreed, S&CA via the audit ICT Service various Environment Agency checked to ensure that all Environment Agency process will check for Operations documents in regards to that the companies documents are up to date evidence that accreditations Manager to Lifestyle & Newstart. However have the correct and reviewed annually to are current. update by end it was noticed that some of Environment Agency ensure that the companies of December these had expired. An example documents in place who are recycling the 2014. Internal Audit Report – Computer Recycling Ref. 11 12 Priority Medium Medium Findings Risk Arising/ Consequence being in respect of Overton whose waste management th licence is dated 7 November 2008. for the recycling of computers in accordance with WEEE Directive. The Council carried out a tendering exercise in 2012 for the recycling of the Authority's computers. The tendering exercise was carried out by the Corporate Systems manager who unfortunately no longer works for the Authority. It is unclear how the contract was awarded as there are no scoring sheets to support the evaluation process. Since the audit commenced Systems & Customer Access has carried out an inspection of both Lifestyles and Newstart. However it is unclear from the records held what testing was carried out and if a sample of computer equipment was inspected. It is unclear how the tenders were scored and who was involved in the process. There is no protection to the Council in the event of any challenge over the process. It is unclear if the Council has carried out sufficient testing of a sample of computers to ensure that they have been cleansed and all data removed before being resold. The asset disposal company will be acting on the Council's behalf, the Council will be Recommendation Management Response Responsibility Recommendation and Timescale Implemented (Officer & Date) computers have the correct documentation in place. Reviews of documentation could be included in the current inspections of both Lifestyles and Newstart. The Council should ensure that when a tendering exercise is carried out that sufficient evidence is retained in accordance with the requirements of the County Council's Procurement Code. The Council should ensure that a sample of computers sent for recycling has been tested to ensure that computers have been cleansed in accordance with the procedure agreed. Internal audit have sought further clarification of the testing carried out. Evidence of the process is stored within files in CIMU, but no evidence exists on online files to substantiate the procurement exercise. ICT Service Operations Manager with immediate effect. S&CA will comply with the Councils Procurement code. This will be included in the audit to ensure compliance. To execute this responsibility the audit will include evidence of the actual data cleanse process by watching the process and inspection of tools used. This should be as specified in their accreditation. ICT Service Operations Manager to update by end of December 2014. Internal Audit Report – Computer Recycling Ref. Priority Findings Risk Arising/ Consequence Recommendation responsible under the DPA for what the provider does with any personal data contained on the devices that it is recycling. If the provider does not successfully delete personal data that is subsequently compromised the Council may be responsible for the breach. Key to Priorities: High Medium Low This is essential to provide satisfactory control of serious risk(s) This is important to provide satisfactory control of risk This will improve internal control Management Response Responsibility Recommendation and Timescale Implemented (Officer & Date) Internal Audit Report – Computer Recycling Limitations relating to the Internal Auditor's work The matters raised in this report are limited to those that came to our attention, from the relevant sample selected, during the course of our audit and to the extent that every system is subject to inherent weaknesses such as human error or the deliberate circumvention of controls. Our assessment of the controls which are developed and maintained by management is also limited to the time of the audit work and cannot take account of future changes in the control environment.
© Copyright 2026 Paperzz