Fishbeck, Thompson, Carr & Huber, Inc. Brick Tunnel Replacement University of Michigan IDEA 2011 Distribution Workshop Introductions  Jeff Schumaker, P.E. – FTC&H  Project  Manager and Structural Engineer George MacKellar, P.E. – FTC&H  Mechanical  Engineer Mike Swanson – University of Michigan  Owner Brick Tunnel Replacement     The Master Plan The Challenges Options The Project The Master Plan    Deteriorating 80-year-old brick utility tunnel Approximately 500 feet North edge of the Diag Tunnel The Master Plan        LPS (15 psi) HPS (60 psi) LPC Compressed Air DHWS/R Testing and analysis Surpassed useful life The Challenges   Park like setting High profile area The Challenges   Running against and parallel with buildings Under Kraus Building Replacement Options     Abandonment In-place replacement Conduit system through existing tunnel New alignment – under sidewalk Replacement Options  Abandonment  Flow Model  Interconnects two legs  Redundancy  Reliability  Maintenance  Repairs Replacement Options  In-Place Replacement  Against and under buildings  Mature trees  Sacrifice character of area Replacement Options  Conduit System through existing tunnel  Fill tunnel with lean concrete  Inexpensive vs. other options  Excavation to repair would be difficult Replacement Options  New Alignment Under Sidewalk  Sidewalk parallels current alignment  Trees Trees Trees  Cutting through a major thoroughfare Replacement Options  Consulted with University of Michigan Grounds Department  Limit construction width to 13’-0”  Tie up some tree limbs Replacement Options    Walkable tunnel Utility trench Conduit system Replacement Options  Walk Tunnel  Tall and narrow  Deep excavation  Not ideal piping configuration  Access for maintenance  Considered one-sided forms Replacement Options  Utility Trench  Shallower excavation  Protection from elements  Removable top  Add spare condensate Replacement Options  Conduit System  Multi-pipe system  Shallow excavation  Add spare condensate Life Cycle Cost Analysis Option First Cost 100-yr Life Cycle Cost Walk Tunnel $8.1M $8.7M Conduit System $5.1M $9.2M Utility Trench $6.4M $12.7M  Assumptions:  Conduit system replacement in year 50  Utility trench replacement in year 75  Walk tunnel replacement in year 100  Maintenance and replacement included The Project  Existing vault on west end  New vaults  Two thrust blocks  Pedestrian traffic flow Existing Tunnel Proposed Route The Project  Tie-in point at East end  Utility  Tree conflict conflict Existing Tunnel Proposed Route The Project  Reinforce portion of brick tunnel from within Existing Tunnel Proposed Route The Project The Project  Underpinning  Vault at existing tunnel  Vault floor 6-foot below Chemistry Building foundation Existing Tunnel Proposed Route The Project  Layout to accommodate accessories  Drip legs  Expansion joints  Valves  Anchorage Construction Photos Construction Photos Construction Photos Construction Photos Questions? Thank you!  Jeff Schumaker, P.E. – FTC&H (616) 464-3841 / [email protected]  George MacKellar, P.E. – FTC&H (616) 464-3819 / [email protected]  Mike Swanson, C.E.M. – University of Michigan  (734) 763-3011 / [email protected]
© Copyright 2025 Paperzz