Fishbeck, Thompson, Carr & Huber, Inc. Brick Tunnel Replacement University of Michigan IDEA 2011 Distribution Workshop Introductions Jeff Schumaker, P.E. – FTC&H Project Manager and Structural Engineer George MacKellar, P.E. – FTC&H Mechanical Engineer Mike Swanson – University of Michigan Owner Brick Tunnel Replacement The Master Plan The Challenges Options The Project The Master Plan Deteriorating 80-year-old brick utility tunnel Approximately 500 feet North edge of the Diag Tunnel The Master Plan LPS (15 psi) HPS (60 psi) LPC Compressed Air DHWS/R Testing and analysis Surpassed useful life The Challenges Park like setting High profile area The Challenges Running against and parallel with buildings Under Kraus Building Replacement Options Abandonment In-place replacement Conduit system through existing tunnel New alignment – under sidewalk Replacement Options Abandonment Flow Model Interconnects two legs Redundancy Reliability Maintenance Repairs Replacement Options In-Place Replacement Against and under buildings Mature trees Sacrifice character of area Replacement Options Conduit System through existing tunnel Fill tunnel with lean concrete Inexpensive vs. other options Excavation to repair would be difficult Replacement Options New Alignment Under Sidewalk Sidewalk parallels current alignment Trees Trees Trees Cutting through a major thoroughfare Replacement Options Consulted with University of Michigan Grounds Department Limit construction width to 13’-0” Tie up some tree limbs Replacement Options Walkable tunnel Utility trench Conduit system Replacement Options Walk Tunnel Tall and narrow Deep excavation Not ideal piping configuration Access for maintenance Considered one-sided forms Replacement Options Utility Trench Shallower excavation Protection from elements Removable top Add spare condensate Replacement Options Conduit System Multi-pipe system Shallow excavation Add spare condensate Life Cycle Cost Analysis Option First Cost 100-yr Life Cycle Cost Walk Tunnel $8.1M $8.7M Conduit System $5.1M $9.2M Utility Trench $6.4M $12.7M Assumptions: Conduit system replacement in year 50 Utility trench replacement in year 75 Walk tunnel replacement in year 100 Maintenance and replacement included The Project Existing vault on west end New vaults Two thrust blocks Pedestrian traffic flow Existing Tunnel Proposed Route The Project Tie-in point at East end Utility Tree conflict conflict Existing Tunnel Proposed Route The Project Reinforce portion of brick tunnel from within Existing Tunnel Proposed Route The Project The Project Underpinning Vault at existing tunnel Vault floor 6-foot below Chemistry Building foundation Existing Tunnel Proposed Route The Project Layout to accommodate accessories Drip legs Expansion joints Valves Anchorage Construction Photos Construction Photos Construction Photos Construction Photos Questions? Thank you! Jeff Schumaker, P.E. – FTC&H (616) 464-3841 / [email protected] George MacKellar, P.E. – FTC&H (616) 464-3819 / [email protected] Mike Swanson, C.E.M. – University of Michigan (734) 763-3011 / [email protected]
© Copyright 2024 Paperzz