In Confidence Office of the Minister for Building and Construction Cabinet Economic Growth and Infrastructure Committee Proposals to improve the Dam Safety Scheme Proposal 1 This paper proposes amendments to the Building Act 2004 (the Act) and the Building (Dam Safety) Regulations 2008 (the Regulations) to improve the Dam Safety Scheme (the Scheme). Executive summary 2 The Scheme, which is a light-handed risk-management scheme for large dams in New Zealand, was recently the subject of an independent review, prior to taking effect, to determine whether it was fit for purpose. This Review addressed concerns that the current requirements of the Scheme might capture dams for which the impact of failure is low, resulting in unnecessary compliance costs for these dam owners. 3 The Review concluded that while the Scheme is necessary – in terms of protecting human safety, property, infrastructure and the environment, from the risks of a large dam failure – it could be better targeted and made more efficient. The commencement of the Regulations setting out the details of the Scheme was consequently deferred until 1 July 2012, to allow time for Government to consider the Review’s recommendations and make changes to the Scheme. 4 Most, but not all, of the Review’s recommendations are being proposed for implementation. The recommendations that are not favoured relate to reviewing all dam-related legislation, and setting up a central dam safety authority to administer the Scheme. There is a divergence of views on one recommendation regarding the size threshold of dams that should be covered by the Scheme. 5 The proposals in this paper should collectively improve the effectiveness and efficiency of the Scheme, whilst reducing compliance costs. The proposals seek to retain the light-handed nature of the Scheme (whereupon dam owners are primarily responsible for ongoing monitoring of their dam) while enabling regional councils to act if a dam might be unsafe. The proposals fall into two categories: a. those that better target those dams to be covered by the Scheme – either automatically by virtue of their size, or as required by regional authorities based on risk factors; and 1 b. those that clarify requirements, so as to improve administration of the Scheme. Background 6 Once dams are constructed and commissioned, they require ongoing monitoring, maintenance and repair in order to maintain their integrity. The failure of a dam could result in damage to life, property, infrastructure and the environment. The potential impact of a dam can change over time due to downstream developments. 7 The Scheme, a light-handed risk-management scheme for large dams, seeks to manage these ongoing risks through assessing the risks of individual dams and then ensuring the owners undertake appropriate ongoing monitoring. All regional authorities are responsible for the administration and monitoring of the Scheme in their regions. A summary of requirements of the Scheme is included in Appendix 1. 8 The Scheme was established in 2004 under the Act, but requires Regulations to bring it into effect. These Regulations were promulgated in July 2008, and were due to come into effect in July 2010. 9 Prior to the Scheme coming into effect, concerns were raised that the Scheme may impose unnecessary costs on owners of some low-risk dams, including small dams on farms in remote areas where a dam failure may only impact the dam owner’s land. As a result, the Government agreed to a review of the Scheme [EGI Min (10) 1/12 refers]. The purpose of reviewing the Scheme was to ensure it was 'fit for purpose' – with the costs posed by the Scheme being balanced with the potential risk to human safety. Review of the Dam Safety Scheme 10 An independent reviewer was engaged to assess the Scheme. The Review concluded that while the Scheme is necessary – in terms of protecting human safety, property, infrastructure and the environment – improvements could be made to its efficiency and effectiveness, and to reduce overall compliance costs. 11 The Review recommended possible changes to the Scheme. A summary of the Review’s recommendations and commentary by the Department is included in Appendix 2. These recommendations were considered by the Economic Growth and Infrastructure Committee on 2 June 2010. It was agreed that the Scheme should be deferred until 1 July 2012, to allow time for Government to consider the Review’s recommendations and make changes to the Scheme [EGI Min (10) 12/9 refers]. 12 The Department subsequently consulted with stakeholders to seek feedback on the Review’s recommendations and how they would apply in practice to the operation and management of dams. Feedback received showed a lack of consensus between large dam owners, and regional authorities on the key recommendations. 13 The Review primarily identified that the current size threshold of a large dam (being three metres in height and 20,000 cubic metres in volume), captured too many 2 1 dams, which consequently placed unnecessary compliance costs on the owners of these dams. It therefore recommended that the size threshold be raised to eight metres in height and 50,000 cubic metres in volume (with such dams being called ‘classifiable dams’) – but also that regional authorities be given the power to issue a notice requiring classification of any other large dam if there is reason to believe the dam may put persons at risk (with such dams being called ‘referable dams’). 14 Consultation with stakeholders on these key recommendations identified significant concerns from regional authorities, on two levels. Firstly, that the current threshold already excludes some small dams, they considered to be at-risk, so instead of increasing the size threshold (as recommended in the Review), it should actually be reduced to capture more dams. This would obviously increase (not reduce) compliance costs. 15 Secondly, the size threshold should remain as the only means by which dams are covered by the Scheme. Regional authorities did not want to take on the perceived additional liability associated with having the power to require that a dam be classified. Moreover, if they were given such a power, some regional authorities advised they would likely investigate every dam in their region to assess whether any may put persons at risk, as a means of reducing their liability. The costs of such investigations would need to be met by ratepayers. 16 The Department considered this feedback, and developed an alternative approach that seeks to achieve the same outcome as that of the Review but taking into account the issues raised by regional authorities. These revised proposals were the subject of further consultation with key stakeholders and the reviewer. Proposals to narrow the scope of the Scheme 17 The amendments proposed below collectively seek to better target the dams that should be subject to the Scheme due to their size and potential impact. Better targeting ensures the costs imposed by the Scheme are balanced with the potential risks to people and property. Proposals 18 It is proposed to amend the Act to introduce ‘classifiable dam’ and ‘referable dam’ categories. These categories of dam will be used to identify the large dams, as presently defined by the Act, that are to be subject to the requirements of the Scheme. 19 A ‘classifiable dam’, which will automatically require classification under the Scheme, will be defined in Regulations as a large dam that is: a. three or more metres in height; and holds 100,000 or more cubic metres volume of water or other fluid; or b. is eight or more metres in height, and holds 20,000 or more cubic metres volume of water or other fluid. 1 Under the Building Act, the owner of a large dam is required to classify the dam as having a low, medium or high potential impact (PIC). The different classifications refer to the potential impact of a failure of the dam on persons, property, and the environment. 3 20 A ‘referable dam’ will be defined in Regulations as a ‘large dam’ that is not a ‘classifiable dam’. Referable dams may be forwarded for classification under the Scheme, if the potential impact of the dam is considered great enough. 21 It is proposed to amend the Act to give regional authorities the discretion to investigate whether to refer a ‘referable dam’ for classification, where there are reasonable grounds to so. ‘Reasonable grounds’ will be aligned with the existing medium and high potential impact dam grading as prescribed in Schedule 1 of the Regulations. 22 The following diagram illustrates the concept of classifiable dams and referable dams, as a subset of a large dam as currently defined in the Act: 4 Discussion 23 Establishing the classifiable dam category to increase the size threshold of dams that would be automatically included in the Scheme results in a significant number of low potential dams being excluded, thus reducing compliance costs for the sector. 24 The proposed definition of classifiable ensures dams that either have a high height or a big capacity are captured by the Scheme. Advice from the reviewer is that an eight metre high and 20,000 cubic metre volume dam has the same risk characteristics as a three metre high and 100,000 cubic metre volume dam. This is also supported by submissions that referred to empirical guidelines from international literature for the likely peak breach outflow from an earth-fill dam based on data from historical earth-fill dam failures. 25 This proposal has been modified from the size threshold of eight metres in height and 50,000 cubic metres in volume recommended in the Review. The proposed dam size threshold has been selected on the basis that it provides a better coverage of high potential impact dams - it captures the majority of the higher risk dams (high and medium potential impact) and does not include many low risk dams. 26 Out of an estimated 1,150 large dams in New Zealand, it is estimated that 712 would become classifiable dams under the proposed approach. This is approximately 40 percent fewer dams than under the current size threshold. At an estimated cost of $3,000 per classification of dam, this should reduce compliance costs by an estimated $1,314,000 to low potential impact dam owners. 27 Establishing the referable dam category reduces the risk that raising the quantitative threshold for the automatic inclusion would result in some medium or high potential impact dams being excluded from the Scheme. Of the remaining 438 dams, it is estimated 10 percent would be high potential impact and 15 percent would be medium potential impact. If regional authorities referred these dams for classification, this would mean approximately 70 additional dams would then be classified under the Scheme. This still results in a 33 percent reduction in the overall number of dams that would be subject to the Scheme compared to the current size threshold, resulting in a saving of $1,141,500 for low potential impact dam owners. 28 The concerns of regional authorities have been addressed under the proposed approach by limiting a regional authority’s discretion to investigate a referable dam for classification, by narrowly defining the reasonable grounds on which they can investigate. This in turn will limit their potential liability, and remove their perceived need to investigate all dams in their region. Because the costs of any investigations undertaken fall on the regional authorities, this should provide an additional discipline on them to ensure they use their discretion in a balanced and moderate manner. 29 It should be noted that since 2004, under the Act, if a dam, small or large, is likely to pose immediate danger to the safety of people, property or the environment, a regional authority can issue a warrant to take action to mitigate the immediate danger posed by the dam, with the owner being liable for the costs of the action. 5 30 Despite the proposed new threshold better targeting the medium and high risk dams that should be subject to the Scheme, and the new role of regional authorities being limited as a means of reducing their potential liability, regional authorities remain opposed to the proposals, and consider that the Scheme needs to cover more dams and impose greater costs on dam owners. Given the Government’s aim of reducing compliance costs, this view is not supported by the Department. Proposals to improve administrative efficiencies 31 The Review also recommended a number of changes to improve the administration of the Scheme. Defining how to measure a dam 32 There is currently some confusion around the depth measurement of a dam reservoir. Specifying in the Act how dam height is to be measured would remove this confusion and ensure the Act and the Scheme are consistently applied. 33 In line with the recommendation of the Review, it is proposed to amend the Act to specify that dam height is defined as the vertical distance from the top of the dam and measured: a. in the case of a dam across a stream, from the natural bed of the stream at the lowest downstream outside limit of the dam; or b. in the case of a dam not across a stream, from the lowest elevation at the outside limit of the dam. Increase the review period for a Dam Safety Assurance Programme from five to seven years 34 Under the Act, dam owners are required to prepare a dam safety assurance programme (DSAP) and have it verified by a recognised engineer, as defined under section 149 of the Act. Section 146 of the Act requires owners of medium potential impact dams to review their DSAPs: a. within ten years after the date on which the regional authority approves the DSAP; and b. at intervals of not more than five years after the first review. 35 The subsequent review period of five years, is the same review period to which high potential impact dams are subject. 36 In line with the recommendation of the Review, it is proposed that the review period for the DSAP be increased from five yearly to seven yearly for medium potential impact dams. This will align the DSAP with the guidelines produced by the New Zealand Society on Large Dams. Compliance costs for the owners of medium potential impact dams will be further reduced, whilst still maintaining an appropriate level of risk management for dams classified as medium potential impact. Reducing the review period has the benefit of balancing the demand of recognised engineers by allowing them to focus their limited resources on higher risk dams. 6 Complying with the Annual Dam Compliance Certificates 37 Section 150(2)(b) currently requires that dam compliance certificates must state that all procedures in the DSAP have been “fully complied with” during the previous 12 months. Compliance must be confirmed by a category A recognised engineer, as defined in the Regulations, and signed by the dam owner. 38 There are many valid reasons why a DSAP may not be fully compliant that do not impact on the overall safety of the dam. During the consultation process, submitters highlighted that the current strict compliance requirement may result in a risk that DSAPs will be written less rigorously in such a way that avoids compliance requirements. 39 In line with the recommendation of the Review, it is proposed to amend section 150(2)(b) of the Act with a less strict requirement for dam owners to “comply” with criteria and standards of the DSAP, and where necessary, include a list of any noncompliances that warrant corrective action. 40 Removing the requirement for strict compliance and allowing for immaterial noncompliances to be noted, will ensure owners take the appropriate level of responsibility by implementing good practice DSAPs for their dams. This amendment enhances the effectiveness of this element of the Scheme. Removing references to earthquake-prone and flood-prone dams 41 The Act currently requires regional authorities to develop a region-specific policy on earthquake-prone and flood-prone dams, and gives them the ability to request the owners of such dams to review their DSAP to ensure their relevance. The intention behind specifying these dams in the Act was to ensure deficiencies in earthquake or flood-prone dams are addressed. 42 As noted by the Review, it is no longer necessary to refer to earthquake-prone and flood-prone dams in the Act. This is because the amendments proposed in this paper give regional authorities more responsibility for dams in their region, including the discretion to refer a dam for classification. This new power should ensure any risks associated with medium or high impact dams, including deficiencies that could cause a dam to fail in an earthquake, are adequately managed. 43 In line with the recommendation of the Review, it is therefore proposed that all references to earthquake-prone and flood-prone dams be removed from the Act. 44 The proposed amendment does not compromise risk management because any issues with dam safety that arise due to earthquake or flood proneness will be identified during assessment and are required to be noted in the DSAP. These dams will be subject to review requirements appropriate for their classification under the programme – prepare and submit a DSAP to the regional authority, and provide ongoing evidence of implementing surveillance and maintenance procedures in accordance with the approved DSAP through submitting an annual Dam Compliance Certificate, and seek advice from a recognised engineer to certify future, ongoing audits of the DSAP. 7 Recognised Engineers to report dangerous dams 45 The Act currently requires regional authorities to develop a dangerous dams policy within their regions. The purpose of this policy is to help prevent catastrophic failure of a potentially dangerous dam. The regional authority has functions and powers under the Act, including putting up hoardings, attaching a warning on the dam, and requiring work to be carried out on the dam to reduce or remove danger. 46 In line with the recommendation of the Review, it is proposed to include a provision in the Act that requires a recognised engineer, if during the process of certifying a dam it becomes apparent that the dam is dangerous, to notify the regional council and the dam owner. The notification must be provided in writing within five working days. 47 It is also proposed to include a provision in the Act that requires dam owners to notify the regional council if the owner becomes aware their dam is dangerous. 48 The proposed amendments will ensure regional authorities are notified of dangerous dams in their region, making sure that such dams are then subject to the dangerous dam policy. Determination of appurtenant structure 49 Under the Regulations, the requirements of appurtenant structures are to be noted in the DSAP. An appurtenant structure is a structure that is integral to the proper functioning of the dam, such as intake towers, powerhouse structures and surge tanks and towers. 50 In line with the recommendation of the Review, it is proposed that the appurtenant structures for each dam be determined by the recognised engineer responsible for certifying the DSAP. 51 The appurtenant structures that need to be subject to the Scheme are different for each dam and therefore difficult to prescribe. A recognised engineer is the most appropriate person to define what structures are appurtenant to the safe operation of each individual dam. Review recommendations not adopted 52 In the review of the Scheme, the reviewer also made two other significant recommendations which have not been adopted. Comprehensive review of all dam-related legislation 53 The Review recommended that legislation, as it applies to dams (including resource consent and building consent legislation) be reviewed as a whole in order to provide effective, clear legislation that reduces compliance costs and provides consistent implementation across the sector. 54 Although the scope of the Review did not include the resource consent and building consent processes required under the Resource Management Act 1991 and the Building Act, the Review noted there is a potential for some overlap between the two Acts and the Scheme. 8 55 This recommendation is not supported as a major review of the Building Act has only recently been completed. This resulted in the review of the Scheme, the Department developing options to improve the administration of building regulatory functions, including their consolidation across local authorities or centralisation. 56 A review of the Resource Management Act is currently underway. The Resource Management Act is being reviewed with the aim of streamlining and simplifying provisions, and focussing on improving process. The focus on improving process will include the resource consenting process in relation to dams. Establishment of dam safety authority 57 The Review also recommended that a new central government body (an authority specific to dam safety management) be established to administer and monitor the Scheme to provide a nationwide consistent approach. 58 This recommendation is not supported. In accordance with Cabinet direction [CAB Min (10) 5/3 refers], the Department is currently looking at options to improve the administration of building regulatory functions, including their consolidation across local authorities or centralisation. The aim is to develop a more nationally consistent approach to administering all building regulatory requirements. This broader project will include consideration of building control functions in relation to dams, as well as dam safety management. Advice on the preferred option for improving administration, and how it could be implemented, will be provided to Ministers in April 2011. 59 Although this work could result in future changes to the way the Scheme is administered, it is not recommended that decisions about the Scheme are postponed. This would result in further delays to the commencement of the Scheme, creating uncertainty for industry about whether or not their dams are affected by the revised requirements. Monitoring of proposed amendments 60 The Scheme will become effective on 1 July 2012. Following the commencement of the Scheme, the Department will closely monitor the operation of the Scheme to ensure it meet its objectives. 61 It is expected the monitoring will include, but not be limited to: a. the number of referable dams investigated by regional authorities and/or required to be classified; b. the proportion of referable dams regional authorities require to be classified that turn out to be low, medium or high impact dams, respectively; c. the size, by height and volume, of dams that are low, medium or high impact dams; and d. benchmarking of quality of DSAPs (detailing best practice and shortcomings, based on international experience); with a particular emphasis on dams such as hydro dams where the impact of failure could be particularly substantial. 62 There is currently a degree of imperfection in the information available for determining which large dams should be referable and which should be 9 Consultation 63 The following Departments have been consulted on the proposals in this paper and their views incorporated: The Treasury, Ministry of Economic Development, Department of Internal Affairs, Ministry for Culture and Heritage, Ministry of Agriculture and Forestry, Ministry for the Environment, Ministry of Justice and Te Puni Kōkiri. 64 The Ministry of Civil Defence and Emergency Management has been informed of the paper but was unable to provide comment due to involvement in the Christchurch earthquake. 65 The Department of Prime Minister and Cabinet has been informed. Financial implications 66 There are no financial implications from the specific proposals set out in this paper. Any costs will be covered from the Department's baseline funding. 67 The benefits and costs associated with the proposals are detailed in the attached Regulatory Impact Statement (RIS). Human rights 68 The proposed amendments are unlikely to raise issues under the New Zealand Bill of Rights Act 1990 or Human Rights Act 1993. A final view will be possible once the legislation has been drafted. Legislative implications 69 The proposals in this paper involve amendments to the Act and the Building (Dam Safety) Regulations 2008. The amendments proposed to the Act in this paper will be binding on the Crown. 70 The Building Amendment Bill (No 4) has a category 3 priority (to be passed in 2011 if possible) in the 2011 Legislation Programme. If possible, the amendments proposed in this paper could be included in that Bill. Regulatory impact analysis 71 Regulatory Impact analysis requirements apply to the proposal in this paper; consequently the Department has prepared a RIS. The Department confirms the 10 72 The RIS is attached to this paper as Appendix 3. 73 Alison Geddes, Deputy Chief Executive Sector Capability has reviewed the RIS prepared by the Department and considers the information and analysis summarised in the RIS meets the quality assurance criteria. 74 I have considered the analysis and advice of my officials, as summarised in the attached RIS and I am satisfied that, aside from the risks, uncertainties and caveats already noted in this Cabinet paper, the regulatory proposals recommended in this paper are consistent with our commitments in the Government statement “Better Regulation, Less Regulation”. 75 The RIS was circulated with this Cabinet paper for Departmental consultation. Disability perspective 76 There are no disability implications associated with these proposals. Publicity 77 The Department has developed a communications plan to communicate with dam owners and other stakeholders, including publicising the requirements of the Scheme and providing suitable support material. Recommendations 78 The Minister for Building and Construction recommends the Committee: 1. note the Government agreed to a review of the Dam Safety Scheme (the Scheme) prior to its implementation to ensure the Scheme was fit for purpose [EGI Min (10) 1/12 refers]. 2. note the commencement of the Building (Dam Safety) Regulations 2008 (the Regulations) were deferred until 1 July 2012 to allow time for Government to consider the Review’s recommendations and make the necessary changes to the Scheme [EGI Min (10) 12/9 refers]. 3. note the Department of Building and Housing is currently developing options to improve the administration of all building regulatory functions, including functions relating to dams and dam safety management. 4. note that although this work could result in future changes to the way the Scheme is administered, it is not recommended that decisions about the Scheme are postponed because this would result in further delays to, and uncertainty about, the Scheme. 5. agree to amend the Building Act 2004 (the Act) to introduce the concept of a ‘classifiable dam’ and ‘referable dam’ for the purposes of the Scheme. 11 6. agree the definition of a ‘classifiable dam’ be prescribed in the Regulations as a large dam that: i. is three or more metres in height; and holds 100,000 or more cubic metres volume of water or other fluid; or ii. is eight or more metres in height, and holds 20,000 or more cubic metres volume of water or other fluid. 7. note that the size threshold of a ‘classifiable dam’ was modified from eight metres in height and 50,000 cubic metres in volume, as recommended in the review of the Scheme, to the definition proposed in recommendation 6 (above). 8. note that the size threshold in recommendation 6 (above) provides the best balance of capturing high and medium potential impact dams, while excluding many low potential impact dams. 9. agree the definition of a ‘referable dam’ be prescribed in the Regulations as a large dam that is not a classifiable dam. 10. agree to amend the Act to give regional authorities the discretion to investigate and refer a referable dam for classification where there are reasonable grounds to do so. 11. agree that ‘reasonable grounds’ be prescribed in the Regulations and align with the existing provisions for the potential impact grading prescribed in Schedule 1 of the Regulations. 12. agree to amend the Act to specify that dam height is defined as the vertical distance from the top of the dam and measured: i. in the case of a dam across a stream, from the natural bed of the stream at the lowest downstream outside limit of the dam; or ii. in the case of a dam not across a stream, from the lowest elevation at the outside limit of the dam. 13. agree to amend the Act to increase the review period for the Dam Safety Assurance Programme to an interval of not more than seven years for medium potential impact dams. 14. agree to amend section 150(2)(b) of the Act by removing the requirement for a dam owner to have “fully complied with” the criteria and standards of the Dam Safety Assurance Programme, and replacing it with the less strict requirement to “comply” with criteria and standards of the Dam Safety Assurance Programme, and where necessary, include a list of any non-compliances that warrant corrective action. 15. agree to remove all references to “earthquake-prone dams” and “flood-prone dams” from the Act. 16. agree to amend the Act to require a recognised engineer, if during the process of certifying a dam it becomes apparent that a dam is dangerous, to notify the regional authority and the dam owner. The notification must be provided in writing within five working days. 12 17. agree to amend the Act to require dam owners to notify the regional authority if the owner becomes aware their dam is dangerous. 18. agree to amend the Act to require the recognised engineer to determine the appurtenant structures for each dam, for the purposes of the Dam Safety Assurance Programme. 19. agree that the Minister for Building and Construction has delegated authority to approve amendments to correct any minor errors, omissions and inconsistencies that may be identified, where no new policy matters arise. 20. note the Building Amendment Bill (No 4) has a category 3 priority (to be passed in 2011 if possible) on the 2011 Legislation Programme. 21. invite the Minister for Building and Construction to issue drafting instructions to Parliamentary Counsel Office to draft amendments to the Act to give effect to the proposals. Hon Maurice Williamson Minister for Building and Construction ____/______/___ 13 Appendix 1 Requirements of the Dam Safety Scheme The Dam Safety Scheme (the Scheme) currently applies to large dams as defined by section 7 of the Building Act as being a dam that retains three or more metres depth, and holds 20,000 or more cubic metres volume of water or other fluid. Requirements of large dam owners The Act requires the owner of a large dam to: Classify the dam as either a low, medium or high potential impact category (PIC) dam. The different classifications refer to the potential impact of a failure of the dam on persons, property, and the environment. The owner of a large dam will need a recognised engineer to audit and confirm the dam’s classification in a certificate. Classify the dam and submit the classification of the dam to the appropriate regional authority. For medium and high PIC dams, prepare and submit a Dam Safety Assurance Programme to the regional authority. Provide ongoing evidence of implementing surveillance and maintenance procedures in accordance with the approved Dam Safety Assurance Programme. This is done by submitting an annual Dam Compliance Certificate. Seek advice from a recognised engineer to certify future, ongoing audits of the Dam Safety Assurance Programme. Role and responsibility of a regional authority The Act requires regional authorities to: Perform the function of a building consent authority (if accredited and registered) Carry out a variety of other building control functions such as issuing project information memoranda and issuing certificates of acceptance (in relation to unconsented building work on dams) Administer and monitor the Scheme, which means that regional authorities must: - establish and maintain a register of large dams in their region - consider and approve (or not approve) dam classifications of large dams - consider and approve (or not approve) the Dam Safety Assurance Programmes for each medium and high PIC dam in their region - consider and approve (or not approve) annual Dam Compliance Certificates Adopt and implement a policy on dangerous dams, flood prone dams and earthquake prone dams. This includes setting up processes and procedures that would be triggered for medium or high PIC dams should they be determined to be dangerous, flood prone or earthquake prone. Take action if necessary, if any dam, large or small, poses an immediate danger to the safety of persons, property or the environment. 1 Appendix 2 Review of Dam Safety Scheme – Recommendations # Recommendation Comment 1 That a Dam Safety Scheme (the Scheme) is needed in New Zealand. Agreed. 2 That the Scheme in its current form needs modifying to improve its efficiency and effectiveness and to reduce compliance costs. Agreed. 3 That the definition of large dams be changed (for the purpose of the Scheme) to include dams having the capacity to hold a reservoir of 50,000m³ or more and to be at least eight metres high. This recommendation has been modified to better target the medium and high potential impact dams that should be subject to the Scheme. Large dams will be required to be classified if they are either 20,000m³ in capacity and 8 metres high OR 100,000 m³ in capacity and 3 metres high. 4 That a dam requiring classification under the Scheme be described as an Inventory Dam, Classifiable Dam or a Referable Dam (and not a Large Dam as at present). This recommendation has been adopted. Two sub-categories of Large Dam will be established: Classifiable Dam and Referable Dam. A new dam definition is needed (rather than changing the definition of a Large Dam) to adopt the recommendation above because the Large Dam definition is used in the Building Act for more purposes than dam safety. 5 That dam height is defined as the vertical distance from the top (crest) of the dam measured: This recommendation has been adopted. in the case of a dam across a stream, from the natural bed of 1 Review of Dam Safety Scheme – Recommendations # Recommendation Comment the stream at the lowest downstream outside limit of the dam, or in the case of a dam that is not across a stream, from the lowest elevation at the outside limit of the dam. That the body responsible for administering the Scheme have the power to issue a notice requiring classification of any dam, regardless of whether the dam meets the dam criteria. Any such notice will only be issued if there is reason to believe the dam may put persons at risk. This recommendation has been adopted. 7 That Appurtenant Structures for each dam be determined by the recognised Engineer responsible for certifying the Dam Safety Assurance Programme (DSAP). This recommendation has been adopted. 8 That the start date for the Scheme be delayed sufficiently to allow any legislative changes arising from this Review to be passed, to allow sufficient publicity to be communicated to dam owners and other stakeholders and to allow the Scheme to be properly implemented. This recommendation has previously been adopted. That a period of twelve months be allowed after the Scheme’s start date for dam owners to have the dam classifications certified by a recognised engineer. This recommendation has not been adopted. 6 9 Regional authorities will have the discretion to investigate and refer a dam for classification. Boundaries will be placed around the use of this discretion to prevent regional authorities investigating and referring all dams in their regions. The Building (Dam Safety) Regulations 2008, which set out the details of the Scheme, were due to come into force on 1 July 2010. These have been deferred until 1 July 2012, to allow time for the Government to consider the review’s recommendations. This is because: there has already been a two year delay in the introduction of 2 Review of Dam Safety Scheme – Recommendations # Recommendation Comment the Scheme delaying the Scheme further will result in the time frame for production of DSAPs being pushed out a further nine months (to two or three years after commencement of the Scheme) as long as amendments to the Scheme are made well before 1 July 2012 (when the Scheme comes into effect) dam owners will have considerably more than three months after 1 July to have their dam classifications certified. 10 That no change be made to the methodology for classifying dams. This recommendation has been adopted – no legislative amendment required. 11 That category B engineers be required to undertake a one or two day dam classification training course before being able to classify dams. This course to be organised by the Department in conjunction with NZSOLD. The Department will consider this recommendation when implementing the Scheme. No legislative amendment is required for this amendment. 12 That a panel of two or three category A engineers be established to review all dam classifications at the end of the classification period and recommend any needed legislative changes to the Department at that time. The Department will consider this recommendation when implementing the Scheme. No legislative amendment is required for this amendment. 13 That the authority(s) responsible for administering and monitoring the Scheme monitors the availability of recognised engineers during the Scheme’s implementation. This recommendation has not been adopted. The Department and nearly all submissions received from consultation did not believe monitoring the availability of engineers should be a regional authority responsibility, primarily due to 3 Review of Dam Safety Scheme – Recommendations # Recommendation Comment questions around how this would work in practice. 14 That a new body responsible for administering and monitoring the Scheme on a nation-wide basis be established within central government and that the new body is named to clearly identify its role (such as the “Dam Safety Authority”). This recommendation has not been adopted. This is because: it is not certain the benefits of establishing a Dam Safety Authority would outweigh the costs it provides a potential disconnect between building consents and the Scheme (as noted in the Dam Safety Review Report). the role of the Authority would be limited – the only grounds it would have for not approving dam classifications, DSAPs and Dam Compliance Certificates is if the engineer is not a category A engineer. The Department is reviewing the current regulatory system and aims to develop a more nationally consistent approach to administering regulatory requirements through either a regionalised or centralised system. The management of dam safety can be included in this review. 15 That consideration is given to (at least partially) funding the body with a simple low fee charge regime to all dam owners included in the Scheme. This recommendation has not been adopted. The recommendation is not applicable as recommendation 14, to establish a new body responsible for dam safety, has not been adopted. 4 Review of Dam Safety Scheme – Recommendations # Recommendation Comment 16 That the DSAP for a medium PIC dam be required to be in place twelve months after the date on which the Scheme authority approves the classification for the dam. This recommendation has not been adopted. 17 That DSAP review periods be increased from five to every seven years for medium PIC dams to align with NZSOLD Guidelines. This recommendation has been adopted. 18 That the wording of the Annual Compliance Certificate be changed so that there is not a requirement for the DSAP to be “fully complied with”. Instead the category A recognised engineer and dam owner (or chief executive) will certify that the dam owner has complied with the criteria and standards of the DSAP as set out in section 8 of the Building (Dam Safety) Regulations 2008 and where necessary, include a list of any noncompliances that warrant corrective action. This recommendation has been adopted. 19 That consideration be given to allowing a dam owner to supply bi-annual Dam Compliance Certificates provided a category A recognised engineer certifies the implementation of the DSAP warrants it. This recommendation has not been adopted. 20 That if in the process of certifying a dam it becomes apparent to the recognised engineer that a dam is dangerous then it will be This recommendation has been adopted. Dam owners have had a significant notice period of the need to produce a DSAP ready for submission to their regional authority. It should not take 12 months (let alone two years) to produce a DSAP. Dam owners are currently required to undertake an annual inspection of their dams. The additional costs from certification are not substantial. 5 Review of Dam Safety Scheme – Recommendations # Recommendation Comment notified as such to the Scheme authority. 21 That all references to earthquake-prone and flood-prone dams are removed from the Act. This recommendation has been adopted. 22 That a communications plan be developed to communicate with dam owners and other stakeholders, including publicising the requirements under the Act, and providing suitable support material. The Department will develop a communications plan prior to implementation of the Scheme – no legislative amendments required. 23 That, for owners of a portfolio of dams, a recognised engineer be able to review any existing dam safety management systems that are in place, and certify the system meets the criteria and standards as set out in section 8 of the Building (Dam Safety) Regulations 2008. Recognised engineers are able to do this under existing legislation. No legislative amendment is required. 24 That legislation as it applies to dams (including resource consent and building consent legislation) be reviewed as a whole in order to provide effective, clear legislation that reduces compliance costs and provides consistent implementation across the sector. This recommendation has not been adopted. This recommendation is not favoured by the Department. This is because a major review of the Building Act 2004 has only recently been completed, and a review of the Resource Management Act 1991 is currently underway. As a consequence of a recent review of the Building Act, the Department is reviewing the current regulatory system and aims to develop a more nationally consistent approach to administering regulatory requirements through either a regionalised or centralised system. The management of dam safety can be included in this review. 6 Review of Dam Safety Scheme – Recommendations # Recommendation 25 That following consideration of this Review, Government should consult stakeholders before making changes to the Dam Safety Scheme. Comment The Department has undertaken two rounds of consultation with industry on the recommendations presented in the review. 7
© Copyright 2025 Paperzz