Shaul Zemach Director-General Ministry of Energy and Water 216A Jaffa Road PO Box 36148 Jerusalem Israel 12 March 2012 Dear Shaul Gas Development Policy You have asked Petroleum Development Consultants (PDC) to provide some additional information on a number of the suggestions that we have made regarding an overall gas development policy. The purpose of this letter is to provide this additional information. Please note, however, that these proposals were made in the context of an overall policy including covering the issue of exports and the proposals in this letter have to be taken into consideration in this context. The areas that are discussed in this letter are the following: Open access in a Leviathan landing terminal and LNG liquefaction terminal Our position regarding government participation in an LNG liquefaction terminal Our position regarding future connection of fields other than Tamar and Leviathan Our position regarding the proposed provision of sub-sea tees in a Leviathan domestic pipeline system Open Access: Leviathan Land Terminal and LNG Liquefaction Terminal PDC has proposed that the Leviathan field owners should be required to land some of their gas in Israel in return for a concession from the Government of Israel to allow a certain level of exports. As part of an overall settlement PDC has proposed that the Leviathan owners shall be required to construct and pay for additional capacity both in the main pipeline to Israel and the land terminal. It was suggested that a minimum of 25% of the capacity of the pipeline and the terminal should be made available by the Leviathan owners. On the basis that the minimum annual capacity of the pipeline and the terminal would be 2 bcm, the capacity available for third party access would be 0.5 bcm. This would allow a smaller field with reserves of around 50 bcm to be connected to the system. We have done some rough scoping field economics which indicates that such a development would be economic even based on the Sheshinsky assumed domestic gas price of $4.5/MMBTU. We will be able to provide you further details of the economics of such a field over the next few days as we further develop our field economics model. The provision of third party access as described above will allow some limited supply competition in Israel to emerge, a precursor to the development of gas competition. However the extent of this should not be exaggerated particularly as the unit costs of Leviathan are likely to be less than the unit costs of a third party field due to the large size of Leviathan even allowing for the fact that the unit capacity costs in the pipeline and the terminal will be identical. However the third party field will not be required to build either its own main pipeline or terminal and this will reduce the capital investment required. A further point to be made is this third party access requirement needs to be considered in the context of the proposed strategic reserve envisaged for Leviathan. This provides that not only is the physical capacity provided for third party access but also a market is provided for. This is very similar to the small fields policy in the Netherlands which requires that the giant Groningen field is reserved in order to allow smaller fields to have access to the market. You have asked whether the provision of additional capacity for third party access for pipelines and terminals is a solution adopted elsewhere. We can confirm that this has been the case and quote from PDC’s specific experience the development of BP’s Nam Con Son development in offshore Vietnam where PDC was advising PetroVietnam the state oil and gas company. In this case the state wished the offshore producers to provide additional capacity in the pipeline and onshore terminal. This additional capacity was provided by the producers with PetroVietnam paying for and owning the additional capacity. PDC would argue that the provision of extra capacity in Israel should be paid for by the Leviathan owners rather than the government. Firstly unlike Vietnam the government of Israel is not a participant in the offshore licences. Secondly a significant issue in Israel is the shortage of land for a terminal which can only be resolved by the government actively supporting the provision of this limited asset. In return for this support PDC believes that the Leviathan owners should be required to provide this additional capacity at their cost. We have had limited time to consider the additional costs that the provision of this third party access might entail. Our initial view that is it would involve about 15% on top of the base costs for the terminal. Assuming that cost of a terminal is $600 million suggests that the extra cost for the additional terminal capacity would be $90 million. The cost of additional pipeline capacity could be around $60 million giving a cost of $150 million – basically the cost of an offshore Israeli exploration well. PDC has proposed that the level of third party access is 25% and you might ask the question why this number rather than any other number has been used. It is really set from a minimum which must be large enough to allow a single field to use it. Generally it is usually possible to get this sort of increase in most process plant by de-bottlenecking. Typically at this level of increase not all the equipment will need to be increased in size. We have not specifically proposed that third party access shall be provided in the LNG liquefaction terminal although if the government wishes to take an interest in such a facility it could offer their capacity to a third party field developer if it so desired. However the subject of a LNG liquefaction terminal is discussed further below. Government Participation in an LNG Liquefaction Terminal Any LNG liquefaction terminal project is likely to involve a utility rate of return. This sort of terminal would normally have a dedicated gas supply and dedicated LNG customers. It is not necessary that the owners of the LNG liquefaction terminal are identical to the owners of the gas production licences. However there does need to be significant alignment between these two owners. The example of Trinidad and Tobago is instructive in evaluating the potential role for government investment in LNG liquefaction. There are four separate trains of the plant with differing government interests. Train 1 had a government interest through the National Gas Company (NGC) of Trinidad and Tobago of 10%. The government had no interest in Trains 2 and 3. NGC had an interest of 11.1% in Train 4. The development of the Oman LNG liquefaction terminal is another example of an aligned interest between the owners of the terminal and the gas producers. The Oman LNG terminal is owned by the Government of Oman (51%) in cooperation with Royal Dutch Shell (30%), Total S.A. (5.54%), Korea LNG (5%), Partex Oil & Gas (2%), Mitsubishi Corporation (2.77%), Mitsui & Co. (2.77%), and Itochu Corporation (0.92%). The main producer Petroleum Development Oman (PDO) is owned 60% by the Government of Oman, Shell (34%), Total (4%) and Partex (2%). However PDO is dominated by Shell rather than the Oman government and PDO failed to find additional gas to support the LNG liquefaction terminal beyond the initial dedication of gas. The result is that the LNG liquefaction plant has been operating below capacity for many years. As noted earlier the government of Israel does not have an interest in oil and gas production as a direct participant. It is PDC’s considered view that a limited involvement of the government of Israel in the ownership of an LNG liquefaction terminal would be accepted by the offshore producers. However the government of Israel would have to provide its proportionate share of investment. It would be up to the government of Israel to whom it would rent its capacity to and it could if it wished facilitate third party access. Position Regarding Future Connection of fields other than Tamar and Leviathan The shear size of the Tamar and Leviathan fields provides a real obstacle to the development of other offshore fields. This comes about because these two fields are likely to dominate the physical infrastructure (pipeline and terminal) and the domestic market. This is very typical of the development of offshore fields and is very comparable to the initial developments in the UK North Sea as has been described to the Committee previously. However these Israeli fields are so large that the development of any other fields is going to be difficult. For this reason PDC has proposed the establishment of a strategic reserve which would allow smaller fields to be developed. It is premature to establish policy for these smaller fields as the actual technical development of these smaller fields remains uncertain. The example of the UK is not helpful in this instance as the early large development involved fixed platforms. Smaller additional fields could be brought into production as satellites of these larger fields. A more relevant example is the development of deep water gas fields in Egypt. In this case smaller fields are developed as a group with each group having a dedicated pipeline to shore. Another alternative is the pre-installation of sub-sea tees (described below) which would allow smaller fields to have direct access to the offshore pipelines. Provision of Sub-sea Tees in a Leviathan Domestic Pipeline System Sub-sea tees are installed at the same time as the subsea pipeline. They allow a subsequent field or pipeline to be connected directly to the main pipeline with out interruption to flow in the main pipeline as the tees have an isolation valve that prevents sea water entering the main pipeline. The cost of a sub-sea tee is quite modest in comparison to the cost of retrofitting a connection. An example of this type of system is the UK CATS system which has six sub-sea tees (T1-T6) of which three are available for third party use (T1, T2 and T5). Please see Appendix 1 for details of the system Yours sincerely David Aron Managing Director Appendix 1 CATS Sub-sea Tees
© Copyright 2026 Paperzz