Fiber Distribution Hub ACE-102V Pedestal-Mount

ADCP-96-005 • Issue 2 • December 2004
Fiber Distribution Hub
ACE-102V Pedestal-Mount Cabinet
Installation Instructions
19154-C
Content
Page
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1
DESCRIPTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2
BEFORE STARTING THE INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3
MOUNTING THE PEDESTAL-MOUNT CABINET ON A FIBERGLASS MOUNTING SLEEVE . . . . . . . . . . . . . . . . . . . . . . . . 11
4
MOUNTING THE PEDESTAL-MOUNT CABINET ON A CONCRETE PAD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
5
FEEDER AND DISTRIBUTION CABLE CONFIGURATION INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
6
SPLITTER MODULE INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
7
ROUTING AND CONNECTING THE SPLITTER OUTPUT FIBERS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
8
GUIDELINES FOR USING THE SPLICE DRAWER AND MINI SPLICE TRAYS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
9
MAINTENANCE AND REPAIR PROCEDURES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
10
CUSTOMER INFORMATION AND ASSISTANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
_________________________________________________________________________________________________________
1302878 Rev A
Page 1
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
INTRODUCTION
This publication describes the Fiber Distribution Hub (FDH) ACE-102V Pedestal-Mount
Cabinet and provides instructions for installation. The pedestal-mount cabinet may be mounted
on a fiberglass mounting sleeve or concrete pad. Each mounting option requires an installation
kit that is not included with the cabinet and which must be ordered separately. The cabinet is
shipped with the outside plant (OSP) feeder and distribution cables installed.
Revision History
ISSUE
DATE
REASON FOR CHANGE
1
04/2004
Initial release
2
12/2004
Revised to cover cabinet design changes including swing-out connector panels, isolation gasket installation, OSP cable routing changes, plastic radius limiters, new splice drawer, and removal of louvered vent
openings. Also added splitter output fiber routing guidelines, splitter module installation procedures, and
guidelines for using the splice drawer.
List of Changes
PAGE
IDENTIFIER
All
DESCRIPTION OF CHANGE
Complete revision
Trademark Information
ADC and ADC Telecommunications are registered trademarks of ADC Telecommunications, Inc.
Related Publications
Listed below are related manuals and their publication numbers. Copies of these publications
can be ordered by contacting the ADC Technical Assistance Center at 1-800-366-3891 (in
U.S.A. or Canada) or 952-946-3000, extension 63475 (outside U.S.A. and Canada).
Title/Description
ADCP Number
Optical Fiber Connector Wet and Dry Cleaning Instructions
90-159
ACE Cabinet Splitter Installation Guide
96-033
Fiber Distribution Hub ACE-102V Pole-Mount Cabinet Installation Instructions
96-008
Page 2
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Admonishments
Important safety admonishments are used throughout this manual to warn of possible hazards to
persons or equipment. An admonishment identifies a possible hazard and then explains what
may happen if the hazard is not avoided. The admonishments — in the form of Dangers,
Warnings, and Cautions — must be followed at all times. These warnings are flagged by use of
the triangular alert icon (seen below), and are listed in descending order of severity of injury or
damage and likelihood of occurrence.
Danger: Danger is used to indicate the presence of a hazard that will cause severe personal
injury, death, or substantial property damage if the hazard is not avoided.
Warning: Warning is used to indicate the presence of a hazard that can cause severe personal
injury, death, or substantial property damage if the hazard is not avoided.
Caution: Caution is used to indicate the presence of a hazard that will or can cause minor
personal injury or property damage if the hazard is not avoided.
General Safety Precautions
Danger: Wet conditions increase the potential for receiving an electrical shock when installing
or using electrically-powered equipment. To prevent electrical shock, never install or use
electrical equipment in a wet location or during a lightning storm.
Danger: Do not look into the ends of any optical fiber. Exposure to laser radiation may result.
Do not assume the laser power is turned-off or that the fiber is disconnected at the other end.
Danger: Use adequate lifting equipment when moving or installing FDH cabinets. Verify that
the maximum lift weight rating of the equipment is sufficient to handle the weight of the cabinet.
Danger: Do not stand under a FDH cabinet as it is being hoisted into position for mounting. A
failure of the lifting equipment or apparatus could result in serious personal injury.
Warning: Before digging, check with all local utilities for the presence of buried cables or
pipes. Contact with underground cables or pipes, especially electric power cables and gas
service lines, could interrupt local utility service and cause serious personal injury and
extensive property damage.
Page 3
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
1
DESCRIPTION
This section provides a description of the ACE-102V pedestal-mount cabinet plus
specifications. Also included is a listing of the various accessories and kits.
1.1
ACE-102V Pedestal-Mount Cabinet
The pedestal-mount cabinet, shown in Figure 1, is a secure, above-ground, outdoor fiber optic
distribution cabinet that is designed to hold the splice trays, splitters, connector panels, and
connector storage panel required for a customer-specific Fiber To The Premises (FTTP)
application.
SPLICE
DRAWER
SPLITTER
CHASSIS
RADIUS LIMITERS
FOR PIGTAIL
STORAGE
CONNECTOR
PANELS
CONNECTOR
STORAGE
PANEL
19941-A
Figure 1. Typical ACE-102V Pedestal-Mount Cabinet (Dual-Door Version Shown)
The outside plant (OSP) feeder and distribution cables are factory installed in the pedestalmount cabinet. Both cables enter/exit the cabinet from the bottom and are secured near the entry
point with clamps. The cable entry/exit holes are fitted with grommets to resist the entry of dirt,
insects, debris, etc. from the pedestal cavity. Extra entry/exit holes and clamps are provided so
that if necessary, additional distribution and feeder cables may be installed after the cabinet is
mounted. The bottom of the cabinet is equipped with a removable barrier plate (bottom cover)
to allow access to the pedestal cavity.
Page 4
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
The pedestal-mount cabinet is constructed of heavy gauge aluminum and is available with a
beige, brown, or green finish. The cabinet is available with either one or two doors (option)
which are equipped with tamper-resistant latches, a hasp for installing a padlock, stainless steel
hinges, and door catches to prevent accidental closing. Access to the cabinet requires a 216B key
tool (accessory) to operate the latch. Lifting eyes are attached to the sides of the cabinet to allow
use of hoisting equipment. A grounding bus is provided within the cabinet for grounding the
cabinet per local practice.
The cabinet is equipped with one splice drawer, one 8-position splitter compartment, three precabled 72-position connector panels equipped with SC adapters, and one 64-position connector
storage panel. Two splice trays are included with the splice drawer for splicing the feeder cable
fibers to the input pigtails of the splitters. One 1x32 splitter module is pre-installed in the splitter
compartment. The specifications for the cabinet are provided in Table 1.
Table 1. ACE-102V Pedestal-Mount Cabinet Specifications
PARAMETER
SPECIFICATION
Cabinet
Cabinet dimensions (W x D x H) – See
Figure 2 for additional information
24.8 x 17.18 x 39.15 inches (63.0 x 43.64 x 99.44 cm)
Weight (fully loaded)
110 lbs (49.9 kg)
Certification (pending)
GR-2898-CORE (Issue 2, December 1999)
Distribution ports
216
Distribution port connectors
APC/SC
Splitter module capacity (1x16 or 1x32)
8
Splice tray capacity (mini)
2
Total splices
24 (12 splices per tray)
Feeder cable length
25 or 100 feet (7.4 or 30.5 meters)
Feeder cable fiber count
12 or 24
Distribution cable length
25 or 100 feet (7.4 or 30.5 meters)
Distribution cable fiber count
216
Splitter Modules
Splitter module output pigtails
2 mm with APC/SC connectors
Splitter module input pigtail
2 mm
Test bandpass
1260–1360 nm, 1480–1500 nm, 1550–1560 nm
Overall bandpass
1260–1625 nm
Maximum insertion loss at test bandpass
1x16 standard (includes connector)
1x32 standard (includes connector)
1x32 premium (includes connector)
14.4 dB with APC/SC
17.8 dB with APC/SC
17.2 dB with APC/SC
Return loss at test bandpass
>55 dB
Page 5
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
17.18 IN.
(43.64 CM)
24.80 IN.
(63.0 CM)
39.15 IN.
(99.44 CM)
23.5 IN.
(59.7 CM)
16.18 IN.
(41.1 CM)
19155-E
Figure 2. ACE-102V Pedestal-Mount Cabinet Dimensions
Page 6
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
1.2
Accessories and Replacement Parts
Refer to Table 2 and Table 3 for a listing of the various accessories and replacement parts that
are available for the pedestal-mount cabinet.
Table 2. ACE-102V Pedestal-Mount Cabinet Accessories and Replacement Parts
DESCRIPTION
CATALOG NUMBER
Mounting Kits
Fiberglass Mounting Sleeve (see Figure 3 for dimensions)
FMS-20000
FMS sleeve cover
FCVR-200CVR
FMS adapter cover
FCVR-200ACE1000
Concrete pad mount frame (PMF) kit
ACE-100PMF
6 in. ground spacer - Beige
ACE-ACCSPCR06-102
6 in ground spacer - Brown
ACE-ACCSPCR0BR-102
6 in ground spacer - Green
ACE-ACCSPCR0GR-102
Door Replacement Kits
Single door replacement kit
ACE-ACC100-DRO1KT1
Dual door replacement kit
ACE-ACC100-DRO2KT1
Door gasket kit
ACE-ACC-DGSKT1
Cable Hardware Kits
Blocking kit, loose buffer tube
FBK-OSP002
Clamping kit
OSP-CLPSST
Grounding kit, loose buffer tube
GND-STPKIT
Miscellaneous
Connector panel
ACE-ACC100-TRM0700
Connector panel with 25 foot cable
ACE-ACC100-TRM0702
Parking lot panel
ACE-ACC100-PKLT1
Barrier plate (bottom cover)
ACE-ACC100-MBKT01
Slack storage kit
ACE-ACC100-SSKT1
216B key tool (required to open door)
OSP-216BKEY1
Security key (required to remove lifting eye screws)
OSP-SECKEY1
Mini splice tray with heat shrink splice chip
FSC-HS
Lifting eye kit
ACE-ACC-LFTKT1
Touch-up paint - Beige
ACE-ACC-PTALMD
Touch-up paint - Brown
ACE-ACC-PTBRN
Touch-up paint - Green
ACE-ACC-PTGRN
Cable grommet kit
ACE-ACC-CBLGRMT
Cleaning kit
FPC-CLNKIT1
Page 7
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Table 2. ACE-102V Pedestal-Mount Cabinet Accessories and Replacement Parts, continued
DESCRIPTION
CATALOG NUMBER
Designation label kit
ACE102V-LABLEKIT1
Straight retainer kit
FBA-ASCZ-S/R
Table 3. ACE-102V Pedestal-Mount Cabinet Splitter Modules
2
DESCRIPTION OF SPLITTER MODULE
CATALOG NUMBER
1x16 single, standard - ASC/SC
FPS-SPF1C0J
1x16 dual, standard - ASC/SC
FPS-SPF1M0J
1x32 single, standard - ASC/SC
FPS-SPF1A0J
1x32 single, premium - ASC/SC
FPS-SPF1B0J
Splitter chassis (holds eight splitter modules)
ACE-ACC100-SPLTCH1
BEFORE STARTING THE INSTALLATION
This section provides general installation considerations, unpacking and inspection procedures,
and lists the tools and materials required for cabinet installation.
2.1
Installation Overview
Installation of the pedestal-mount cabinet involves the following main tasks:
Installing a Support Base–The cabinet must be mounted on a suitable support base. The
following two mounting options are available:
• Fiberglass Mounting Sleeve (FMS)–The FMS is a rectangular sleeve that mounts in the
ground. The FMS provides a stable mounting platform plus storage space under the
cabinet for OSP cable slack. The FMS may also be used as a splicing vault for the OSP
feeder and distribution cables.
• Poured Concrete Pad–Concrete slab with Pad Mounting Frame (PMF). The PMF
provides a stainless-steel frame that is embedded in the concrete during installation of the
slab. The cabinet attaches to the PMF which holds it securely to the concrete slab.
Mounting the Cabinet–After the support base is installed, the cabinet must be secured to the
support base. An isolation gasket must always be placed between the support base and cabinet.
The OSP feeder and distribution cables must be uncoiled and routed to a separate splice
enclosure (not provided) before the cabinet is secured to the support base.
Feeder and Distribution Cable Routing and Splicing–The attached OSP feeder and
distribution cables must be routed to a separate splice enclosure (not provided) and spliced to
the system OSP cables.
Page 8
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Splitter installation–The cabinet is equipped with a single splitter module that is spliced to
OSP feeder cable fiber #1. If additional splitters are required, they must be mounted in the
cabinet and the splitter input leads must spliced to the OSP feeder cable.
Splitter Output Fiber Connections–Service is enabled by connecting the splitter output fiber
connectors to the subscriber distribution ports. Unused output fibers are temporarily “parked” in
the storage panel until they are needed for service.
2.2
Unpacking and Inspection
This section provides instructions for opening the shipping boxes, verifying that all parts have
been received, and verifying that no shipping damage has occurred.
Use the following procedure to unpack and inspect the cabinet and all accessories:
1. Open the shipping carton(s) and carefully unpack the cabinet and any accessories from the
protective packing material.
2. Open the cabinet door (requires 216B key tool) and check for broken or missing parts. If
there are damages, contact ADC (see Section 10) for an RMA (Return Material
Authorization) and to reorder if replacement is required.
2.3
Installation Hardware
The cabinet is shipped with fasteners (see Table 4) for securing the cabinet to the FMS or the
PMF.
Table 4. ACE-102V Pedestal-Mount Cabinet Installation Fasteners
ITEM
2.4
QUANTITY
3/8 x 1-inch hex head capscrews
4
3/8-inch flat washers
4
Isolation gasket
1
Tools and Materials Required for Installation
The following tools and materials are required for cabinet installation:
All Installations
•
•
•
•
•
•
9/16-inch wrench
Hammer
Wire cutter
Utility knife
Screwdriver (flat blade)
Tape measure
Page 9
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
•
•
•
•
•
•
•
Pen or marker
216B key tool (required to open cabinet door)
Security key (required to remove lifting eyes)
Padlock (optional)
Grounding system, copper wire, and grounding clamp (per local requirements)
Splicing equipment for splicing OSP feeder and distribution cables
Lifting equipment for hoisting the cabinet into position for mounting
Fiberglass Mounting Sleeve Installations (FMS)
•
•
•
•
•
•
•
Fiberglass Mounting Sleeve (FMS), FMS sleeve cover, FMS adapter cover (see Table 2)
Excavation and earth moving equipment
Stone aggregate (per local practice)
Tamping equipment
Level
Hole saw and drill (use to cut holes for cable conduit if pre-drilled holes are not usable)
Landscaping equipment and site restoration supplies
Concrete Pad Installations
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
2.5
Pad Mount Frame kit for ACE-102V
Excavation and earth moving equipment
Concrete finishing equipment
Approximately 4.5 cu. ft. concrete
Sand or gravel
Tamping equipment
2 x 6 inch framing lumber
1 x 4 inch wooden stakes (4)
Nails and construction screws
Wire (to secure PMF during installation)
Saw
Drill with screwdriver bits
Square
Level
Landscaping equipment and site restoration supplies
Cabinet Mounting
The next two sections provides instructions for mounting the pedestal-mount cabinet on either a
fiberglass mounting sleeve or concrete pad. Use whichever procedure is appropriate for the
installation.
Page 10
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
3
MOUNTING THE PEDESTAL-MOUNT CABINET ON A FIBERGLASS MOUNTING SLEEVE
The FMS-20000, shown in Figure 3, is a fiberglass and polymer concrete sleeve that may be
used to support the cabinet at ground level. The FMS may also be used as a splicing vault. Four
vertical racks are molded into the sides of the FMS to accommodate removable rungs (not
provided). The rungs provide support for splice cases or OSP cable storage.
3.1
Installation Recommendations
The site chosen for the installation must conform to all local codes and any permits required
must be obtained prior to the start of installation. The location must be accessible and provide
adequate parking for worker and vehicle safety. The FMS should be located near the trench that
was used for routing the OSP fiber cables for the system. The basic cabinet is equipped with
either a 12 or 24 fiber (option) feeder cable and a 216-fiber distribution cable.
The installed cabinet must not create a visual or physical obstruction to vehicular or pedestrian
traffic. Ensure that there is sufficient space on all sides to facilitate cabinet installation.
Depending on the landscaping requirements, the top surface of the mounting sleeve may be
located from 0 to 4 inches (10.2 cm) above the surrounding grade.
FMS COVER
38.5 IN.
FMS ADAPTER
COVER
29.81 IN.
FIBERGLASS
MOUNTING
SLEEVE (FMS)
30.0 IN.
68.0 IN.
47.0 IN.
19161-B
Figure 3. FMS-20000 (Fiberglass Mounting Sleeve)
Page 11
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
3.2
Excavation
The excavation must be large enough to provide a fill base that will maintain stability for the
FMS and the cabinet mounted on it. There must be room for 12 inches (30.5 cm) of fill below
and on each side of the FMS. The excavation dimensions for the FMS 20000 are shown in
Figure 4. Excavate a rectangular hole for the FMS.
TOPSOIL OR
DECORATIVE ROCK
VERTICAL RACKS
FOR MANHOLE
CABLE SUPPORT BARS.
CONDUIT
ENTRANCE
HOLES
THE FMS MAY EXTEND
0 TO 4 INCHES ABOVE GRADE
GRADE
SIDE VIEW
42 IN
(106.7 CM)
STONE
AGGREGATE FILL
COMPACTED SOIL
12 IN
(30.5 CM)
92 IN (234 CM)
CONDUIT
ENTRANCE
HOLES
END VIEW
TAMP AGGREGATE AS
HOLE IS FILLED
STONE
AGGREGATE FILL
COMPACTED SOIL
12 IN
(30.5 CM)
71 IN (180 CM)
19090-C
Figure 4. Excavation Recommendations for FSM-20000
3.3
Placement of the FMS
Danger: Use adequate lifting equipment when installing the FMS. Do not stand in the hole while
placing the FMS in position. An unexpected shift of the FMS could result in personal injury.
Use the following procedures to place the FMS into the excavation.
1. Fill the bottom of the hole with stone aggregate, tamping it as it is filled to build a 12 inch
(30.5 cm) layer with a level surface. The stone aggregate will provide a stable base to
support the FMS.
Page 12
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Note: Use crushed rock 3/8-inch or less in size mixed with stone dust (per local practice)
to fill the hole. The name of the material may differ in different geographical areas.
Possible names are Class 5, stone dust, aughts (0s) and ones (1s), or stone aggregate
2. Use appropriate lifting equipment to place the FMS into the center of the hole. Lifting
loops are provided on either side of the FMS for attaching a sling or chain.
3. Use a carpenter’s level to verify that the FMS is level. If it is necessary to add or remove
fill for leveling, tamp any added fill to maintain the base stability.
3.4
Cable Conduit Installation
Select the conduit entrance hole(s) for the OSP feeder and distribution cables. Refer to Figure 4
for the location of the holes. If necessary, additional conduit entrance holes may be cut using a
power drill and hole saw. Place and route the conduit into the entrance hole(s). If preferred, the
FMS may be installed without conduit. The OSP cables may be routed out of the FMS at any
point that is convenient. Cut the cable exit hole to match the size of the cable.
3.5
Grounding System Installation
Install a grounding system (not provided) that meets all local electrical codes. Check local codes
for grounding system installation, use of clamps, wire size, and any other grounding
requirements. Typically, #6 AWG copper wire is used for the grounding wire. Install the
grounding system inside the FMS where it will not interfere with the conduit or cables. Connect
the grounding wire to the grounding system. Leave sufficient slack in the grounding wire to
allow it to be routed into the cabinet as the cabinet is being mounted on the sleeve.
3.6
Back Fill
If installing conduit, hand shovel stone aggregate under the conduit to avoid damage from the
power tamper. Complete the back fill as follows:
1. Add stone aggregate evenly around the FMS and tamp. Fill to approximately 6 inches
(15.2 cm) from the top of the excavation.
2. Complete the back-fill with crushed rock or topsoil depending on the landscaping
requirements. The top surface of the mounting sleeve may be located from 0 to 4 inches
(10.2 cm) above the surrounding grade (see Figure 4).
3.7
Mounting the Cabinet on the FMS-20000
Use the following procedures to mount the ACE-102V pedestal-mount cabinet on the FMS.
Refer to Figure 5 as necessary during the installation.
Warning: Use appropriate lifting equipment when moving or installing the cabinet. Do not
stand under a cabinet as it is being hoisted into position for mounting. A failure of the lifting
equipment could result in serious personal injury.
Page 13
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
ACE-102V CABINET
(FRONT)
CAPSCREWS (4), LOCK
WASHERS (4), AND FLAT
WASHERS (4)
CAPSCREWS (4), LOCK
WASHERS (4), AND FLAT
WASHERS (4)
GROUND SPACER
(OPTIONAL ACCESSORY)
FMS SLEEVE
COVER
ISOLATION GASKET
(REMOVE EDGE STRIPS
AFTER INSTALLATION)
CA
BIN
ET
FR
ON
T
FMS ADAPTER
COVER
GROUNDING WIRE
(INSERT THROUGH
GROMMET AND ROUTE
INTO CABINET)
FMS-20000
19922-B
Figure 5. Mounting the ACE-102V Pedestal-Mount Cabinet on the FMS-20000
Page 14
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
1. Install the FMS adapter cover (see Figure 3) on the FMS and secure using the two
capscrews and flat washers provided. Tighten both capscrews securely.
2. Place the isolation gasket (provided with cabinet) on the adapter cover and align the holes
in the gasket with the holes in the adapter cover. Make sure the “CABINET FRONT” side
of the gasket (look for markings on gasket) is on the side of the adapter cover that
corresponds to the door side of the cabinet.
3. If a ground spacer (optional accessory) will be installed, place the spacer in position for
mounting on the adapter cover. The isolation gasket installed in step 2 should remain in
place between the adapter cover and ground spacer. If a ground spacer will not be
installed, proceed to step 6.
4. Align the mounting holes in the spacer with the mounting holes in the adapter cover.
5. Secure the spacer to the adapter cover using the four capscrews, four lock washers, and
four flat washers provided with the spacer. Tighten all capscrews securely.
6. Using appropriate lifting equipment, hold the cabinet in position for mounting over the
adapter cover.
Danger: Do not stand directly under the cabinet as it is being hoisted into position for cable
installation. A failure of the lifting equipment could result in serious personal injury.
7. Carefully route the feeder and distribution cables, shown in Figure 6, through the
rectangular hole located in the center of the adapter cover.
CABLE
CUTOUT SECTIONS
DETAIL DRAWIING
OF GROMMET
GROUNDING
WIRE
19942-A
GROMMET
FEEDER
CABLE
DISTRIBUTION
CABLE
Figure 6. Feeder, Distribution, and Grounding Cables
8. Feed the OSP feeder and distribution cables into the appropriate conduit sections and route
to the designated splice enclosure (not provided). Any excess cable slack may be stored in
the bottom of the FMS.
Note: The FMS may be used as a splicing vault or the cabinet OSP feeder and distribution
cables may be routed through the conduit to a separate splicing enclosure.
Page 15
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
9. Insert the grounding wire (installed in Section 3.5) through one of the unused grommeted
holes (see Figure 6) located on the bottom-left or bottom-right (front) of the cabinet and
pull through several feet of slack.
10. Lower the cabinet onto the adapter cover or spacer and align the mounting holes in the
bottom of the cabinet with the holes in the cover or spacer. If a ground spacer was not
installed, the isolation gasket installed in step 2 should be left in place between the adapter
cover and cabinet.
11. Secure the cabinet to the adapter cover or spacer using the four capscrews, four lock
washers, and four flat washers provided. Tighten all four capscrews securely.
12. Tear off the perforated edge strips located on the left and right sides of the installed
isolation gasket and discard.
13. Attach the grounding wire to the grounding lug located on the lower front side of the
cabinet as shown in Figure 7. The grounding lug can be used for #6 – #14 AWG wire.
Tighten the ground lug set screw securely.
GROUNDING LUG
(#6 - #14 AWG WIRE)
19159-A
NOTE: SHOWN WITH BOTH FRONT AND
REAR SECTIONS OF BOTTOM COVER
(MOISTURE BARRIER) REMOVED
Figure 7. Grounding Wire Connection To Cabinet
14. The lifting eyes may be left in place or removed from the cabinet. To remove the lifting
eyes, use the security key tool (accessory) to remove the lifting eye screws. Store the
lifting eyes inside the cabinet and then re-install the lifting eye screws in the cabinet.
15. If the FMS will be used as a splicing vault for the OSP feeder and distribution cables,
install the required splice enclosure. If the OSP cables will be spliced in a separate splicing
enclosure, route each cable through the conduit to the splice enclosure. Leave several turns
of slack in the bottom of the FMS as a service loop.
16. Install the FMS cover on the FMS (see Figure 3) and secure using the two capscrews and
washers provided. Tighten both capscrews securely.
Page 16
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
4
MOUNTING THE PEDESTAL-MOUNT CABINET ON A CONCRETE PAD
The Pad Mount Frame (PMF), shown in Figure 8, is a stainless steel frame that provides a
mounting base for the cabinet when installed in a concrete pad foundation.
Caution: Mounting the cabinet directly on a concrete pad may cause chemical corrosive action
to the cabinet. Use only the Pad Mount Frame (PMF) as a mounting base for the cabinet. Do
not use caulking compounds as a sealer between the cabinet and PMF.
5.5 IN.
(14.0 CM)
16.4 IN.
(41.7 CM)
25.8 IN.
(65.5 CM)
19065-B
Figure 8. Pad Mount Frame Dimensions
4.1
Installation Recommendations
The site chosen for the installation must conform to all local codes and any permits required
must be obtained prior to the start of installation. The location must be accessible and provide
adequate parking for worker and vehicle safety. Situate the concrete pad along the trench that
was used for routing the OSP fiber cables for the system. The basic cabinet is equipped with a
12 or 24 fiber (option) feeder cable and a 216-fiber distribution cable.
The installed cabinet must not create a visual or physical obstruction to vehicular or pedestrian
traffic. Ensure that there is sufficient space on all sides to facilitate cabinet installation.
Depending on the landscaping requirements, the top surface of the concrete pad may be located
from 0 to 3 inches (7.6 cm) above the surrounding grade.
4.2
Cable Conduit Installation
Install the cable conduit from below as shown in Figure 9 and position it so that the top of each
upward bend will be located within the PMF opening at the indicated point. When installed, the
top of the conduit should be located 1 to 2 inches (2.54 to 5.08 cm) below the top of the finished
concrete pad. Install the conduit before pouring the pad.
4.3
Base Installation
Prepare a base for the concrete pad that meets all local code requirements. The base must have a
footing of 4 to 6 inches (10.2 to 15.2 cm) of sand or gravel on firmly compacted soil. Refer to
the construction diagram (see Figure 9) for details.
Page 17
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
42 IN.
(106.7 CM)
29.1 IN.
(73.9 CM)
4 IN DUCT FOR PREINSTALLED FEEDER
AND DISTRIBUTION
CABLES (LOCATE
1 - 2 INCHES BELOW
TOP OF PAD)
14.9 IN.
(37.8 CM)
12.7 IN
(32.3 CM)
8 IN. (20.3 CM)
13.5 IN.
(34.3 CM)
GROUND ROD
(LOCATE 1 - 2 INCHES
BELOW TOP OF PAD)
DO NOT POUR
CONCRETE
INSIDE PAD
MOUNT FRAME
REINFORCED
CONCRETE PAD
19.5 IN.
(49.5 CM)
PAD MOUNT FRAME
CAST IN PLACE
CABINET FRONT
42.5 IN.
(108.0 CM)
18 IN.
(45.7 CM)
4 IN DUCT FOR SPARE
DISTRIBUTION CABLE (LOCATE
1 - 2 INCHES BELOW TOP OF PAD)
6.0 IN.
(15.2 CM)
4 IN DUCT FOR SPARE
FEEDER CABLE (LOCATE 1 - 2
INCHES BELOW TOP OF PAD)
TOP OF PMF SHOULD BE
FLUSH WITH TOP OF CONCRETE
TOPSOIL OR
DECORATIVE ROCK
GRADE
SAND OR GRAVEL
4.0 IN. MIN.
(10.2 CM)
90 BEND
IN DUCT
COMPACTED SOIL
19929-A
Figure 9. Constructing the Concrete Pad for the ACE-102V Pedestal-Mount Cabinet
Page 18
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
4.4
Concrete Pad Construction
Use the following procedure to construct the concrete pad:
1. Build a wood form for the concrete pad using 2 x 6 framing lumber as shown in Figure 10.
2. Locate the PMF as shown in the construction diagram (see Figure 9). When installed, the
top surface of the PMF must be flush and level with the top of the concrete pad.
Note: Use temporary top framing to keep the top surface of the PMF flush and level with
the top of the concrete pad (see Figure 10).
3. Place reinforcing material inside the form but outside of the PMF.
40 IN.
(101.6 CM)
DIMENSIONS SHOW FINISHED
SIZE OF CONCRETE PAD
40 IN.
(101.6 CM)
FRO
NT
19930-A
2 x 6 FRAMING
FOR FORM
PAD MOUNT
FRAME (PMF)
LEVELING
STAKES
(4 PLACES)
TEMPORARY
SUPPORT WIRES
(4 PLACES)
Figure 10. ACE-102V Pedestal-Mount Cabinet Concrete Pad Framing
4. Verify that the PMF and form are level. Depending on the landscaping requirements, the
top surface of the concrete pad may be 0 to 3 inches (0 to 7.6 cm) above the final grade. The
weld nuts are covered with plugs which must be left in place until the enclosure is mounted.
5. Pour the concrete to form the pad but do not pour concrete into the center area of the PMF.
Note: Allow some concrete to flow under the flanges on the bottom of the PMF so the
PMF will be locked in place when the concrete hardens. However, do not allow concrete to
fill the center of the PMF. If necessary, partially fill the center of the PMF with sand or
gravel to prevent an inflow of concrete.
6. Remove the top framing and the temporary support wires when the concrete is ready to be
finished.
7. Allow concrete to cure before proceeding with the installation.
Page 19
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
4.5
Grounding System Installation
Install a grounding system (not provided) that meets all local electrical codes. Check local codes
for ground system installation, use of clamps, wire size, and any other grounding requirements.
Typically, #6 AWG copper wire is used for the ground wire. If the ground system includes a
ground rod, install the rod (see Figure 9) within the PMF opening at the indicated point. The top
of the rod should be located 1 to 2 inches (2.54 to 5.08 cm) below the top of the finished concrete
pad. Connect the grounding wire to the grounding system. Leave sufficient slack in the grounding
wire to allow it to be routed into the cabinet as the cabinet is being mounted on the pad.
4.6
Mounting the Cabinet on the Concrete Pad
Use the following procedures to mount the cabinet on the concrete pad. Refer to Figure 11 as
necessary during the installation.
Warning: Use appropriate lifting equipment when moving or installing the cabinet. Do not
stand under the cabinet as it is being hoisted into position for installation. A failure of the lifting
equipment could result in serious personal injury.
1. Remove the plastic plugs that are installed in the threaded corner holes and clean off any
concrete that may have adhered to the top of the PMF.
Note: Make sure all remnants of concrete are removed from the PMF prior to mounting
the cabinet. It is not necessary to use shims to level or align the cabinet as long as the top
surface of the PMF is clean and free of any installation debris.
2. Place the isolation gasket (provided with cabinet) on the PMF and align the holes in the
gasket with the holes in the PMF. Make sure the “CABINET FRONT” side of the gasket
(look for markings on gasket) is on the side of that corresponds to the door side of the
cabinet.
3. If a ground spacer (optional accessory) will be installed, place the spacer in position for
mounting on the PMF. The isolation gasket installed in step 2 should remain in place
between the PMF and ground spacer. If a ground spacer will not be installed, proceed to
step 6.
4. Align the mounting holes in the spacer with the mounting holes in the PMF.
5. Secure the spacer to the PMF using the four capscrews, four lock washers, and four flat
washers provided with the spacer. Tighten all capscrews securely.
6. Using appropriate lifting equipment, hold the cabinet in position for mounting over the
PMF or spacer.
Danger: Do not stand directly under the cabinet as it is being hoisted into position for cable
installation. A failure of the lifting equipment could result in serious personal injury.
7. Carefully route the attached OSP feeder and distribution cables (see Figure 6) into the
conduit and pull each cable through to the splice enclosure.
Note: A separate splice enclosure (not provided) is required for splicing the cabinet OSP
feeder and distribution cables to the system OSP feeder and distribution cables.
Page 20
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
ACE-102V CABINET
(FRONT)
CAPSCREWS (4), LOCK
WASHERS (4), AND FLAT
WASHERS (4)
CAPSCREWS (4), LOCK
WASHERS (4), AND FLAT
WASHERS (4)
GROUND SPACER
(OPTIONAL ACCESSORY)
ISOLATION GASKET
(REMOVE EDGE STRIPS
AFTER INSTALLATION)
GROUNDING WIRE
(INSERT THROUGH
GROMMET AND ROUTE
INTO CABINET)
CAB
INET
FRO
NT
FEEDER AND DISTRIBUTION
CABLE CONDUIT
CONCRETE
PAD
19921-B
SPARE DISTRIBUTION
CABLE CONDUIT
(OPTIONAL)
PAD MOUNT
FRAME (PMF)
SPARE FEEDER
CABLE CONDUIT
(OPTIONAL)
Figure 11. Mounting the ACE-102V Pedestal-Mount Cabinet on the Concrete Pad
Page 21
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
8. Insert the ground wire (installed in Section 4.5) through one of the unused grommeted
holes (see Figure 6) located on the bottom-left or bottom-right (front) of the cabinet and
pull through several feet of slack.
9. Lower the cabinet onto the PMF or spacer and align the mounting holes in the cabinet with
the threaded holes in the PMF or spacer.
10. Secure the cabinet to the PMF or spacer using the four capscrews, four lock washers, and
four flat washers provided. Tighten all four capscrews securely.
11. Tear off the perforated edge strips located on the left and right sides of the installed
isolation gasket and discard.
12. Attach the ground wire to the grounding lug located on the lower front side (see Figure 7)
of the cabinet. The grounding lug can be used for #6 – #14 AWG wire. Tighten the ground
lug set screw securely.
13. The lifting eyes may be left in place or removed from the cabinet. To remove the lifting
eyes, use the security key tool (accessory) to remove the lifting eye screws. Store the
lifting eyes inside the cabinet and then re-install the lifting eye screws in the cabinet.
Page 22
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
5
FEEDER AND DISTRIBUTION CABLE CONFIGURATION INFORMATION
The ACE-102V pedestal-mount cabinet is equipped with OSP feeder and distribution cables
that enter/exit the cabinet from the bottom. Both cables must be spliced to the system feeder and
system distribution cables at a separate splice enclosure (not provided). Depending on the
option ordered, the feeder and distribution cables may be either 25 or 100 feet (7.6 or 30.5
meters) in length. The following sections describe how the cables are configured for splicing.
5.1
OSP Feeder Cable Configuration
The OSP feeder cable is a ribbon-type cable that may have fiber count of 12 or 24 fibers. At the
entry/exit point to the cabinet, the feeder cable is secured with a pair of clamps. Beyond the
clamps, the outer sheath of the cable is removed to expose the fiber ribbon. For protection, the
fiber ribbon is inserted into a flexible clear plastic tube. The clear plastic tube and the enclosed
fiber ribbon are routed to the splice tray panel at the top of the cabinet. A diagram of the feeder
cable configuration is shown in Figure 12.
FIBER DESIGNATIONS
WITHIN FEEDER
CABLE SUBUNIT(S)
FIBER #1
(BLUE)
SPLICE
SPARE
FIBERS
FIBER
COLOR
8
7
4
1
2
3
4
5
6
7
8
9
10
11
12
BLUE
ORANGE
GREEN
BROWN
SLATE
WHITE
RED
BLACK
YELLOW
VIOLET
ROSE
AQUA
6
2
5
SPLITTER 1
3
SPLITTER
INPUT FIBER
CONNECTOR
PANEL 1
CONNECTOR
PANEL 2
CONNECTOR
PANEL 3
OSP FEEDER
CABLE
CONNECTOR STORAGE
19163-A
Figure 12. Feeder Cable Configuration
Page 23
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Storage space for two mini splice trays is provided in the splice panel. Two splice trays with are
provided with each cabinet. Each mini splice tray provides space for 12 heat shrink splices.
Fiber #1 (blue) in the feeder cable is spliced to the input lead from splitter #1. The remaining
fibers are spares. As additional splitters are installed in the cabinet, the spare feeder cable fibers
must be spliced to the input leads of the additional splitters. Up to eight splitters may be
mounted in the cabinet.
Designation labels, shown in Figure 13, are provided on the door(s) of the cabinet for recording
splice tray and splitter module information.
FDH ID# :
FDH ADDRESS :
CLLI Code :
Splice Tray 1
F1 Cable ID
F1
Splitter Module #
Fiber #
Splice Tray 2
Splitter Module
Serial #
F1 Cable ID
F1
Splitter Module #
Fiber #
Splitter Module
Serial #
SPLITTER MODULE
DESIGNATION LABEL
SPLICE TRAYS
DESIGNATION LABEL
SPLITTER TYPE
AND SERVICE INFO
Splice Tray 1
F1
F1 Cable ID
Splitter Module #
Fiber #
Splitter Module
Serial #
19950-A
Figure 13. Splice Tray and Splitter Module Designation Labels – Dual-Door Cabinet
Page 24
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
5.2
OSP Distribution Cable Configuration
The OSP distribution cable is a ribbon-type cable with a fiber count of 216 fibers. At the entry/
exit point to the cabinet, the distribution cable is secured with two clamps. Beyond the clamps,
the outer sheath of the cable is removed and the fiber ribbons are broken out into eighteen 12fiber subunits. Each subunit is fanned out into twelve individual fibers, each of which is
terminated with an angled APC/SC connector
Subunits 1–6 are routed to the back of connector panel 1, subunits 7–12 are routed to the back of
connector panel 2, and subunits 13–18 are routed to the back of connector panel 3. Each fiber
connector is connected to a specified bulkhead adapter. A diagram of the distribution cable
configuration is shown in Figure 14.
SPLICE DRAWER
SPLITTERS
SUBUNITS
1-6
CONNECTOR
PANEL 1
SUBUNITS
7 - 12
CONNECTOR
PANEL 2
SUBUNITS
13 - 18
CONNECTOR
PANEL 3
OSP
DISTRIBUTION
CABLE
CONNECTOR STORAGE
19931-A
Figure 14. Distribution Cable Configuration
Designation labels are provided on the cabinet door(s) for recording subscriber information for
each connector panel port. The labels, shown in Figure 15, indicate the fiber number and cable
number associated with each fiber port. The subunits are numbered (1–18) for identification and
the individual fibers are color-coded for identification. Refer to Table 5 for a listing of the port
numbers and the corresponding distribution cable subunit and fiber numbers.
Page 25
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
ENTER SUBSCRIBER INFO
AND SERVICE TYPE
1
2
3
4
5
6
1 FBR
2 FBR
3 FBR
4 FBR
5 FBR
PORT
NUMBER
FBR
FIBER NUMBER
CABLE 1 CABLE 1 CABLE 1 CABLE 1 CABLE 1 CABL
19
20
21
22
23
24
FBR
19 FBR
20 FBR
21 FBR
22 FBR
23 FBR
CABLE NUMBER
PANEL
1
FIBERS
1-72
CABLE 1 CABLE 1 CABLE 1 CABLE 1
37
38
39
40
CABLE 1
CABLE
41
42
DESIGNATION LABEL
FOR PANEL 1
FBR
37 FBR
38 FBR
39 FBR
40 FBR
41 FBR
CABLE 1 CABLE 1 CABLE 1 CABLE 1 CABLE 1 CABLE
55
56
57
58
59
60
FBR
55 FBR
56 FBR
57 FBR
58 FBR
59 FBR
CABLE 1 CABLE 1 CABLE 1 CABLE 1
PANEL 1
1
PANEL 2
2
PANEL 3
3
CABLE 1
CABLE
19951-A
Figure 15. Connector Panel Designation Labels – Dual-Door Cabinet
Page 26
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
Table 5. Distribution Cable Port, Subunit, and Fiber Designations
PORT
SUBUNIT*
FIBER
1
1, 7, or 13
1 (Blue)
2
1, 7, or 13
2 (Orange)
3
1, 7, or 13
3 (Green)
4
1, 7, or 13
4 (Brown)
5
1, 7, or 13
5 (Slate)
6
1, 7, or 13
6 (White)
7
1, 7, or 13
7 (Red)
8
1, 7, or 13
PORT
SUBUNIT*
FIBER
37
4, 10, or 16
1 (Blue)
38
4, 10, or 16
2 (Orange)
39
4, 10, or 16
3 (Green)
40
4, 10, or 16
4 (Brown)
41
4, 10, or 16
5 (Slate)
42
4, 10, or 16
6 (White)
43
4, 10, or 16
7 (Red)
8 (Black)
44
4, 10, or 16
8 (Black)
9
1, 7, or 13
9 (Yellow)
45
4, 10, or 16
9 (Yellow)
10
1, 7, or 13
10 (Violet)
46
4, 10, or 16
10 (Violet)
11
1, 7, or 13
11 (Rose)
47
4, 10, or 16
11 (Rose)
12
1, 7, or 13
12 (Aqua)
48
4, 10, or 16
12 (Aqua)
13
2, 8, or 14
1 (Blue)
49
5, 11, or 17
1 (Blue)
14
2, 8, or 14
2 (Orange)
50
5, 11, or 17
2 (Orange)
15
2, 8, or 14
3 (Green)
51
5, 11, or 17
3 (Green)
16
2, 8, or 14
4 (Brown)
52
5, 11, or 17
4 (Brown)
17
2, 8, or 14
5 (Slate)
53
5, 11, or 17
5 (Slate)
18
2, 8, or 14
6 (White)
54
5, 11, or 17
6 (White)
19
2, 8, or 14
7 (Red)
55
5, 11, or 17
7 (Red)
20
2, 8, or 14
8 (Black)
56
5, 11, or 17
8 (Black)
21
2, 8, or 14
9 (Yellow)
57
5, 11, or 17
9 (Yellow)
22
2, 8, or 14
10 (Violet)
58
5, 11, or 17
10 (Violet)
23
2, 8, or 14
11 (Rose)
59
5, 11, or 17
11 (Rose)
24
2, 8, or 14
12 (Aqua)
60
5, 11, or 17
12 (Aqua)
25
3, 9, or 15
1 (Blue)
61
6, 12, or 18
1 (Blue)
26
3, 9, or 15
2 (Orange)
62
6, 12, or 18
2 (Orange)
27
3, 9, or 15
3 (Green)
63
6, 12, or 18
3 (Green)
28
3, 9, or 15
4 (Brown)
64
6, 12, or 18
4 (Brown)
29
3, 9, or 15
5 (Slate)
65
6, 12, or 18
5 (Slate)
30
3, 9, or 15
6 (White)
66
6, 12, or 18
6 (White)
31
3, 9, or 15
7 (Red)
67
6, 12, or 18
7 (Red)
32
3, 9, or 15
8 (Black)
68
6, 12, or 18
8 (Black)
33
3, 9, or 15
9 (Yellow)
69
6, 12, or 18
9 (Yellow)
34
3, 9, or 15
10 (Violet)
70
6, 12, or 18
10 (Violet)
35
3, 9, or 15
11 (Rose)
71
6, 12, or 18
11 (Rose)
36
3, 9, or 15
12 (Aqua)
72
6, 12, or 18
12 (Aqua)
*Panel 1 uses subunits 1–6, Panel 2 uses subunits 7–12, and Panel 3 uses
subunits 13–18.
Page 27
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
6
SPLITTER MODULE INSTALLATION
The ACE-102V cabinet can accommodate up to eight 1x16 or 1x32 splitter modules. Each
splitter module provides a single non-connectorized input fiber which must be spliced to the
feeder cable. Each splitter module also provides either sixteen or thirty-two connectorized
output fibers. The output fibers connect to the distribution ports to provide service to
subscribers. The cabinet provides a maximum of 216 optical ports for the distribution of optical
services. Use the following procedure to install additional splitters in the cabinet:
1. Install the splitter module in the next available mounting position as shown in Figure 16.
Note: Install splitters in the order shown in Figure 16, beginning on the lower right side of
the splitter compartment and then working from the bottom to the top.
2. Route the splitter output fibers to the connector storage panel or to the designated
customer port. Refer to Section 7 for the routing procedure.
3. Route the splitter input fiber to the splice panel at the top of the cabinet.
4. Open the splice panel drawer and coil up the splitter input fiber around the splice tray for
temporary storage. Refer to Section 8 for the routing procedure and the feeder cable and
splitter input fiber splicing procedure.
8
4
7
3
6
2
5
1
DETAIL DRAWING OF
SPLITTER MODULES
19970-A
Figure 16. Splitter Module Installation
Page 28
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
7
ROUTING AND CONNECTING THE SPLITTER OUTPUT FIBERS
The splitter modules are mounted near the top of the ACE-102V cabinet. When a splitter
module is initially installed, the output fibers are routed to the storage panel located at the
bottom of the cabinet. At the storage panel, the output fibers are temporarily “parked” until they
are needed. Service to a subscriber is enabled by removing an unused output fiber from the
storage panel, routing it to the appropriate connector panel, and then connecting it to the
subscriber port.
7.1
Storing The Splitter Output Fibers
Use the following procedure to store the splitter output fibers:
1. Following installation of a splitter module, route each output fiber over the specified spool
on the right side of the cabinet as shown in Figure 17 and Figure 18.
2. Locate an unused connector pack slot on the storage panel.
3. Insert the connector pack into the unused slot in the storage panel. Refer to the ACE
Cabinet Splitter Installation Guide (ADCP-96-033) provided with the splitter module for
additional information on installing connector packs in the storage panel.
4. Use the slack storage spools on the right side of the cabinet to store any excess fiber slack.
USE CENTER RADIUS LIMITER
WHEN ROUTING FROM RIGHT SIDE
19971-A
Figure 17. Routing to Storage Panel from Right Side Splitter Module
Page 29
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
USE LOWER RADIUS LIMITER
WHEN ROUTING FROM LEFT SIDE
19972-A
Figure 18. Routing to Storage Panel from Left Side Splitter Module
7.2
Enabling Service To a Subscriber
Use the following procedure to enable service to a subscriber:
1. Check the designation labels on the cabinet door to determine the connector panel number
and distribution port number that correspond to the address of the subscriber.
2. Locate the subscriber port on the specified connector panel and remove both the adapter
dust cap and the connector ferrule dust cap.
3. Select and remove an unused splitter output fiber from the storage panel and carefully
work it free of any other fibers.
4. Remove the ferrule dust cap from the connector and then clean the connector as specified
in the Optical Fiber Connector Wet and Dry Cleaning Instructions (ADCP-90-159).
5. Hold the output fiber connector near the subscriber port.
6. Route each output fiber over the specified spool on the right side of the cabinet as shown
in Figure 19 and Figure 20. Use the slack storage spools on the right side of the cabinet to
store any excess fiber slack.
7. Insert the output fiber connector into the connector panel port adapter.
Page 30
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
USE CENTER RADIUS LIMITER
WHEN ROUTING FROM RIGHT SIDE
TAKE UP SLACK ON
APPROPRIATE
RADIUS LIMITER
19973-A
Figure 19. Routing To Connector Panels From Right Side Splitter Modules
USE LOWER RADIUS LIMITER
WHEN ROUTING FROM LEFT SIDE
TAKE UP SLACK ON
APPROPRIATE
RADIUS LIMITER
19974-A
Figure 20. Routing To Connector Panels From Left Side Splitter Modules
Page 31
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
8
GUIDELINES FOR USING THE SPLICE DRAWER AND MINI SPLICE TRAYS
This section provides guidelines for using the splice drawer and the mini splice trays that are
installed in the splice drawer. On an optional basis, the ACE-102V cabinet is equipped by the
factory with either a 12 or 24 fiber feeder cable and a single splitter. The feeder cable optical
fiber subunit is routed into the splice drawer and fiber #1 (blue) is spliced to the input fiber of
splitter module #1. When addition splitter modules are installed, the splitter input fibers must be
routed into the splice drawer for splicing to the spare feeder cable fibers.
Use the following procedures to route additional splitter input fibers into the splice drawer and
to prepare the input fibers for splicing:
8.1
Opening The Splice Drawer
To open the splice drawer, push the drawer release tabs inward and with both hands, pull the
drawer straight out as far as it will go as shown in Figure 21. The splice drawer will lock into the
open position.
Caution: The maximum loading force that may be applied to a fully extended splice drawer
must not exceed 12 lbs. Exceeding the maximum specified loading force will cause permanent
damage to the splice drawer components.
PRESS TO
RELEASE
19945-A
Figure 21. Drawer Locked in Open Position
Page 32
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
8.2
Routing Splitter Input Fibers Into the Splice Drawer
Use the following procedure to route the splitter input fibers into the splice drawer and to
prepare the input fibers for splicing:
1. Route the splitter input fiber into the splice drawer through the trumpet flare opening on
the right side of the drawer as shown in Figure 22.
SPLITTER INPUT
FIBER
FIBER
RETAINING
FINGER
TRUMPET
FLARE
OPENING
19944-B
Figure 22. Routing Fiber Into Splice Drawer
2. Lift upward on the end of the fiber retaining finger to allow the fiber to be placed in the
trumpet flare.
3. Route the splitter input fiber around the spool in the right rear corner of the splice drawer
as shown in Figure 23 and then loop it 1.5 times around the splice trays.
4. Release the rubber strap that secures the splice trays to the splice drawer and remove the
plastic cover from the top splice.
5. Use lacing to secure the splitter input fiber to the splice tray at the tie point indicated in
Figure 24.
6. From the tie point on the splice tray, trim the splitter input fiber to a cut length of 18 inches
(457 mm).
7. Remove the protective outer jacket from the splitter input fiber to expose the bare optical
fiber.
Page 33
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
FEEDER
CABLE
SUBUNIT
SPLITTER
INPUT
FIBER
19923-B
Figure 23. Routing Fiber Within the Splice Drawer
TIE POINT
FOR FEEDER
SUBUNIT
TIE POINT
FOR SPLITTER
INPUT FIBER
19943-A
Figure 24. Placing Fiber Within The Splice Tray
Page 34
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
8. Splice the splitter input fiber to the appropriate feeder cable fiber per local practice and
procedure. To facilitate the splicing process, the splice tray may be removed from the
splice drawer and the excess slack uncoiled from the slack storage area within the drawer.
9. When splicing has been completed, replace the splice tray top cover and then re-install the
splice tray and the attached optical fibers in the splice drawer. Coil all excess fiber slack
around the center of the splice drawer.
10. Use the rubber strap released in step 5 to secure the splice trays to the splice drawer.
11. Verify that all fibers are properly stored within the splice drawer and that no kinks or
excessive bends occur as a result of the fiber routing within the drawer.
8.3
Closing The Splice Drawer
To close the splice drawer, release the latch by pressing downward on the latch tab (see Figure
21). Verify that all optical fibers are properly secured and located below the top surface of the
drawer. Slowly close the drawer while verifying that no fiber kinks or bends occur as the drawer
is closed.
Page 35
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
9
MAINTENANCE AND REPAIR PROCEDURES
The ACE-102V pedestal-mount cabinet requires no regular maintenance to insure continuous
and satisfactory operation. Maintenance is limited to repairing or replacing any cabinet
components that may be damaged or broken in the course of normal operation. The following
sections provide procedures for repairing or replacing common cabinet components.
9.1
Painting
Brush-in-cap type bottles of paint are available (see Table 2) for touching-up nicks and
scratches in the factory coat of paint. Lightly sand the area to be painted and then clean it
thoroughly to remove any dirt, dust, or foreign matter. Shake the paint bottle until thoroughly
mixed and then apply a light coat of paint to the damaged area using the small brush attached to
the cap. Wait until the paint is dry and then apply a second coat if necessary. When finished
painting, replace the paint bottle cap and tighten securely.
9.2
Adapter Replacement
Replacement adapters are available (see Table 2) for the connector panels. Use the following
procedure to remove and replace a damaged adapter:
1. Disconnect the splitter connector from the front side of the adapter as shown in Figure 25.
DISTRIBUTION
CONNECTOR
TAB
ADAPTER
SPLITTER
CONNECTOR
19199-A
Figure 25. Adapter Removal and Replacement (Typical Connector Panel)
Page 36
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
2. Push down on the small tab at the top of the adapter retainer and at the same time pull
outward on the adapter until it is released from the panel.
3. Pull the adapter away from the panel until about 6 inches of fiber are exposed.
4. Disconnect the distribution connector from the rear side of the adapter.
5. Discard the damaged adapter.
6. Clean the distribution fiber connector as specified in Optical Fiber Connector Wet and Dry
Cleaning Instructions (ADCP-90-159).
7. Orient the replacement adapter as shown in Figure 25 and then mate the distribution
connector with the rear side of the adapter.
8. Re-install the replacement adapter in the connector panel. Make sure the small tab on the
adapter is facing up and that the fiber feeds smoothly back into the connector panel.
9. Clean the splitter connector (see ADCP-90-159) and mate it with the front side of the
replacement adapter.
9.3
Connector Replacement
Damaged fiber optic connectors may be replaced using a field-installable connector
replacement kit. The following sections provide basic access and replacement procedures for
both the splitter output fiber connectors and the distribution fiber connectors.
9.3.1
Splitter Output Fiber Connector Replacement
Use the following procedure to replace a damaged splitter output fiber connector:
1. Disconnect the damaged splitter output fiber connector from the front side of the adapter.
2. Replace the damaged connector as specified in the procedures provided with the fieldinstallable connector replacement kit.
3. Push down on the small tab at the top of the adapter retainer and at the same time pull
outward on the adapter until it is released from the panel.
4. Pull the adapter away from the panel until about 6 inches of fiber are exposed.
5. Disconnect the distribution connector from the rear side of the adapter.
6. Clean the distribution fiber connector as specified in the Optical Fiber Connector Wet and
Dry Cleaning Instructions (ADCP-90-159) or by locally approved procedures.
7. Orient the adapter as shown in Figure 25 and then mate the distribution connector with the
rear side of the adapter.
8. Re-install the adapter in the connector panel. Make sure the small tab on the adapter is
facing up and that the fiber feeds smoothly back into the connector panel.
9. Clean the splitter output fiber connector (see ADCP-90-159) and mate it with the front
side of the adapter.
Page 37
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
9.3.2
Distribution Fiber Connector Replacement
Use the following procedure to replace a damaged distribution fiber connector:
1. Disconnect the splitter output fiber connector from the front side of the adapter.
2. Unsnap the latch in the lower left corner of the front panel and carefully open the panel as
shown in Figure 26.
TOP VIEW
BULKHEAD
REAR
CONNECTOR
19947-A
ADAPTER
FRONT
CONNECTOR
Figure 26. Open Connector Panel
Page 38
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
3. Disconnect the distribution connector from the rear side of the adapter.
4. Replace the damaged distribution connector as specified in the procedures provided with
the field-installable connector replacement kit.
5. Clean the distribution fiber connector as specified in the Optical Fiber Connector Wet or
Dry Cleaning Instructions (ADCP-90-159) or by locally approved procedures.
6. Connect the distribution fiber connector to the rear side of the adapter.
7. Carefully close the connector panel front panel and re-snap the latch.
8. Clean the splitter output fiber connector (see ADCP-90-159) and mate it with the front
side of the adapter.
9.4
Door Gasket Replacement
Damaged door gaskets may be replaced using the door gasket kit which includes a roll of gasket
material. The ideal installation temperature for the adhesive used on the replacement gaskets is
between 60 and 100 ºF (16 and 38 ºC). Installation is not recommended if the temperature is
below 50 ºF (10 ºC). Remove any damaged sections of gasket material from the door. If
necessary, use a citrus based adhesive cleaner to remove any adhesive that may stay attached to
the door. Cut replacement lengths of gasket material from the roll as needed. Remove the paper
backing to expose the adhesive and then carefully apply the replacement gasket to the door.
9.5
Door Replacement
Damaged cabinet doors may be replaced using either the single or dual-door replacement kit.
Use the following procedure to remove and replace the cabinet door(s):
1. Open the cabinet door(s) and lock in the open position as shown in Figure 27.
2. Use a 3/8-inch nut driver to remove the two locking nuts that secure the grounding strap
lug to the door. Save nuts for reuse.
3. Pull out the pin that secures the door linkage to the bracket on the upper edge of the
cabinet. Save the pin for reuse.
4. Use a 3/8-inch nut driver to remove the three locking nuts that secure each hinge to the
door. Save nuts for reuse.
Note: Support the door as the last nuts are removed to prevent the door from falling.
5. Carefully lift the door away from the cabinet.
6. Transfer all designation information that may be recorded on the damaged door to the
labels on the replacement door.
7. Place the replacement door in position for installation on the hinges.
8. Using a 3/8-inch nut driver, reinstall the three locking nuts (saved in step 4) that secure
each hinge to the door.
Page 39
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
LEFT
DOOR
LINKAGE
DOOR LINKAGE
PINS
LEFT DOOR
HINGES
RIGHT
DOOR
LINKAGE
RIGHT DOOR
HINGES
19952-A
GROUNDING
STRAP LUG
GROUNDING
STRAP LUG
Figure 27. ACE-102V Pedestal-Mount Cabinet Door Replacement (Dual-Door Version Shown)
9. Reinstall the pin (saved in step 3) that secures the door linkage to the bracket on the upper
edge of the cabinet.
10. Use a 3/8-inch nut driver to reinstall the two locking nuts (saved in step 2) that secure the
grounding strap lug to the door.
11. If cabinet has dual-doors, repeat procedure for second door.
12. Close door(s) and check for proper operation.
Page 40
© 2004, ADC Telecommunications, Inc.
ADCP-96-005 • Issue 2 • December 2004
10 CUSTOMER INFORMATION AND ASSISTANCE
PHONE:
EUROPE
Sales Administration: +32-2-712-65 00
Technical Assistance: +32-2-712-65 42
EUROPEAN TOLL FREE NUMBERS
Germany: 0180 2232923
UK:
0800 960236
Spain:
900 983291
France: 0800 914032
Italy:
0800 782374
U.S.A. OR CANADA
Sales: 1-800-366-3891 Extension 73000
Technical Assistance: 1-800-366-3891
Connectivity Extension 73475
Wireless Extension 73476
ASIA/PACIFIC
Sales Administration: +65-6294-9948
Technical Assistance: +65-6393-0739
ELSEWHERE
Sales Administration: +1-952-938-8080
Technical Assistance: +1-952-917-3475
WRITE:
ADC TELECOMMUNICATIONS, INC
PO BOX 1101,
MINNEAPOLIS, MN 55440-1101, USA
ADC TELECOMMUNICATIONS (S'PORE) PTE. LTD.
100 BEACH ROAD, #18-01, SHAW TOWERS.
SINGAPORE 189702.
ADC EUROPEAN CUSTOMER SERVICE, INC
BELGICASTRAAT 2,
1930 ZAVENTEM, BELGIUM
PRODUCT INFORMATION AND TECHNICAL ASSISTANCE:
[email protected]
[email protected]
[email protected]
13944-M
[email protected]
Contents herein are current as of the date of publication. ADC reserves the right to change the contents without prior notice.
In no event shall ADC be liable for any damages resulting from loss of data, loss of use, or loss of profits and ADC further
disclaims any and all liability for indirect, incidental, special, consequential or other similar damages. This disclaimer of
liability applies to all products, publications and services during and after the warranty period. This publication may be
verified at any time by contacting ADC's Technical Assistance Center.
© 2004, ADC Telecommunications, Inc.
All Rights Reserved
Printed in U.S.A
Page 41