I would like to talk to you about a man named Cecil. Cecil is in his 30’s. He is a very talented lineman who currently works for a Contracting company. He got started in the trade in 2002. Initially he worked for a small utility, but really like the idea of travelling and working for a Contract line construction company. He advanced quickly working for the contractor and became a general foreman. A “GF” runs several crews at a time. He has a strong value of safety, and considers it in everything he does. Cecil is the interface with the host company, as well as other neighboring utilities in the area of the job. He acts as a working project manager, schedules outages and hold orders, and ensures the project is on schedule. He is truly a jack of all trades in line construction. Cecil had a busy summer in 2014. The re-conductoring two 115 thousand volt lines running from an urban area to the Oregon coast. This was an important job, working for a big host company. Cecil had scheduled multiple outages during this time including the 13-32 crossing that belonged to a customer utility. This structure is where cover would be applied. For two weeks linemen from Cecil’s crew picked up hold orders on the 13KV feeder shown in the picture and installed cover on the line. Everything went smoothly. In November Cecil found himself back on the same jobsite finishing up some work. His crews needed to install bird diverters (scarecrows) in the same area where the 13-32 crossing was. This day was a little different; Cecil got a call from Portland General before the outage occurred. The customer utility was confused by the outage request submitted by the host company. They said that pole 13-32 had a 57KV main feeder on top in addition to the 13KV he requested. Cecil immediately knew something was wrong. His heart sunk. He knew then that his crews did not have protection from the 57KV during the August work for 13 days in a row. As he drove back to the job trailer to find a computer he was thinking of his crew, he pictured a giant arc flash engulfing his linemen, and what it would be like telling their families that they were in the hospital. When Cecil got back to the job trailer he submitted a Contractor Near Miss report as required by the host company. Cecil waited several weeks with no response from the company. “Why is it that when we (the contractor) screw up, we immediately get a call, but when the host company screws up there is no response. “Cecil then talked to his superintendent, and asked for some answers. Cecil’s company used the process for RFI (request for information). This was done through a third party QA rep. The QA rep had attempted to schedule a meeting before the thanksgiving holiday with no response, and then a meeting in December which was cancelled due to lack of participants. It was after the cancelled meeting that he called his contact John at the host company. He had worked with John for the last three years, and felt he could talk openly with him. Cecil was extremely frustrated he had received no response to the near miss report. John assured Cecil he would look into it, and get back to him ASAP. When John spoke with his safety department, they didn’t understand what happened. They got the report, but didn’t know what to do with it. Typically they only investigate if a major rule violation occurred, and in this they didn’t understand what happened. John didn’t work for safety at the time, but offered to try out an HP investigation as he was formerly the program manager for the contractor clearance and hold order program. Safety agreed to the investigation.
© Copyright 2026 Paperzz