River Street Pump Station Twin-Forcemain Extension and Ravensview Trunk Sewer Twinning Environmental Assessment Screening Report Prepared for Utilities Kingston January 2012 Prepared by 416205_WBG062011103040OTT Contents 1. Introduction ......................................................................................................................... 1-1 1.1 Background ............................................................................................................. 1-1 1.2 Report Organization .............................................................................................. 1-3 2. Municipal Class EA Planning Process ........................................................................... 2-1 2.1 Ontario Environmental Assessment Act ............................................................. 2-1 2.2 Municipal Class EA Process.................................................................................. 2-2 2.3 Municipal Class EA Schedule ............................................................................... 2-5 3. Problem Statements ........................................................................................................... 3-1 3.1 River Street Pump Station Twin-Forcemain Problem Statement .................... 3-1 3.2 Ravensview Trunk Sewer Problem Statement ................................................... 3-1 4. Existing Conditions ............................................................................................................ 4-1 4.1 Natural Environment ............................................................................................. 4-1 4.1.1 Hydrology .................................................................................................. 4-1 4.1.2 Groundwater .............................................................................................. 4-1 4.1.3 Physiography, Geology and Soils ........................................................... 4-2 4.1.4 Natural Heritage........................................................................................ 4-2 4.2 Social/Cultural/Legal Environment ................................................................... 4-3 4.2.1 Land Use ..................................................................................................... 4-3 4.2.2 Archaeological Resources......................................................................... 4-3 5. Initial Screening of Options ............................................................................................. 5-1 6. Route Options ..................................................................................................................... 6-1 6.1 Forcemain ................................................................................................................ 6-1 6.1.1 Existing Alignment ................................................................................... 6-1 6.1.2 New Forcemain Alignment Options ...................................................... 6-1 6.2 Gravity Sewer ......................................................................................................... 6-5 6.2.1 Existing Alignment ................................................................................... 6-5 6.2.2 New Gravity Sewer Alignment Options ................................................ 6-5 6.2.3 Summary .................................................................................................... 6-7 7. Evaluation Criteria and Methodology ............................................................................ 7-1 7.1 Evaluation Criteria ................................................................................................. 7-1 7.2 Evaluation Methodology ....................................................................................... 7-3 7.2.1 Alternatives Scoring .................................................................................. 7-3 7.3 Scenario Analysis.................................................................................................... 7-4 416205_WBG062011103040OTT i CONTENTS 8. Evaluation Results ............................................................................................................. 8-1 8.1 Phase 2 Evaluation: Considerations .................................................................... 8-1 8.1.1 Natural Environment Evaluation ........................................................... 8-1 8.1.2 Social/Cultural/Legal Evaluation ......................................................... 8-1 8.1.3 Economic Evaluation ................................................................................ 8-1 8.1.4 Technical Evaluation ................................................................................ 8-1 8.2 Evaluation ............................................................................................................... 8-2 8.3 Discussion ............................................................................................................... 8-3 8.3.1 Forcemain................................................................................................... 8-3 8.3.2 Trunk Sewer............................................................................................... 8-3 9. Consultation Program ....................................................................................................... 9-1 9.1 Consultation Plan Activities ................................................................................. 9-1 9.1.1 Mailing List ................................................................................................ 9-1 9.1.2 Notice of Commencement ....................................................................... 9-1 9.1.3 Public Information Centers ..................................................................... 9-2 9.1.4 Agency Consultation ................................................................................ 9-2 9.1.5 First Nations Consultation....................................................................... 9-3 9.1.6 Direct Notifications................................................................................... 9-3 9.1.7 Meeting with Barriefield Village Association ....................................... 9-3 9.1.8 Project Website .......................................................................................... 9-3 9.1.9 Project Email Account .............................................................................. 9-4 9.1.10 Notice of Completion ............................................................................... 9-4 9.1.11 Federal CEAA Screening ......................................................................... 9-4 10. Recommended Alternatives ........................................................................................... 10-1 10.1 Forcemain .............................................................................................................. 10-1 10.1.1 Forcemain Rehabilitation ....................................................................... 10-1 10.1.2 New Forcemain Route ............................................................................ 10-3 10.2 Trunk Sewer.......................................................................................................... 10-3 10.2.1 Trunk Sewer Rehabilitation ................................................................... 10-3 10.2.2 New Trunk Sewer Route........................................................................ 10-3 10.3 Connection of Forcemain to Trunk Sewer ........................................................ 10-3 10.4 Flows and Sewer Sizing ...................................................................................... 10-4 10.5 Impacts and Mitigation ....................................................................................... 10-6 10.5.1 Natural Environment ............................................................................. 10-7 10.5.2 Social and Cultural Considerations ...................................................... 10-8 10.6 Compliance Monitoring Measures .................................................................. 10-10 11. Technical Considerations ............................................................................................. 11-11 12. Construction Staging, Schedule, Costs and Approvals .......................................... 12-14 12.1 Staging and Schedule ........................................................................................ 12-14 12.2 Preliminary Opinion of Probable Cost............................................................ 12-14 12.3 Required Permits and Approvals .................................................................... 12-14 13. References ......................................................................................................................... 13-1 ii 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL CONTENTS Tables 5-1 6-1 6-2 7-1 8-1 8-2 10-1 Alternative Solutions .......................................................................................................... 5-2 Summary of Existing and Proposed Forcemain Alignments ........................................ 6-4 Summary of Advantages and Disadvantages for Proposed Forcemain Route Options .................................................................................................................................. 6-4 Evaluation Criteria .............................................................................................................. 7-1 Forcemain Alternative Scenario Rankings ....................................................................... 8-2 Trunk Sewer Alternative Scenario Rankings................................................................... 8-2 Forcemain Rehabilitation Techniques ............................................................................ 10-2 Figures 1-1 2-1 6-1 6-2 10-1 Project Study Area ............................................................................................................... 1-2 Overview of the Class Environmental Assessment Planning Process......................... 2-3 River Street Forcemain Extension Routing Options ....................................................... 6-3 Ravensview Trunk Sewer Routing Options .................................................................... 6-6 Design Flows – Existing Connectivity ............................................................................ 10-5 Appendices A B C D E F Reference Figures Geotechnical Report Natural Environment Report Route Option Figures Alternative Evaluation Matrix Public Consultation 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL III 1. Introduction 1.1 Background CH2M HILL Canada Limited has been retained to assist Utilities Kingston (UK) in completing a Class Environmental Assessment (EA) for the River Street Pump Station (RSPS) Twin Forcemain Extension and Ravensview Trunk Sewer (RTS) Twinning. The study is being planned under Schedule B of the Municipal Class Environmental Assessment (October 2000, as amended in 2007). Phase 1 of this process involves identification of the problem or opportunity to be addressed by the project. Phase 2 involves development of alternative solutions to address the problem or opportunity. The alternatives will be evaluated to identify a preferred solution that minimizes impacts on the natural and social/cultural environment, while optimizing capital and operating investments. The purpose of this memorandum is to detail various alternatives developed to address the project objectives and to summarize the methodology employed to identify the preferred solution. Wastewater collected from the central portion of the City of Kingston is directed to the River Street Pumping Station (RSPS) and discharged through the recently constructed twin forcemains across the Great Cataraqui River. The twin forcemains currently join and connect to a single, older forcemain on the east side of the river. Flows are pumped up the Barriefield hill and discharged to the Ravensview gravity trunk sewer (Figure 1-1). The Ravensview trunk sewer carries the flow through CFB Kingston to the Ravensview Wastewater Treatment Plant (WWTP), while also receiving sewage at various locations from CFB Kingston. CH2M HILL worked with UK to complete a Sewage Infrastructure Master Plan for the City of Kingston Urban Area in September 2010. The Sewage Infrastructure Master Plan identified both the RSPS forcemain (single portion) and the Ravensview gravity sewer as requiring attention and further study for a number of reasons: • Condition assessments identified the 50+ year old Ravensview Trunk sewer as being in generally poor condition • The Ravensview Trunk is a critical link in the sewer collection system (carrying the entire wastewater flow from the central and east portions of the City to the Ravensview WWTP) which lacks redundancy, and is in a location with difficult or restricted access along much of the length • Proposed increased flows from the River Street pumping station (as part of a strategy for reducing combined sewer overflows) plus proposed future development in the catchment area results in the sewer capacity being exceeded in the future 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 1-1 INTRODUCTION FIGURE 1-1 Project Study Area 1-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL INTRODUCTION The completion of the twinning of the final 960 m of the River Street Forcemain was also recommended in the Master Plan. In addition to providing redundancy in this critical piece of infrastructure, hydraulic analysis demonstrated that completion of the forcemain twinning would increase the capacity of the RSPS and forcemain system and contribute to a reduction in combined sewer overflows (CSO) during wet weather. Improvements to these sewers are important elements in the City of Kingston’s long-term plan for eliminating CSOs. 1.2 Report Organization The purpose of this report is to document the planning process and its results, including the public and agency consultation activities to determine the preferred alternative for establishing a new trunk sanitary sewer to the Ravensview WWTP; this includes consideration for rehabilitation of the existing Ravensview Trunk Sewer, and the determination a preferred approach and alignment for the completion of the twinned section of the River Street forcemain. This report is intended to address the requirements of the Municipal Class EA Planning process as well as the Canadian Environmental Assessment Agency (CEAA) requirements. This report contains the following thirteen sections: • Section 1: Provides background information that led to initiation of this study and describes the Environmental Assessment Screening Report format. • Section 2: Begins with an overview of the EA Act and Municipal Class EA planning process and identifies the Class EA planning schedule that was followed for this project. • Section 3: Outlines the EA problem statements. • Section 4: Describes the existing conditions in the project study area, including its location, existing land uses, and socio cultural and natural environmental features. This information was considered when reviewing alternative solutions and design concepts. • Section 5: Describes the initial screening of alternatives and identification of those carried forward through to the detailed screening phase. • Section 6: Provides details related to each of the routing alternatives carried through for the detailed screening. • Section 7: Describes the evaluation criteria and methodology applied to the alternative screening. • Section 8: Provides a summary of the evaluation results, including a discussion of key criteria that influenced selection of the preferred routing alternatives. • Section 9: Describes public and agency consultation activities undertaken as part of this Class EA. • Section 10: Identifies the recommended alternative solutions and design alternatives. The section also describes recommended measures to mitigate disturbances, includes a discussion of compliance monitoring measures, schedule and cost and required permits and approvals. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 1-3 INTRODUCTION Section 11: Provides details related to specific technical details associated with design and implementation of the preferred alternative. Section 12: Describes the staging and schedule of the proposed works, includes a preliminary opinion of probable cost, and outlines required permits and approvals. Section 13: Provides a list of references. 1-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 2. Municipal Class EA Planning Process 2.1 Ontario Environmental Assessment Act Ontario’s Environmental Assessment Act (EA Act) was passed in 1976 and first applied to municipalities in 1981. The EA Act requires the study, documentation, and examination of the environmental effects that could result from major projects or activities. The objective of the EA Act is to consider the possible effects of these projects early in the planning process—when concerns are most easily resolved—and to select a preferred alternative with the fewest environmental impacts. The EA Act defines the environment very broadly as: • Air, land, or water • Plant and animal life, including humans • The social, economic, and cultural conditions that influence the life of humans or a community • Any building, structure, machine, or other device or thing made by humans • Any solid, liquid, gas, odour, heat, sound, vibration, or radiation resulting directly or indirectly from human activities • Any part or combination of the foregoing and the interrelationships between any two or more of them, in or of Ontario. The following two types of EA planning and approval processes are applied to projects to meet requirements of the EA Act: • Individual EAs (Part II of the EA Act): Projects for which a Terms of Reference (TOR) and an individual EA are carried out and submitted to the Minister of the Environment (MOE) for review and approval. • Class EAs: Projects that are approved subject to compliance with an approved Class EA process with respect to a class of undertakings. Provided that the appropriate Class EA approval process is followed, a proponent will comply with Section 13(3) a, Part II.1 of the EA Act. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 2-1 MUNICIPAL CLASS EA PLANNING PROCESS 2.2 Municipal Class EA Process All municipalities in Ontario are subject to provisions of the EA Act when undertaking public works projects. The MEA’s Municipal Class Environmental Assessment (September 2007) document provides municipalities with a five-phase planning procedure approved under the EA Act to plan and undertake all municipal sewage, water, stormwater management, and transportation projects that occur frequently, are usually limited in scale, and have a predictable range of environmental impacts and applicable mitigation measures. The EA planning process includes the following key components: • • • • • • Consultation early and throughout the process Reasonable range of alternatives Consideration of effects on the environment and ways to avoid/reduce impacts Systematic evaluation of alternatives Clear documentation Traceable decision making MEA Municipal Class Environmental Assessment Document Figure 2-1 illustrates the process followed in the planning and design of projects covered by a Municipal Class EA, including the River Street Pump Station Twin-Forcemain Extension and Ravensview Trunk Sewer Twinning. The figure incorporates steps summarized in the following sub-sections that are considered essential for compliance with the EA Act. Phase 1 Identify the problem (deficiency) or opportunity. Phase 2 Identify alternative solutions to the problem or opportunity by taking into consideration the existing environment and establish the preferred solution accounting for public and agency review and input. Document the planning process in a Municipal Class EA project file and make such documentation available for scrutiny by review agencies and the public. Phase 3 For Schedule C projects, examine alternative methods of implementing the preferred solution based on the existing environment, public and government agency input, anticipated environmental effects, and methods of minimizing negative effects and maximizing positive effects. 2-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL MUNICIPAL CLASS EA PLANNING PROCESS FIGURE 2-1 Overview of the Class Environmental Assessment Planning Process 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 2-3 MUNICIPAL CLASS EA PLANNING PROCESS Phase 4 For Schedule C projects, document in an ESR a summary of the rationale and the planning, design, and project consultation process, and make such documentation available for scrutiny by review agencies and the public. Phase 5 Complete contract drawings and documents, proceed to construction and operation, and monitor construction for adherence to environmental provisions and commitments. Where special conditions dictate, also monitor the operation of the completed facilities. The MEA Municipal Class EA document also serves as a public statement of the decision making process followed by municipalities in planning and implementing infrastructure. Based on the September 2007 MEA Municipal Class EA document, projects are classified as either Schedule A, A+, B, or C projects. Each classification requires a different level of review to satisfy Municipal Class EA requirements and comply with the EA Act. Schedule A Projects are limited in scale, have minimal adverse effects and include the majority of municipal sewage, stormwater management and water operations, and maintenance activities. These projects are approved and may be implemented without following the Class EA planning process. Schedule A projects typically include normal or emergency operational maintenance activities where the environmental effects of these activities are usually minimal. Examples of Schedule A projects include watermain and trunk sewer extensions where all such facilities are located within the municipal road allowance or an existing utility corridor. As such, these projects are pre-approved and subsequently do not require any further planning and public consultation. Schedule A+ The purpose of this Schedule is to ensure some type of public notification for certain projects that are pre-approved under the Municipal Class EA. However, there would be no ability for the public to request a Part II Order. Examples of Schedule “A+” projects include modifications to a retention/detention facility for the purpose of stormwater quality control or installation of new standby power equipment where new equipment is located in an existing building or structure. Schedule B Projects have the potential for some adverse environmental effects. The proponent is required to undertake a screening process involving mandatory contact with directly affected public and relevant review agencies to ensure that they are aware of the project and that their concerns are addressed. Schedule B projects require that Phases 1 and 2 of the Class EA planning process be followed and a project file report be prepared and submitted for review by the public. If there are no outstanding concerns raised by the public and/or review agencies, then the 2-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL MUNICIPAL CLASS EA PLANNING PROCESS proponent may proceed to project implementation. However, if the screening process raises a concern that cannot be resolved, then the Part II Order procedure (formerly referred to as a “bump-up”) may be invoked. Alternatively, the proponent may voluntarily elect to plan the project as a Schedule C project. Schedule B projects generally include improvements and expansions to existing facilities where there is the potential for some adverse environmental impacts. As a result, the proponent is required to proceed through a screening process including consultation with those who may be affected. Examples of Schedule B projects include activities such as the establishment of new sewage pumping stations and expanding a wastewater treatment plant (WWTP) to existing rated capacity where new land acquisition is required. As a result, the proponent is required to proceed through a screening process (Phases 1 and 2) including consultation with stakeholders and public who may be affected. Schedule C Schedule C projects have the potential to significantly affect the environment; therefore, these projects are subjected to the full planning and documentation procedures (Phases 1 to 4) that are specified in the Municipal Class EA document. An ESR must be prepared for Schedule C projects and submitted to the public for review. The Part II Order procedure may be invoked if concerns are raised that cannot be resolved. An example of a Schedule C project is the siting or construction of a new WWTP or expansion of an existing WWTP beyond existing rated capacity, including an outfall to a receiving body of water. 2.3 Municipal Class EA Schedule The project described in this report involves a Schedule B Environmental Assessment. This report provides documentation of a summary of the project as required to satisfy Phase 2 of the Class EA process. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 2-5 3. Problem Statements Phase 1 of the five-phase Municipal Class EA planning process requires proponents of projects to document why infrastructure improvements are needed and to develop a Problem Statement that identifies what is being investigated. A Municipal Class EA begins with a Problem Statement that becomes the central integrating element throughout the course of the project and helps to define the scope of work. A number of information sources were considered in developing the Problem Statement, as discussed in the following sub-sections. Problem statements were developed collaboratively with UK staff to properly reflect the technical issues at hand and the goals to be achieved by the project. 3.1 River Street Pump Station Twin-Forcemain Problem Statement The recently installed twinned section of the River St. Sanitary Sewer Forcemain (Cataraqui River crossing) currently terminates on the eastern shore of the Cataraqui River, after which it continues in a single forcemain. This portion of the original single forcemain has been in service for more than 50 years, lacks redundancy, and represents a hydraulic bottleneck in the sewer system. An assessment of the options for completion of the twinning of the forcemain and rehabilitation or replacement of the remaining section of original single forcemain is required. 3.2 Ravensview Trunk Sewer Problem Statement The Ravensview Trunk Sewer is a large gravity sewer main that represents a critical and essential link in the sanitary sewage collection system as it conveys all sewage from the Central and East portions of the City of Kingston to the Ravensview Wastewater Treatment Plant. The Ravensview Trunk Sewer is deteriorating and requires remedial action, a problem accentuated by a lack of redundancy and poor access for maintenance. Consequently, a study is required to assess future opportunities and develop a strategy for providing continuous, safe, and efficient sewage conveyance for this vital link. Given the interconnected nature of the forcemain and the Ravensview Trunk sewer, the two infrastructure needs must be evaluated concurrently. 416205_WBG062011103040OTT 3-1 4. Existing Conditions This section describes existing conditions in the project study area and references locations, applicable aspects of the City of Kingston’s Official Plan, existing land uses, and socioeconomic and natural environmental features. The project study area is generally located in the eastern part of the City. It is bordered to the north by James Street and Highway 2 and to the south by Lake Ontario. It is bordered by the Ravensview Wastewater Treatment Plant (WWTP) to the east and by the Great Cataraqui River to the west. Ground surface elevation slopes southerly towards the St. Lawrence River and westerly towards the Cataraqui River. 4.1 Natural Environment 4.1.1 Hydrology As per Schedule 6 of the City of Kingston’s Official Plan (OP), the western portion of the study area is situated within the Butternut Creek Watershed while the eastern portion is in the St. Lawrence Watershed (Appendix A). A report was prepared by Aqua Terre Solutions Inc. for Public Works and Government Services Canada and the Department of National Defence titled “Stormwater Management Study – Canadian Forces Base Kingston, Kingston, Ontario” in March 2008. This report provided a characterization of the 24 watershed and 66 subwatersheds identified on the Base, as well as the 15 outfalls that drain into the Cataraqui and St. Lawrence Rivers. A copy of the Watershed Delineation and Stormwater Outfall Locations figure from the March 2008 report is included in Appendix A. Existing stormwater management practices were reviewed and opportunities for water quantity and quality control were identified. It was concluded in this report that the presence of shallow soils overlying fractured limestone bedrock results in infiltration rates that are exceptionally high across the base. Although there are smaller ephemeral drainage courses which serve localized areas of the base as well as some sewer system outfalls, no significant water features are present. 4.1.2 Groundwater As part of the current project, a report was prepared by Houle Chevrier Engineering titled “Soil and Bedrock Inventory Environmental Assessment – River Street Pump Station Twin – Forcemain Extension and Ravensview Trunk Sewer Twinning, Kingston, Ontario”. A copy of the complete report is included in Appendix B. As detailed in this report, a MOE Water Well Records search was carried out for the study area. The search identified a total of 231 wells, all of which appeared to be installed in bedrock. As summarized in the report, homes on Cartwright Point and within the east part of the study area are serviced by water wells. Although a number of wells are mapped in the Barriefield development within the west part of the site, it is reported that the homes in this area are all currently serviced by municipal water. 416205_WBG062011103040OTT 4-1 EXISTING CONDITIONS It was noted in the Houle Chevrier Engineering 2011 report that groundwater levels often reflect topographic features and that groundwater typically flows towards nearby lakes, rivers, and wetlands. As such, it is expected that the shallow groundwater flow in the study area either flows to the west to the Cataraqui River or to the south to the St. Lawrence River. 4.1.3 Physiography, Geology and Soils As noted in the Houle Chevrier Engineering 2011 report (Appendix B), the surficial geology of the study area is formed from the last period of glaciations in the region completed approximately 10,000 years ago. Large amounts of debris or eroded Palaeozoic and Precambrian rocks were transported to the region and deposited as glacial till. These deposits are in turn overlain by glacio-lacustrine deposits composed of clay, silty clay, and silt, which are locally overlain by thin lenses of sand. Clay, silty clay and silt are mapped along Highway 2 and north of Highway 2, and likely overlie the glacial till. The glacial till is characterized as a thin sandy till layer over bedrock and covers most of the area to the south of Highway 2 and a section east of the Cataraqui River and north of Highway 2. In general, the overburden in the area, where present, is thin. Geology maps indicate that the study area is located on a limestone plain with shallow bedrock described as limestone of Gull River Formation. The Gull River Formation bedrock is underlain by sandstone followed by Precambrian bedrock, which, in areas along the shorelines of Cataraqui River and St. Lawrence River, is exposed at ground surface. MOE water well records indicate exposed Precambrian bedrock near Cartwright Point, and to the east of the Ravensview WWTP. Bedrock geology maps indicate that Karst topographic conditions may also be present at the site. The study area is mapped as inferred or potential Karst zones. 4.1.4 Natural Heritage As per the City of Kingston OP Schedule 7-A (Appendix A), the shoreline along both the Great Cataraqui River and St. Lawrence River is classified as riparian habitat. Schedule 8-A from the OP (Appendix A) identifies areas adjacent to the St. Lawrence River, primarily though Cartwright Point and CFB Kingston as having Contributory Woodland with a small area of Significant Woodland identified along the inner cove of Deadman’s Bay extending into the CFB Kingston lands. The City’s OP (Section 6.1.22) indicates that these areas are important areas of wildlife habitat and are critical to the movement of wildlife. Therefore, the City’s goal is to protect, enhance, and restore these linkages and corridors in the long term. As part of the evaluation of existing conditions, Ecological Services completed an inventory of natural features in the study area. The report is included in Appendix C. The potential for environmental impact was assessed with regard to the natural heritage features identified in the Provincial Policy Statement. Meadows, shrubland, and woodlands through the study area were found to contain migratory birds including the Eastern Kingbird, Downy Woodpecker, Cedar Waxwing, Oriole, Meadowlark, and Flicker. Butternut trees were also identified along Sterling Avenue which are classified as endangered under the Species at Risk Act. 4-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL EXISTING CONDITIONS The ecological land classification (ELC) was determined for various sites. In general, it was determined that the bulk of the study area was classified as Cultural, which are sites that have been strongly influenced by human activity and have low ecological value. The forested area situated south of Highway 2, west of Sterling Avenue and extending south towards the St. Lawrence River, has an area of about 35 hectares. The forest is dominated by Sugar Maple with Red and White Oak being secondary dominants. This woodlot has been labeled as contributory (i.e. not significant) by the Cataraqui Region Conservation Authority; however, this labeling was based on remote sensing and not based on field work. A more detailed analysis of this woodlot was conducted as part of the current project. The woodlot was found to have a low score with respect to interior habitat and linkages, but was found to have a high score with respect to erosion buffering and water protection. As such, this area was classified as significant woodland based on field assessments. 4.2 Social/Cultural/Legal Environment 4.2.1 Land Use A review of Schedule 3-A from the City’s OP (Appendix A) reveals that the predominant land use within the study area is institutional. The majority of this area, Canadian Forces Base Kingston, is operated by the Department of National Defense (DND) as a military establishment including lands for military purposes, staff colleges and training facilities, administrative offices, dining areas, enclosed storage areas, residential accommodation, recreation facilities, and museums. The study area also has residential, commercial, and parkland uses (Barriefield Rock Garden, Arrowhead Beach Park, Ravensview Park, etc.). Schedule 9 from the City’s OP (Appendix A) includes lands designated as Heritage District. This area, referred to as Barriefield Village, is situated north of Highway 2 and west of Highway 15. As per the City’s OP (Section 7.3.C.7), the Barriefield Heritage District is a designated Heritage Conservation District containing historic buildings, laneways, and landscapes that have preserved a 19th century village setting. A commercial development is also situated within the study area in the southeast quadrant of the intersection of Highway 2 and Niagara Park Drive. 4.2.2 Archaeological Resources A Stage 1 Archaeological Assessment was undertaken to determine whether proposed works related to the forcemain and trunk sewer would have a negative impact on any archaeological resources. Because of its proximity to Fort Henry, the Village of Barriefield, the core of the City of Kingston, and the mouth of the Cataraqui River, the study area west of Highway 15 is potentially the most sensitive area. However, some recent archaeological investigations, and subsequent development have removed some areas from further consideration. Additionally, a historical cemetery is assumed to exist along the southern edge of James Street. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 4-3 EXISTING CONDITIONS The lands within the study area which lie east of Highway 15 were found to offer little archaeological potential because of the extent or prior developments. Until the twentieth century much of this area remained in the hands of a series of small scale farmers. A number of dwellings and outbuildings are known to have been present in the area, although their precise locations have not been identified. Nevertheless, while parts of this area have clearly been affected by modern developments, extensive portions of the land adjacent to the shoreline of Lake Ontario have not been affected by development and exist as essentially undisturbed woodland. These areas have a high potential to contain Pre-Contact and Historic archaeological sites. 4-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 5. Initial Screening of Options The Municipal Class EA Document (June 2000, as amended in 2007) defines “alternative solutions” as: “feasible alternative ways of solving an identified problem (deficiency) or addressing an opportunity, from which a preferred solution is selected”. The “Do Nothing” alternative must be considered in the Class EA process as a baseline condition against which alternative solutions are evaluated. Summarized in Table 5-1 are various alternative solutions that were considered. Alternatives including those that do not require new infrastructure, those that include rehabilitated infrastructure, and those that involve construction of new infrastructure were identified. Only alternatives that satisfy the problem statement are carried through for evaluation. Where feasible, rehabilitation of existing infrastructure has been investigated as such works typically result in reduced cost as compared to new infrastructure and have the potential for less impact on surrounding properties during construction. Details related to specific rehabilitation projects, including their relative advantages and disadvantages, are described in Section 6. For a complete project, two forcemain options and two trunk sewer options are required to satisfy the respective Problem Statements with respect to redundancy and capacity considerations. For example, a complete project could be the combination of: • Rehabilitate the existing forcemain (EF #1) • Construct a new forcemain parallel to the existing (FM #1) • Rehabilitate the existing Ravensview Trunk Sewer and construct a new Trunk Sewer parallel to the existing trunk 416205_WBG062011103040OTT 5-1 INITIAL SCREENING OF OPTIONS TABLE 5-1 Alternative Solutions Carry Satisfies Forward Problem For Statement? Evaluation? Notes Initial Alternatives Without New Infrastructure Requirements Alternative 1 Do Nothing No No Alternative 2 Limit Community Growth No No Alternative 3 Reduce Flows No Does not satisfy the requirements of the City of Kingston's Official Plan and Utilities Kingston's Sewage Infrastructure Master Plan (2010), specifically related to the planned growth within the City Urban Area. No Does not satisfy the requirements of Utilities Kingston's Sewage Infrastructure Master Plan (2010), specifically related to increased capture of combined sewer flows. Forcemain Alternatives (Rehabilitation and New Construction) Existing Forcemain Options Option EF #1 Rehabilitate existing Yes, in forcemain in current location combination with new twin sewer Yes Option EF #2 Install two new parallel twin forcemains and abandon existing forcemain Yes No Option EF #3 Abandon existing forcemain and service with new, larger, single forcemain sized to address the hydraulic constraint No No Does not meet the Problem Statement with respect to required redundancy for the forcemain. Yes Yes All identified route options for the new Twin Forcemain are considered viable, and are carried forward for more detailed evaluation. Existing forcemain is assumed to be a candidate for rehabilitation (e.g. lining) to extend service life. Rehabilitation techniques need to be reviewed for constructability and technical considerations as part of conceptual design. Constructing two new forcemains is not recommended because: • Existing forcemain is assumed to be a good candidate for rehabilitation (e.g. lining) to extend service life • Cost and impact of construction of a new forcemain is anticipated to be greater than for trenchless rehabilitation • Current forcemain location is relatively accessible for future maintenance New Twin Forcemain Options Existing FM Route 5-2 Locate adjacent to/parallel with existing forcemain 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL INITIAL SCREENING OF OPTIONS Carry Satisfies Forward Problem For Statement? Evaluation? Notes Option FM #1 Locate along Duty Drive/ Navy Way to Highway 2, then along Highway 2 to connect to trunk sewer near Highway 15 intersection Yes Yes All identified route options for the new Twin Forcemain are considered viable, and are carried forward for more detailed evaluation. Option FM #2 Locate along James Street roughly parallel to existing forcemain to Highway 15, then connect to the trunk sewer on Highway 2 Yes Yes All identified route options for the new Twin Forcemain are considered viable, and are carried forward for more detailed evaluation. Option FM #3 Locate along James Street, then through new sports dome parking area to Highway 2, then along Highway 2 to connect to trunk sewer near Highway 15 intersection Yes Yes All identified route options for the new Twin Forcemain are considered viable, and are carried forward for more detailed evaluation. Yes, in combination with new twin sewer Yes Existing sewer is assumed to be a candidate for rehabilitation (e.g. lining) to address identified deficiencies and extend service life. Trunk Sewer Alternatives Existing Trunk Sewer Options Option ET #1 Rehabilitate existing sewer Rehabilitation techniques need to be reviewed for constructability and technical considerations as part of conceptual design. Option ET #2 Replace existing sewer in current location Yes No Reconstruction in the existing location is considered viable as part of an overall solution involving construction of a second sewer. However: • Existing sewer is assumed to be a candidate for rehabilitation (e.g. lining) to address identified deficiencies and extend service life • Construction disruptions and costs for full reconstruction are typically greater than for trenchless rehabilitation and would have an unacceptable level of impact/disruption on CFB Kingston and residents of Cartwright Point 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 5-3 INITIAL SCREENING OF OPTIONS Carry Satisfies Forward Problem For Statement? Evaluation? Option ET #3 Install two new parallel twin sewers and abandon existing sewer Yes Option ET #4 Abandon existing sewer and replace with single new sewer in a new location sized appropriately for future flows No No Notes Constructing two new trunk sewers is not recommended because: • Existing sewer is assumed to be a candidate for rehabilitation (e.g. lining) to address identified deficiencies and extend service life • Cost and impact of construction of a new trunk sewer is anticipated to be greater than rehabilitation • Improvements to maintenance accessibility for the current sewer location can be made to address current access issues • Abandoning the current trunk sewer location would require significant modifications to sewer servicing for CFB Kingston areas south of Highway 2 No Construction of a new sewer in a new location is not recommended because: • Does not address redundancy requirements identified in Problem Statement • May require significant modifications to sewer servicing for CFB Kingston areas south of Highway New Trunk Sewer Existing TS Route Locate adjacent to/parallel with Existing Sewer Yes Yes All identified route options for the new Trunk Sewer are worthy of consideration and are carried forward for more detailed evaluation. Option TS #1 Locate along new corridor through CFB Kingston following established rightsof-way/road allowances Yes Yes All identified route options for the new Trunk Sewer are worthy of consideration and are carried forward for more detailed evaluation. Option TS #2 Along Highway 2 to Gates Blvd, along Gates to tie in to plant headworks Yes Yes All identified route options for the new Trunk Sewer are worthy of consideration and are carried forward for more detailed evaluation. Option TS #3 Along Highway 2, turning south just west of Elva, then east just south of Sterling to Gates Blvd, along Gates to tie in to plant headworks Yes Yes All identified route options for the new Trunk Sewer are worthy of consideration and are carried forward for more detailed evaluation. In addition, where multiple options exist, further evaluation is required to determine the preferred alternative. 5-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL INITIAL SCREENING OF OPTIONS Based on the initial screening of alternatives, the Preferred Solution will be comprised of: • • Rehabilitation of existing trunk sewer Rehabilitation of existing forcemain Plus • • One of the Route Options for the new trunk sewer, and One of the Route Options for the new forcemain As discussed in Section 7, evaluation criteria have been developed for the analysis and review of the various gravity sewer and forcemain route options. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 5-5 6. Route Options Potential routes for the twinned sections of the forcemain and trunk sewer were developed based on a high level review of logical routes. Summarized below are details regarding the existing alignment of the forcemain and gravity trunk sewer, as well a description of various alternative routes for each twinned section. Refer to Figures 6-1 and 6-2 for schematic layouts of the various options. Preliminary profiles for each of the routes are included in Appendix D. 6.1 Forcemain 6.1.1 Existing Alignment The existing 1,050 mm diameter reinforced concrete forcemain runs from a chamber on the eastern shore of the Cataraqui River (the termination point of the currently twinned section of forcemain) to a manhole situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where it discharges to a gravity sewer for subsequent conveyance to the Ravensview WWTP. The total length of the existing forcemain between these points is approximately 945 metres. From the chamber on the eastern shore of the Cataraqui River, the forcemain runs south along the eastern side of James Lane and then east along the southern side of James Street. The forcemain is routed south of the James Street water booster station and then runs in an easterly direction south of James Street, uphill through the CFB Kingston lands and the Barriefield Rock Garden. The forcemain crosses to the southern side of Highway 2, just east of Highway 15, where it continues on the south side of the Highway to the point where it discharges to the gravity sewer. There are three connection points to the forcemain east of the Cataraqui River: the B64 pumping station; a private connection servicing a residence near the intersection of James St. and Main St.; and a gravity sewer connection northwest of the intersection of Highway 15 and Highway 2 that receives flow from the upstream B40 & B64 sanitary pumping station catchment areas. 6.1.2 New Forcemain Alignment Options Option 1 The first option for the new forcemain alignment follows the same route as the existing forcemain from the chamber on the eastern shore of the Cataraqui River to the intersection of James Lane and James Street. From this point, the forcemain would be directed south along Navy Way/Duty Drive to the intersection with Highway 2 where it would then follow the highway alignment east towards the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges into the gravity sewer. The total length of this option is approximately 1,230 metres. 416205_WBG062011103040OTT 6-1 ROUTE OPTIONS Option 2 The second option for the new forcemain alignment follows the same route as the existing forcemain from the chamber on the eastern shore of the Cataraqui River to the intersection of James Lane and James Street. From this point, the forcemain would run east along the James Street corridor within, or directly adjacent to, the Municipal right-of-way and continue under the intersection of Highway 15 and Highway 2 where it would connect to the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges into the gravity sewer. This route option effectively parallels the existing forcemain route. The total length of this option is approximately 1,000 metres. Option 3 The third option for the new forcemain alignment follows the same route as the existing forcemain from the chamber on the eastern shore of the Cataraqui River to the intersection of James Lane and James Street. From this point, the forcemain would be aligned along the southern side of James Street for approximately 150 metres where it would then cut across the parking lot for the future CFB sports facility dome to the southern side of Highway 2. The forcemain would then follow the highway alignment east towards the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges into the gravity sewer. The total length of this option is approximately 1,145 metres. 6-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL ROUTE OPTIONS FIGURE 6-1 River Street Forcemain Extension Routing Options 11x17 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 6-3 ROUTE OPTIONS Summary Table 6-1 provides a summary of the existing and proposed routes with respect to length and diameter. As described above, each reach begins at the chamber on the eastern shore of the Cataraqui River and terminates approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges into the gravity sewer. TABLE 6-1 Summary of Existing and Proposed Forcemain Alignments Forcemain Length (m) Diameter (mm) Existing 945 1,050 (existing) Option 1 1,230 1,050 (proposed) Option 2 1,000 1,050 (proposed) Option 3 1,145 1,050 (proposed) Table 6-2 provides a summary of general advantages and disadvantages to each of the route options (including the existing route). TABLE 6-2 Summary of Advantages and Disadvantages for Proposed Forcemain Route Options Route Option 1 Option 2 (Existing Route) Option 3 6-4 Advantages • Generally follows existing road rights-of-way • Avoids narrow and congested James Street • Avoids the need for rock excavation on James Street • Connection of flows from B-64 PS, Highway 15 sewers may be more challenging • Potentially less disturbance of Highway 15/Highway 2 intersection • Parallels existing forcemain route, providing a single corridor for both sewers • Stays mainly within Municipal right-of-way • Shortest forcemain length • Could potentially be coordinated with other work (e.g. watermain, road improvements) on James Street • Avoids majority of construction along Highway 2 • Second shortest length • Avoids other utilities on Duty Drive • • Disadvantages • Requires DND approval for use of Duty Drive • Traffic impacts on Highway 2 during construction • Narrow Highway 2 corridor through rock cut • Requires disturbance of rock garden • Close proximity to residences on James Street • Potentially greater impacts of Highway 15/ Highway 2 intersection • Routing requires avoidance of high archaeological potential areas south of James Street Avoids construction in Duty Drive//Highway 2 intersection • Traffic impacts on Highway 2 during construction Potentially less disturbance of Highway 15/Highway 2 intersection • Narrow Highway 2 corridor through rock cut • Requires DND coordination with 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL ROUTE OPTIONS construction of parking lot 6.2 Gravity Sewer 6.2.1 Existing Alignment The existing 1,200 mm diameter gravity sewer begins at the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges. From this point, the gravity sewer flows east along the southern side of Highway 2 and then south along the western side of Niagara Park Drive. The gravity sewer then heads east along Remorquage Drive and through residential development. The sewer crosses Lundy’s Lane at approximately Queenston Heights Crescent and then travels east through the back side of residences at the northern edge of Cartwright Point. The sewer follows the alignment of the lake, approximately 60 to 80 metres north of the shoreline to the northern side of Lasalle Boulevard. The 1,200 mm diameter sewer becomes a 1,350 mm diameter approximately 260 metres west of Gates Boulevard and continues as a 1,350 mm to its tie-in point at the Ravensview WWTP approximately 225 metres east of Gates Boulevard. The total length of the sewer is approximately 3,405 metres. Slopes range from 0.25% to 5.0%. The existing alignment has a depth of cover over the obvert of the pipe of up to 8 metres but is actually above ground at two locations along the alignment. In addition to the option of constructing a twin sewer generally adjacent and parallel to the existing sewer, three other route options have been developed for consideration. 6.2.2 New Gravity Sewer Alignment Options Option 1 The first option for the new 1,200 mm diameter gravity sewer alignment begins at the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the forcemain discharges. From this point, the gravity sewer flows east along the southern side of Highway 2 and then south along the western side of Niagara Park Drive. Unlike the existing alignment that turns east through the shopping plaza on Niagara Park Drive, this option would follow Niagara Park Drive towards the south and then head east following Lundy’s Lane, south along Canal du Nord, east on Byng Avenue, north on Signal Avenue, and then east on Radar Street. Beyond Radar Street, the sewer would cut through an existing clearing and wooded area towards the western end of LaSalle Boulevard where it would then match the existing alignment for the rest of the distance to the WWTP. The total length of this sewer would be approximately 3,330 metres and would range in slope from approximately 0.4% to 0.9%. The depth of cover over the obvert of the pipe given this alignment would range from approximately 2 metres up to 15 metres. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 6-5 ROUTE OPTIONS Figure 6-2 Ravensview Trunk Sewer Routing Options 11x17 6-6 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL ROUTE OPTIONS Option 2 The second option for the new 1,200 mm diameter gravity sewer alignment would begin at the same chamber that the existing sewer does, but would continue easterly along Highway 2 for approximately 2,600 metres before turning south along Gates Boulevard and then east along LaSalle Boulevard towards the WWTP. The total length of this sewer would be approximately 3,200 metres with slope ranging from approximately 0.5% to 4.5%. Due to the approximately 14-metre drop in ground surface elevation between Highway 2 and LaSalle Boulevard (i.e. along Gates Boulevard), a series of drop structures would be required along this section of the proposed sewer alignment. Option 3 The third option for the new 1200 mm diameter gravity sewer alignment would follow the same path of Option 2, with the exception of being directed behind the residential properties situated in the southwest quadrant of the intersection of Highway 2 and Gates Boulevard. The total length of this sewer would be approximately 3,200 metres with slope ranging from approximately 0.5% to 4.5%. As with Option 2, a series of drop structures would be required along the section of alignment between Highway 2 and LaSalle Boulevard. 6.2.3 Summary Table 6-3 provides a summary of the existing and proposed routes with respect to length, diameter, and slope. As described above, each reach begins approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive where the forcemain discharges into the gravity sewer and terminates at the headworks of the Ravensview WWTP. TABLE 6-3 Summary of Existing and Proposed Trunk Sewer Alignments Gravity Sewer Diameter (mm) Length (m) Slope (%) 1,200 3,180 0.4 – 5.0 1,350 220 0.3 Option 1 1,500* 3,300 0.4 – 0.9 Option 2 1,500* 3,200 0.5 – 4.5 Option 3 1,500* 3,200 0.5 – 4.5 Existing *Note: Diameter to be confirmed and finalized through hydraulic analysis during conceptual design Table 6-4 provides a summary of general advantages and disadvantages to each of the gravity sewer route options (including the existing route). 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 6-7 ROUTE OPTIONS TABLE 6-4 Summary of Advantages and Disadvantages for Existing and Proposed Gravity Sewer Route Options Route Existing Option 1 Option 2 Option 3 6-8 Advantages Disadvantages • Shallowest burial depth for sewer • Poor access • Likely open-cut construction • Heavy tree cover in sections • Minimal traffic disruption during construction • Constrained right-of-way at Cartwright Point • Routed through DND property including areas of potentially heightened security • Located mostly in existing rights-ofway for upper two-thirds of route • Routed through DND property including areas of potentially heightened security • Avoids construction on Highway 2 corridor • Disruptions to CFB traffic and intersections during construction • Depth requires tunneled construction through potentially variable rock conditions • Poor access along lower third of route • Servicing CFB areas south of Highway 2 will be challenging, potentially impossible without pumping • Straight forward alignment allows flexibility in sewer grades • Depth requires tunneled construction through potentially variable rock conditions • All sewers within municipal right-ofway, avoids DND property and Cartwright Point • Installation depth is below groundwater table and near private wells • • Shortest length of any option Need for drop structures along Gates Blvd may result in odour and corrosion issues • Servicing CFB areas south of Highway 2 will be challenging, potentially impossible without pumping • Same as Option 2 • Same as Option 2 • Route may alleviate potential impacts on some wells • Will impact woodlot which is considered ‘significant’ woodland 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 7. Evaluation Criteria and Methodology 7.1 Evaluation Criteria Project-specific evaluation criteria that addressed four categories – the technical, natural, social/cultural, and economic environments – were developed. The evaluation criteria’s development was influenced by discussing opportunities, constraints, and heritage aspects, and was guided by the requirements of the Class EA process. The following table summarizes the identified criteria for each of the four categories listed above. TABLE 7-1 Evaluation Criteria Criteria Name Description Measure Natural Environment N1 Impact on Surface Water Resources/ Aquatic Habitat Potential construction or operations impacts on surface water resources including aquatic habitat, fisheries, lakes, rivers and streams etc. Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. N2 Impact on Terrestrial Resources (e.g. parks, woodlots, etc.) Potential construction or operations impacts on terrestrial resources Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. N3 Impact on Birds and Potential construction or Waterfowl operations impacts on birds and waterfowl Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. Social/Cultural/Legal S1 Temporary Construction Impacts Number of residents impacted/duration of impacts during construction including traffic disruptions, noise, dust, etc. Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. S2 Impact on Groundwater / Private Wells Potential construction or operations impacts on groundwater resources and/or private wells Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. S3 Cultural/Heritage and Archaeological Resources The potential for the option to avoid cultural and heritage and/or archaeological resources Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. 416205_WBG062011103040OTT 7-1 EVALUATION CRITERIA AND METHODOLOGY Criteria Name Description Measure S4 Property Requirements Potential land requirements, including temporary and permanent easements Fewer property requirements / easements than other options – 10; Property requirements are roughly the same as other options – 5; More property requirements/easements than other options – 1. S5 Impact on Services – Sewers Ability to maintain sanitary sewer services during construction or rehabilitation Negative impacts are lower than other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are higher than other options – 1. S6 Public Acceptance of Solution Public acceptance and support of option, including perception of construction disruptions, potential longer term impacts (e.g. groundwater), and comparison with other Options Strong public support for option anticipated, or with easily mitigated concerns – 10; Public concern anticipated to be generally same as other options – 5; Significantly more public concern anticipated, and difficult or impossible to mitigate – 1. Economic E1 Estimated Capital Costs Estimated Capital Costs Estimated capital costs of option are low compared to other options – 10; Estimated capital costs are approximately the same as other options – 5; Estimated capital costs are higher than other options – 1. E2 Estimated O&M Costs Estimated annual operating costs for staff resources, ongoing operation and maintenance activities Estimated O&M costs of option are low compared to other options – 10; Estimated O&M costs are approximately the same as other options – 5; Estimated O&M costs are higher than other options – 1. E3 Business Impacts Number of Businesses/ Duration of Business interruption during construction (based on businesses directly along construction routes) Fewer businesses anticipated to be negatively impacted than with other options – 10; Impacts are approximately the same as other options – 5; Negative impacts are anticipated to be higher as compared to other options– 1. Technical 7-2 T1 Ease of Implementation The ability of the option to be easily implemented on a technical, regulatory and practical basis The option is easier to implement in comparison to other options with respect to approvals and construction – 10; The option has similar implementation challenges as compared to other options – 5; The option is more difficult to implement than other options – 1 T2 Operation and Maintenance The ability of the alternative to be operated and maintained with ease, including requirements for routine O&M activities O&M requirements are lower relative to other options – 10; O&M requirements are roughly the same as other options – 5; O&M requirements are greater than other options –1 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL EVALUATION CRITERIA AND METHODOLOGY Criteria Name Description Measure T3 Infrastructure Accessibility The ability of the option to be accessed for operations and maintenance under normal and emergency conditions, with consideration to seasonal impacts The option has easier access along entire length of sewer than other options – 10; Access roughly the same as other options – 5; More challenging access than other options – 1. T4 Capacity for Future Growth The ability of the option to provide capacity for growth beyond current projections, flexibility for integration into future requirements The option provides significant additional capacity for growth as compared to other options – 10; The option provides limited additional capacity for growth – 5; The option provides no additional capacity for growth as compared to other options – 1. T5 Compatibility with Planned Infrastructure Upgrades The ability of the alternative to be implemented in conjunction with planned infrastructure upgrade programs The option allows greater coordination with other planned infrastructure upgrades than other options – 10; Potential coordination with other infrastructure upgrades is similar to other options – 5; Minimal opportunity for coordination with other planned infrastructure upgrades than other options – 1. T6 Utility Conflicts The potential for the alternative to require relocation of other existing utilities Less required utility relocations required as compared to other options – 10; Required utility relocations are similar to other options – 5; More utility relocations required as compared to other options – 1. 7.2 Evaluation Methodology 7.2.1 Alternatives Scoring Each Alternative received a criteria score for each of the various criteria identified in each category. Criteria were assigned a score of 10, 5, or 1 based on how that Alternative compared to the other alternatives being considered, with 10 being the best score and 1 being worst. The criteria score for each alternative was determined as follows: 10 Alternative generally has less or lower negative impacts, is lower priced, or is easier to implement as compared to the other Alternatives 5 Negative impacts, costs and ease of implementation are roughly the same as the other Alternatives 1 Negative impacts, costs and ease of implementation are considered worse than the other Alternatives Scoring of the criteria was based on qualitative and/or quantitative measures as appropriate for the criteria in question. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 7-3 EVALUATION CRITERIA AND METHODOLOGY 7.3 Scenario Analysis Two scenarios were analyzed as part of the evaluation process. For Scenario 1, the four categories of criteria were equally weighted (i.e. Technical: 25%; Natural: 25%; Social/Cultural: 25%; Economic: 25%). The scores generated by alternatives in each criteria category were totaled and then normalized so that each of the four criteria categories were equally weighted, even though each have a different number of individual criteria. The normalization process involved dividing a category’s raw score by the total possible score for that category. The normalized scores from all four categories were totaled for each alternative, providing an overall score. The measures are designed such that an Alternative that scores higher than another is considered to be a better solution. A questionnaire was sent out to UK staff ahead of a workshop on June 28, 2011, which asked each team member to weight each of the four main categories as well as the respective subcategories under these headings. The purpose of this exercise was to establish weightings that were subsequently applied to Scenario 2. Project team weightings from the workshop were as follows: Technical: 48%; Natural: 15%; Social/Cultural: 16%; Economic: 21%. Details of the criteria rankings for both the four main categories, as well as for each of the sub-categories, are summarized in Appendix E. 7-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 8. Evaluation Results This section presents results of the Phase 2 Evaluation of the forcemain and trunk sewer routing options. A detailed evaluation of alternatives was carried out based on the evaluation criteria presented in Section 7. Available information was supplemented by additional field work and studies. 8.1 Phase 2 Evaluation: Considerations 8.1.1 Natural Environment Evaluation The environmental evaluation criteria generally centered on impacts to land, water, and associated aquatic and vegetation species, as well as on terrestrial resources including parks and woodlots. The key differentiating criteria determined during the natural environment evaluation for the forcemain alignment were potential impacts to park land, including the Barriefield Rock Garden. Key differentiating criteria for the trunk sewer from a natural environment perspective included impacts on terrestrial resources including woodlots. 8.1.2 Social/Cultural/Legal Evaluation The social and cultural evaluation criteria were impacts on residents and institutions due to the proposed sewer alignments and the associated construction activity. The cultural factors included known and likely archaeological impacts including the impacts on cultural and heritage features. The key differentiating criteria for both the forcemain and trunk sewer, determined during the social and cultural evaluation, were direct impacts to residents from potential construction activity. Potential impact on groundwater wells was also a key criterion in selection of the preferred trunk sewer alignment. 8.1.3 Economic Evaluation Economic criteria were focused on capital and operational and maintenance costs associated with the alternatives under consideration. The key differentiating criteria determined during the technical and economic evaluation were ease of construction and capital costs of the alternatives. 8.1.4 Technical Evaluation Criteria used to complete the technical evaluation included the ease of construction including the ability to phase in proposed works with other construction projects in the study area as well as factors such as utility conflicts and road crossings. 416205_WBG062011103040OTT 8-1 EVALUATION RESULTS 8.2 Evaluation Details of the alternative evaluation are included in Appendix E. Table 8-1 summarizes the final ranking of forcemain routing alternatives using equally weighted rankings for each of the four categories (Scenario 1) and based on rankings derived from UK staff (Scenario 2): TABLE 8-1 Forcemain Alternative Scenario Rankings Alternative ID Description Scenario 1 Ranking Scenario 2 Ranking Option1 Locate along Duty Drive/Navy Way to Highway 2, then along Highway 2 to connect to trunk sewer near Highway 15 intersection 2 3 Option 2 Locate within James Street corridor roughly parallel to existing forcemain to Highway 15, then connecting to the trunk sewer on Highway 2 2 1 Option 3 Locate along James Street, then through new sports dome parking area to Highway 2, then along Highway 2 to connect to trunk sewer near Highway 15 intersection 1 2 As shown in Table 8-1 and in Appendix E, the preferred alternative based on equal ranking of the four criteria categories (i.e. Scenario 1) is Option 3. However, the preferred alternative is Option 2 when criteria rankings derived from UK staff are applied to the analysis. Table 8-2 summarizes the final ranking of trunk sewer routing alternatives using equally weighted rankings for each of the four categories (Scenario 1) and based on rankings derived from UK staff (Scenario 2): TABLE 8-2 Trunk Sewer Alternative Scenario Rankings Scenario 1 Ranking Scenario 2 Ranking Locate adjacent to/parallel with Existing Sewer 4 4 Option 1 Locate along new corridor through CFB Kingston following established rights-of-way/road allowances 3 3 Option2 Along Highway 2 to Gates Blvd, along Gates to tie in to plant headworks 1 1 Option 3 Along Highway 2, turning south just west of Elva, then east just south of Sterling to Gates Blvd, along Gates to tie in to plant headworks 2 2 Alternative ID Existing Route Description Results from the routing alternative evaluation analysis indicate that there is no difference in the final ranking of alternatives based on weightings applied to both Scenario 1 and Scenario 2. Under both scenarios, Option 2 is identified as the preferred alternative. 8-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL EVALUATION RESULTS 8.3 Discussion 8.3.1 Forcemain As noted above in the evaluation, the results change for the highest weighted forcemain route depending on whether unequal or equal weights were applied to the categories and criteria. With equal weightings, Forcemain Option 3 receives the highest score, while using unequal weightings results in Option 2 being scored highest. In reviewing the differences between the two results, the following observations are noted: • From a traffic perspective, although both options have the potential to disrupt traffic, Option 2 is likely to impact less people for a shorter period due to the reduced length of construction on Highway 2. • Option 2 simplifies the necessary interconnection between existing and new forcemain at Pumping Station B-64, and may simplify construction staging due to required connection details at the starting point of the new forcemain near the Cataraqui River. • Option 2 presents a great likelihood for coordination of construction with other infrastructure projects (e.g. watermain and steamline work along the James Street corridor). • Option 3 presents potentially significant geotechnical challenges that could complicate construction techniques due to potential rock issues through the Highway 2 rock cut. Geotechnical concerns may in fact result in higher construction costs than currently forecast. • Without minimizing in any way the importance of social and environmental impacts of construction, these impacts are mainly short term in nature and specific to the construction period, and are generally able to be mitigated during and after construction. Based on the additional review, results of the unequal weighted analysis appears justified, and it is recommended that Option 2 be taken forward for as the preferred alternative. 8.3.2 Trunk Sewer Both equal and unequal weighted categories and criteria resulted in Trunk Sewer Route Option 2 receiving the highest score. This result is not surprising, given the straightforward nature of the route, the ability to construct exclusively within municipal road rights-of-way, and the general lack of impacts from a natural environment perspective. However, Option 2 is not without challenges; potential groundwater interferences, traffic impacts during construction, and the potential need for tunneled installation of sections of the sewer all need to be adequately considered and evaluated during design. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 8-3 9. Consultation Program Consultation minimum requirements for EA studies are outlined in the Municipal Class EA (October 2000, as amended in 2007). A Schedule B Class EA requires two mandatory points of contact plus a Notice of Completion. This mandatory consultation is often achieved through the publishing of the Notice of Commencement and either a Public Meeting or a mail out to directly affected stakeholders. Given the nature of this project and the potential public and stakeholder interest, two Public Information Centres (PIC) were held in addition to publishing the Notices of Commencement and Completion. Consulting with project stakeholders is an important element in the process of building and maintaining community trust and credibility and ultimately achieving community endorsement and acceptance of the study recommendations. Starting consultation efforts early in the decision-making process can help to identify issues and concerns early enough that they can be effectively addressed before final decisions are made. The objectives of the public consultation plan prepared for this project were as follows: • To conduct a consultation program that is meaningful to those involved • To deliver a program that is understandable, accessible, and transparent • To engage stakeholders early and throughout the decision-making process • To provide educational value to participants by providing information on the issues and challenges of Kingston’s sewer system 9.1 Consultation Plan Activities The consultation activities undertaken as part of this project are presented below. 9.1.1 Mailing List Two mailing lists were developed (one each covering the public contacts and the agency contacts) and were maintained by CH2M HILL for the duration of the study. The data was augmented with new additions to the list as stakeholders became engaged in the process. The public mailing list included names and mailing information for members of the public, special interest groups, and stakeholders that are on current mailing lists of UK. The agency mailing list was compiled from the most recent list issued by the Ministry of the Environment and modified using previous mailing lists developed by UK. The agency mailing list was updated and modified based on responses to the first mail out of the Notice of Commencement (NOC). The initial and final mailing lists are attached in Appendix F. 9.1.2 Notice of Commencement The NOC includes a clear statement of the purpose of the study and is an invitation for interested persons to participate in the process. It also includes contact information, including a project website hosted by UK 416205_WBG062011103040OTT 9-1 CONSULTATION PROGRAM (http://www.utilitieskingston.com/Water/Projects/RiverStreetPumpStation.aspx). The NOC was published in local papers on February 22, 2011. The NOC was also posted to the UK website. Responses received from the notice were documented and shared with the study team. Contact information was added to the mailing list for notification of project activities. An Agency Contact Letter was also prepared and sent to the various contacts. Both the NOC and Agency Contact Letter are included in Appendix F. 9.1.3 Public Information Centers Two PICs were conducted for this study. The purpose of the PICs was to provide the public with an opportunity to meet with the project team at key points in the decision making process to discuss the study and provide comments, questions, and concerns. Each PIC was designed as a drop-in Information Centre with a display of project information, a take-home Information Brief, and a Comment Sheet to provide feedback. The purpose of PIC #1 was to introduce the study, present the problem statement and rationale for the study, provide an overview of the decision-making process, and explain the types of investigation and data collection activities that were undertaken. Outcomes of PIC #1 included a growing public awareness of the key issues, initial reaction, and comment on the problem statement and purpose of the study, and suggestions for options to consider. PIC #1 was held on March 29th, 2011 with a Notice being published in local newspapers on March 15 and 22. Copies of the Notice were also hand-delivered to residents in the vicinity of the project study area as described below. A copy of the Notice of PIC#1 is attached in Appendix F. Copies of the presentation material as well as completed comment sheets from PIC #1 are also included in Appendix F. The purpose of PIC #2 was to present the analysis and results of the investigations and evaluation of alternative strategy solutions. The outcome of PIC #2 was an understanding of the key issues, questions and concerns of the recommended alternative, confirmation that the public understands how the preferred alternatives were selected, confirmation that key public issues were addressed and incorporated into study recommendations, and identification of issues regarding implementation. A Notice for PIC #2 was published in local newspapers on September 27 and October 4, 2011. PIC #2 was held on October 5, 2011. A copy of the Notice of PIC #2 is attached in Appendix F. Copies of the presentation material as well as completed comment sheets from PIC #2 are also included in Appendix F. Comments received from each of the PICs were compiled and reviewed by the Study team prior to continuing work. 9.1.4 Agency Consultation Agencies were mailed the Notice of Study Commencement at the beginning of the project and asked if they wished to continue to participate in the process. Those who respond with a request to maintain participation in the study continued to receive project information and notices. Agency comments were carefully reviewed by the project team so that issues, concerns, and comments were incorporated into the decision-making process as the study progresses. Copies of messages and letters received from various agencies are included in Appendix F. 9-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL CONSULTATION PROGRAM A meeting was also held with the Department of National Defence on April 18, 2011 to present the issues, alternatives evaluation, and proposed design criteria and solution. The purpose of this meeting was to obtain and document DND’s approvals in-principle with the proposed plan prior to finalizing design criteria and the selected alternative solution. The Canadian Environmental Assessment Agency was contacted to update the Agency on the objectives of the project and to confirm requirements under the CEAA. A copy of the CEAA letter is attached in Appendix F. Once the preferred alternative is identified through the Class EA process, the project was filed with the CEAA. 9.1.5 First Nations Consultation The City of Kingston currently has a working group specifically engaged on First Nations consultation. The project team used this working group to identify various First Nations groups that were subsequently contacted as part of the study. In addition, a copy of the Agency Letter and Notice of Commencement was sent to Indian and Northern Affairs Canada as per the Public and Agency mailing list included in Appendix F. 9.1.6 Direct Notifications In addition to the Public and Agency mailing lists and the project website, direct notification has been used to notify residents/stakeholders in the immediate study area via handdelivered mail-drops. These areas included: • • • • • • Barriefield Royal Military College CFB Kingston Cartwright Point Highway 2 residents/businesses up to the Ravensview WWTP entrance Residents along Elva Ave., Ridge Ave., Sterling Ave., Gates Blvd. and LaSalle Blvd. Copies of the Notice of PIC #1 and PIC #2 were hand-delivered to the above areas approximately two weeks before each meeting. 9.1.7 Meeting with Barriefield Village Association A meeting was held with the project team and representatives of the Barriefield Village Association on October 25, 2011 to discuss the proposed sewer-twinning project as well as other planned infrastructure plans in the area. The proposed routing of the forcemain, anticipated construction techniques and potential impacts on the Heritage Area were reviewed. With the proposed forcemain following route generally south of James Street and offset from the Heritage homes will exist, mitigating many of the concerns. Possible impacts on the Barriefield Rock Garden were discussed, with recognition of the need for restoration to existing conditions following construction. Agrement was reached to continue the dialogue with BVA throughout design. 9.1.8 Project Website In order to promote effective and timely communication, relevant project documents were posted to the UK website (http://www.utilitieskingston.com/Water/Projects/ 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 9-3 CONSULTATION PROGRAM RiverStreetPumpStation.aspx). This website served to enhance collaboration and improve communications by providing up-do-date information and background documents for review. 9.1.9 Project Email Account A project e-mail account was set up to allow for stakeholders to contact the project team. The email address was published in the Notice of Commencement as well as in each of the PIC notices and was included on all information made available to the public. The email address was: [email protected]. The email account was managed by UK with messages automatically forwarded to the CH2M HILL team. 9.1.10 Notice of Completion A NOC will be prepared for publication by the UK. The Notice will be distributed to the public and agency mailing list and will be published in the local papers as determined appropriate by UK. The Notice of Completion will also be posted to the UK website. The Notice will conform to the content outlined in the Municipal Class EA document. A suitable review period will be determined in consultation with UK and will not be less than 30 days. 9.1.11 Federal CEAA Screening It is anticipated that final sign-off of the CEAA will occur during the 30-day Class EA review period. The CEAA and relevant federal agencies will be kept updated with the progress of the study through the course of the project. 9-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 10. Recommended Alternatives Based on evaluations completed in Section 8, the preferred alternative for the forcemain and trunk sewer are as follows. 10.1 Forcemain In general, the preferred alternative for the River Street Pump Station forcemain involves rehabilitation of the existing forcemain as well as installation of a new forcemain to provide redundancy and additional capacity. 10.1.1 Forcemain Rehabilitation The existing forcemain is a 1,050 mm diameter reinforced concrete pipe (RCP) which has been in service for more than 50 years. The physical condition of the forcemain pipe is unknown because, as the only means of conveying sewage from central Kingston to the trunk sanitary sewer, is has not been feasible take the forcemain out of service to allow for inspection. Nevertheless, given the age of the pipe, it is reasonable to assume that at least some degree of rehabilitation is required. The rehabilitation work will require the forcemain to be taken out of service, consequently the work cannot be undertaken until a new twin forcemain has been constructed and put into service. Before the rehabilitation work can begin, a full condition assessment must be completed to confirm the condition of the pipe and determine the appropriate restoration requirements. The general sequence of steps is outlined below: • Construct and commission new forcemain • Take old forcemain out of service • Inspect old forcemain (CCTV, profiling, non-destructive testing, material sampling or testing as needed) • Complete condition assessment (if condition permits, forcemain can be returned to service in the interim) • Evaluate and select a preferred rehabilitation method(s) • Prepare rehabilitation design, contract documents, tendering • Take the old forcemain out of service, conduct rehabilitation (cleaning, rehabilitation, post-CCTV or other inspections) • Return rehabilitated forcemain to service Scheduling of the rehabilitation work should consider seasonal flow variations. For example, it may be necessary to undertake the work during the winter when flows are lower. A variety of techniques can be considered for rehabilitation of RCP in a forcemain application, including spot repairs, cured-in-place-pipe (CIPP) and sliplining. Depending on the nature, degree and location of pipe deterioration, a combination of rehabilitation techniques may be appropriate (e.g. spot repairs at specific locations, relining elsewhere). 416205_WBG062011103040OTT 10-1 RECOMMENDED ALTERNATIVES CIPP involves insertion of a resin-impregnated felt sock into the pipe which is inflated using water pressure against the side of the pipe and then cured using heat (steam or hot water) to form a new structural liner within the old pipe. Slip lining is the insertion of a smaller diameter pipe, typically plastic such as HDPE, into the old pipe and grouting the annular space between the old and new pipes. Spot repair methods could include replacement of short segment of pipe by open cut, and trenchless methods to remove protrusions (e.g. displaced gaskets), grouting of poor joints/cracks/defects, or localized use of CIPP or slip lining. A summary of rehabilitation techniques and considerations is provided in Table 10-1 below. TABLE 10-1 Forcemain Rehabilitation Techniques Method Spot Repairs Advantages • Useful if deterioration is localized or limited to short segments Disadvantages • Access to repair locations may require excavation • If locations are numerous, it may be more cost effective to rehabilitate entire pipe Features/Materials • Replacement of short segments of pipe (open cut) • Localized use of trenchless repair methods • Materials • Pipe • Grouts (for joint repair) • CIPP • Sliplining Cured-in-place Pipe (CIPP) • Faster installation than open cut • Full bypass pumping necessary • Thermosetting resins and felt liner • No excavation • High setup costs on small projects • Standard and custom sizing available • Does not correct lateral defects or sags • Pre-inspection and highpressure cleaning required • Spot repairs may be required prior to installation • For gravity and pressure pipelines • Accommodates bends and minor deformation • Maximizes capacity • Annulus grouting not required • Internal lateral reopening • Designed for full structural conditions • Extensive history of successful installations Sliplining • Designed for full structural pipe • Extensive history of successful installations • Relies on existing pipe for installation • Curing: steam, hot water, UV • Connection treatment required if I/I reduction desirable • Limitation for grade changes and curved alignments • Requires large excavation pit for staging • Materials: - HDPE - PVC - GRP • Removal of structural obstructions and heavy debris needed • Reduction of effective inside pipe diameter • Quality control of annular grout operation 10-2 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL RECOMMENDED ALTERNATIVES 10.1.2 New Forcemain Route The preferred alignment for the new forcemain generally follows the same route as the existing forcemain from the chamber on the eastern shore of the Cataraqui River to the intersection of James Lane and James Street. From this point, the forcemain would run east along the James Street corridor either within, or directly adjacent to, and south of, the Municipal right-of-way and continue under the intersection of Highway 15 and Highway 2. The new forcemain would connect to the chamber situated approximately 110 metres west of the intersection of Highway 2 and Niagara Park Drive, where the existing forcemain discharges into the gravity sewer. This route option effectively parallels the existing forcemain route. The total length of this option is approximately 1,000 metres. 10.2 Trunk Sewer In general, the preferred alternative for the Ravensview trunk sewer involves rehabilitation of the existing trunk sewer as well as installation of a new trunk sewer to provide redundancy and additional capacity. 10.2.1 Trunk Sewer Rehabilitation UK is undertaking a more detailed review of the rehabilitation requirements for the trunk sewer and will be identifying access requirements for this work under a separate assignment. Rehabilitation options for the trunk sewer are expected to be similar to those listed for the forcemain. The timing and extent of the work will be determined through a separate study. However, the new trunk sewer will likely be completed in advance of rehabilitation to allow for the diversion of sewage flows to facilitate the rehabilitation work. 10.2.2 New Trunk Sewer Route The preferred alignment for the new trunk sewer would begin at the same chamber that the existing sewer does, but would continue easterly along Highway 2 for approximately 2,600 metres before turning south along Gates Boulevard and then east along LaSalle Boulevard towards the WWTP. The total length of this sewer would be approximately 3,200 metres. Due to the approximately 14-metre drop in ground surface elevation between Highway 2 and LaSalle Boulevard (i.e. along Gates Boulevard), a series of drop structures would be required along this section of the proposed sewer alignment. 10.3 Connection of Forcemain to Trunk Sewer At present, the existing forcemain discharges to the trunk sewer at a chamber located approximately 110 metres west of the intersection of Highway 15 and Highway 2. Under the preferred configuration, an expanded chamber will be required to accommodate the two discharging forcemains as well as the two receiving trunk sewers. Associated with this chamber may be the requirement for remote actuation of isolation gates which will facilitate discharge from either one or both of the forcemains to one or both of the gravity sewers. The configuration and features of the chamber will be determined during detailed design. Property acquisition and/or easements in this area will also have to be investigated ahead of design and construction of this chamber. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 10-3 RECOMMENDED ALTERNATIVES 10.4 Flows and Sewer Sizing A detailed assessment of existing and proposed future sanitary flows was conducted as part of the Sewage Infrastructure Master Plan for the City of Kingston Urban Area, completed by CH2M HILL in 2010. In general, trunk sewer design flows were based on the 10-year wet weather design condition. It was assumed for the current analysis that peak flows tributary to the RSPS forcemain would be based on the capacity of the twin-forcemain crossing the Great Cataraqui River from the RSPS. Design flows were also based on the full build-out condition as described in the 2010 Master Plan. It was also assumed that peak flows from each of the contributing sewage pumping stations were coincident at the receiving forcemain and trunk sewer. Pipe design capacities used in the current analysis did not take into account capacity limits at the Ravensview WWTP. The following figure (Figure 10-1) provides a schematic summary of contributing sanitary conveyance systems and their associated peak flow rates. 10-4 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL RECOMMENDED ALTERNATIVES B-40 PS Peak (firm) – 90 l/s Existing Ravensview TS Capacity ~2,200 to 2,400 l/s Butternut Crk PS Peak (firm) – 200 l/s Surcharged flow in certain sections during peak flow conditions JE Horton School Peak (firm) – ? Hwy 15 Flow (Total) Peak (firm) ~ 300l/s CFB Flows (North) Peak – 37 l/s River St. PS* Peak (firm) – 1,750 l/s Peak (max) – 2,400 l/s Peak max to be re-confirmed After FM twin completion B-64 PS Peak (firm) – 110 l/s CFB Flows (South) Peak – 51 l/s Ravensview WWTP Capacity Avg – 1,100 l/s Peak Day – 2,153 l/s Peak Hr – 2,228 l/s Current firm cap. Is sufficient for wet weather flows = FORCEMAIN = TRUNK SEWER Sketch not to scale *Flows once FM twin complete. Modeled flow based on current pump curves Note: Flows based on full build-out conditions, peak flow conditions (sewers) or firm capacity (PS) as noted, based on Master Plan recommendations of 10-y wet weather event FIGURE 10-1 Design Flows – Existing Connectivity 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 10-5 RECOMMENDED ALTERNATIVES As summarized in Figure 10-1, the future total peak flow tributary to the Ravensview trunk sewer under full build-out condition is approximately 2,900 L/s. The objective of the twinning project is to allow for full redundancy in the trunk sewer whereby both the existing and proposed trunk sewers have sufficient capacity to convey peak flows from under most conditions from the upstream tributary area, assuming that one of the sewers is offline. In addition, the proposed capacity of the trunk sewer will also take into consideration potential future upgrades to the River Street Pumping Station, development on the CFB Kingston property, and possible expansion of the urban boundary. A preliminary assessment of ground profile and existing connection inverts along the proposed trunk sewer alignment indicates that the slope of the trunk will likely range between approximately 0.25% and 0.50%. The following table (Table 10-2) summarizes the full-flow capacity of various pipe diameters as well as their respective velocities. TABLE 10-2 Full Flow Capacity of Various Pipe Diameters and Slopes Slope – 0.25% Slope – 0.50% Diameter (mm) Capacity (L/s) Velocity (m/s) Capacity (L/s) Velocity (m/s) 1,200 1,949 1.7 2,757 2.4 1,350 2,669 1.9 3,774 2.6 1,500 3,534 2.0 4,998 2.8 *Based on Manning's 'n' of 0.013 As summarized in Table 10-2, in order to convey the peak flow tributary to the Ravensview trunk sewer, a diameter of at least 1,350 mm is required given a slope ranging from 0.25% to 0.50%. The final diameter of the trunk sewer will have to take into consideration both hydraulic constraints as well as construction methods. Under the proposed twinned condition, average day flows will be divided between the two lines to ensure self scouring flow velocities are maintained in both sewers. Average day flows are currently 750 L/s and will rise to 935 L/s in the future as per results included in the Sewage Infrastructure Master Plan. 10.5 Impacts and Mitigation This section provides details related to potential impacts and mitigation techniques for each of the preferred forcemain and trunk sewer alternatives. The components of the natural environment that may potentially be affected by the new sewer include ground water resources and impacts on terrestrial systems (e.g. parkland and woodlots). Technical considerations include the anticipated need for easements on DND property, and controlling impacts on utilities and other infrastructure. Social/cultural considerations include the need to mitigate impacts on local residents, such as noise, air quality, traffic, drainage, erosion, the need to control effects on archaeological and heritage resources, and the need to protect worker and public health and safety. 10-6 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL RECOMMENDED ALTERNATIVES 10.5.1 Natural Environment Groundwater Resources Seepage barriers should be constructed along the proposed forcemain on James Street and along the trunk sewer on Highway 2 to mitigate possible groundwater flow along the bedding and backfill material for the sewer, thereby reducing the potential for groundwater level lowering. Houses on Cartwright Point, as well as houses on Gates Boulevard, Ridge Avenue, Sterling Avenue, and Glenview Avenue are known to be serviced with conventional water wells. Based on MOE Water Well Records, there is potential for construction pits/shafts/tunnels to intersect the upper water bearing zones that supply some of these well. This could result in an increase in turbidity, and changes to water chemistry, quantity, and quality in some of the wells. If tunnelling is selected as the preferred construction method, betonite slurries and grouting during the shaft construction may reduce groundwater inflow into the tunnels/shafts, may not necessarily eliminate well interference. Significant water bearing zones could be encountered at the transition between the limestone and Precambrian bedrock, which would require significant groundwater pumping. Groundwater inflow could be reduced using grouting techniques. A Permit to Take Water will be required from the MOE for the construction. A hydrogeological assessment will be required to assess the amount of groundwater pumping and the effects of construction on the groundwater and nearby wells. Soil and Groundwater Additional soil and groundwater testing will be conducted during detailed design of the forcemain and trunk sewer. A Phase 2 EA is planned for the forcemain route. An appropriate mitigation plan will be developed for the management of contaminated soils and groundwater should they be identified during testing. Investigations for detailed design will be required to further characterize the anticipated groundwater conditions and to develop a comprehensive mitigation approach to protect private wells from a quality and quantity perspective. Terrestrial Systems Physical intrusion and noise generated by construction activities represents a short-term disturbance to wildlife within the study area. To minimize impacts, the following mitigation measures are proposed: • To minimize impacts on nesting birds, and to correspondingly avoid contravention of the Migratory Birds Convention Act, construction activities should be restricted within the potential nesting period. If this is unavoidable, a nest search of the area will be scheduled a minimum of three days before site work, and will be undertaken by qualified individuals so that no active nests covered by the Migratory Birds Convention Act are destroyed or damaged 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 10-7 RECOMMENDED ALTERNATIVES Drainage and Erosion Controls During pipe line construction, erosion control measures will be implemented to prevent degradation of the adjacent vegetated areas in accordance with the requirements of Cataraqui Region Conservation Authority. The erosion control measures will be tailored to the site to prevent sediment-laden water from leaving the site. A combination of the following erosion control measures will be used onsite: • Site development will be considered with construction scheduling • Maintenance of buffer zones with existing vegetation will remain in place • Disturbed soil areas will be stabilized with permanent vegetation • Dust control will be implemented on disturbed areas and access roads • To protect excavations, runoff will be diverted around the excavation • A silt fence will be installed at the limits of work areas • Storm drain inlet protection will be implemented (geotextile filter cloth under CB covers) • Materials management will include material delivery, storage, and waste management • Vehicle and equipment management will include construction practices, cleaning, fueling, and maintenance Fuel Spills In refueling construction equipment, spills could occur and contaminate surface and groundwater. Proposed mitigation measures include the following: • The requirement of health and safety plans for construction activities • Preparation of a contingency plan for cleaning up fuel spills, ready for implementation • Establishing designated areas for refueling construction equipment with a minimum separation distance of not less than 15 metres from any watercourse 10.5.2 Social and Cultural Considerations The majority of impacts will be short term during the construction period, and the primary groups affected by construction activities will be the residents in the vicinity of James Street within the Barriefield Village area, residents in the vicinity of Gates Boulevard, and the commuters using Highway 2. This subsection describes various categories of the potential impacts and associated mitigation. Construction Impacts Hoe ramming, rock excavation, and other construction will cause vibration on and off the site. Vibrations from these activities are expected to be localized, and are normally not sufficient to cause damage to nearby structures and services in good condition. The existing houses along James Street are historic homes. Damage could be triggered if there are any existing structural issues with the nearby homes. Pre-construction surveys should be carried out on the existing houses so that any potential construction related claims can be resolved in a fair manner. 10-8 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL RECOMMENDED ALTERNATIVES Noise The following construction traffic and equipment noise mitigation measures will be implemented: • All vehicles and construction equipment will be equipped with effective muffling devices and operated to minimize noise in the project area • The City’s noise by-law will be enforced for all construction activities Air Quality To preserve air quality, construction vehicles will not be allowed to idle for more than a designated period of time, and not more than a designated number of idling vehicles will be allowed in the same area at any time. For dust control, a temporary truck wash-down station may be set up to limit dust and dirt on roads adjacent to the residents. Dust and Mud Excavation traffic could create dust and mud problems, pending weather conditions. The proposed mitigation methods include the following: • Dust control measures such as the application of water or calcium chloride will be undertaken as necessary to minimize dust migration • Public roadways will be kept clean and free of mud by regular street cleaning and/or by tire-washing facilities for vehicles exiting the construction site Traffic Management Plan The roads affected during the proposed construction will be James Street, Highway 2, Gates Boulevard, and LaSalle Boulevard. James Street and Gates Boulevard largely carry local traffic, while Highway 2 is a major road. A minimum of one lane will be available for traffic in either direction during construction on James Street and Gates Boulevard, and appropriate flagging and signage will be provided. Temporary access will be provided for residents on LaSalle Boulevard. Traffic management will also be required at the intersection of Highway 2 and Highway 15 for construction of the forcemain crossing at this location. Construction hours may also be staggered and adjusted to avoid work during the busiest times of the day. The work restricting access to private driveways will be minimized by limiting the work to be completed during the business hours and by keeping short trench lengths. An emergency access via a ramp over the open trench will be provided as required. It will also be ensured that all pedestrian access and walkways to transit routes are maintained at all time during construction. Impact on Emergency Vehicles The various route options present different challenges and potential impacts on emergency response times. Highway 2 and Highway 15 are major routes for emergency vehicles with few or no alternatives. Construction staging and the approach to traffic management needs 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 10-9 RECOMMENDED ALTERNATIVES to ensure acceptable access for emergency vehicles is maintained during construction. This issue will require further review and refinement during detailed design. Archaeology For archeological impact mitigation, a Stage 2 Archaeological assessment will be carried out during the design stage and recommendation of the same will be implemented as per the directions provided by the Ministry of Culture. Worker Health and Safety The contractor will be responsible for ensuring that a proper health and safety plan is in place that meets provincial requirements, and that all workers are trained with respect to health and safety. This process will be ensured through the contract document process and the contractor will be required to ensure that all staff have appropriate training and follow required safety procedures. Excavation through the Barriefield rock cut may require additional health and safety measures to be implemented to protect workers from falling rock hazards. Public Information Updates It is recommended that the local landowners be kept up to date of design and construction activities through regular information bulletins. 10.6 Compliance Monitoring Measures Compliance and effectiveness monitoring of the mitigation measures during construction will be implemented. The monitoring measures will ensure accountability on the part of the construction team. The primary objectives of the construction monitoring program will be as follows: • Ensure compliance with contractual agreements dealing with the environmental construction practices specified for the project • Assess the overall performance and effectiveness of the proposed mitigating measures making modifications if and when required The key operations to be monitored during the construction period could include the following: • • • • • • • 10-10 Impacts upon adjacent lands Noise control activities Dust and particulate control activities Clearing of rights-of-way Compliance with working area designations Tree maintenance Site restoration 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 11. Technical Considerations The following sections include details related to specific technical details associated with design and implementation of the preferred alternative. Requirement for Property/Easements It is anticipated that lands outside of the municipal right-of-way will be required either during construction or permanently as a result of the proposed alignments. Further work is required during detailed design, but specific locations where it is anticipated that works may encroach on DND property include: • Parallel to James Street south of the Municipal right-of-way • Between the intersection of James St. and George St. and the intersection of Highway 2 and Highway 15 • Construction staging area(s) along Highway 2 • Construction staging area(s) along Gates Boulevard Communication with DND personnel has been initiated and will continue throughout the design stage. Heritage District Barriefield Village has designation as a Heritage Conservation District under the Ontario Heritage Act. As such, the heritage impact must be considered when designing and constructing the proposed forcemain within the James Street corridor. This includes consideration of native plants, existing structures, and the landscape of the Village. It is recommended that the Barriefield Village Association be updated on the proposed project schedule and scope and that the requirement for consultation with the Kingston Municipal Heritage Committee be confirmed during the design stage of the project. Utilities As-built drawings of existing utilities have been provided by UK. In addition, additional survey work has been completed to identify locations of utilities. As the design progresses further in to the detailed stage, conflicts with other potential utilities will be ascertained and addressed. Conflicts or needs to relocate are being identified as the design of the forcemain and trunk sewer progresses into detailed design. Connection of Highway 15 sewer to Forcemain Disconnecting the Highway 15 gravity sewer from the forcemain would allow full redundancy without the need to connect the Highway 15 sewer to the new forcemain. Grades and construction issues need to be reviewed to confirm the viability of this proposal. A review of the existing connection will be conducted in order to assess options for disconnecting this sewer from the forcemain. 11-11 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL TECHNICAL CONSIDERATIONS Connection of Pumped Discharge from B-64 Pumping Station Currently B-64 Pumping Station discharges directly to the River Street Forcemain. Connection of B-64 to the new forcemain will be required to allow for full redundancy of the system. Depending on which option is selected, a section of forcemain from B-64 to the new forcemain may be required, and valving installed to allow selection of discharge location. Sanitary Flows from North of Highway 2 Certain areas of CFB Kingston north of Highway 2 currently flow south to connect to the existing Ravensview Trunk. A review of the benefits of intercepting these flows with the new twin trunk should be reviewed in detailed design. Highway 15 Sanitary Flows Sanitary flows arising from development north along Highway 15 are directed via forcemain and gravity sewer to a chamber that is installed on the existing forcemain situated approximately 100 m west of the intersection of Highway 2 and Highway 15. The existing forcemain tributary to this chamber is situated on CFB lands north west of the intersection. Construction of a gravity sewer within the Highway 15 right-of-way, discharging into the trunk sewer east of the intersection of the two highways is technically feasible. However, the cost of such an undertaking is likely prohibitive, and the existing connection to the forcemain, although not ideal, is functional. UK intends to maintain the form and function of the existing forcemain connection and provide the necessary interconnection between the old and new forcemains rather than explore further the option of gravity drainage in the Highway 15 corridor. Baseflow in Existing Trunk Sewer Diversion of flows to a new twin sewer would reduce flow in the existing trunk to those from CFB Kingston only, potentially resulting in velocities lower than those required to maintain self-scour. The distribution of flows between sewers and required self-scour velocities will need to be considered and confirmed during detailed design. Pipe sizing Sizing of the new twin trunk sewer needs to account for the handling of existing and future flows, and potential full flow redundancy. However, consideration of construction (e.g. tunneling) techniques and costs that could vary based on the pipe sizing need to be accounted for in the decision making during functional design. Pipe sizing in the range of 1,350 to 1,500 mm inside diameter appear adequate depending on final pipe slopes and grades. A balance of currently forecast capacity requirements, potential future capacity needs, specific constriction requirements, and present-day construction costs will be required in the final pipe size selection. Geological Conditions Much of the potential forcemain and gravity sewer routes are anticipated to be through bedrock. For shallower installations, bedrock removal could be carried out using hoe ramming techniques. Hard and/or thick bedrock beds could require significant effort and progress could be slow. 11-12 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL TECHNICAL CONSIDERATIONS Bedrock conditions at the level of the proposed tunnel installations are expected to consist of bedded limestone with potential granitic intrusions. Tunneling through the limestone and granitic bedrock is considered to be feasible, although tunneling progress may be somewhat slower through harder rock zones. Intermediate tunnel shafts will be required where abrupt changes in the tunnel alignment are planned, or as required, based on the tunneling technique. Additional geotechnical investigations are planned to better characterize the rock conditions along the preferred trunk sewer route alignment. Corrosion resistance of new pipe The existing Ravensview Trunk Sewer is experiencing deterioration due to hydrogen sulfide corrosion. The new gravity sewer will need to consider corrosion protection or lining requirements, particularly in zones of super critical flows or high turbulence (e.g. drop structures at Gates Blvd.). Chemical dosing at the River Street Pumping Station is currently being implemented to mitigate such corrosion. Construction Costs An Opinion of Probable Cost is currently being developed for the twinned forcemain and Ravensview Trunk with consideration of new information collected to date, including geotechnical and groundwater conditions. Coordination with other Major Projects Consideration should be given to other major projects within the area affected by construction to ensure that cumulative impacts are appropriately mitigated. This issue should be investigated in greater detail during detailed design. Specific projects include CFB Kingston developments and potential steamline/watermain works on James Street. 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 11-13 12. Construction Staging, Schedule, Costs and Approvals 12.1 Staging and Schedule It is anticipated that forcemain construction will take place during 2012 or 2013. Trunk sewer construction may begin in 2013 depending on the final cost anticipated for the project and the availability of funding. Rehabilitation of the forcemain and trunk sewer will take place following completion of the twin-forcemain and trunk sewer construction. During construction, access to all businesses and institutions will be maintained at all times. The access to individual residences will likely be affected for only a day at a time. Emergency access to residences will, however, be made available at all times. 12.2 Preliminary Opinion of Probable Cost A preliminary Opinion of Probable Cost (OPC) for the forcemain and twinned trunk sewer has been prepared based on the proposed route alignment and profile, and taking into account the current best assumption of methodologies to be employed in the construction of the infrastructure. For the trunk sewer, the depth of the proposed sewer is such that tunnelled installation of the infrastructure will be necessary. As such, additional geotechnical information was collected to verify the geologic conditions and confirm that a tunnelled installation is viable. Based on various assumptions, the OPC for the forcemain (including the tunnelled installation beneath Highway 2) is $3.25 million, while the OPC for the trunk sewer (including sections of tunnel installation) is $25.4 million (excluding allowances for engineering and applicable taxes in both cases). These OPC are in 2011 dollars and include allowances for contractor mark-ups and overheads of 15% and contingencies of 20%as is appropriate for the current project stage and conceptual level of detail. 12.3 Required Permits and Approvals MOE Certificate of Approval for construction of the forcemain and sanitary sewer will be required. A permit from the City of Kingston will be required for the construction of the sanitary sewer within the City’s roadways. Also, a Permit to Take Water may be required for dewatering during construction based on results of hydrogeological testing. The Cataraqui Region Conservation Authority may also require permits for erosion and sediment control and work adjacent to the Cataraqui River. The Kingston Municipal Heritage Committee should also be consulted to confirm permit requirements under the Ontario Heritage Act for works conducted in the vicinity of Barriefield Village. 12-14 416205_WBG062011103040OTT COPYRIGHT 2011 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL 13. References Adams Heritage, 2011, An Archaeological Assessment (Stage 1) of the Proposed Forced Main and Trunk Sewer Route, City of Kingston Aqua Terre Solutions Inc., 2008, Stormwater Management Study Canadian Forces Base Kingston, Kingston, Ontario – Prepared for Public Works Government Services Canada and Department of National Defence (March 3, 2008) CH2M HILL, 2010, Sewage Infrastructure Master Plan for the City of Kingston Urban Area City of Kingston, 2010, Official Plan – Approved January 27, 2010, Consolidated as of August 1, 2011 Ecological Services, 2011, Environmental Assessment: City of Kingston Forcemain Sewage Line Extension (June 29, 2011) Houle Chevrier Engineering, 2011, Soil and Bedrock Inventory Environmental Assessment River Street Pump Station Twin-Forcemain Extension and Ravensview Trunk Sewer Twinning Kingston, Ontario (September 2011) 416205_WBG062011103040OTT 13-1
© Copyright 2025 Paperzz