NORTHERN BLVD ESA’s SEM challenge In a project full of demanding underground contracts, the short 125ft (38m) section of SEM tunnel under the Northern Boulevard, has the accolade of being one of the most technically challenging elements of New York’s East Side Access Project. Kyle Ott, Senior Engineering Manager for Parsons Brinckerhoff, Paul Madsen, Project Manager for Kiewit Infrastructure, and Paul Schmall, Vice President and Chief Engineer for specialty contractor Moretrench, explain THE EAST SIDE ACCESS (ESA) project, the largest capital construction project ever undertaken by New York’s Metropolitan Transportation Authority (MTA), will connect the Long Island Rail Road’s (LIRR) Main and Port Washington lines, in Queens, to a new terminal beneath Grand Central Terminal, in Manhattan. The project will increase the LIRR's capacity into Manhattan, and significantly reduce commuter travel time from Long Island and eastern Queens into east Manhattan. The overall project includes four tunneling contracts between the Sunnyside Rail Yard complex in Queens and Grand Central Terminal. In Queens, four soft ground tunnels have been completed linking the LIRR mainline tracks beneath Sunnyside and LIRR's Existing Rail Yards to the Plaza Structure. In Manhattan, new tunnels and caverns have been mined in Manhattan schist from the existing Bellmouth structure at Second Avenue and 63rd Street, west and then south, under Park Avenue and Metro-North Railroad's four-track right of way (see NATJ, April/May, p20). The Northern Boulevard Crossing in Queens is the keystone that connects the Plaza Structure to the existing 63rd Street Bellmouth shaft on the other side of Northern Boulevard. It is by far the shortest of the tunnels at just 38m (125ft). Nevertheless, it presented project designer General Engineering Consultant (a tri venture of Parsons Brinckerhoff, STV and Above: MIDAS finite element model developed for analysis of the SEM excavation sequence. Right: The crossing was successfully mined by SEM methods under a protective arch of frozen soil 24 NORTH AMERICAN TUNNELING JOURNAL Horizontal drilling for the bottom hole of the frozen arch was accomplished from a pit excavated in the rock Parsons Transportation Group), the construction management team (URS/HMM), tunnel contractor Schiavone/Kiewit JV, and specialty geotechnical contractor Moretrench with design and construction challenges. Methodologies considered The Northern Boulevard Crossing was constructed using the sequential excavation method (SEM), and is the first SEM tunnel constructed to date within the five Boroughs of New York. The tunnel passes beneath an active five-track subway box structure, with only 12ft to 16ft (3.6m to 4.8m) of ground above the SEM excavation. Above the fivetrack subway is the Northern Boulevard itself (six lanes), and a pile-supported elevated rail structure for New York City Transit’s BMT Line. The tunnel was mined through an upper stratum of mixed glacial silty sands, a thick deposit of bulls liver silt and silty sand, glacial till/reworked till/outwash, decomposed rock, and bedrock. Depth to bedrock ranges from approximately 70ft to 90ft (21m to 27m) below ground level, with groundwater located about 16ft (5m) below the surface. Groundwater control and stabilization of the NORTHERN BLVD Above: As-built sequence of drift excavation Above left: Thermal modeling of the frozen arch with heat pipes after 41 days of operation Left: Thermal model of as-built pipe array showing temperature distribution after 59 days of freezing soils beneath the subway were required. In accordance with New York State Department of Environmental Conservation (NYSDEC) Long Island Well Permit requirements, dewatering was not allowed outside of the groundwater cut-off system so as not to cause movement of contaminant plumes that exist within the adjacent Sunnyside Rail Yard. Initial concepts for the crossing therefore included various means to cut off water locally without the need for groundwater lowering. At the adjacent New York City Transit 63rd Street to Queens Boulevard Connection Project constructed in the 1990’s, such methods had included micropile underpinning and jet grout cut-off walls, which involved drilling through and from within the subway box. However, for the CQ039 Northern Boulevard Crossing, construction from within the subway box or from ground surface at Northern Boulevard was not permitted so the previously adopted methods and other various cut-off methods considered were discarded in favor of a horizontally constructed frozen arch around the tunnel perimeter extending to bedrock. This approach was considered to meet the project criteria of groundwater cut-off and structural settlement control while meeting the access limitations. Tunnel excavation sequence modeling The design called for installing freeze pipes along the tunnel perimeter to develop a minimum 6ft (1.8m) thick frozen soil arch followed by sequential excavation of six drifts for the tunnel excavation. For the SEM design, the frozen arch would function as a groundwater cut-off; ground support to provide standup time to place the initial shotcrete liner; ground support as part of the initial support system to limit deformations within the shotcrete liner system during excavation; and ground support as part of the initial support system to limit ground deformations (settlement) at the subway box and at the ground surface. The frozen arch was required to be maintained through completion of the final liner placement and curing to 28-day strength. To verify the SEM design, the GEC performed 3-D numerical modeling using the MIDAS software. Based on the MIDAS modeling results, an initial liner was developed of 3in (76mm) of plain shotcrete placed against the frozen soil, and 12in (300mm) of welded wire fabric reinforced shotcrete with lattice girders at 4ft (1.2m) centers to support the soil load and subway box along with the frozen arch. In situ soil samples were obtained by ground freezing contractor Moretrench and laboratory testing was performed to evaluate the strength and deformation behavior of the frozen and thawed soils, thermal conductivity, and frost heave potential to enable finalization of the required ground freeze temperatures. Ground freezing design challenges The same site constraints that precluded vertical drilling for pre-drainage dewatering and other groundwater control methods also applied to the installation of freeze pipes. Drilling of horizontally oriented pipes below the water table, through the glacial silty sands and “bulls liver-like” silts, was likely to result in some loss of ground, potentially causing settlements and movement of the installed pipes. The bull’s liver material would also be susceptible to the formation of ice lenses and heave. Ice lenses typically exert forces in the direction of the temperature gradient, which is normal to the orientation of the freeze pipes and the freezing plane. For vertical freezes, the forces are lateral, counteracted by greater lateral earth pressures at depth, and are rarely an issue, but for horizontal freezes they are vertical, which could exacerbate heave of the structure, particularly at shallower depths. With minimal deviation of the drilled freeze pipes, there would still be only several feet between the top of the frozen arch and the bottom of the existing subway structure, and it was from this horizon that the growth and heave of the freeze had to be controlled. Heat pipes, i.e. pipes with heating elements, were installed above the uppermost pipes of the freeze arch to control the upward growth of the freeze towards the five-track subway structure. Thermal modeling was performed to evaluate the effectiveness of the heat pipes. Thermal modeling was also performed with the as-built freeze pipe surveys to evaluate the time to closure and the structural thickness of the freeze. NORTH AMERICAN TUNNELING JOURNAL 25 NORTHERN BLVD As with any freeze, placement of the freeze pipes within the design tolerance is important. Several significant conditions would make alignment of the pipes very challenging. Four clusters of 16 concrete filled pipe piles had to be penetrated (without damaging the piles), as well as cobbles and boulders, and an undulating rock surface. range of ground and obstruction conditions. In areas where obstructions were not anticipated, casing was advanced by duplex, cased-hole, positive flush methods. All pipes were surveyed with a gyroscope immediately upon completion. SEM tunneling Upon closure of the frozen arch, tunneling proceeded. The tunneling process was accomplished using a step-by-step approach, with the successive excavation and installation of support. The three upper drifts were excavated in 4ft (1.2m) rounds, and the lower drifts were excavated in 8ft (2.4m) rounds. A 9in (230mm) thick shotcrete initial lining was installed as a temporary invert in Settlement and heave control In order to address any settlement that may occur during drilling of the horizontal holes, and any heave that may occur during the freeze, specific mechanisms were developed. Compensation grout holes were installed enabling grouting to be performed to mitigate settlement of the overlying structures during installation of the freeze pipes. Provision was also made for soil extraction from the zone between the frozen arch and the base of the subway box to counteract heave of the structure during freeze formation and freeze maintenance, and heat pipes were installed around the top of the arch to control the outward growth of the freeze. During thawing of the frozen ground following completion of the SEM tunneling, compensation grouting could be performed through the preinstalled grout pipes if necessary to mitigate against settlement. Since pre-conditioning/void filling and compensation Frozen ground visible during drift excavation grouting with conventional cement based grouts could the upper sidewall drifts. For initial support of render the soils unworkable for subsequent sequential excavation, the outer shotcrete soil extraction, a specially formulated nonliner segments consisted of a 3-bar lattice cementitious grout was developed that girder embedded in a 1ft (300mm) thick mimicked the strength and consistency of the shotcrete layer. Shotcrete strength in situ soils. requirements were 1,800 psi (12MPa) at 24 hours, 2,500 psi (17MPa) at 3 days and 5,000 Installation of freeze pipes psi (34.5MPa) at 28 days. Additionally, two Maintaining drill alignment while penetrating layers of welded wire fabric were placed with through concrete-filled pipe pile clusters, each 4ft (1.2m) long round. For temporary cobbles and boulders, and an undulating rock sidewalls, steel lattice girders were installed surface was challenging. Accomplishing that along with two layers of welded wire mesh. from below the water table, through very Only one layer of welded wire mesh was sensitive silty soils, compounded the installed at temporary inverts. Drift sequence complexity of the work as well as restricting and stagger between headings were altered drilling methodologies. Measures were during construction to accommodate the therefore put into place by the ground conditions encountered. freezing contractor to install the pipes within The design included a 3in (76mm) permissible tolerances while preventing insulating layer of flashcrete prior to lattice ground loss. girder installation. However, the heat of These included groundwater control hydration from the flashcrete would thaw a devices (blow-out preventers) with design thin layer of frozen soil, causing the unfrozen features that eliminated ground loss during soil and the flashcrete to delaminate from the drilling as well as being able to advance frozen ground. To resolve this issue, it was multiple casings to overcome obstructions. decided to apply the insulating layer together Platform-mounted core drills could advance a with the initial structural shotcrete layer. The wide range of casing and tool diameters at full thickness of shotcrete was applied in two high or low rotation speeds to address a wide 26 NORTH AMERICAN TUNNELING JOURNAL passes so that the inside wire mesh could be applied by the crews under the protection of the first pass. The main piece of excavation equipment was a tunnel excavator outfitted with a quick connect that allowed for easy exchange of four different tools: grinding head, hydraulic hammer, aggressive bucket with tiger teeth and a bulk excavation bucket. Shotcrete was applied using a small track mounted robot. The shotcrete was pumped from the surface to the headings through a 4in (100mm) slick line using shotcrete pumps with integrated accelerator dosing system. All shotcrete was delivered by a ready mix supplier, retarded and accelerated on site. Following completion of the SEM excavation and initial liner, a PVC waterproofing membrane was installed followed by a 30in (760mm) reinforced concrete final liner. The interior dimensions of the final liner are approximately 53ft (16m) wide by 33ft (10m) high. The SEM modeling indicated the settlement at the crown of tunnel to be 1.2in (30mm) and the base of the subway box to settle approximately 0.6in (15mm). Slight 0.1in to 0.2in (2.5mm to 5mm) movement was observed within the overlying five-track subway settlement monitoring during tunnel excavation and removal of the temporary sidewalls. Following excavation of the center drift, only 0.3in to 0.6in (7.5mm to 15mm) of movement was observed in the crown. No further movement was observed during or after the removal of the temporary sidewalls. Given the very limited amount of movement, ultimately, soil extraction during freezing was not required. Currently, after five months of thawing of the freeze, the maximum movement at the surface is approaching 2in (50mm). Compensation grouting will be forthcoming to address this. Close cooperation and teamwork between the design engineers, owner and contractors was key to the success of this challenging project. Modeling of the SEM tunneling and the frozen arch provided a sound approach to mitigate many geotechnical uncertainties. The ground freezing provided excellent groundwater cut off and ground support. SEM excavation was performed in a safe and satisfactory manner, with actual ground and structural deformations less than the numerical modeling indicated. The ground freezing installation was performed with negligible ground loss, and no compensation grouting was required during system installation. Ground heave due to ice lensing was also within acceptable limits and no soil extraction was necessary.
© Copyright 2026 Paperzz