“PERFORMANCE TESTING OF A 380 ML/D RETROFITTED MEMBRANE/UV OXIDATION WTP” Brian Sahely, M.A.,Sc., P.Eng, AECOM Canada Ltd. 5600 Cancross Court, Suite A, Mississauga, ON L5R 3E9 [email protected] Phone: 905-712-6995 Jeff Hennings, P. Eng., M.Sc.Eng., Region of Peel, Brampton, ON Sheldon Belbin, M.Env.Sci., Ontario Clean Water Agency, Mississauga, ON Dean Baker, Ontario Clean Water Agency, Mississauga, ON Brian Vistorino, P.Eng., Genivar, Markham, ON Sophie Pease, P.Eng., GE Water & Process Technologies, Oakville, ON Introduction The Lorne Park Water Treatment Plant (WTP) is located in Mississauga, Ontario, Canada and is owned by the Region of Peel. Between 2007 and August 2012, construction was completed for the expansion of the plant to 500 ML/d, including the retrofit of 227 ML/d settling tanks (Figure 1) with 380 ML/d of membranes (Figure 2). Once the Lorne Park WTP was fully commissioned, the membrane system had to be tested in accordance with the pre-selection document. This was completed over a six month period with two of the sixteen membrane trains operating in supervisory mode at maximum design capacity of 31.7 ML/d per train. This article presents the results of the performance testing that was conducted and lessons learned for future membrane performance testing. Testing Results – General Figure 1: 8 Settling Tanks w/ Plate Settlers (227 ML/d Conv. Plant) 1 Figure 2: 16 Membrane Tanks w/ GE ZW1000 Modules (380 ML/d Membrane Plant) Performance Testing Results – General Figures 3 to 6 shows the general performance testing results for cycles 2 and 3 passing the following criteria: · Membrane flux @ 51 Lmh, i.e., 31.7 ML/d per train · Recovery @ 95% except when turbidity > 5 NTU · Log removal value (LRV) > 4.3-logs for first two years and then 4.0-logs afterwards · Permeate turbidity ≤ 0.1 NTU, 99% of time & ≤ 0.3 NTU, 100% of time · CIP frequency greater than 42 days cycle (or when TMP trigger at -83 kPa) 2 UF 42-FluxBeforeBP UF 53-FluxBeforeBP Target 54 Flux (Lmh) 53 52 51 50 49 48 06/07/2013 16/07/2013 26/07/2013 05/08/2013 15/08/2013 25/08/2013 04/09/2013 14/09/2013 24/09/2013 Figure 3: Membrane Flux 100 98 data not available in InSIght Recovery (%) 96 94 92 feed water turbidity spike 90 88 7/6/2013 7/20/2013 8/3/2013 8/17/2013 8/31/2013 Figure 4: Recovery 3 9/14/2013 9/28/2013 UF 42-LRV UF 53-LRV Target 5.4 5.2 LRV (logs) 5.0 4.8 4.6 4.4 4.2 4.0 06/07/2013 16/07/2013 26/07/2013 05/08/2013 15/08/2013 25/08/2013 04/09/2013 14/09/2013 24/09/2013 Figure 5: LRV UF 42-PermeateTurbidity UF 53-PermeateTurbidity Target 100 90 Permeate Turbidity (mNTU) 80 70 60 50 40 30 20 10 0 06/07/2013 16/07/2013 26/07/2013 05/08/2013 15/08/2013 25/08/2013 04/09/2013 14/09/2013 24/09/2013 Figure 6: Permeate Turbidity 4 UF 42-TMPBeforeBP UF 53-TMPBeforeBP UF Plant-PermeateTemperature1 Train 42 Hypo RC Train 42 Acid RC Train 42 Hypo RC Train 42 Acid RC Train 53 Hypo RC Train 53 Acid RC Train 53 Hypo RC Train 53 Acid RC Train 53 Hypo RC Train 53 Acid RC TMP (kPa) and Temperature (°C) 90 80 70 60 50 40 30 20 10 0 06/07/2013 16/07/2013 26/07/2013 05/08/2013 15/08/2013 25/08/2013 04/09/2013 14/09/2013 24/09/2013 Figure 7: TMP Testing Results – Chemical Usage Figures 8 to 10 show the target chemical concentrations and pH required for chemically enhanced backwashes (CEBs) and/or clean-in-place (CIP) cycles and the chemical volumes consumed versus those guaranteed for cycle 3. As shown, some of the chemical volumes guaranteed were exceeded. 5 Guaranteed 160 145 140 Actual 135 120 100 80 60 38.4 35 40 20 9.2 14.6 0 Chlorine residual (mg/L) 2.4 2.6 Sodium Sodium Sodium hydroxide bisulphite hypochlorite volume (L/clean) volume (L/clean) volume (L/clean) Figure 8: Non-heated CEBs (~40 min duration, Every 2nd Days) Guaranteed 450 400 350 300 250 200 150 100 50 0 Actual 385 320 96.2 94.5 23.2 22.6 Chlorine residual (mg/L) 6 4.9 Sodium bisulphite Sodium hydroxide Sodium volume (L/clean) volume (L/clean) hypochlorite volume (L/clean) Figure 9: Heated High pH CIPs (~5 Hours Duration, Every 42 Days) 6 Guaranteed 80 Actual 74.7 74.9 70 60 52.4 50 38.6 40 30 20 10 0 8.3 10.5 2.1 2.4 Cleaning pH Citric acid volume Sulphuric acid Sodium hydroxide (L/clean) volume (L/clean) volume (L/clean) Figure 10: Heated Low pH CIPs (~5 Hours Duration, Every 42 Days) Testing Results - Power Usage Figures 11 and 12 show the power distribution given various equipment. As shown, the permeate pumps consume the most power at 96.6% of the total power usage. As a result, it was agreed that only the permeate pump power will be monitored and evaluated for compliance with the performance guarantee. Two ION 7350 meters (Figure 13) were installed for the permeate pumps for the two membrane trains being tested. Given 17,191 kWh/day permeate pump total plant guarantee, the corresponding power expected from one permeate pump is 1,146 kWh/day at 2oC at 1,152 min/day. Given higher water temperatures and higher operating time, the corrected power expected from one permeate pump at 14.4oC and 1,344 min/day is1,169 kWh/day. Figure 14 shows the permeate pump speed during cycle 3 being 47% with the pump power averaging 837 kW/day, which is lest than that required of 1,169 kWh/day. 7 1.30% 0.30% 0.30% 1.40% 0.10% Backpulse Pumps Cleaning Pumps Blowers Compressors Recirculation Pumps 96.60% Permeate Pumps Power Distribution (%) 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 55 249 10 Compressor s Recirculatio n Pumps 55 Blowers 230 Cleaning Pumps 17,191 Backpulse Pumps 20,000 18,000 16,000 14,000 12,000 10,000 8,000 6,000 4,000 2,000 0 Permeate Pumps Power Consumption (Kwh/day) Figure 11: Membrane Equipment Power Distribution (Percentage) Figure 12: Membrane Equipment Power Distribution (kWh/day) 8 Figure 13: ION 7350 Meters Installed on Two Permeate Pumps 700 30% 600 20% 500 10% 400 0% 24-Sep-13 40% 17-Sep-13 800 10-Sep-13 50% 3-Sep-13 900 27-Aug-13 60% Figure 14: Permeate Pump Power and VFD Speed for Cycle 3 9 Pump Speed (%) Equivalent Average Pump Speed % 1,000 20-Aug-13 Pump Power Usage (kW.h) kW.h Usage Liquidated Damages/Penalties The pre-selection document specified liquidated damages/penalties for various performance parameters. These are shown in Table 1 with the performance achieved in this peformance testing for cycle 3 shown along with the net liquidated damages listed. As shown, a savings of approximately $4.61MM can be recognized from cycle 3 performance testing. Table 1: Liquidated Damages (Net Savings of $4.6MM) Performance Parameter Recovery (%) CIP Interval (# cleans/year) Power use for 1 Process Pump (kWh/day) Production Capacity for 1 Process Pump (ML/d) Chemical Usage Total Net Liquidated Damages Performance Unit for Liquidated Performance Achieved Required Liquidated Damages per Unit Damages 0.5 $400,000 $95.75 95 1 $78,000 6 9 Net Liquidated Damages -$600,000 -$234,000 1,169 1 $11,388 837 -$3,780,816 31.67 0.1 $80,000 31.67 $0 Varies Varies Varies Varies $229,919 - - - - -$4,614,816 10 Lessons Learned 1. Lengthy performance testing is beneficial as operator training and “new findings”, e.g., incorrect recovery calculations, membrane tank temperature maintenance, backwash trigger logic, CIP trigger setpoints, analyzer concerns, etc. 2. Develop a performance testing protocol during pre-selection that matches exactly how it would be performed given any limitations such as flow. Request guarantees specific to performance testing, even if different from long-term guarantees. Request specific programming for the specific protocol. 3. Install ION meters on membrane equipment to allow for tracking of power short-term and long-term. Separate building loads from ION meters. 4. Specify TMP guarantees instead of power guarantees given difficulty in monitoring power and correction factors that are required. 5. Targeting a pH or chlorine concentration can be difficult. If possible, on-line analyzers to allow for chemical dosing compound loops to achieve targets. 6. Monitor and maintain sufficient flow to on-line analyzers for them to work properly. 7. Avoid long sample lines to on-line analyzers to prevent incorrect readings, especially temperature, given the impacts of ambient temperature. 8. Performance testing with penalties can inhibit optimization of the system given that suppliers primary goal is to remain within guarantees at all times. 9. Continue testing and reporting for 1st year across all seasons especially at worst water quality, e.g., temperature. 10. Conduct plant wide FAT in advance of commissioning as done for the Lorne Park WTP. This made performance testing a “piece of cake” when it came to controls!!! 11
© Copyright 2026 Paperzz