Centre for Geo-Information Thesis Report GIRS-2016-14 OPTIMIZING SUGAR CANE TRANSPORT IN RWANDA 28 April 2016 Laura Wools i Optimizing Sugar Cane Transport in Rwanda L.M.A. Wools Registration number: 90 11 09 972 100 Supervisor: Dr. Ir. S. de Bruin A thesis submitted in partial fulfilment of the degree of Master of Science at Wageningen University and Research Centre, The Netherlands. 28 April 2016 Wageningen, The Netherlands Thesis code number: GRS-80436 Thesis Report: GIRS-2016-14 Wageningen University and Research Centre Laboratory of Geo-Information Science and Remote Sensing ii Abstract The production of sugar in Rwanda is a growing sector, as up to 80% of the consumed sugar in Rwanda has to be imported. The largest cost component of sugar production is the cane transport. Transport costs can account up to 30% of the total production costs. The current sugar transport in Rwanda is mainly done by trucks. Implementing a multimodal transport network by using the road network and the river to transport the sugar cane can reduce the costs of transport. The main objective of this research is optimization of sugar cane transport in Rwanda by assessing different transport modes conditional to factory constraints and field and network conditions. Along the Nyabarongo river 42 landing and loading points were created. Within a distance of 1 km a landing or loading point can be reached from all sugar cane fields. From these 42 landing and loading points, the optimal routes to the sugar mill were calculated. The optimal routes were computed as the least-costs paths using Dijkstra’s algorithm. An average reduction of 40% of the current transport costs can be realised when implementing transport over the river. These optimal routes from all 42 landing and loading points uses the river and switch at the landing point near the Ruliba bridge to the road network. Further improving the efficiency of the total supply chain can be done by researching each component of the supply chain in detail. Additionally, the costs of different transport modes could be predicted more accurate when assessing different variables. Keywords; Dijkstra’s algorithm, Kabuye Sugar Works, multimodal transport, network analysis, least-cost path, R, sugar cane, transport optimization iii Table of Content 1 Introduction ..........................................................................................................1 1.1 Context and background ......................................................................................1 1.2 Problem definition ................................................................................................3 1.3 Research objective...............................................................................................4 2 Current situation ...................................................................................................5 2.1 Factory constraints ...............................................................................................5 2.2 Field conditions ....................................................................................................5 2.3 Network conditions ...............................................................................................8 3 Methods ............................................................................................................. 11 3.1 Conceptual Model .............................................................................................. 11 3.2 Loading points.................................................................................................... 11 3.2.1 Methods ............................................................................................................. 11 3.2.2 Implementation .................................................................................................. 12 3.2.3 Assign sugar cane fields to loading points .......................................................... 13 3.3 Optimal route to the factory ................................................................................ 14 3.3.1 Dijkstra’s algorithm ............................................................................................. 14 3.3.2 Pre-processing ................................................................................................... 15 3.3.3 Implementation .................................................................................................. 18 3.4 Economic feasibility............................................................................................ 19 3.4.1 Capital investment.............................................................................................. 19 3.4.2 Breakeven analysis ............................................................................................ 19 4 Results ............................................................................................................... 21 4.1 Location of loading points................................................................................... 21 4.2 Costs of different transport modes ..................................................................... 21 4.2.1 Transport by road ............................................................................................... 21 4.2.2 Transport by river ............................................................................................... 22 4.3 Optimal Route .................................................................................................... 23 4.3.1 Optimized route on the road network.................................................................. 23 4.3.2 Reduction of transport costs ............................................................................... 24 4.3.3 Efficient use of river transport ............................................................................. 26 4.4 5 Feasibility ........................................................................................................... 27 Discussion.......................................................................................................... 29 5.1 Current situation ................................................................................................. 29 5.2 Landing and loading points ................................................................................ 30 iv 5.3 Costs of transport network ................................................................................. 30 5.4 Optimal Route .................................................................................................... 31 5.5 Feasibility ........................................................................................................... 31 6 Conclusion ......................................................................................................... 32 6.1 Research objective............................................................................................. 32 6.1.1 What is the current situation of cane transportation in Rwanda? ........................ 32 6.1.2 Which method is suitable for this cane transportation optimization problem? .... 32 6.1.3 Which variables of the transport network can predict the costs of the road network?........................................................................................................................ 32 6.1.4 Which conditions are important to be considered when implementing the results of this research in KSW circumstances? .......................................................................... 32 6.2 7 Further research and recommendations ............................................................. 33 References......................................................................................................... 34 v 1 Introduction 1.1 Context and background The price of sugar has been in a downward trend for the last couple of years. International competiveness, low prices of commodity goods and increased interest in alternatives to sugar put a lot of pressure on the sugar price (Higgins, 2006b, 2007). In the summer of 2015, the price of sugar reached its lowest point since six and a half years (Durisin, 2015; Wernau, 2015). For producers the best option to maintain a profitable business is by reducing their production costs (López-Milán, 2006). The largest cost component of sugar production is cane transport (López-Milán, 2014). Transportation from the fields to collection sites and from collection sites to the mill can be very costly due to several production conditions. Depending on the case, transportation costs can account for about 25-30% of total production costs (Higgins, 1999, López-Milán, 2014). The costs of sugar cane transport are high due to the fact that there are some strict conditions which have to be dealt with when processing sugar cane. The first and most important constraint is that the mill needs enough supply to process 24 hours a day. This means that during the day, a stock must be made for the night. This first constraint does not only concern the transport component, since sugar cane also has to be harvested during the day. The second condition concerns the quality of the cane. In order to achieve high sugar content, the cane has to be harvested at maturity. The timing and length of the period of maturity depends on crop cultivar and climatic conditions of the environment. For example, a hot climate and large seasonal variations can lead to overmaturity of the crop. Overmaturity leads to loss of sucrose and juice quality (Fauconnier, 1993; James, 2008). A loss of quality also occurs after the cane is burned or cut. Therefore the cane has to be processed as soon as possible after being harvested (Fauconnier, 1993; López-Milán, 2006). The speed at which the quality decreases highly depends on environmental conditions; in warmer climates there is a bigger rush to process the cane (Fauconnier, 1993). These two constraints, the urge for constant milling and the cane quality, make the transport of sugar cane a complicated but interesting topic. A lot of research has been done on this topic and most of it has focussed on large sugar cane producing countries such as Australia, Brazil, Cuba and South Africa (Higgins, 2003; Lejars, 2008; López-Milán, 2006). Research focussed on the Australian sugar industry is targeted primarily on cooperation between growers, haulers and the mills. There have been several projects that have led to a reduction of transportation costs by applying modelling when scheduling road transport (Higgins, 2006a, 2006b). According to those studies, it is important to approach this challenge with a holistic solution. The supply chain must be seen as a whole instead of focussing on individual parts of the production chain (Higgins, 2003; Le Gal, 2009; Lejars 2008). Next to the technical aspects of the supply chain, socio-economic features such as collective participation play an important role in improving the supply chain (Le Gal, 2009; Higgins, 2007). The possibilities of optimizing the supply chain depend on the structure of the sugar supply chain. When the total supply chain is property of one company, the efficiency of the complete process is the main goal. This is the case in for example Cuba, where the whole process is owned by the government (López-Milán, 2006). However, when more farmers deliver to a mill, sometimes even with a haulier company in between, there are different interests. In that way 1 the optimization process requires more managing, such as in Australia (Higgins, 2007). It also matters whether the harvesting is done mechanically or manually. Mechanically cut cane requires a different way of transportation than manually cut cane. The first are long stalks which are transported in bundles, while the latter are cut into short sticks and is transported in baskets. (Grunow, 2007). The studies performed by Higgins (1999, 2006a, 2006b) and López-Milán (2014) showed that transportation costs, in different contexts, can be reduced by using a technical solution. However, every sugar cane company is different and has different aspects and constraints. These companies all have the same goal; reducing transportation costs in order to compete with the falling sugar prices. In Rwanda, the sugar industry is purely meant for own consumption. The more sugar is produced in the country, the less has to be imported. Currently, up to 80% of the sugar consumed in Rwanda is imported (“Sugar: make it work”, 2014). The single player in the sugar industry in Rwanda is Kabuye Sugar Works (KSW). The single producing factory of the country is located near the capital Kigali (Figure 1). In 1998, the Madhvani Group acquired this sugar factory from the government and the industry has been growing from that point. All sugar cane fields are located near the Nyabarongo River. 400 employees are working in the factory and around 5.000 employees on the fields. KSW leases approximately 3.700 ha of land which can be used for cultivation (Kabuye Sugar Works, Rwanda, 2015). However, currently they can only use 1.700 ha because of regular flooding. Another approximately 3.100 ha is leased by independent out growers, farmers who sell their yield to the factory (Royal Haskoning, 2015). Figure 1: Location of the KSW Factory, the landing points and the sugar cane fields 2 Because of heavy flooding and the subsequent low yield, 60% of the processed sugar cane at the KSW factory originated from out growers in 2008. Unfortunately this still was not enough to keep the factory going 24 hours a day and the mills had to be stopped for some time. Soon they picked up again at 12 hours a day (Mukaaya, 2008). In 2011 80% of the sugar cane fields flooded again which led to unaffordable sugar prices for the Rwandan population (Royal Haskoning, 2015). In 2013, the project ‘Sugar: make it work’ started with as main goal; drainage of sugar cane fields to remove water in case of floods as efficiently as possible. Because of the flood and the importance of the sugar cane industry for Rwanda, the focus of the project is mainly on reducing the effects of floods. However, an optimization of cane transport can potentially bring a major decrease in production costs, which is a great opportunity for the sugar industry in Rwanda. 1.2 Problem definition Within the project ‘Sugar: make it work’, Milan Innovincy and the WUR work on both crop development monitoring and information to support sugar cane logistics. This research intents to investigate the transport component of the sugar cane value chain. More efficient transport would contribute to reducing sugar production costs in Rwanda. When the components of the supply chain have been researched, the production process can be optimized by scheduling the harvest and crop cycling in line with factory or even market demands. The climate conditions in Rwanda are of major influence on the sugar cane production (Fauconnier, 1993). The climate influences the crop itself; also cultivar, the crop cycle and the harvest cycle are all a function of the environment. The weather in combination with the geographic location of the fields is also influencing transportation. The sugar cane fields are located close to the Nyabarongo River (Figure 1). This river is prone to flooding and the roads connecting the fields with the factory are therefore not always transitable. Furthermore, the road network is in suboptimal conditions. The fields are hard to reach, even under normal conditions. The areas on the west and south side of the river are the hardest to access, since the road network is less dense on those sides (Figure 1). In addition there are only few options to cross the river. However, transport over water seems to provide a feasible option that has hardly been explored to date. Most of the sugar cane fields are located close to the river, so using the water network could be a good alternative. Three main issues that transport has to deal with are: factory constraints, field conditions and network conditions. The first factory constraint is the demand of the factory. The mill needs enough cane so they can process 24 hours a day during the harvesting season. Storing capacity and circumstances have to be kept in mind. For instance, storage over longer periods (24 hours), affects the quality of the sugar cane juice. Next, the transport is subject to the field conditions. The cane must be mature in order to achieve highest recovery rates. In a climate like Rwanda, the cane is not easily overmature, which means that the harvest period can be spread over a longer period (Fauconnier, 1993). This is very convenient for planning purposes. The exact field conditions are of major importance; crop age, crop cultivar, area and the status of the crop are only some examples of essential information. Last the transport network conditions have an important influence. The condition of the road network partly depends on the weather conditions and the river is also subject to weather circumstances. The purpose of this research is to develop and implement a method for assessing river and road transport options and deciding about the most efficient transport for fields delivering to the KSW mill. 3 1.3 Research objective The main objective of this research is optimization of sugar cane transport in Rwanda by assessing different transport modes conditional to factory constraints and field and network conditions. This will be achieved by answering the following research questions: Q 1: What is the current situation and what are the; factory constraints field conditions network conditions to be considered in optimization of cane transportation in Rwanda? Q 2: Which optimization of network method is suitable for this cane transportation optimization problem? Q 3: Which variables of the transport network can be used for predicting the costs of transport over the road network? Q 4: Which practical conditions are important to be considered for implementing the results of this research in KSW circumstances? 4 2 Current situation In order to explore the possibilities of the optimization of the cane transport, a detailed overview of the current situation is necessary. Based on data provided by KSW and Royal Haskoning DHV (RHDHV), and a visit to Kigali, the three main factors affecting the transport optimization problem are described in this chapter. 2.1 Factory constraints The operational period of the factory is 9 to 10 months every year. The heavy rain season in the months April and May make it impossible to keep the harvesting, transportation and factory going. Besides those two months, the factory is occasionally shut down for some days for example during heavy rainfall outside the main rain season and during public holidays. Otherwise, the factory operates twenty-four hours a day, seven days of the week. During the operational period the rate of sugar cane processing is virtually constant (M. Thiru, personal communication, December 8-12, 2015). Ideally, the factory would run at full capacity, which requires a constant supply of cane each day. The KSW factory can process 600 tonnes of sugar cane per day (S. Jayakumar, personal communication, November 10, 2015). Currently, most of the sugar cane is transported from the field to the factory by trucks. The capacity of these trucks varies from 5 to 12 tonnes. With an average capacity of 8 tonnes, this implies that over 60 times a day, a truck brings sugar cane from the field to the factory (KSW, 2015b). Planning of cultivation, harvesting and transportation is managed at the factory in Kigali. Harvesting is scheduled based on crop age, optimal harvesting period and mill demand. Transport is scheduled, based on the actual harvest (S. Jayakumar, personal communication, December 8-12, 2015). 2.2 Field conditions The sugar cane fields are located in the marshlands of the Nyabarongo river. Due to this location, the area is prone to flooding (Royal Haskoning DHV, 2015). Since sugar cane is not thriving well in the swampy lands along the river, the groundwater management in this area is to be improved. Rehabilitation of former drainage routes and old river courses makes it possible to drain the flood plains much faster. The improved water management infrastructure will eventually account for the reclamation of an area of 1.500 ha. Currently, a third of this area is reclaimed of which 82% is in use as sugar cane plantation (“Kabuye Sugar award winning”, 2015; “The Sugar: Make it Work Project”, 2016). Figure 2 shows the difference of the area close to the Ruliba Bridge, near the city centre of Kigali. The area has changed from papyrus to sugar cane between July of 2014 and September 2015. The location of this site is indicated in Figure 3. 5 Figure 2: Aerial imagery of an area near de Ruliba bridge with mainly papyrus in July 2014 (left) and sugar cane cultivation in preparation in September 2015 (right). Source: Google Earth. Currently, KSW has access to 3773 ha of land on which sugar cane is cultivated. This area is divided in the fields leased by KSW and fields cultivated by out growers (Figure 3). Figure 3: Sugar cane fields cultivated by KSW and out growers Close to 65% of the 3773 ha is leased and cultivated by out growers (KSW, 2015a). 6 Harvesting these sugar cane fields is the responsibility of the out growers. Transport of the sugar cane from those fields to the factory is arranged by KSW. The other 36% of the sugar cane fields is leased by KSW and the people working on those lands are employed by KSW. KSW can manage the workforce on these fields more flexibly if necessary. For example, when due to circumstances such as flooding, the sugar cane fields have to be harvested as soon as possible or fields cannot be harvested at all. The crop variety, crop cycle and crop age for the KSW fields is documented, which makes it possible to time the harvesting of each field at the most optimal moment. Crop information is a key factor in efficient chain supply management. The sugar cane fields are divided in circles, compartments and zones. A zone consists out of several sugar cane plots or fields. Every circle consists out of several zones and the compartments can consist out of multiple parts of different zones and circles. The data is based on the subdivision in circles and zones, but in practice, the division in compartments is mostly being used. The crop cycle varies between plant and different ages of ratoon. Due to the climate in Rwanda, planted sugar cane takes around 21 months to mature. Ratoon crops take between 16 and 18 months to mature (S. Jayakumar, personal communication, December 8-12, 2015). Ratoon crops are grown out of stubbles of the previous crop. This is a lucrative way of growing sugar cane, since the investments have to be done for another crop cycle are much lower than those of replanting. Ratoon crops yields slightly less sugar cane per hectare compared to planted sugar cane (James, 2008). With the combination of crop variety, crop cycle and the crop age, the expected month of harvest can be estimated. Figure 4 presents the month and year of harvest for the sugar cane fields of which the information is complete. Comparison of Figure 3 and Figure 4 show that the information of the sugar cane fields cultivated by the out growers is not complete. Furthermore, the crop data is outdated. Figure 4 shows fields of which the date of harvest has already passed, which means that either the fields are empty, or more likely, new sugar cane is planted or a ratoon crop is grown on these sites. 7 Figure 4: Expected month of harvest of sugar cane fields In general, each hectare of sugar cane is claimed to yield 100 tonnes of fresh cane stalks (S. Jayakumar, personal communication, December 8-12, 2015). For the area which is in use at this moment, this means that the area would yield approximately 3.77 × 105 tonnes of sugar cane. With an average growing season of 18 months, this means that each year, about 2.52 × 105 tonnes can be harvested. Such productivity exceeds the capacity of the mill and therefore KSW plans to expand the factory (S. Jayakumar, personal communication, December 8-12, 2015). 2.3 Network conditions The transport network is divided into the road network and the river. Currently, the road network is being used most frequently. The roads around Kigali can be divided into tarred and very well accessible roads and untarred or dirt roads on which driving is more difficult and driving speed is limited. About 50% of the route the trucks travel is untarred. These untarred roads are mainly located close to the fields and with that close to the river (Figure 5). Accordingly, those roads are prone to flooding. A flooded road is even harder to traverse and after flooding the road condition is worsened. Keeping the untarred roads in the floodplains in good condition is costly and is not considered a main priority of KSW (S. Jayakumar, personal communication, December 8-12, 2015). 8 The period between harvesting and milling the sugar cane is at most 72 hours. Bringing the maximum time back to 36 hours increases the quality of sugar with 10% (S. Jayakumar, personal communication, December 8-12, 2015). Transportation is mainly done by truckers who aren’t employed by KSW. The cost of transport is based on the length of the route the trucks have to cover and the weight of the sugar cane which is being transported. In the year 2015, a total amount of 592.319.822,- RWF is spend on the transport, which an average of 5393,- RWF per metric ton of sugar cane (KSW, 2015c). KSW itself owns seven trucks which are mainly used to pick up the sugar cane from the most difficult to reach places (S. Jayakumar, personal communication, December 8-12, 2015). Figure 5: Condition of the road network around the sugar cane fields and the KSW factory The second part of the transport network is the river Nyabarongo. The river flows through the sugar cane area over a length of 85 km. The river is 30 to 50 meters wide and the river depth varies from 1,5 meter in the bends in the dry season to up to 6 meters in the middle of the river during the rainy season. Half way the sugar cane area, the river confluences with the Akanyaru river. The Nyabarongo river is rain-fed and therefore a dynamic river which erodes mostly in the outer bends. Downstream, the river is eroding less, due to the confluence with the Akanyaru river, which is a perennial river. Although the bends of the river are eroding over the years, the straight sections of the river have remained stable over the last years (de Boer, 2016). 9 Part of the sugar cane fields is not accessible by road or located at the south side of the river. Currently, 35% of the sugar cane has to cross the river. The harvested sugar cane of these fields is transported over small distances with boats across and over the river. This small scale river transport is arranged by local out growers. These boats carry on average 4 tonnes of sugar cane per trip and they are mostly moved by manpower. A trip of 12 km down the river takes about 4 hours and the return journey, which is upstream, takes some 7 hours on average (S. Jayakumar, personal communication, December 8-12, 2015). In order to fill one truck, two or three boats trips are necessary. In this way transportation over the river is very time consuming. Furthermore, the current of the river and the fact that most of the boats don’t have an engine make these river trips very dangerous. In the past several fatal accidents have occurred (Bucyensenge, 2015). 10 3 Methods Transportation of the sugar cane from the fields to the factory is done in multiple phases. First, harvested sugar cane is stacked at loading points. From those loading points, the sugar cane is transported by truck to the factory. When the sugar cane fields aren’t accessible by road, the cane is transported over the river by boats and loaded onto the trucks at landing points. Currently, only when the transport is almost impossible by truck, the river is being used. This research assesses the possibility of transport over the river in order to reduce the total transport costs. 3.1 Conceptual Model This optimization problem is presented in the conceptual model of Figure 6. Harvested sugar cane is stacked at the assigned loading point. At the loading point, the cane is loaded on the barges and transported over the river to the most optimal landing point. At the landing point the cane is loaded on trucks and transported to the KSW factory. Figure 6: The conceptual model illustrates the two options transport by truck over road or a combination of barge and truck to the factory The conceptual model indicates two factors; the location of the loading points and finding the least-cost route from loading point to the factory. Lastly, the economic feasibility of implementing river transport is calculated. 3.2 Loading points 3.2.1 Methods The location of a suitable loading point is determined by several factors. First, a loading point should be within one km walk of the fields it serves. Harvested sugar cane is transported by foot to the loading points, therefore one km is the maximum distance (S. Jayakumar, personal communication, December 8-12, 2015). Currently, loading points have to be close to a road, since the cane is transported by trucks. The new loading points have to be on the river banks and if possible near a road. The second important factor in assigning locations of the loading points is the river. Due to the dynamic character of the river, the river course tends to change over the years. The bends in the river are the most dynamic parts of the river, which means that the straight sections of the river are most suitable as location for the loading points. The future meandering of the river is hard to predict, but satellite imagery of previous years shows the dynamics and the stable sections of the river. 11 The barges that will be operating on the river will be around 30 metres long, which makes a loading point in a river bend close to impossible. Furthermore, the depth of the river has to be deep enough at the river banks at the locations of the loading points during the harvest season. Therefore, the parts of the river which are suitable as a location of a loading point, have to be chosen at straight sections of at least 50 metres long and the minimum water depth needs to be 2 metres. Detailed information of the river is not yet available and will be researched in the future. Due to the specific requirements of the river, it is hard to automate the process of finding the right location of the loading points. Based on satellite images, the current course of the river and the range of the loading points, the loading points were assigned manually. Since landing points are also deemed to serve as loading points, there are no new loading points within 1 km of landing points. 3.2.2 Implementation The data used for finding the locations of the landing and loading points are presented in Table 1. A shapefile with the geometry of the river was also available, but it appeared to be outdated. For that reason, the section of the river that flows through the sugar cane fields was manually digitized based on satellite images and the geometry of the sugar cane fields. Table 1: Used data for locating loading points File Source Shapefiles Sugar Cane Fields KSW Barge landing map (PDF) KSW Satellite imagery Google Earth The locations of the landing points derived from the barge landing map were digitized as landing points. These locations were visited during the field work and were found to be feasible. These locations are easily accessible and there is enough space to develop these sites as landing points. The loading points were newly created. The first reason for this was that the current loading points are only located near fields that aren’t or very hard to access by road. The optimal location of loading points is likely to be different when all fields need access to a loading point. Furthermore, the current loading points are designed to handle boats with a length of a mere 7m. In the future the length of the barge will be around 30m, which makes some locations unsuitable in the future. Both the fields on the north and the south side of the river needed loading points within 1 km distance from fields. Therefore, a division was made between the sugar cane fields located north of the river and the fields located south of the river. The landing points are easy accessible from both sides of the river since they are close to a bridge. Creation of loading points started at each of the four landing points. In order to indicate the range of all landing points, a buffer of 1 km was created around the four landing points. Locating the first loading point started at the landing point 4 (Figure 1). The location of the first loading point upstream from the landing point was derived by the steps in Figure 7. First the centroid of each field was computed. By visual assessment, the centroid closest to the buffer of the landing point and the most far away from the river is selected (2a). A buffer of 1 km was 12 created around the selected centroid (3a). Close to the intersection of the sugar cane fieldcentriod buffer and the river, based on the requirements of a loading point, a suitable location for the first loading point was chosen (4a). The next loading point was determined by creating a 1 km buffer around this first loading point (5a) and repeating the previous steps (2b-4c). This procedure is followed for each sugar cane field of both sides of the river. Figure 7: Creation of new loading points along the river 3.2.3 Assign sugar cane fields to loading points Data of the sugar cane fields was provided by KSW in different formats. The geometry of the fields was presented in separate shapefiles for each zone. Data such as crop age, crop type and owner of the land were available in excel files. Based on overlapping attributes these data was combined in to one dataset. Additional attributes, such as expected month of harvest were calculated from these data. The fields were assigned to a loading point based on Euclidean distance, i.e. the fields were assigned to the nearest loading point at the same side of the river. Landing points were assumed to serve as loading points for fields within 1 km distance. Next to river side and the distance from the sugar cane fields to the loading points other factors influence the optimal loading point for each field. For example, crop condition can be a key factor in the accessibility of the landing and loading points. Passing recently harvested fields is different from walking to a field with 18 months old sugar cane. Unfortunately, 13 because dynamic and detailed information were not available of all fields, it was not possible to use this information. 3.3 Optimal route to the factory The next step of this optimization problem is calculating the optimal route from each landing and loading point to the factory. 3.3.1 Dijkstra’s algorithm The optimal route is calculated by a least cost path algorithm based on the costs of transport. Of all algorithms used to compute the least cost path, the classical Dijkstra’s algorithm is used the most (Yu, 2003). This algorithm is widely implemented in several route planning applications (Delling, 2009). When computing the least-cost path in a road network, Dijkstra’s algorithm performs the calculations the fastest (Deyfrus, 1969). Dijkstra’s algorithm was developed by E. Dijkstra and published in 1959 (Dijkstra, 1959). The second problem addressed in his paper ‘A Note on Two Problems in Connexion with Graphs’ is finding the path of minimum total length between two given nodes. Input of this algorithm is a graph consisting out of nodes and edges with a weight attribute. The algorithm starts at the source node of which the cost is set to 0. First the neighbouring node of which the edge has the smallest value, i.e. the least-cost path, is visited. The weight of this edge is assigned to this particular node. Next the neighbouring node of which the edge has the second lowest value is visited. When all neighbouring nodes are visited, the algorithm starts again at the node with the lowest value and visits the neighbouring node with the lowest edge weight. If this node has already been visited and the weight assigned to this node is lower than the total weight of the edges from the source node, the weight of the node stays unchanged. However, if the total weight of the edges from the source node is lower compared to the weight of the node, this new weight is assigned to the node. This procedure continues until the destination node is reached and the total weight of the edge from the source node is smaller or equal to the total weights of any other node. The nodes which are part of the path of minimum total length are listed as the least-cost path. (Dijkstra, 1959). The result is the least-cost path from the source node to the destination. Several studies show that Dijkstra’s algorithm performs the best when computing the leastcost path with a network with nonnegative costs (Cherkassky, 1996; Dreyfus, 1969; LaValle, 2006; Zhan, 1998). This algorithm is especially suited in situation where a one-to-one leastcost path has to be computed (Zhan, 1998). This is mainly due to the fact that the algorithm can stop when the destination is reached without visiting all nodes in a network. For large networks and relative close proximity of the source and destination node, more efficient methods exist (Zhan, 1998). However, Dijkstra’s algorithm was deemed suitable for the relatively small network and well separated nodes used in this thesis research. Dijkstra’s algorithm is widely implemented in programming languages like Python and R, which make it very accessible to use. For both Python and R, the package igraph provides an implementation of Dijkstra’s Algorithm. Next to Dijkstra’s algorithm, also Johnson’s algorithm and the Bellman-Ford algorithm can be used when calculating the shortest path (Csardi, 2006). The Bellman-Ford algorithm and Johnson’s algorithm only out-perform Dijkstra’s algorithm when the graph has negative edge weights, and therefore Dijkstra’s algorithm was chosen to compute the optimal path to the factory. 14 3.3.2 Pre-processing In order to perform the least-cost path analysis, a transport network including weights is needed. The computation was done twice. The first time the current situation was simulated and the transport network consisted of the road network provided by KSW and the roads from the new loading points to the current road network, which were added based on aerial imagery. The second time the least-cost path analysis was conducted, it was based on the total transport network including the river. This second run calculated the optimal routes from each loading point to the factory. The aim of this research is to find to optimal routes, therefore the weight on which the leastcost path analysis was done were the costs of transport. The costs of each network segment were calculated. These costs are the main component of the total transport costs. The costs of the road segments were derived from the field visit and data provided by KSW and the costs of river transport were derived from RHDHV (Boer, 2016). The analysis was done from each loading point to the KSW factory, this means that the costs of collecting the sugar cane at the loading points were not included in this analysis. These costs differ between the two transport modes, because the sugar cane transported by barge has to be collected at one of the loading points at the river bank and the sugar cane transported by truck can be loaded in the truck next to the field. Although those costs are supposed to be higher when using the river transport, these differences are deemed to be negligible when comparing total costs. Transhipment costs can be implemented when modelling a multimodal network by assigning labels to each edge (Delling, 2009). Since the transhipment component is such a small component of the total transport costs this is also deemed negligible. Furthermore, in this particular case, the transhipment costs are unknown. Therefore, the costs of transhipment between the transport modes are not included. 3.3.2.1 Road transport The road network is provided by KSW and originates from the Rwanda Natural Resources Authority. The road network part of the attributes of this data is the condition of the roads. The costs of the road segments were calculated based on the current costs of transport provided by KSW (KSW, 2015c). The slope of the road segments was obtained for the total road network. The relation between the two variables, the condition and the slope of the road segments, and the costs of the road network was being researched using regression analysis. The costs assigned to each network segment are done based on GPS-tracks measured during the field work. At the factory a GPS-tracker was placed on the trucks which saved a waypoint every 30 seconds. The trucks tracked with the GPS-trackers were selected based on the location of their destination. Ten different circles and compartments were visited during the fieldwork (Table 2). Ten trucks were tracked of which 8 GPS-tracks could be used for the analysis. KSW provided data on the costs of transport of the year 2015 in Rwandese Francs (RWF) per metric ton (MT) sugar cane (KSW, 2015c). Costs of the transport from the Ntarama landing point and from Aja Paraya weren’t available, since those fields had not been harvested in 2015 (Table 2). 15 Table 2: Starting point and costs of GPS-tracked routes in Rwandese Francs per metric ton Destination DR2 5 x Costs per MT in RWF 7245 Rwesero 1 DB 3 GPS Failure 4772 Mwendo 3 DB 3 x 4082 Zone 24 BCR 2 x 3852 Ruramba 4 DR2 4 Accident 6382 CS 14 x 3565 EF2 6 x 6440 Ntarama NA 7 x NA Burema EF2 9 x 5807 NA NA x NA Rugalika 2B Nzove Nyarubande 2 Aja Paraya Circle Compartment Results Measurement The GPS-data consists out waypoints measured every 30 seconds of the tracks. Each track was divided in the outward journey and the return. Of every outward and return journey line segments were created between the GPS-points. The costs of the track divided by the number of segments of that track was assigned to each segment of 30 seconds. Based on that, the cost per km of each segment was calculated. This resulted in an overview of the more and the less expensive parts of the route ( Figure 8). The map shows that the road segments close to the river are more costly to travel compared to the roads towards the city centre of Kigali and the KSW factory. 16 Figure 8: Costs per road segments in RWF of GPS-tracks To extrapolate these costs to the total road network a function based on two variables was developed. The first variable which is likely to influence the costs of the road transport is the surface of the road. The tarred roads are very well accessible. The untarred roads on the other hand are very hard to access. Details about the road network surface are included in the provided road network and by visual assessment of Google Earth, the surface of the routes tracked by GPS is assigned to those tracks as an attribute. The second variable which is likely to influence the costs of the road transport is the slope of the road. Roads with a very steep slope are harder and therefore costlier to travel than a gradual or no slope at all. Based on the Digital Elevation Model (SwedeSurvey, 2010) of the area the slope of each segment is calculated (Figure 9). The location of the roads is influenced by the slope of the area, the height differences over the roads is low. The R script of this computation can be found in appendix A. 17 Figure 9: The slope of the road segments in % on the DEM of the area The relationship between the two variables and the costs of the road transport is tested in a linear regression analysis. The regression equations were used to calculate the costs of the total road network. 3.3.2.2 River transport The costs of transport over the river are derived from the pre-feasibility study by RHDHV (Boer, 2016). The pre-feasibility study is divided in two phases. The first phase is based on the current capacity of the sugar cane fields. The second phase is an estimation based on further development of the sugar cane area and therefore further expansion of the barge system (Boer, 2016). Therefore, the costs of phase 1 are used in this research, since these concern the current situation. An estimation of the operational costs of the barges of one year is included in their report and presented in Table 3 (Boer, 2016). Table 3: Yearly operational costs of river transport Operational Costs (rounded on USD 10.000,-) in USD Staffing 150.000 Fuel and power 100.000 Maintenance 50.000 18 Total operational costs 300.000 The estimation of the operational costs is based on several assumptions. Firstly, there are 3 barges with a capacity of 112 MT. The calculations are done assumed that the barges are loaded to their full capacity at any time. The second assumption is that the 3 barges in total, can cover a distance of 80 km per day. Furthermore, the barge will only operate in harvest season, a year was estimated at 286 operating days. The estimated costs of transporting a metric ton sugar cane per km by barge is 29,13 Rwandese Francs (Table 4). Table 4: Operational costs of river transport Operational costs river transport in RWF Per Year 21.847.500 Per Day 7.645.860 Per Metric Ton Per MT/km 2.272 29 With this average costs per km, the costs of each river segment was calculated and added as an attribute to the transport network. 3.3.3 Implementation The shortest path analysis was done on two transport networks. First, a simulation of the current situation only assessed the road network. The optimal route when including the river as transport possibility is calculated after this. The costs of transport of the different transport network segment are added as an attribute to the shapefile and used as weight for the shortest path analysis. The implementation of the shortest path analysis was done in R using the packages shp2graph (Lu, 2014) and igraph (Csardi, 2006). The full script of the analysis can be found in appendix B. In order to conduct the shortest path analyses, the format of the network had to be converted from a SpatialLinesDataFrame to a graph. With the function readshpnw from the package shp2graph the SpatialLinesDataFrame is split in an edgelist, a nodelist and an attribute table of the edgelist. The function nel2igraph produces an igraph out of the edgelist, the node list and the column of the attribute table which contains the cost per segment (Lu, 2014). The result is an igraph of the transport network with the costs of each segment as weight of the graph. Both the transport network containing the roads and the transport network including both the roads and the river were converted to graphs. For both networks, the least-cost path was calculated with the function get.shortest.paths from the package igraph (Csardi, 2006). This function calculates the shortest path from the graph to perform the analysis on, the edgeID of the starting point of the path to be calculated, the edgeID of the destination of the path, and the weight on which the analyses in being done and the algorithm used in this function. The edgeIDs of the starting points are the edgeIDs of the landing and loading points (appendix C). The edgeID of the destination is the edgeID of the KSW factory. When creating the graph, the cost of each segment is set as the weight edge attribute. 3.4 Economic feasibility Implementing the river barges in the current transport system needs capital investment. Calculations of the reduction of transport costs in the optimal routes analysis were based on 19 the operational costs of the river transport. The capital investment was not taken into account in this analysis. Therefore, based on an estimation of the yearly possible reduction the breakeven point of the yearly reduction and the capital investments is calculated. 3.4.1 Capital investment The capital investment is an estimation derived from the pre-feasibility study of RHDHV. Due to uncertainties in this stage of the project, a lower and an upper value of the investment costs of the project are given (Table 5). The investments costs consist of the construction of the barges including a gantry crane and the construction of landing points (Boer, 2016). Table 5: Capital investments of river transport Phase Capital investment Phase 1, lower value 1.490.000 USD Phase 1, upper value 2.460.000 USD 3.4.2 Breakeven analysis Based on the estimation that on average, the sugar cane can be harvested after 18 months and the average production of one hectare sugar cane is 100 tonnes, the yearly transport costs are calculated. Of all the sugar cane fields, the average production and the estimate of yearly production is calculated (Figure 10). For both the current transport costs as the costs of the optimal routes, the transport costs for each field are calculated. The total amount spend on transport in the current situation is compared to the total costs when using the optimal routes. This results in an estimate of the possible yearly reduction of transport costs. Figure 10: Calculating yearly reduction of transport costs The breakeven point was calculated by dividing the capital investments (Table 5) of the river transport system by the yearly reduction of transport costs. 20 4 Results 4.1 Location of loading points In total 42 points along the 85 km that the river flows through the sugar cane fields were created. The four landing points, near the Ruliba Bridge, the Confluence with the Akanyaru river, at the Kanzenze Bridge and downstream at the beginning of Phase 2 were copied from the barge landing map (River Transportation, 2015). Both at the north and the south bank of the river 19 loading points are created (Figure 11). Figure 11: Location of landing and loading points 4.2 Costs of different transport modes 4.2.1 Transport by road The relationship between the costs and slope is tested in a linear regression analysis. The tarred and untarred road segments are separated from each other. From both the scatterplots it is hard to derive a clear relationship between the costs and the slope of the trucks (Figure 12). 21 Figure 12: Scatterplot of the relation between the slope in % and the costs per km in RWF for tarred and untarred roads The statistical results of the regression analysis are presented in Table 6. Both the data on the tarred road segments as the data on the untarred road segments show a negative relation between the costs of the road segments and the slope. The standard error of the coefficient shows the average difference between the predicted value by the estimate of the coefficient and the actual data. The adjusted R² shows the percentage of the costs that can be explained by the slope of the segments. Less than 1% percent of the costs can be explained by the slope of the road segments. Table 6: Results of regression analysis Intercept Coefficient Std. error coefficient Adjusted R² Tarred 176,217 -4,554 1,834 0,013 Untarred 428,506 -0,979 1,906 -0,001 The results of this statistical analysis show that the slope is cannot be used as a variable when predicting the costs of the road segments. Firstly, the relation between the slope and the costs was expected to be positive. The cost of road transport was expected to increase when the slope of the road increased. In contrast to the expectation, the regression shows a negative relation between the slope and the costs. Furthermore, the adjusted R² shows that at most 1% of the costs can be explained by the slope. Therefore, the costs of the road segment are calculated based on the mean costs of the surface of the road segments (Table 7). Table 7: Costs of road transport per km in RWF Costs per KM in RWF Tarred Untarred 4.2.2 85,5 215,5 Transport by river The costs of transport by river were derived from the feasibility study of RHDHV. The river is separated in different segments between the different landing and loading points and to all segments the same costs per km is assigned. Table 4 presents the costs per metric ton per km when the sugar cane is transported over the river. 22 4.3 Optimal Route 4.3.1 Optimized route on the road network The GPS-tracks and the optimized route on the road network of these routes are presented in Figure 13. For these 6 starting points, the optimized route is almost similar to the GPS-tracks. Only at Rugalika 2B, the first part of the route is different and the trucks coming from Nyarubande and Burema follow a slightly different route close to the city centre of Kigali. The differences of the first part of the route of Rugalika 2B is due to the fact that this part is manually added to the road network based on aerial imagery and the route the GPS-tracks shows is not included in the road network. The different routes in the city centre of the routes coming from Nyarubande and Burema could be explained by the fact that these are very well maintained untarred roads in the centre of Kigali and the optimized route is following the tarred roads. Figure 13: Difference between current route and the optimized route on road network. The costs and the length of the current tracks and the optimized route are presented in Table 8. The costs and length of the current tracks are originating from the data provided by KSW. Five of the six simulated tracks have a higher costs compared to the current situation. Comparison of the costs of the currents routes from the 42 landing and loading points to the simulated routes shows that on average the simulated costs are 11% higher than the original costs. Although the lengths of the tracks do not differ much on the map, the numbers in Table 8 show some significance difference. 23 Table 8: Difference in costs and length between current and optimized route on the road network Name Current Costs in RWF 1782,50 Current Length in KM 15,00 Optimized Costs in RWF 2186,02 Optimized Length in KM 16,10 Costs current optimized -403,52 Zone 24 1926,00 15,55 2071,65 17,93 -145,65 -7,56 Mwendo 3 2041,00 17,18 2235,54 18,11 -194,54 -9,53 Rugalika 2B 3680,00 59,00 4849,37 33,12 -1169,37 -31,78 Nyarubande 2 3220,00 39,00 3996,28 34,72 -776,28 -24,11 Burema 2990,00 29,00 2481,96 28,47 508,04 16,99 Nzove 4.3.2 in % -22,64 Reduction of transport costs The optimal routes from all the 42 landing and loading points are presented in Figure 14. The most striking result from the shortest path analysis based on the costs of the road segment is that the optimal route from each landing and loading point goes over the river to the landing point near the Ruliba Bridge. From that point the cane is transported over the road since the KSW factory is not located along a navigable river. Figure 14: Optimal routes on road and total network from all landing and loading points to the factory The costs of the calculated optimal routes compared to the current transport costs are on average reduced by 40% of the current costs. Comparing the costs of transport calculated by the least-cost path analysis of the total network with the least-cost paths of the road network, 24 the costs can be reduced by 45% on average. The 5 routes with the highest possibility of reduction are presented in Figure 15. The percentage showed in the map is the percentage of the current transport costs which can be reduced when using the optimal route. For this top 5, the costs could be reduced with more than 50% of the current transport costs. The top 3 originates from loading points on the south side of the river. Figure 15: Optimal routes and reduction of current routes in % Table 9 shows the costs of the current transport, the optimal route by road, the optimal route using the complete transport network and the reduction of the optimal route compared to the current situation in percentages. The costs of the optimized routes of the road network are on average an overestimation of the current transport costs. This also results in higher reduction rates when comparing the costs of the optimal routes. Therefore the reduction of the optimal routes compared to the current transport is presented in the last two columns. The top 5 of routes on which the most can be reduced is therefore based on the last column. 25 Table 9: Costs of transport routes in RWF Name Loading Point Costs Current New 12 Zone Ruramba New 10 Zone Mwongo Nyarubande 4 Zone Nyarubande New 9 Zone Mugina Rwesero 3 Zone Rwesero 4.3.3 Difference Difference Difference Optimal Route total network 1448,37 Current –Road network Road – Total Network Current- Total Network 3191 in RWF Optimal Route road network 3421,38 -230,38 1973,01 1742,63 54,61 3622,5 4516,71 1703,41 -894,21 2813,30 1919,09 52,98 3422,5 3865,70 1646,30 -443,20 2219,40 1776,20 51,90 3680,00 4849,37 1773,99 -1169,37 3075,38 1906,01 51,79 3047,50 3008,13 1476,27 39,37 1531,86 1571,23 51,56 Efficient use of river transport Although transport from all sugar fields could be more efficient by using the barges on the river, the capacity of the barges cannot transport all harvested sugar cane of one day. When planning the transport, the tracks on which the most money can be saved should be done by barge and the relative less costly tracks have to be transported by trucks from field to factory. Figure 16 presents an overview of the sugar cane fields to be harvested in April 2016, the according loading points and the current and most optimal route. The current route is classified according to the amount which can be saved when using the river transport instead of the current transport mode. On the transport of the cane coming from the loading points Rwesero 3, New 9 South and New 10 South more than 1000 RWF per MT/km can be saved. The reduction of the transportation costs of the sugar cane originating from the fields near the loading points downstream the river, at the Kanzenze Bridge, New 2, F07 and Phase 2 is at most 500 RWF per MT/km. In order to make the most efficient use of the barge system, the transport routes with the highest reduction rate should be prioritized when changing to river transport. 26 in % Figure 16: Reduction of transport routes of sugar cane to be harvested in April 2016 4.4 Feasibility The capital investment was not taken into account in the least-cost path analysis. Therefore, based on an estimation of the yearly possible reduction the breakeven point of the yearly reduction and the capital investments is calculated. Table 10 presents the yearly transportation costs of the current situation and the optimal route, when using the river barges. The possible yearly reduction is calculated as the difference between the transport costs. Table 10: Yearly transport costs and possible reduction in RWF in USD (rounded on 10.000 RWF) (rounded on 10.000 USD) Transport costs Current Situation 420.240.000 550.000 Transport costs Optimal Route 276.210.000 360.000 Reduction 144.030.000 190.000 Table 11 shows the breakeven points of the capital investments for each phase. The estimation of the capital investments is given in an upper and lower value due to the uncertainty in this stage of the project. Phase 1 is based on the current capacity of the sugar cane fields, therefore, the costs of river transport used in the shortest path analysis were 27 based on the operational costs of phase 1. Based on these operational costs, the breakeven point of phase 1 will be reached after 8 to 13 years. Table 11: Breakeven point of capital investment Phase Phase 1 lower value Phase 1 upper value Capital investment Yearly Reduction Breakeven point 1.490.000 190.000 8 years 2.460.000 190.000 13 years 28 5 Discussion This chapter discusses the results of this research. First the outcomes of the second chapter are reviewed. Similarities and differences between the situation in Rwanda and examples in literature will be discussed. Furthermore the results on location of the landing and loading point, the costs of the transport network, the optimal route and the feasibility of river transport will be discussed. 5.1 Current situation The current situation of the sugar cane production is described based on the data provided by KSW and a visit to Rwanda in December 2015. Currently, the sugar cane is processed within 72 hours after harvesting. Reducing this time frame to 36 hours is possible by implementing the barge system. This would increase the cane quality with 10% (S. Jayakumar, personal communication, December 8-12, 2015). According to several studies (Fauconnier, 1993; James, 2008), the quality increases with the speed of the process. Ideally, the sugar cane needs to be processed within 9 hours after harvesting. In that way, the quality of the cane is the most optimal. At Kabuye Sugar Works, processing the sugar cane within this time frame is impossible. Another reason why reducing the processing time from harvest to processing is not one of the major focuses in Rwanda could be the climate conditions. According to Fauconnier (1993), in a relative cold and stable climate like the climate of Rwanda, the quality of the sugar cane is not decreasing as fast as for example in Brazil. Furthermore, compared to other studies and cases (Higgins, 2003; Grunow, 2007), both the urge for constant milling at the factory and the speed of the total process from harvest to processing are less important in Rwanda. Although the factory of Kabuye Sugar Works tends to process 24/7, this is not always possible and this is accepted by KSW. In Rwanda, there is almost no focus on reducing the speed between the harvest of sugar cane and the processing of cane. Next to this, over 60% of the sugar cane processed by the KSW factory is originating from out growers fields. In contrast to the sugar cane inventory on the fields cultivated by KSW, the crop data on the out grower fields is far from complete. These data is essential when managing planting, harvesting and transport. A good relationship between Kabuye Sugar Works and the out growers is therefore an important factor when optimizing the total supply chain. Especially when not the whole supply chain is owned by one company, good communication is key (Higgins, 2007). Several studies show the importance of a holistic approach when it comes to optimizing the supply chain (Higgins, 2003, 2006a,b; Le Gal 2009; Lejars 2008). Last, socio-economic factors play a role in the production and transportation of sugar cane. When visiting the people who currently transport little amount of sugar cane by boat, their main concerns were their safety and their jobs. The current way of transporting cane over the river can be dangerous due to the strong current of the river and the manual handling of the relative small boats. In the past, some fatal accidents have happened. The safety of river transport would be assured when implementing the barge system by RHDHV. Furthermore, it is important that no jobs will be lost when implementing the river transport. Increasing employment is a major component in ‘The Sugar; Make it Work’-project (“The Sugar: Make it 29 Work Project”, 2016). Studies of Higgins (2007) and Le Gal (2009) show that the socioeconomic factors play a major role in the sugar cane production. 5.2 Landing and loading points The location of the landing points were copied from the already existing landing points. KSW assigned these locations also as future landing points and these points were visited and visually assessed by the consultant of RHDHV during the field visit. According to RHDHV, these locations are suitable to develop a landing point. The landing points will be permanent and require capital investment and development. Further research on those exact locations is therefore recommended. Furthermore, the optimal path analysis showed that for every field, the landing point at the Ruliba Bridge is the most optimal landing point to use (Figure 14). Developing the three other landing points might not be necessary. The location of the loading points is derived from a manual procedure. This procedure based on several assumptions on the character of the river and the main factor was the distance of from the fields to either a landing or a loading point. Visual assessment during the field visit and research of previous years are fragile arguments to base the locations on. Therefore, further research on the river dynamics should be conducted before the final locations of the loading points is defined. For the four landing points and even more for the 38 loading points the number of points also needs to be discussed. As said, for every loading point, the landing point at the Ruliba Bridge is part of the most optimal route to the factory. A result from the optimal path analysis could be that other landing points are not necessary with the current area of sugar cane fields. Also, the number of loading point is with 19 on each side of the river, a bit high. From some fields, the sugar cane will be transported by foot to the loading points, while others could better be transported by truck to the loading points. However, this means that the sugar cane has to be transhipped twice during the total transportation. Neither the costs of transhipment nor the transport from the fields towards the loading points are included in the analysis. Decisions on how to arrange the transport to the loading points and data on the costs of this transport and transhipment should be done prior to further decision making. The uncertainty of the final amount and location of the landing and loading point does not influence the result of the analysis, since the optimal route of all locations go through one single landing point. 5.3 Costs of transport network The costs of the road transport are based on the surface of the road (Table 7). The costs of the road network were calculated based on the facts whether the road was tarred or untarred. It should be noted that a single variable to make an estimation of the costs is rather minimal. Unfortunately, the second variable, the slope of the road network could not be used because this variable did not show a significant relation with the costs of the road segments. The costs of the river transport are based on estimations of the operational costs by RHDHV. Although these costs are based on experiences with other projects, an uncertainty analysis has not been done, since the there is no other data than the estimate. An uncertainty analysis could describe the range of the output and therefore how well the estimation fits the real situation. The outcome of the shortest path analysis based on only the road network was compared to the costs of the current situation and showed that the simulated costs were slightly 30 overestimating the current costs. These differences can have two possible reasons. First, the noted length for the distance to cover from each field, of which the data was provided by KSW, did not always correspond with the actual length measured for this track; optimal path based on the road network. The length of several tracks is underestimated compared to the measurements, which can cause an underestimation of the costs. Furthermore, the simulation is done based on the assumptions that in the current situation all sugar cane is transported by road. However, parts of the harvested sugar cane of some of the fields is already been transported by river. The exact fields were not known, and therefore, this is not implemented in the least-cost path analysis. For those fields, this possibly results in higher costs of the optimized route over the road network compared with the current situation. Although both the costs of the road transport, as the costs of river transport seem to be calculated based on minimal data, this is not considered to have big influence on the final results. The differences between the costs of different transport modes are that big, that even large error ranges will not change the final outcome of this research. 5.4 Optimal Route Transportation over the river is for all 42 landing and loading points cheaper compared to the current costs of transport (Figure 14). The possible reduction of transport costs varies from 8% up to 54% of the current transport costs. These results are based on several assumptions. First, the calculations were done assuming there are 3 barges with a 112 tonnes capacity each. The barges were assumed to be fully loaded at any time. Furthermore, transhipment costs are not included in the analysis. Even though this research is a simplification of the real situation, the results of the analysis clearly indicate that a substantial decrease in transport costs can be realised. RHDHV proposed barges with a total capacity of 336 tonnes a day. Since the current factory can handle 600 tonnes a day when milling on maximal capacity, not all sugar cane can be transported over the river. Therefore, either the capacity of the barges needs to be reconsidered or the capacity must be used in the most efficient way. The routes on which the most money can be saved, should change to river transport. Every month, depending on the fields to harvest, decisions on the choice of transport mode can be made. 5.5 Feasibility The economic feasibility is calculated on the capital investments of implementing the river transport (Table 11). The estimation of the lower and upper value of the capital investments varies almost 1.000.000 USD. This range is due to the insecurity of this phase of the project (Boer, 2016). Furthermore, the breakeven point is calculated based on the assumption that the total capital investment finally has to be financed by the reduction of transport costs. There is an opportunity that a part of the capital investments are funded by other parties (“The Sugar: Make it Work Project”, 2016). Therefore the estimation of the breakeven point is probably an overestimate of the final breakeven point. 31 6 Conclusion 6.1 Research objective The main objective of this research is optimization of sugar cane transport in Rwanda by assessing different transport modes conditional to factory constraints and field and network conditions. This research has shown that implementing river transport can contribute in a major decrease in transport costs. Along the 85 km that the river Nyabarongo flows through the sugar cane fields, 42 locations were assessed to find the most optimal route to the mill. All optimal routes follow the river until the landing point near the Ruliba bridge and from there they follow their route by road to the factory. Based on operation costs, the costs of transport can be reduced with values varying between 8 to 54% with an average of 40% of the current transport costs. 6.1.1 What is the current situation of cane transportation in Rwanda? The sugar cane fields are mostly located on the river banks of the Nyabarongo river. In the current situation the harvested sugar cane is transported by road from the fields to the factory. The condition of the roads is very poor, what results in slower transport and damage to the trucks. Especially near the fields and therefore near the river, the road is in poor condition. After harvesting, sugar cane is processed within 72 hours, which influences the quality of the cane. A part of sugar cane fields is not accessible by road and is transported over the river in small boats. The transport is time consuming and can be dangerous due to the characteristics of the river. 6.1.2 Which method is suitable for this cane transportation optimization problem? Based on the shortest path algorithm developed by Dijkstra based on the costs of the transport network, the optimal routes from each loading point to the factory were calculated. Based on the characteristics of Dijkstra’s algorithm and this optimization problem, the algorithm was preferred over other methods. Next to that Dijkstra’s algorithm is widely implemented and therefore a convenient choice. 6.1.3 Which variables of the transport network can predict the costs of the road network? This research showed that the condition of the road network as a variable is a main predictor of the final costs of the road network. In contrast to other research, the slope of the road did not show any relation with the costs of the transport network. 6.1.4 Which conditions are important to be considered when implementing the results of this research in KSW circumstances? The implementation of river transport can account for a major decrease in transport costs. When taking the future into account, this can be a first step in optimizing the whole supply chain. For further optimizing the supply chain, the cooperation of out growers and transporters, which are part of the supply chain is necessary. Therefore, a good relationship between these two parties is considered to be important. Optimizing the total supply chain requires complete crop data on all sugar cane fields. Therefore, efficient management of planting, harvesting and transportation demands up to date crop data on the sugar cane fields cultivated by out growers. 32 6.2 Further research and recommendations Transport of sugar cane is a component of the total supply chain. Comprehensive research on all other components is required to optimize the total supply chain. First, up to date crop information on all the sugar cane fields is essential for further optimization. In this research, primarily crop information of sugar cane fields cultivated by KSW was linked to the geometry. Crop information on sugar cane fields cultivated by out growers could not be used in this research. Based on those data, a constant supply to the factory can be planned. Efficient harvest and therewith the transport of sugar cane can be calculated with complete and up to date crop information. Second, the location and the number of loading points were based on several assumptions. The river dynamics influence the possible locations of the loading points. Before assigning possible locations, further research needs to be done on the river dynamics. The exact location and number of loading points can determine based on the outcome of river research. The analysis of this research shows that one landing point, near the Ruliba bridge is used in all optimal routes. Creating one instead of four landing points means that the planned capacity of that landing point should be increased. Furthermore, the costs of the transport network could be researched in more detail. In this research, the costs of river transport were based on the estimation by RHDHV. The costs of the road network are based on the condition of the roads. The prediction of the costs of both transport modes could be more accurate when these are based on more variables. An uncertainty analysis of these variables on both road and river transport could show how well the predicted costs fit the real situation. Last, the socio-economic effects of implementing river transport on a larger scale should be researched. Although this project would create more jobs in the near future, the effect on the current trucks drivers and boat owners should be kept in mind. 33 7 References Boer, T. de (2016). Pre-Feasibility Study sugar cane barging. 1-33. HaskoningDHV Nederland B.V., Rotterdam. Bucyensenge, J. (2015, January 2015). Nyarabarongo boat accident: Two more bodies recovered. The New Times. Retrieved from www.newtimes.co.rw. Csardi, G. & Nepusz, T. (2006). The igraph software package for complex network research. InterJournal, Complex Systems, 1695. Cherkassky, B. V., Goldberg, A. V., & Radzik, T. (1996). Shortest paths algorithms: Theory and experimental evaluation. Mathematical programming, 73(2), 129-174. Delling, D., Sanders, P., Schultes, D., & Wagner, D. (2009). Engineering route planning algorithms. Algorithmics of large and complex networks (pp. 117-139). Springer Berlin Heidelberg. Dijkstra, E. W. (1959). A note on two problems in connexion with graphs. Numerische mathematik, 1(1), 269-271. Dreyfus, S. E. (1969). An appraisal of some shortest-path algorithms. Operations research, 17(3), 395-412. Durisin, M. (2015, July 20). Another Commodity Down: Sugar Falls to Six-Year Low. Bloomberg Business. Retrieved from www.bloomberg.com. Fauconnier, R. (1993). The Tropical Agriculturist: Sugar Cane. Macmillan Press Ltd, London. Grunow, M., Günther, H. O., & Westinner, R. (2007). Supply optimization for the production of raw sugar. International Journal of Production Economics,110(1), 224-239. Higgins, A. J. (1999). Optimizing cane supply decisions within a sugar mill region. Journal of Scheduling, 2(5), 229-244. Higgins, A. J., & Muchow, R. C. (2003). Assessing the potential benefits of alternative cane supply arrangements in the Australian sugar industry. Agricultural Systems, 76(2), 623-638. Higgins, A. (2006a). Scheduling of road vehicles in sugarcane transport: A case study at an Australian sugar mill. European Journal of Operational Research, 170(3), 987-1000. Higgins, A. J., & Laredo, L. A. (2006b). Improving harvesting and transport planning within a sugar value chain. Journal of the Operational Research Society, 57(4), 367-376. Higgins, A., Thorburn, P., Archer, A., & Jakku, E. (2007). Opportunities for value chain research in sugar industries. Agricultural Systems, 94(3), 611-621. James, G. (Ed.). (2008). Sugarcane. John Wiley & Sons. Kabuye Sugar in award winning public-private partnership (2015). Madhvani Group Magazine, 23,2, 29. Kabuye Sugar Works, Rwanda (2015). Retrieved from www.kakirasugar.com. 34 KSW (2015a, November 29). Standing Cane Inventory as at 01st May- Est & OG. [Data file]. KSW (2015b, November 29). Vehicle Registration Details. [Data file]. KSW (2015c, November 29). Year Wise, Zoe Wise Cane Quantity Supplied and Transport Amount Paid Details. [Data file]. Le Gal, P. Y., Le Masson, J., Bezuidenhout, C. N., & Lagrange, L. F. (2009). Coupled modelling of sugarcane supply planning and logistics as a management tool. Computers and Electronics in Agriculture, 68(2), 168-177. Lejars, C., Le Gal, P. Y., & Auzoux, S. (2008). A decision support approach for cane supply management within a sugar mill area. Computers and electronics in agriculture, 60(2), 239249. López-Milán, E., & Plà-Aragonés, L. M. (2014). A decision support system to manage the supply chain of sugar cane. Annals of Operations Research,219(1), 285-297. López-Milán, E., Fernandez, S. M., & Aragones, L. M. P. (2006). Sugar cane transportation in Cuba, a case study. European Journal of Operational Research, 174(1), 374-386. Lu, B. (2014). Convert a SpatialLinesDataFrame object to a “igraph-class”. LaValle, S. M. (2006). Planning algorithms. Cambridge university press. Mukaaya, E. (2008, April 13). Kabuye Sugar Works short of sugarcane. The New Times. Retrieved from www.newtimes.co.rw. River Transportation (Barge Landing & Existing Loading point) [Map]. (2015). Kigali. Kabuye Sugar Works Ltd. Royal Haskoning DHV (2015). Rwanda ready for sustainable sugar cane production. Retrieved from www.royalhaskoningdhv.com. Sugar: make it work, a Public Private Partnership. (2014, November 6). Retrieved from http://www.dutchwatersector.com/solutions/projects/353-sugar-make-it-work-a-public-privatepartnership.html. Swedesurvey (2010). Report for Production of ortho photo in Rwanda. Project Rwanda National Land Use and Development Master Plan. The Sugar: Make it Work Project. (2016, February 4). New Times Rwanda. Wernau, J. (2015, May 27). Sugar Falls to Six-Year Low on Global Glut. The Wall Street Journal. Retrieved from www.wsj.com. Yu, C., Lee, J. A. Y., & Munro-Stasiuk, M. J. (2003). Extensions to least-cost path algorithms for roadway planning. International Journal of Geographical Information Science, 17(4), 361376. Zhan, F. B., & Noon, C. E. (1998). Shortest path algorithms: an evaluation using real road networks. Transportation Science, 32(1), 65-73. 35 Appendix A: Computation of slopes of the GPS-tracks – Rscript 36 Appendix B: Computation of Shortest Path - Rscript 37 Appendix C: Edge IDs of Landing and Loading Points Landing/Loading Point Phase 2 Side NA Type Landing Edge ID Optimal Route 3552 Edge ID Current Situation 3536 New 1 South Loading 3480 3450 New 1 North Loading 3497 3534 New 2 South Loading 3386 3360 F07 North Loading 3383 3384 New 3 South Loading 3377 3355 New 2 North Loading 3370 3382 Kanzenze Bridge NA Landing 3320 3306 New 3 North Loading 3297 3357 New 4 South Loading 3271 3266 New 4 North Loading 3284 3276 New 5 South Loading 3314 3303 New 6 South Loading 3359 3337 Nyarubande 1 North Loading 3357 3344 New 7 South Loading 3277 3272 Nyarubande 2 North Loading 3302 3294 Confluence Akanyaru NA Landing 3217 3217 New 8 South Loading 3247 3247 Nyarubande 3 North Loading 3281 3292 New 9 South Loading 3295 3284 New 5 North Loading 3379 3364 New 10 South Loading 3422 3396 Nyarubande 4 South/North Loading 3542 3511 New 11 South Loading 3745 3881 New 7 North Loading 3721 3686 Rwesero 3 North Loading 3951 3910 New 12 South Loading 3989 3944 New 8 North Loading 4158 4204 New 9 North Loading 4744 4695 New 13 South Loading 5424 5941 Ruliba Bridge NA Landing 6449 7004 New 14 South Loading 7414 7359 New 10 North Loading 7990 8530 New 15 South Loading 8700 8654 New 11 North Loading 9072 9070 New 16 South Loading 9732 9677 New 12 North Loading 9914 9881 New 17 South Loading 10212 10157 New 13 North Loading 10262 10273 New 18 South Loading 10258 10209 New 14 North Loading 10370 10321 New 19 South Loading 10559 10498 38 39
© Copyright 2026 Paperzz