The Gemini Project

The Gemini Project
Jens Møller, Senior Project Manager
May 26, 2016 | Gemini Bankers Day
Restricted © Siemens AG 2016
siemens.com/wind
Presentation scope
1
The Gemini Project
2
What happens in general when a contract
is signed and become operational
3
Initiatives/improvements implemented
4
Questions
Restricted © Siemens AG 2016
Page 2
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Project Information – Location and sourcing of the
Gemini Project
Site Information – Location
Aalborg
• Blades
Brande
• Nacelles
Vejle
• Offshore Competence Center
Eisbjerg
• Pre-assembly
• Installation Port
Restricted © Siemens AG 2016
Page 3
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Gemini – The world’s largest project-financed
offshore wind farm
€ 440 million
in equity invested
60% Northland Power
130 m
rotor diameter
150
wind turbines with a
capacity of 4 MW each
Technical Key Data
• 150 WTGs, type SWT 4.0-130
(G4 platform)
• 15 years warranty
contract – LTP
• Each WTG: 4.0 MW,
63 m
20% Siemens
Financial Services
130 m rotor
• In total a 600 MW
“power plant”
10% HVC
10% Van Oord
Targets
• Secure adequate
project organization
(skills/resources in time)
• Be realistic and open
to new ideas/improvements
• Prepare well and in advance
• Manage Risks and
Opportunities actively
1.8 m
The wind park –
Gemini’s importance
to green-energy development
1.5 million people
785,000
households
With a capacity
of 600 MW, the plant
will produce 2.6 TWh
annually
Twice as many
inhabitants as in
the Dutch capital
of Amsterdam
Challenges 2015
Solutions/Success Criteria
• Weather conditions
in the North Sea (WDT)
• New G4 turbine platform with
ø 5.5 tower and 130 m rotor
• Project-financed
à Inflexible/little room
to maneuver (contract)
• Satisfied customer
• Geographical setup (NL/DK)
• Low number of HSE incidents
• Deliver on time/beyond
of expectations
• Introduce of new methods
for execution of the project
• Compact time schedule
Renewable energy production
and clean energy supply
Restricted © Siemens AG 2016
Page 4
26.05.2016
Jens Møller | WP OF PM PRJ ROW
What happens when a contract is signed
and becomes operational
Today
1
Handover contract
2
Transfer documentation
from Sales and IT control
3
Setting up team and
internal kick-off
4
Budget, plan and schedule
reviews and scrutinizing
5
Transfer account
responsibility
6
Setup adm. systems/
finance SAP
7
Agree communication
with Employer/customer
2014
2015
2016
2017
September 2014
Detailed planning start
June 26, 2014
Kick-off Gemini/SWP
May 14, 2014
Commencement date
May 1, 2014
Contract signed
February 4, 2016
Start Installation
Project Closure:
Early 2017
November 2015
Pre-assembly start
November 2015
Planned delivery Ex
Works of the 1st turbine
September 2015
1st production date (turbines)
Explore Opportunities…
Restricted © Siemens AG 2016
Page 5
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on the GEM project
(after contract signature)
DP2 vessel
implementation
agreed with
Employer
Reduction of time
from erection to
power production.
Business case: 12
days improvement –
Target more than 16
days earlier power
production
Investment à time reduction à early power generation – maximize power production
Restricted © Siemens AG 2016
Page 6
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on the GEM project
(after contract signature)
Video of DP2
operation from GEM
project
Investment à time reduction à early power generation – maximize power production
Restricted © Siemens AG 2016
Page 7
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on GEM project
(after contract signature)
Helicopter transfer
of people from
shore to offshore
New setup à new procedures à new training à faster transfer à time cost savings
Restricted © Siemens AG 2016
Page 8
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on GEM project
(after contract signature)
3 Party agreement between Employer and Service and Siemens Wind
Power on TETRA communication supply – financial split
(cost reduction for all parties and full benefit from start of installation)
Restricted © Siemens AG 2016
Page 9
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on GEM project
(after contract signature)
Additional testing in Port of Esbjerg moving Offshore activities (risk and
time) from offshore to onshore (time/cost reduction)
Before
Now
Testing offshore
Pre-Testing onshore using PC simulation
Tower
Nacelle
Restricted © Siemens AG 2016
Page 10
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on GEM project
(after contract signature)
Relocation of some of the 500h service program from after ‘start
operation’ to production and pre-assembly phase
Time/cost/risk reduction. Before: 4 men x 4 days off shore à Now: 1 day two men offshore
Restricted © Siemens AG 2016
Page 11
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Initiatives implemented on GEM project
(after contract signature)
Optimize operations between
Power Service and SWP
project by
• Sharing resources/splitting tasks
• Sharing crew transfer vessels
• Staying on same accommodation
vessel (hotel vessel/DP2)
• Using same spare part stock
• Using same communication
platform
Restricted © Siemens AG 2016
Page 12
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Any questions?
Expected project completion
- as per contract
Platzhalter Bild
• Installation: 30. August 2016
• Commissioning: 1 Oct. 2016
• Wind Farm Take Over: 25. Dec
2016
• Project closure January 2016
Platzhalter Bild
Restricted © Siemens AG 2016
Page 13
26.05.2016
Jens Møller | WP OF PM PRJ ROW
Thank you very much for your attention –
Please, contact us for further information
Jens Møller
Senior Project Manager
WP OF PM PRJ ROW
Fiskergade 1
DK-7100 Vejle
Phone: +45 30 37 66 46
E-mail: [email protected]
siemens.com/wind
Restricted © Siemens AG 2016
Page 14
26.05.2016
Jens Møller | WP OF PM PRJ ROW