The Gemini Project Jens Møller, Senior Project Manager May 26, 2016 | Gemini Bankers Day Restricted © Siemens AG 2016 siemens.com/wind Presentation scope 1 The Gemini Project 2 What happens in general when a contract is signed and become operational 3 Initiatives/improvements implemented 4 Questions Restricted © Siemens AG 2016 Page 2 26.05.2016 Jens Møller | WP OF PM PRJ ROW Project Information – Location and sourcing of the Gemini Project Site Information – Location Aalborg • Blades Brande • Nacelles Vejle • Offshore Competence Center Eisbjerg • Pre-assembly • Installation Port Restricted © Siemens AG 2016 Page 3 26.05.2016 Jens Møller | WP OF PM PRJ ROW Gemini – The world’s largest project-financed offshore wind farm € 440 million in equity invested 60% Northland Power 130 m rotor diameter 150 wind turbines with a capacity of 4 MW each Technical Key Data • 150 WTGs, type SWT 4.0-130 (G4 platform) • 15 years warranty contract – LTP • Each WTG: 4.0 MW, 63 m 20% Siemens Financial Services 130 m rotor • In total a 600 MW “power plant” 10% HVC 10% Van Oord Targets • Secure adequate project organization (skills/resources in time) • Be realistic and open to new ideas/improvements • Prepare well and in advance • Manage Risks and Opportunities actively 1.8 m The wind park – Gemini’s importance to green-energy development 1.5 million people 785,000 households With a capacity of 600 MW, the plant will produce 2.6 TWh annually Twice as many inhabitants as in the Dutch capital of Amsterdam Challenges 2015 Solutions/Success Criteria • Weather conditions in the North Sea (WDT) • New G4 turbine platform with ø 5.5 tower and 130 m rotor • Project-financed à Inflexible/little room to maneuver (contract) • Satisfied customer • Geographical setup (NL/DK) • Low number of HSE incidents • Deliver on time/beyond of expectations • Introduce of new methods for execution of the project • Compact time schedule Renewable energy production and clean energy supply Restricted © Siemens AG 2016 Page 4 26.05.2016 Jens Møller | WP OF PM PRJ ROW What happens when a contract is signed and becomes operational Today 1 Handover contract 2 Transfer documentation from Sales and IT control 3 Setting up team and internal kick-off 4 Budget, plan and schedule reviews and scrutinizing 5 Transfer account responsibility 6 Setup adm. systems/ finance SAP 7 Agree communication with Employer/customer 2014 2015 2016 2017 September 2014 Detailed planning start June 26, 2014 Kick-off Gemini/SWP May 14, 2014 Commencement date May 1, 2014 Contract signed February 4, 2016 Start Installation Project Closure: Early 2017 November 2015 Pre-assembly start November 2015 Planned delivery Ex Works of the 1st turbine September 2015 1st production date (turbines) Explore Opportunities… Restricted © Siemens AG 2016 Page 5 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on the GEM project (after contract signature) DP2 vessel implementation agreed with Employer Reduction of time from erection to power production. Business case: 12 days improvement – Target more than 16 days earlier power production Investment à time reduction à early power generation – maximize power production Restricted © Siemens AG 2016 Page 6 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on the GEM project (after contract signature) Video of DP2 operation from GEM project Investment à time reduction à early power generation – maximize power production Restricted © Siemens AG 2016 Page 7 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on GEM project (after contract signature) Helicopter transfer of people from shore to offshore New setup à new procedures à new training à faster transfer à time cost savings Restricted © Siemens AG 2016 Page 8 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on GEM project (after contract signature) 3 Party agreement between Employer and Service and Siemens Wind Power on TETRA communication supply – financial split (cost reduction for all parties and full benefit from start of installation) Restricted © Siemens AG 2016 Page 9 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on GEM project (after contract signature) Additional testing in Port of Esbjerg moving Offshore activities (risk and time) from offshore to onshore (time/cost reduction) Before Now Testing offshore Pre-Testing onshore using PC simulation Tower Nacelle Restricted © Siemens AG 2016 Page 10 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on GEM project (after contract signature) Relocation of some of the 500h service program from after ‘start operation’ to production and pre-assembly phase Time/cost/risk reduction. Before: 4 men x 4 days off shore à Now: 1 day two men offshore Restricted © Siemens AG 2016 Page 11 26.05.2016 Jens Møller | WP OF PM PRJ ROW Initiatives implemented on GEM project (after contract signature) Optimize operations between Power Service and SWP project by • Sharing resources/splitting tasks • Sharing crew transfer vessels • Staying on same accommodation vessel (hotel vessel/DP2) • Using same spare part stock • Using same communication platform Restricted © Siemens AG 2016 Page 12 26.05.2016 Jens Møller | WP OF PM PRJ ROW Any questions? Expected project completion - as per contract Platzhalter Bild • Installation: 30. August 2016 • Commissioning: 1 Oct. 2016 • Wind Farm Take Over: 25. Dec 2016 • Project closure January 2016 Platzhalter Bild Restricted © Siemens AG 2016 Page 13 26.05.2016 Jens Møller | WP OF PM PRJ ROW Thank you very much for your attention – Please, contact us for further information Jens Møller Senior Project Manager WP OF PM PRJ ROW Fiskergade 1 DK-7100 Vejle Phone: +45 30 37 66 46 E-mail: [email protected] siemens.com/wind Restricted © Siemens AG 2016 Page 14 26.05.2016 Jens Møller | WP OF PM PRJ ROW
© Copyright 2026 Paperzz