Proposal - Performa 15

/2015
SIKI IM STUDIO
/PERFORMA 15
SIKI IM
Select Works
Arnhem Mode Biennale with Archi-Tectonics
SIKI IM x Leong Leong
Siki Im was born in Cologne, Germany. He moved to the
UK and studied at the Oxford School of Architecture.
After working as an architect in various cities around
the world, he started his career in fashion in New
York and was Senior Designer for both Karl Lagerfeld
and Helmut Lang. In September 2009 in New York
City, Siki Im introduced his first solo collection
which won him the prestigious Ecco Domani award
for Best Men’s Wear in 2010. In 2011, Siki Im was
awarded with the Samsung Design & Fashion Fund
and 2015, Im received the Vilcek Prize and Woolmark
Award. To expand SIKI IM, Siki Im introduced in 2014
the extension line DEN IM, which encompasses
essential utilitarian clothing. Currently, he is also
PERFORMA 15
Design Team: Siki Im, Nicole Mater, & Kamilla
Intersection
Why must
authorities
stand with their
back to a wall?- Stephen Joseph
on theatre configuration
Inspired by Elizabethan theatre configurations,
Lounge spaces are made of light, soft furniture,
Performa 15 creates an multi-directional
allowing users to rearrange their space to
theatre that encourages interaction between
create additional viewing spaces or more
the audience and performer. A dynamic
private lounge seating. The exterior of the store
sectional slice through the narrow space
front, covered in the same anonymous rubber
creates several types of settings. By partially
material as the stands, frames a dramatic view
suspending the viewing platforms, allowing
of the underside of the structure, beckoning
them to rest at the stage in the centre, the
passers by to enter.
areas beneath the seats can be utilized as
lounge, kiosk, and food preparation space. The
stairs and stage are covered in soft, textured
rubber mat, sharply contrasting the underside
of the stands, which are left raw and structural.
PERFORMA 15
Dynamic Section
Kiosk
Viewing and performance
Lounge
Kitchenette
At 12’ 0” A.F.F.
At 4’ 0” A.F.F.
Additional Furniture
and Lighting hung
Suspended Tables
Secured Aircraft
Cable Suspension
System
OSB and Dimensional
Lumber Steps
Oriented Strand
Board Sheathing with
Lumber Framing for
Base
Steel tube structure
Assembly
Suspended Florescent
Tube Light @ 12’ 0” A.F.F.
Suspended Florescent
Tube Light at 8’ 0” A.F.F.
Projector Location
Suspended Florescent
Tube Light at 10’ 0” A.F.F.
Suspended Florescent
Tube Light at 12’ 0” A.F.F.
Illumination
Storefront Elevation
Regulations Compliance Checklist
– A flexible space considering diverse commissions and happenings.
– Distribution point for materials and information about the biennial.
– Press point.
– Film screening area. (not a black box)
– Lecture and Seminar space.
– Book and Artworks store / Library.
– Communal work table. (discussions, panels)
– Ticket selling kiosk.
– Main performance area with rehearsal space. Seating for 80 people.
– Lounging area(s).
– Area for food and drinks.
– Kitchenette.
Production Schedule
OFF-SITE
Finalize ALL Documentation for Structure
• Cut List for all elements (joist, ribs, panels, etc)
• Consult with Structural Engineer
• Label every member for assembly and reassembly
• Finalize Model-Color Code Materials • Material Take-Offs • Comprehensive Shopping list (fasteners, screws, lights, etc.)
Finalize all Design/Details decision:
• Hanging rods, seating, hanging tables
• Free-standing furniture
• Lighting
• Kitchenette
• Storage
• Facade
Preparation (Oct 7-14):
• Buy all materials 2x4 lumber, materials, etc. • Cut all joists, wood, rubber sheeting etc
• Welt all metal structure
• Build stage-platforms
• Build furniture
• Build façade structure
10/28 Thurs 9am:
• CNC end ribs pick-up from TB
• Assemble Ramp South End and Middle Section
• Build Display Niches and Liners
10/29 Friday 9am: Mock-ups
•
•
•
•
Assemble Entire ramp
Cut Masonite sheathing
Resolve Edge Details at Openings
Layout lighting and wiring plan
10/30 Saturday
• De-Assemble and organize parts 10/31 Sunday
• Build Display Niches and Liners
Production Schedule (continued)
ON-SITE: Oct 15:
• Delivery to site
• Assemble Structure
• Prepare ceiling
Oct 16-21:
• Assemble Structure
• Install structural screws, turnbuckles, and cables into ceiling
Oct 22:
• Assemble stage-platform
• Apply wood on structure
• Install lighting
Oct 23:
• Assemble seating to west ramp
• Apply rubber sheeting
Oct 24:
• Assemble seating to east ramp
• Apply rubber sheeting
Oct 25:
• Hang west ramp to ceiling
• Attach stage-platform
Oct 26:
• Hang east ramp to ceiling
• Attach stage-platform
Oct 27:
• Layout all Display Niches
• Prep all lighting fixtures
• Exterior Furniture
• Prep for rubber installation
Oct 28:
• Rubber Installation
Oct 29:
• Clean Up and prepare for soft open
Budget