INT 07 - Integrated Baseline Review Integrated Baseline Review (IBR) Training: Exploding the IBR Big Bang Theory Presented by: Luis C Contreras, Principal Consultant June 2014 AzTech International goAzTech.com 1 (c) AzTech International, LLC 2014 Our Background… • For over 20 years, AzTech has worked with Government & Contractors on major EVMS reviews • • • • • • • Implementing EVMS Building & assessing Integrated Master Schedules Conducting Schedule Risk Assessments (SRAs) Conducting Integrated Baseline Reviews (IBRs) Conducting EVMS Compliance Reviews Performing EVMS Independent Assessments & Self-Assessments Government • • • • Navy/NAVAIR Air Force DCMA DOE • Prime Contractors • Sub-Contractors 2 (c) AzTech International, LLC 2014 1 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Agenda • What is an IBR? • IBR Big Bang Theory • IBR Timeline • • • • • • • • • Pre-Award Post-Award Phase I - Documentation Quality and Integration Review Phase II - Control Account Level Discussions IBR Exit Briefing / Follow-up Training, Supplier IBRs, & Rolling Waves Sample IBR Templates Benefits of a Streamlined IBR Process Q&A 3 (c) AzTech International, LLC 2014 “A bad review is like baking a cake with all the best ingredients and having someone sit on it.” Danielle Steel (Famous Earned Value Romance Novelist) WHAT IS AN IBR? 4 (c) AzTech International, LLC 2014 2 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review What is an IBR? • Seeks mutual understanding between government / customer and contractor / subcontractor… • of the Performance Measurement Baseline (PMB) • of these 5 risk areas in executing the PMB: • Bottom Line Up Front (BLUF): An IBR answers: • An IBR Answers: “Do we have an achievable, meaningful, realistic baseline—and what are the risks to successful execution?” 5 (c) AzTech International, LLC 2014 IBR Assesses Risks… By answering these “Simple” questions: • Technical - Is the technical scope of the work fully included and consistent with authorizing documents? • Schedule - Are key schedule milestones identified and does the schedule reflect a logical flow? • Resources – Are resources involving cost—budgets, facilities, skilled staff—adequate and available for performing assigned tasks? • Costs - Are tasks well planned and can they be measured objectively relative to technical progress? • Management - Are management processes in place and in use? Credit: GAO Cost Estimating Guide 6 (c) AzTech International, LLC 2014 3 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Who’s involved? • Government & Contractor Program Managers: own the IBR • IBR Integrators: Points of Contact for IBR, assign actions, run meetings, manage data calls, coordinate CAM discussions • Contractor & Government Core Teams: Integrators, Technical (Engineering, Manufacturing), Finance / EVM, and Scheduling • Artifact (Data) Experts: Subject Matter Experts (SMEs) on artifacts being evaluated • CAM Discussion Leaders: Lead CAM Interviews • Control Account Managers: Interviewed to assess their portions of the PMB • DCMA: frequently involved on behalf of government customer 8 (c) AzTech International, LLC 2014 How is an IBR like the Big Bang? 9 (c) AzTech International, LLC 2014 4 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review When does an IBR occur? • Traditional IBR • Usually within 6 months after contract award • Or after a major planning (or replanning) exercise 10 (c) AzTech International, LLC 2014 Minimizing the Bang! • Traditional: IBRs back-loaded with big IBR finale • • • • Inconsistent pre-IBR documentation review Hard to “eat the entire elephant” during single event Action items typically fixed post-IBR ,extends review period Unpleasant surprises anyone? IBR Event “Big Bang Theory” Contract Award • Streamlined: Progressive IBR process with objectives: • • • • Providing consistent IBR methodology Driving up-front program integration Providing incremental assessment of readiness leading up to IBR closure Fostering collaborative Government and Contractor process Incremental Review and Discussions Contract Award +90 +30 IBR Exit Brief +180 11 11 (c) AzTech International, LLC 2014 5 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Top Level View of Process Artifacts Integration Integration Meetings / Workshops (Technical, Schedule, Resource, Cost and Mgmt Processes) CAM Disc IBR Report Exit Brief Ongoing Actions and inputs to the Risk Register (Data Cleanup; Issue, Risk & Opportunity Discovery) 12 (c) AzTech International, LLC 2014 Notional IBR Timeline IBR Planning Integration Meeting (Phase I Planning) Program Documentation Quality/Integration Review Period Mo 1 Clean-up Actions Mo 2 System IBR Phase I: Requirements Program Review Documentation Quality & Integration Review Mo 3 Integrated Risk Assessment Mo 4 Schedule Risk Assessment IBR Exit Brief EVM / IBR Training Mo 3 IBR Phase II: Control Account Level Discussions Data Review Mo 4 Control Account Discussions Supplier IBRs 13 13 (c) AzTech International, LLC 2014 6 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Integrated Baseline Review (IBR) Five Steps PMA Ownership of the Performance Management Framework Contract Award PAC Prior to the end of the third/forth full accounting period * 2 1 Prime Contractor presents their Management Control Processes No later than the end of the fifth full month accounting period 3 180 Calendar Days from Contract Award 4 5 Need for IBR Joint Government & Prime Systems Training Within 90 days of Subcontract Authority to Proceed Prime KTR Government Prior to the end of the first full accounting period Baseline development processes TPM/EV methods Supplier/Subcontract management Risk process Joint setup of Business Rhythm timing & content Prime Management System Assessment (MSA) Ensure the Prime level PMB includes entire technical scope & is consistent with contract schedule requirements Demonstrate that, adequate management processes are being employed, adequate resources assigned, and effective EV methods are being used to accurately status contract cost, schedule, and technical performance Kick off Step 4 SRA Process Subcontractor IBRs Schedule Risk Assessment Prime Contractor conducts IBRs on Subs requiring to EVM report data Subs requiring to EVM flow down requirement (with Government participation) Total Contract IBR Prime Contractor participates in a Government conducted SRA Prime Contractor & Government jointly assess the PMB, including all subcontracted effort Risk Assessment IBR is a recurring process triggered by significant contract options, major modifications, or major replans. Credit: NAVAIR AIR-4.2 Cost Department 14 (c) AzTech International, LLC 2014 * Flexible depending on whether there was a TD phase IBR Post-Award Steps Form Govt IBR Team Govt IBR Team Orientation Initial Supplier Interface Meeting Form Joint IBR Team IPT # 1 Artifact Quality & Traces CAM Discussion Session # 1 IPT # 2 Artifact Quality & Traces Joint IBR Team Training (Discussion) CAM Discussion Session # 2 CAM Improvement Efforts Define Artifact Quality & Integration Traces Contractor BMO Discussion Phase II Status Review IBR Exit Briefing Joint IBR Team Training (Process) IBR Data Readiness Review IPT # 3 Artifact Quality & Traces IPT #N Artifact Quality & Traces CAM Discussion Session # n Data Improvement Efforts 15 (c) AzTech International, LLC 2014 7 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Organizing for the IBR • Small Core Team concept • Continuity for next four months • Program Control focused: Integrator, Engineering, Finance • Roles and Responsibilities • IBR Integrator and core team • Artifact experts • DCMA • Organization • Either by IPT or risk area • IPT or risk topic area organization • IBR Team decides • Training, set expectations • Introduction – for overall IBR process • Phase I – Artifact quality and integration assessment • Phase II – CAM discussions 16 (c) AzTech International, LLC 2014 Quick Quiz True or False: It is common for organizations to fail their first IBR? 17 (c) AzTech International, LLC 2014 8 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review “Torture the data, and it will confess to anything.” Ronald Coase, Economics, Nobel Prize Laureate PHASE 1: ARTIFACT QUALITY & INTEGRATION TRACES Question? 18 (c) AzTech International, LLC 2014 Phase I: Artifact Quality Evaluation Emphasis on improving document quality Ensure all risks are identified PMB is completely documented Jointly define standards for evaluation CDRL, DID compliance Clarity, completeness, industry standards Program requirements Evaluation Joint evaluation against standards established Scoring / Action Items Adequate – quality is recorded Inadequate (action required to achieve adequacy) Track evolution of artifact improvement 19 (c) AzTech International, LLC 2014 9 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Phase I: Integration Traces • Ensure integration of documents that comprise the PMB are accurately and completely flowed to execution level Jointly define proof statements Narrative description of integration points between documents Evaluation Joint evaluation against standards established Scoring / Action Items Adequate – trace is recorded Inadequate – action required to achieve adequacy Track evolution of integration trace improvement 20 (c) AzTech International, LLC 2014 Sample Integration Traces SOW – Statement of Work IMP – Integrated Master Plan BOE = Basis of Estimate WBS = Work Breakdown Structure RAM – Resp Assignment Matrix CAP = Control Account Plan SRA = Schedule Risk Assessment RMP = Risk Mgt Process WAD = Work Authorization Document CBB –Contract Budget Base BCR – Baseline Change Request CPR = Contract Performance report EAC = Estimate at Completion VAR = Variance Analysis Report MR = Management Reserve 21 (c) AzTech International, LLC 2014 10 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Quick Quiz If you could pick one more artifact from the last slide, which would it be? 22 (c) AzTech International, LLC 2014 “To put it bluntly, I seem to have a whole superstructure with no foundation. But I'm working on the foundation.” Marilyn Monroe (Infamous EV Analyst & Scheduler) INTEGRATED MASTER SCHEDULE (IMS) 23 (c) AzTech International, LLC 2014 11 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Baseline Development EVMS 32 Guideline Compliance Identify Project Objectives 1 Establish Organizational Breakdown Structure Adopt Work Breakdown Structure 2 Statement of Work (SOW) Define Detailed Work 1 17 (6)Schedule the authorized work 2 4 Assign Resources and Duration Basis of Estimate 7 WP Tasks Hours Hours 8 Hours 9) Establish budgets for authorized work 10) Identify SOW in discrete work packages 11) Sum all WPs & PPs to = CA budget 12) Identify & control LOE 13) Establish overhead budgets 14) Identify MR & UB (5) Integrate WBS/OBS to create CAs 1/1 Hours 1/5 1/4 Hours 1/5 1/5 Performance Measurement Baseline (PMB) Control Account Plans 10 1/10 Hours 1/14 Hours Hours Adjust Plan to Fit Project Objectives Calculate Dates, Critical Path and Costs Required 9 Hours Hours 8) Establish a time-phased budget baseline 8 9 - 14 BOMs / Resource Agreements Hours Hours Hours Hours (7) Identify physical products/milestones/tech performance goals to measure progress 6&7 Hours WP 5 18 Define Magnitude of Effort Logic Assumptions 6 Integrated Master Plan (IMP) 4 Responsibility Assignment Matrix (18)Summarize direct costs into OBS Construct the IMS Network Control Account WP 3 (4) Identify O/H Mgmt (1) Define WBS (17) Summarize direct costs into WBS 5 (2) Define Project Organization WBS Dictionary Create Schedule Structure 1/15 1/18 Hours 1/1 Hours 1/4 1/5 Hours 1/5 1/8 1/9 1/10 Hours 1/7 Work Authorization Documents RISK Management Plan Hours 1/12 Hours 1/13 1/16 Hours 3 1/8 15 Hours 1/5Hours 1/9 1/10 Hours (3) Integrate Processes (15) Reconcile target Cost Credit: NAVAIR IPM190 IBR Prep Workshop 24 (c) AzTech International, LLC 2014 Management System Integration EVMS Guideline Compliance 28 - 32 22 - 27 22) Generate SV &CV monthly 23) Identify significant differences between plan & actual performance 24) Identify budgeted & applied indirect costs 25) Summarize data elements & variances through WBS & OBS 26) Implement Corrective action 27) Develop estimate of cost at completion 28) Incorporate authorized changes timely 29) Reconcile current to prior budgets 30) Control Retroactive changes 31) Prevent unauthorized revisions to budget 32) Document changes to PMB 20) Identify unit/equivalent/lot costs 21) Full accountability of material costs (16) Record direct costs (19) Record all indirect costs 20 16 19 21 Credit: NAVAIR IPM190 IBR Prep Workshop 25 (c) AzTech International, LLC 2014 12 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review GAO Schedule Assessment Guide: Schedule Best Practices Source: GAO Schedule Assessment Guide Exposure Draft May 2012 26 (c) AzTech International, LLC 2014 NDIA PASEG: Generally Accepted Scheduling Principles (GASP) Valid Schedules… Source: NDIA Planning & Schedule Excellence Guide (PASEG) 27 (c) AzTech International, LLC 2014 13 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review NDIA PASEG: Generally Accepted Scheduling Principles (GASP) Effective Schedules… Source: NDIA Planning & Schedule Excellence Guide (PASEG) 28 (c) AzTech International, LLC 2014 Generally Accepted Scheduling Principles (GASP) Alignment to: ANSI, GAO, DCMA, & NAVAIR Generally Accepted Scheduling Principles (GASP) Complete ANSI/EIA-748-B Earned Value Management Systems (EVMS) Guidelines 1 - WBS 2 - OBS 7 - Interim Milestones 10 - Work Packages & Planning Packages 12 - LOE Traceable 3 - Integration 5 - RAM / Control Accounts 6 - Vertical & Horizontal Integration Transparent 6 - Vertical & Horizontal Integration 10-Work Package Characteristics, Objective Techniques US U.S. Government Accountability Office (GAO) Defense Contract Management Agency (DCMA) Naval Center for Earned Value Management (CEVM) 10 Scheduling Best Practices IMS 14 Point Assessment Program Schedule Assessment (PSA) 1. Capturing all activities. 4. Establishing the duration of all activities. 2. Sequencing all activities. 8. High Duration – Tasks with Duration > 44 working days (Goal < 5%) 1. Does the schedule reflect the work to be done? 6. Are duration estimates meaningful? 1. Logic – Tasks without predecessors and / or 3. Is work sequenced logically? successors (Goal < 5%) 5. Integrating schedule activities horizontally 4. Relationship Types – Finish-to-Start (FS) and vertically. should be the most common (Goal > 90%) 4. Are interdependencies planned in a logical manner? 2. Leads – (negative lag) Distorts the critical path (Goal 0%) 2. Sequencing all activities. 5. Are constraints, leads, and lags justified? 3. Lags – (positive lag) Excessive size and / or usage distorts the critical path (Goal < 5%) 9. Invalid Dates – Tasks with invalid forecast (incomplete tasks to the left of Time Now) or actual start/finish (completed tasks in the future) dates (Goal 0%) Valid Statused 6 - IMS Provides Current Status for All Authorized Work 9. Updating the schedule using logic and durations to determine dates. 11. Missed Tasks – Tasks not completed or forecasted to complete as planned (Goal < 5%) 10. Does the schedule provide logical status and forecasts of completion dates for all authorized work? 14. Baseline Execution Index (BEI) – Tasks completed as a ratio to those tasks that should have been completed to date according to the baseline plan (Goal > 0.95) 6. Establishing the critical path for all activities. Predictive 6 - IMS provides forecast of completion dates for all authorized work Usable 6 - IMS Effective Planning, Statusing, & Forecasting for Achieving Requirements & Measuring Performance 8. Conducting a schedule risk analysis. Resourced 9 - Control Account Level Budgets & Detail 10 - Control Account Plans (CAPs) 3. Assigning resources to all activities. Controlled 8 - Baselined Performance Measurement Baseline (PMB) 29-32 - Documented processes for tracing authorized changes & controlling retroactive changes 10. Maintaining a baseline schedule 9. Are float times reasonable? 7. Negative Float – Tasks with Total Float < 0 working days (Goal 0%) 12. Critical Path Test – Tests the logic in the critical path (Goal “Pass”) 7. Identifying float between activities. Effective 6. High Float – Tasks with Total Float > 44 working days (Goal < 5%) 13. Critical Path Length Index (CPLI) – Measures the “realism” of the critical path (Goal > 0.95) 8. Does the critical path make sense; does the scheduling software calculate it? 5. Hard Constraints – Tasks not designated as 5. Are constraints, leads, and lags justified? As Soon As Possible (ASAP), Start No Earlier Than (SNET), or Finish No Earlier Than (FNET) 2. Are critical target dates identified; are they (Goal < 5%) being used to plan the work? 10. Resources – If loaded, tasks without dollars or hours assigned (Goal 0%) 7. Are resource estimates reasonable; are key resources available to support the plan? 11. Can the current program schedule be accomplished at an acceptable risk level? 29 (c) AzTech International, LLC 2014 14 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Generally Accepted Scheduling Principles (GASP) Alignment to: ANSI, GAO, DCMA, & NAVAIR Generally Accepted Scheduling Principles (GASP) Complete Traceable Transparent ANSI/EIA-748-B Earned Value Management Systems (EVMS) Guidelines 1 - WBS 2 - OBS 7 - Interim Milestones 10 - Work Packages & Planning Packages 12 - LOE 3 - Integration 5 - RAM / Control Accounts 6 - Vertical & Horizontal Integration 6 - Vertical & Horizontal Integration 10-Work Package Characteristics, Objective Techniques US U.S. Government Accountability Office (GAO) Defense Contract Management Agency (DCMA) 10 Scheduling Best Practices IMS 14 Point Assessment 1. Capturing all activities. 4. Establishing the duration of all activities. 2. Sequencing all activities. 8. High Duration – Tasks with Duration > 44 working days (Goal < 5%) Naval Center for Earned Value Management (CEVM) Program Schedule Assessment (PSA) 1. Does the schedule reflect the work to be done? 6. Are duration estimates meaningful? 1. Logic – Tasks without predecessors and / or 3. Is work sequenced logically? successors (Goal < 5%) 5. Integrating schedule activities horizontally 4. Relationship Types – Finish-to-Start (FS) and vertically. should be the most common (Goal > 90%) 4. Are interdependencies planned in a logical manner? 2. Leads – (negative lag) Distorts the critical path (Goal 0%) 2. Sequencing all activities. 5. Are constraints, leads, and lags justified? 3. Lags – (positive lag) Excessive size and / or usage distorts the critical path (Goal < 5%) 30 (c) AzTech International, LLC 2014 Generally Accepted Scheduling Principles (GASP) Alignment to: ANSI, GAO, DCMA, & Naval Center for EVM Generally Accepted Scheduling Principles (GASP) ANSI/EIA-748-B Earned Value Management Systems (EVMS) Guidelines US U.S. Government Accountability Office (GAO) Defense Contract Management Agency (DCMA) Naval Center for Earned Value Management (CEVM) 10 Scheduling Best Practices IMS 14 Point Assessment Program Schedule Assessment (PSA) 9. Invalid Dates – Tasks with invalid forecast (incomplete tasks to the left of Time Now) or actual start/finish (completed tasks in the future) dates (Goal 0%) Statused 6 - IMS Provides Current Status for All Authorized Work 9. Updating the schedule using logic and durations to determine dates. 11. Missed Tasks – Tasks not completed or forecasted to complete as planned (Goal < 5%) 10. Does the schedule provide logical status and forecasts of completion dates for all authorized work? 14. Baseline Execution Index (BEI) – Tasks completed as a ratio to those tasks that should have been completed to date according to the baseline plan (Goal > 0.95) 6. Establishing the critical path for all activities. Predictive 6 - IMS provides forecast of completion dates for all authorized work 6. High Float – Tasks with Total Float > 44 working days (Goal < 5%) 12. Critical Path Test – Tests the logic in the critical path (Goal “Pass”) 7. Identifying float between activities. 9. Are float times reasonable? 7. Negative Float – Tasks with Total Float < 0 working days (Goal 0%) 13. Critical Path Length Index (CPLI) – Measures the “realism” of the critical path (Goal > 0.95) 8. Does the critical path make sense; does the scheduling software calculate it? 31 (c) AzTech International, LLC 2014 15 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Generally Accepted Scheduling Principles (GASP) Alignment to: ANSI, GAO, DCMA, & Naval Center for EVM Generally Accepted Scheduling Principles (GASP) ANSI/EIA-748-B Earned Value Management Systems (EVMS) Guidelines US U.S. Government Accountability Office (GAO) Defense Contract Management Agency (DCMA) Naval Center for Earned Value Management (CEVM) IMS 14 Point Assessment Program Schedule Assessment (PSA) 10 Scheduling Best Practices Usable 6 - IMS Effective Planning, Statusing, & Forecasting for Achieving Requirements & Measuring Performance 8. Conducting a schedule risk analysis. Resourced 9 - Control Account Level Budgets & Detail 10 - Control Account Plans (CAPs) 3. Assigning resources to all activities. Controlled 8 - Baselined Performance Measurement Baseline (PMB) 29-32 - Documented processes for tracing authorized changes & controlling retroactive changes 10. Maintaining a baseline schedule 5. Hard Constraints – Tasks not designated as 5. Are constraints, leads, and lags justified? As Soon As Possible (ASAP), Start No Earlier Than (SNET), or Finish No Earlier Than (FNET) 2. Are critical target dates identified; are they (Goal < 5%) being used to plan the work? 10. Resources – If loaded, tasks without dollars or hours assigned (Goal 0%) 7. Are resource estimates reasonable; are key resources available to support the plan? 11. Can the current program schedule be accomplished at an acceptable risk level? 32 (c) AzTech International, LLC 2014 Integrated Master Schedule (IMS) • • • • • • Networked, detailed tasks to assure successful program execution Traceable to SOW, WBS, IMP (if required), Control Accounts, Work Packages Facilitates effective planning, statusing, and forecasting Significant interdependencies to determine duration & critical path Foundation for Performance Measurement Baseline (PMB) Updated at least monthly with latest forecast and revisions Credit: NAVAIR IPM190 IBR Prep Workshop 33 (c) AzTech International, LLC 2014 33 16 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review “Living at risk is jumping off the cliff and building your wings on the way down.” Ray Bradbury SCHEDULE RISK ASSESSMENT (SRA) Question? 34 (c) AzTech International, LLC 2014 Schedule Risk Assessment (SRA) 35 (c) AzTech International, Credit: NDIA PASEG LLC 2014 17 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Schedule Risk Assessment (SRA) Credit: NDIA PASEG 36 (c) AzTech International, LLC 2014 Schedule Risk Assessment (SRA) Credit: NDIA PASEG 37 (c) AzTech International, LLC 2014 18 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Quick Quiz If the SRA results tell us there is a 10% chance of finishing by the contract finish date, what are our options? 38 (c) AzTech International, LLC 2014 Transition from Phase I to Phase II Readiness Review validates that PMB documentation is adequate for PMO and CAM discussions Review of artifacts evaluated and traces performed Review of outstanding action items Team recommendation to IBR leadership that Phase II can begin 39 (c) AzTech International, LLC 2014 19 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Readiness Review Is program ready to move forward to Phase II (CAM discussions)? Document quality Integration traces Action Items Transition to Phase II PMO discussions CAM discussions Phase I and Phase II overlapping is possible Parts of Phase II can proceed before Phase I is completed 40 (c) AzTech International, LLC 2014 “There's only one interview technique that matters... Do your homework so you can listen to the answers and react to them and ask follow-ups. Do your homework, prepare.” Jim Lehrer PHASE 2: DISCUSSIONS (OR INTERVIEWS?) 41 (c) AzTech International, LLC 2014 20 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Phase II: PMO/Business Office Discussions • Provides background information so CAM discussions are focused on specific technical issues • Explain program unique procedures • Work authorization process and common documentation • CBB Log and the MR/UB guidance • Development and maintenance of CAM EVM information • Introduction to the IMS including integration of suppliers / contractor data • Subcontracts /supplier management • Role of Program Control and CAM • PMB maintenance 42 (c) AzTech International, LLC 2014 Phase II: CAM Discussions • Ensure work is achievable as planned at the control account level CA Selection Moderate to high risk Critical Path Goal ~ 80% of PMB Methods Individual discussions Round table discussions from single IPT / risk area Combination of methods Scoring / Action Items 3 ratings: high risk, medium risk, low risk By risk areas: technical, schedule, cost, resource, management processes Summarized to program level 43 (c) AzTech International, LLC 2014 21 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Overall IBR Scoring 56 (c) AzTech International, LLC 2014 Training, Supplier IBRs, & Rolling Waves IBR Training EVMS, Phase I training, Phase II training Subcontractor and Supplier IBRs Sequencing and incorporating into single IBR (if possible) Differences in award dates Firm-Fixed Price (FFP) Suppliers Subcontractor schedule & integration into IMS still required Rolling Wave Planning Converting Planning Packages into Work Packages Follow-on “mini IBRs”? 57 (c) AzTech International, LLC 2014 22 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Process Document Templates Provide consistent approach Increase efficiency of process Sample IBR schedule Artifact list Data call request Trace Narratives Readiness Review brief CAM questions CAM scoring criteria IBR briefing Memo for Record 58 (c) AzTech International, LLC 2014 Sample IBR Risk Assessment Checklist (DoD) Credit: ACC.DAU.MIL 59 (c) AzTech International, LLC 2014 23 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Sample IBR Program Summary Results Credit: GAO Cost Estimating & Assessment Guide 60 (c) AzTech International, LLC 2014 Sample Program Risk Analysis Credit: Naval Center for EVM (CEVM) Analysis Toolkit 61 (c) AzTech International, LLC 2014 24 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review References… • • • • • • • • PARCA GAO DAU DCMA NASA Navy CEVM NAVAIR Air Force Credit: Performance Assessments and Root Cause Analyses (PARCA) 62 (c) AzTech International, LLC 2014 “The pessimist complains about the wind; the optimist expects it to change; the realist adjusts the sails.” William Arthur Ward CONCLUSIONS 63 (c) AzTech International, LLC 2014 25 ICEAA 2014 Professional Development & Training Workshop INT 07 - Integrated Baseline Review Benefits of Streamlined IBR Process Common understanding of IBR process and expectations Early identification of problems to employ risk mitigation Promotes joint ownership of program goals Enables comparison of IBRs across company or portfolio of programs 64 (c) AzTech International, LLC 2014 Streamlined IBR Process Thank you! Luis C Contreras, [email protected] Q&A 65 (c) AzTech International, LLC 2014 26 ICEAA 2014 Professional Development & Training Workshop
© Copyright 2026 Paperzz