SOUTHPOINT CONDOMINIUM Project Summary Week #29 November 18th through November 22nd, 2013 The 8-man crew worked as much as possible through heavy rain this week to progress on the second phase of east elevation hollow-core panel excavations and parking garage beam and column repairs. Foam EIFS was installed on the north end walkway slab edges and trimmed to create a level edge for kneewall construction. Embedding of reinforcing mesh with Primus cement-based adhesive was in-progress on foam EIFS slab edges in order to prepare for stucco finish application scheduled to begin next week. The second phase of pre-stressed hollow-core floor panel repairs was in-progress on Units 108, 109 and 110. Forms and post shores were removed from cast back floor slabs on Units 107, 109 and 110 and post shores were remounted to allow for completion of floor panel excavations on Units 108, 109 and 110. Forms were built and installation of reinforcing steel was in-progress Friday in preparation for casting. North corner walkway beam spalls were marked out by the engineer on the 5th through 2nd floors. Post shores were mounted, excavations were completed and form construction was in-progress Friday. Parking garage east column and beam spalls were also marked out by the engineer and excavations were completed. Repairs with hand packed patching mortar were in-progress Friday on parking garage beam excavations and are scheduled for completion early next week. Page 1 SOUTHPOINT CONDOMINIUM Foam EIFS installed on north end walkway slab edges. Installation of reinforcing mesh with Primus adhesive in-progress. Page 2 SOUTHPOINT CONDOMINIUM Post shores mounted to allow for north corner walkway beam spall excavations. Excavation completed on north corner walkway beam spall. Page 3 SOUTHPOINT CONDOMINIUM Excavated hollow-core floor panel at Unit 109. Post shores mounted and forms built on Unit 109 excavated floor panel. Page 4 SOUTHPOINT CONDOMINIUM Excavated beam spall in east side parking garage. Forms built on excavated column spall in parking garage. Page 5
© Copyright 2026 Paperzz