WORLDWIDE HEAVY TRANSPORTATION AND LIFTING Case Studies – Europe INSTALLATION OF THE FREYBRÜCKE BRIDGE IN BERLIN, GERMANY WIKINGER PROJECT IN PUERTO REAL, CÁDIZ OVERVIEW: ALE has successfully completed the transportation and load-out of one jacket and one topside in Puerto Real, Cádiz. OVERVIEW: ALE has installed the Freybrücke Bridge, weighing 400t, in Berlin, Germany. SERVICES REQUIRED: The topside was separated into two parts: Topside I and II. SERVICES REQUIRED: The 400t bridge deck was built on supports, about 10m from the quayside. Prior to the transport manoeuvres, ALE performed the weighing of the three structures with 500t capacity load cells and jacks. These weighed between 2,500t – 2,900t. The three manoeuvres were performed following the same procedure and consecutively. To allow ALE to install their skidding system, the bridge deck was jacked-up 400mm using climbing jacks. The barge, with the skidding supports, was berthed and prepared for the load-out operation of the bridge deck. The strand jack construction, consisting of six unit beams, an anchor head and a strand jack, was installed on the arc of the bridge. Using this construction, ALE released the bridge into the separate anchor heads which allowed ALE to remove the strand jacks. The bridge deck could then be suspended in the strand wires for a couple of months. In total, there were eight constructions installed with a 70t strand jack, and four constructions installed with a 500t strand jack. The bridge deck was skidded 30m onto the barge within five hours. During the skidding operation, the barge stability was controlled using pumps with a total ballast capacity of 360m³ per hour. After positioning the bridge deck onto the barge, the link beams between the barge and quay were removed using an 80t crane. To ensure that the bridge deck could cross the existing bridges, the bridges were measured, the water level of the river was studied and the barge was set to maximum draught. The transport height of the bridge deck was decreased by jacking-down the bridge deck using four 150t capacity climbing jacks in order to transport the bridge deck under existing bridges with a clearance of just 100mm. Whilst the bridge deck was being transported 1km, it was turned 180 degrees using two tugs and the mooring lines were connected using a small tug. After connecting the mooring lines, the barge was positioned beneath the arc using six winches, with a total capacity of 40t, and the strand jack anchors were connected. The bridge deck was lifted off the barge by strand jacks, as the barge was released and transported back to the quay side. Whilst the bridge deck was lifted into its end position, a second team was disassembling the barge and preparing it to be transported back to the supplier. All load-out operations were performed on schedule. The operation is part of the Wikinger project and also it includes loading 29 jackets by crane in the port of Ferrol, which is currently still ongoing. These pieces will eventually be part of Wikinger, the German offshore wind farm. This substation will become the heart of the offshore wind energy park based in the Baltic Sea. The electricity produced by its wind turbines offshore will power 350,000 German households and CO2 emissions by almost 600,000t per year. The client then welded the bridge deck and, once the curve was checked, ALE tensioned the strands for the second time when necessary so the pendants of the bridge could be installed. After the pendants were installed, all of the strand jack constructions were removed. OVERVIEW: ALE has performed the transportation of an STS crane, weighing 800t, within the terminal of Port-Nou in Barcelona. SERVICES REQUIRED: The crane was transported from its original location to its new location and placed onto the rails. Prior to the transportation, ALE welded the transport brackets on-site. These were specifically designed by ALE for that manoeuvre. The transportation was performed using 40 axles lines of SPMT and two cross beams, measuring 14m long. The beams were previously assembled on temporary supports which transferred the load from the crane resistant areas to the transport platforms. The transport was completed in just one day - as planned which minimised the impact on the traffic in the terminal. TOGETHER, WE ARE SMARTER, SAFER, STRONGER The jacket was loaded-out onto a single barge and both sides of the topside were loaded-out onto a second barge. The bridge deck was finally set down into the strand jack construction. After the installation, ALE waited until they received confirmation from the client that ALE could proceed with the removal of the strand jacks. ALE tensioned the strands separately upon client instruction to create the right curve into the bridge deck. TRANSPORTATION OF AN STS CRANE IN THE TERMINAL OF PORT-NOU IN BARCELONA, SPAIN 1. First, the jacket was transported from its fabrication yard until it was in line with the barge using 120 axle lines of SPMT in a configuration of 6 x 4 file 10 axles. ALE then loaded-out the jacket in a vertical position using the same transport configuration. The delivery alongside the ship and load-out of the topside was performed using the same method, equipment and sequence of work used for the jacket. For topside I, ALE utilised 72 axle lines of SPMT in a configuration of 2 x 4 file 18 and 48 axle lines in a configuration of 2 x 4 file 12. For Topside II, ALE utilised 120 axle lines of SPMT in a configuration of 2 x 4 file 30. LOAD-OUT AND LIFTING OF A 394T PILE GRIPPER, BELGIUM AND THE NETHERLANDS OVERVIEW: ALE performed the load-out of a 394t pile gripper on quay 136 in Antwerp, Belgium. This was followed by the mobilisation of the pile gripper in Flushing port, the Netherlands. SERVICES REQUIRED: The pile gripper was used during the Geoseas Race Bank project to install the monopiles. The pile gripper was located on stools, approximately 30m from the quayside, and was supported in the centre and at the front. 20 axle lines of SPMT in a 2 x 10 axle configuration were used to perform the load-out. Throughout the load-out, the barge was ballasted. In order to position the SPMTs, ALE needed to remove the stools side by side to stabilise the pile gripper’s Centre of Gravity. Once in position, ALE raised the SPMTs and lashed the pile gripper onto the SPMTs. The following morning, the pile gripper was transported to the quay and loaded in steps onto the barge. The pile gripper was placed on stools in the reverse way as during the lifting procedure. ALE drove the SPMTs underneath the pile gripper, after which a mobile crane was provided by the client to lift the SPMTs off the barge and onto the trucks, which were located on the quayside. The pile gripper was then sea-fastened and transported to Flushing Port in the Netherlands, ready for mobilisation on the ship, Innovation. The barge with the Pile Gripper was positioned at the aft side of the Innovation. ALE chose a special rigging configuration which included strand jacks so ALE could install the pile gripper at its correct angle. ALE configured the rigging on the quayside and lifted the rigging using the main hoist of the Innovation. The main hoist was moved until above the pile gripper, after which the pile gripper was connected to the rigging, lifted and positioned above its final position. Finally, the pile gripper was adjusted to the correct angle using a lifting computer connected to the strand jacks, before being lowered and connected to the ship. TOGETHER, WE ARE SMARTER, SAFER, STRONGER 2. WORLDWIDE HEAVY TRANSPORTATION AND LIFTING Case Studies – Europe TRANSPORTATION AND STORAGE OF A REACTOR HEAD, SPAIN RICKMANSWORTH BRIDGE REPLACEMENT, UK OVERVIEW: ALE has performed the onsite transportation of a 60t reactor head from its temporary storage area, the fuel building, to the storage building at the Vandellos nuclear power plant. The transportation also involved skidding and lifting manoeuvres. OVERVIEW: ALE has carried out the successful removal and installation of overbridge MR88 in Rickmansworth in North West London, UK. SERVICES REQUIRED: In order to transport the reactor head between both buildings, 6 axle lines of SPMT were used. The head was loaded onto the SPMTs at the fuel building using an overhead crane. All manoeuvres were carefully and precisely coordinated, performed to a strict schedule without any significant deviation or impact to other activities inside the plant. Because of this, the client and all other parties involved considered the project a complete success. The new bridge weighed approximately 150t and was installed using another 16 axle lines of SPMT in a 4 file 8 configuration. Again, the SPMTs’ packing consisted of a jacking frame and climbing jacks. The new bridge had to be driven in below the services and above the new cill units, which were at various levels. Once at the entrance of the storage building, the reactor head was offloaded by means of a 500t hydraulic crane and positioned onto the skidding system. A modular skidding steel structure was previously installed so the head could fit through the entrance at a height of 4.3m above ground level. The head was skidded inside the building and, once inside, was lowered into position using a 500t hydraulic crane. The crane was operated from outside the building, through a hole made in the roof in order to allow the use of the long sling during the crane manoeuvre. Once the head was at ground level, it was skidded into its final position. The bearings were attached to the underside of the bridge prior to the bridge move. The bridge was lowered down utilising the climbing jacks on the SPMTs and the bearings were lined up with pre-formed pockets in the cill units by incorporating alignment gear into the scheme. There were several major challenges that ALE needed to overcome to ensure that the scheme was a success. Due to space restrictions in the site compound, it was necessary to rig the SPMTs during planned night time road closures and prior to the possession, as well as de-rig the SPMTs during the planned night time road closures during the possession. The operation also included the transportation and storage of 10 vessels containing Control Rod Drive Mechanisms (CRDMs), weighing 10t each. All of these containers were transported and installed using a similar method. Another challenge ALE faced was moving the old bridge into the site compound up a steep ramp. ALE used a tractor unit to assist with pulling the SPMTs and old bridge off the road and into the compound. This operation had to take place within a one-hour window due to traffic management restrictions. TRANSPORTATION OF A SHIP SECTION, ROMANIA OVERVIEW: ALE has successfully performed the transportation of a 2,400t ship section in Constanta, Romania. then done on the load and all steering functions in the SPMT configuration was checked. SERVICES REQUIRED: The ship’s stern was built by the client onto a frame in a dry-dock behind an intermediate wall. A dock crane was used to lift the SPMTs into the dry dock. The frame allowed for 112 axle lines of SPMT positioned in a 5 file configuration under the ship section. ALE then transported the ship’s stern until it was 5m from the front ship section, where the alignment of the two pieces was checked. The ship’s stern was then transported until 50mm from the other ship section so the levelness of the pieces was corrected. The ship’s stern was cut to the required dimensions before both pieces were joined. Each line of SPMT had its own power pack, which enabled them to be installed under the frame separately. Once positioned, all lines were pressurised to a minimal load and all trailers were hydraulically and electrically connected. Further testing was 3. TOGETHER, WE ARE SMARTER, SAFER, STRONGER SERVICES REQUIRED: The existing bridge weighed approximately 80t and was removed utilising 16 axle lines of SPMT in a 4 file 8 configuration. The SPMTs steelwork packing consisted of a jacking frame and climbing jacks. The climbing jacks enabled the old bridge to be lifted from its bearings and clear of all obstacles on the abutment before being driven back to the compound ready for demolition. The ship section was transported against the front part of the ship. Once the pieces were together the frame from the ship’s stern was removed and the SPMTs were driven out from below the frame and disassembled. LOAD-OUT OF AN 800T SHIP SECTION, THE NETHERLANDS OVERVIEW: ALE performed the load-out of an 800t ship section in Hardinxveld-Giessendam, the Netherlands. SERVICES REQUIRED: Prior to the load-out, ALE jacked-up the ship section using 13 climbing jacks. 40 axle lines of SPMT in a configuration of 2 x 4 file 10 were placed underneath the ship section and in between the climbing jacks. The ship section was transferred by lifting the SPMTs and transported onto the barge during the rising tide to minimise the ballasting. Once on the barge, the ship section was lowered on its supports. The SPMTs were then lowered and removed. The barge was then towed to a suitable location, where the barge was submerged and the float-off of the ship section performed. TOGETHER, WE ARE SMARTER, SAFER, STRONGER 4.
© Copyright 2026 Paperzz