Damage preventing measures for wind turbines Phase 1 – Reliability data Elforks report 10:68 Fredrik Carlsson, Emil Eriksson, Magnus Dahlberg August 2010 Damage preventing measures for wind turbines Phase 1- Reliability data Elforks report 10:68 Fredrik Carlsson, Emil Eriksson, Magnus Dahlberg August 2010 Foreword The Vindforsk III project V-316, Damage preventing measures for wind turbines, aims at developing recommendations regarding damage preventing measures and way of carrying out inspection and condition monitoring to reduce maintenance cost for wind turbines. The project is carried out by Inspecta AB and Vattenfall Research & Development. This report is the reporting from the first phase of the project with an inventory of existing reliability and failure data in the public sources. Vindforsk – III is funded by ABB, Arise windpower, AQSystem, E.ON Elnät, E.ON Vind Sverige, EBL-kompetanse, Falkenberg Energi, Fortum, Fred. Olsen Renwables, Gothia wind, Göteborg Energi, HS Kraft, Jämtkraft, Karlstads Energi, Luleå Energi, Mälarenergi, o2 Vindkompaniet, Rabbalshede Kraft, Skellefteå Kraft, Statkraft, Stena Renewable, Svenska Kraftnät, Tekniska Verken i Linköping, Triventus, Wallenstam, Varberg Energi, Vattenfall Vindkraft, Vestas Northern Europe, Öresundskraft and the Swedish Energy Agency. Comments on the work and the report have been given by a reference group with the following members: Jenny Ohlsson from Statkraft, Hans Sollenberg from O2, and Anders Björck from Elforsk AB. Stockholm augusti 2010 Anders Björck Programme maganger Vindforsk-III Electricity- and heatproduction, Elforsk ELFORSK Sammanfattning Status och kvalitet hos tillgänglig information om tillförlitlighet och skador har undersökts. Det huvudsakliga målet har varit att utvärdera informationen ur ett skadeförebyggande perspektiv. Flera offentliga databaser finns, och deras innehåll har diskuterats i flera artiklar inom litteraturen. Resultatet av undersökningen kan förefalla vara ganska negativt. Detaljerad information saknas och rapporteringsdisciplinen försämras på senare år. Information om hur yttre betingelser som t.ex. lastförhållande påverkar skadestatistiken saknas helt. Några komponenter dominerar skadestatistiken. Ett exempel är växellådor där haveri kan leda till långa stillestånd. Skada på elsystem uppträder oftare men är å andra sidan lättare att åtgärda. Allvarliga rotorhaverier är ovanliga, men har inträffat i några fall. Operatörer underhåll, Samarbete vara viktigt och försäkringsbolag har en klar målsättning att öka insynen i insamling av skadedata och skadeförebyggande åtgärder. med dessa aktörer bör kunna leda till förbättrad kännedom och i arbetet med skadeförebyggande åtgärder. I rapporten föreslås förbättringar för framtida insamling av skade- och tillförlitlighetsdata. En struktur för datainsamling föreslås. I det fortsatta arbetet kommer skadeförebyggande åtgärder för vindkraftkomponenter att utvärderas. Detta görs med utgångspunkt från resultaten i denna rapport. Erfarenheter från andra branscher kommer att jämföras med nuvarande praxis inom vindkraftbranschen. Dessutom kommer kunskap om de olika skademekanismerna att användas vid utvärderingen. ELFORSK Summary The state of existing reliability and failure data in the public sources has been investigated. The prime goal has been to evaluate the data’s usefulness for developing damage preventing measures. Some publicly available databases exist, and the data has been presented in several papers in the literature. The results from the investigation can seem quite negative. Detailed data are lacking and the level of detailed reporting has even been decreasing in recent years. Information on the impact of load condition on failures, which is an important question, are lacking throughout in the statistics. Some components dominate the failure statistics. These are for example the gearboxes, where failures lead to long down times. Failures of the electrical system lead to considerably shorter down times but the failure rate is much higher. Severe rotor failures seem to be rare, but they occur and the consequences can be dramatic. Operators and insurance companies are demanding improved insight in damage collection, maintenance and overall damage preventing measures. Closer cooperation with these parties could be a fruitful way of gathering more useful data. Improvements for future databases are suggested. A structure for damage collection is proposed. Comparing experience of damage preventing measures from other industries, knowledge about the nature of the damage mechanism and current practice in the wind industry will be an important tool in the evaluation of different damage preventing measures. This will be done in the following phases of this project. ELFORSK Table of Contents 1 Introduction 2 List of definitions 3 3 Available databases concerning availability, reliability and failure of wind turbine components 4 1.1 1.2 3.1 4 Sources for wind turbine reliability and availability data ........................ 4 3.1.1 Vindstat – Swedish Database ................................................. 4 3.1.2 WindStats Newsletter – International database ......................... 8 3.1.3 Fraunhofer IWES ................................................................ 11 3.1.4 VTT .................................................................................. 13 3.1.5 LWK ................................................................................. 13 Available reliability data and data quality 4.1 4.2 4.3 4.4 1 Reference group .............................................................................. 2 Acknowledgements .......................................................................... 2 15 Overall information about wind power reliability ................................. 15 4.1.1 General information ............................................................ 15 4.1.2 German information from WMEP ........................................... 16 4.1.3 German information from WindStats ..................................... 19 4.1.4 Finnish information from VTT ............................................... 21 Detailed failure information for turbine components ............................ 23 4.2.1 Electrical system ................................................................ 23 4.2.2 Generator ......................................................................... 24 4.2.3 Gearbox ............................................................................ 24 4.2.4 Pitch regulation .................................................................. 26 4.2.5 Mechanical brake ............................................................... 26 4.2.6 Hydraulic system................................................................ 27 4.2.7 Yaw system ....................................................................... 27 4.2.8 Sensors and control system ................................................. 27 4.2.9 Rotor and structure ............................................................ 27 4.2.10 Transformers ..................................................................... 29 Experiences from operators and insurance companies ......................... 29 4.3.1 Rotor ................................................................................ 29 4.3.2 Gearbox ............................................................................ 30 4.3.3 General experiences and opinions ......................................... 31 General conclusions of available reliability data .................................. 31 5 Conclusions and recommendations 33 6 References 35 Appendix A. Data provided by Trygg Hansa. 37 Appendix B. Suggestion for a database structure. 40 ELFORSK 1 Introduction This report presents results from phase one of the project Damage preventing measures for wind turbines. This title (somewhat differing from the original) was set during the course of the project to accurately describe the aim of the project. The project aims at evaluating and proposing damage preventing measures for wind turbines. It is important that the measures are practical and possible to implement at the current state of technology. Previous experience of damages and reliability data is an essential input. Introducing damage preventing methods that require reliability data on a level that does not exist makes little sense. It is therefore important to define the current level of reliability data. This phase one of the project, Reliability Data, deals with the investigation of sources of reliability data. Publicly available databases and the open literature constitute the main sources. These data are also complemented by interviews and other contribution from operators and insurance companies. The quality of these data and the usefulness for establishing damage preventing methods are evaluated. The initially formulated goals for phase one read: To analyze how damages depend on important parameters such as age and type of turbine and to propose a common, standardized procedure for the reporting of damages to a database. The question about database procedures is dealt with in more detail in a neighbouring VindForsk project, “V-344 RAMS-database for wind turbines”. Hence, the project rather aims at proposing a component breakdown structure suitable to connect with appropriate damage preventing measures. In more detail, the following goals have been governing for phase one: • Investigating the current state of reliability and failure data in the public sources • Evaluating the usefulness and limitations for establishing damage preventing measures • Investigating alternative sources such as direct communication with operators and insurance companies • Investigating how damages depend on important parameters such as age and size. • Defining the needs for improvements. • Proposing a component structure for databases. The structure should enable linking between component and damage preventing measure. Moreover, a structure for the future collection of damage data is proposed. The level of detail should be sufficient for establishing suitable damage preventing measures. The structure is intended to be used for the integration with other databases or as a stand alone database. This report of phase one will later on be integrated in the final report of the project. 1 ELFORSK Figure 1: Modern wind energy plant in rural scenery. 1.1 Reference group Vindforsk finances this project and the members of the reference group are: • Hans Sollenberg, O2 • Jenny Olsson, Statkraft • Anders Björck, Elforsk 1.2 Acknowledgements The reference group are thanked for valuable comments on the report as well as good suggestions during the work. Contributing operators and insurance companies are also thankfully acknowledged. 2 ELFORSK 2 List of definitions The below list defines some of the terms used in the report, thus facilitating the reading. The definitions, where applicable, in all essential follow those in European Standard EN SS 13306[25]. In cases mathematical definitions are needed, these will be given in the text. Reliability: Ability of an item to perform a required function (under given conditions for a given time interval) Availability: Ability of an item to be in a state to perform a required function (under given conditions at a given instant of time or during a given time interval, assuming that the required external resources are provided). Down time (stop time): Time (real or reported) interval during which an item is in a down state Failure rate/frequency: Number of failures of an item in a given time interval divided by the time interval Damage mechanism: The physical process causing degradation and potential failure if the component. Failure data: information about rate, cause, damage mechanism etc. Time for replacement: Total time from failure to installation of a new component including administration, purchase, repair etc. 3 ELFORSK 3 Available databases concerning availability, reliability and failure of wind turbine components 3.1 Sources for wind turbine reliability and availability data 3.1.1 Vindstat – Swedish Database Vindstat (website www.vindstat.nu) is a Swedish database with operational data from about 800 of the approximately 1300 wind turbines installed in Sweden. The Vindstat database [1] is operated by Vattenfall Power Consultant AB (VPC) and paid for by the Swedish Energy Agency. The data collection started in 1988. The information from each wind turbine was sent by fax and then manually put in to the database. A system for automatic reading of the turbines once every 24th hour, was installed in 2002. The data consists of total production during the last 24 hours and current operation mode (if the turbine generator is connected to the grid or not). This information is stored in a database. The data are presented in monthly and annual reports. General information in the database is manufacturer, installation year, and rated power of each turbine. The total production and the total number of hours the generator has been connected to the grid can be found. The number of stops is not reported to the database. This information could possibly be locally available in the logbooks of the individual turbines. During the period of manual reporting, the reason for a stop was occasionally reported. Such information could be if the turbine stopped due to grid failure, planned service or component failure. Sometimes these reasons are still reported to VPC even though the general system of reporting detailed data was abandoned in 2005. The trend today is that a few wind power operators own the majority of all recently installed wind turbines. The service is often performed by the turbine manufacturer during the first years. Thus the wind power owner often has limited access to detailed reliability data and failure data (Carlstedt [8]). Therefore, normally only the (total) down time is reported to the database today. Data from Vindstat [1] is presented in Figure 2 to Figure 7. 4 ELFORSK Size of total numbers of installed Swedish wind turbines 1990-2009 <500 kW 500-1000 kW 1000-2000 kW >2000 kW 2000 2003 100% 90% 80% 70% Percent 60% 50% 40% 30% 20% 10% 0% 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2001 2002 2004 2005 2006 2007 2008 2009 Year Figure 2. Accumulated number of Swedish wind turbines divided by power classes from 1990 to 2009. Note: These are only the turbines reporting to Vindstat and not all Swedish turbines [1]. Share of annual installed Swedish wind turbines 1990-2009, divided by power class <500 kW 500-1000 kW 1000-2000 kW >2000 kW 2000 2003 100% 90% 80% 70% Percent 60% 50% 40% 30% 20% 10% 0% 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2001 2002 2004 2005 2006 2007 2008 2009 Year Figure 3. Annual share of power classes for installed wind turbines in Sweden. Note: These are only the turbines reporting to Vindstat and not all Swedish turbines [1]. 5 ELFORSK The Vindstat reports show the availability in per cent per year of each turbine. The availability during a specified period is defined as Availability = Time of the period − Stoptime ⋅100% , Time of the period (1) The down (stop) time is the total number of hours that the generator has been disconnected from the grid (Carlstedt [3]). The time for one year is set to 8760 h. Since mainly the general stop time is reported to the database today, it is not possible to extract reliability data on component level (Carlstedt [4]). The availability of the around 800 Swedish turbines reporting to Vindstat is included in shown in Figure 4. The mean value is 96% with a standard deviation of 8%. Actually, over 70% have availability over 97%. Furthermore, it can be recognised from Figure 4 that the mean availability does not really change over time, even though the data show noticeable differences between individual years. Figure 8 show that a number of turbines are reported to have 100% availability. This figure may not be realistic. This leads to questions about the quality of the data and it is possible that the reported availability overestimates the real data. Hence, availability data should be analysed with caution. Availability of 100% is reported in cases of absence of information [4]. Since some of the turbines reporting to Vindstat actually fail to report they will increase the Availability to un-realistic levels. It is suggested that this problem is further scrutinized and corrected in future studies. According to information, IEC is developing a standard for availability which may be a solution to the problem. 100 90 80 Availibility [%] 70 60 Wind mill 50 Mean 40 30 20 10 0 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Installation year Figure 4. Availability in 2009 of Swedish turbines included in the Vindstat database [1] by installation year. 6 ELFORSK 300 Number of turbines 250 200 150 100 50 0 <88 89 90 91 92 93 94 95 96 97 98 99 100 Availibility [%] Figure 5. Histogram of wind turbine availability in Sweden during 2009 from Vindstat [1]. A significant number of the turbines show an availability of 100%, which is caused by inadequate reporting routines. The availability for different turbine sizes is shown in Figure 6. The availability seams to be independent of size. Most turbines have a reported availability well over 90%. Only three power classes have a lower availability. Furthermore, the availability for different manufacturers for turbines > 1.5 MW have been investigated in Figure 7. The difference is not significant between the manufacturers. Siemens has the highest availability for the year 2009. However, once again the availability data should be treated cautiously. 7 ELFORSK Availability of Swedish wind turbines divided by power class 100 90 80 Availibility [%] 70 60 50 40 30 20 10 0 150 200 230 450 490 500 600 660 750 800 900 1000 1425 1500 1750 1800 2000 2300 2500 3000 Pow er [kW] Figure 6. Availability in 2009 divided by power class of Swedish wind turbines according to Vindstat [1]. 100,0 90,0 80,0 70,0 60,0 50,0 97,1 93,2 97,8 94,9 Siemens Vestas 40,0 30,0 20,0 10,0 0,0 Enercon NEGMicon Figure 7. Total availability of Swedish wind turbines larger than 1,5 MW during 2009 according to Vindstat [1]. 3.1.2 WindStats Newsletter – International database WindStats Newsletter is a quarterly international wind energy publication with news, reviews, and wind turbine production and operating data from turbines in Sweden, Denmark, Germany and Finland. The data in WindStats are on a similar format as the data in the Swedish database Vindstat, see chapter 3.1.1. Vindstat constitutes the Swedish input to WindStats. The information from Germany comes from Betrieber-Databasis/IWET, from Finland the information comes from VTT Technical Research Centre of Finland and for Denmark the Danish Energy Agency is responsible [5]. 8 ELFORSK The total number of down hours for individual turbines in Sweden, Denmark, Finland and Germany is available in the WindStats Newsletter. The number of stops and down hours is also presented in more detail for all German turbines. These data can to some extent be related to the cause of the stop. This is more useful than only overall data. The numbers of stops and the total down time is reported. The data are also split up on the cause of the stops (Weather, Grid, etcetera) and which component of the turbine that failed (Gearbox, Rotor etcetera). The Betrieber-Databasis/IWET has been in use for over 20 years and around 20000 individual turbines are reporting to the database (Keiler [6]). A table with original data from WindStats Newsletter for the third quarter of 2009 is presented in Table 1 below. Unfortunately, the failure data are not specified for wind turbine size, type or manufacturer. Neither is information on turbine age available. Table 1. Number of stops and down hours for individual turbines in Germany, for the third quarter of 2009. Around 21000 turbines were installed at the time according to WindStats [7]. Reliability data from WindStats during 1999-2008, also divided on wind turbine components, are available thanks to Canter [8]. However, the current reporting routines do not give as detailed information compared to some years ago. The number of stops reported under the categories “Entire unit, “Other” and “Only down hours reported”, i.e. nonspecified reason, increases continuously during period 1999 to 2009. Clearly, the possibilities for adequate analysis of the data are hampered. In 1999, 62% percent of all stops were reported under these categories. In numbers this means 4700 stops out of totally 7600 stops, of around 7000 turbines. In 2008, the corresponding figure was 93% (39500 stops out of totally 42600 stops, and around 20000 turbines). The trend is evident from Figure 8 and Figure 9. The number of stops reported in detail remains fairly constant over the period. Thus the number of stops without specification increases in absolute numbers. 9 ELFORSK Total numbers of stops, 1999 Entire unit Rotor Air brake Mech. brake Pitch adjust. Main shaft/bearing Gearbox Generator Yaw system Anamometer Elec. controls Elec. system Hydraulics Sensors Other Only stop hrs. reported Figure 8. Total number of stops split on components for German wind turbines reporting to WindStats in 1999 [8]. The total number of stops is around 7600, of which 38% is reported on individual components. The total number of turbines was around 7000. 10 ELFORSK Total numbers of stops, 2008 Entire unit Rotor Air brake Mech. brake Pitch adjust. Main shaft/bearing Gearbox Generator Yaw system Anamometer Elec. controls Elec. system Hydraulics Sensors Other Only stop hrs. reported Figure 9. Total number of stops split on components for German wind turbines reporting to WindStats in 2008 [8]. The total number of stops is around 42600, of which only 7% is reported on individual components. The total number of turbines is around 20000. 3.1.3 Fraunhofer IWES The German institute Fraunhofer Institut für Windenergie und Energiesystemtechnik (Fraunhofer IWES, formerly Institut für Solare Energieversorgungstechnik, ISET) has performed a large monitoring programme for wind power turbines. The monitoring programme was called Scientific Measurement and Evaluation Programme (WMEP). Faulstich [9] reports that 1500 turbines of a total rated power of 250 MW were closely monitored during 1989 to 2006. During this period over 64000 maintenance and repair reports and 193000 monthly operational reports were analysed. The German Ministry for the Environment, Nature Conservation and Nuclear Safety (BMU) has supported the German Wind Monitor project since 2007, which can be seen as a continuation of the WMEP. Unfortunately, reporting failure statistics was only mandatory during the original time of the WMEP period. Today the reporting is done on a voluntary basis. Consequently, the number of wind turbines involved dropped substantially after the last year of the program (Echiavarra et al [10]). The continuation of the WMEP on the smaller scale however still releases a report once a year, the Windenergy Report Germany [11]. Unfortunately, no raw data, but only diagrams and graphs were available from WMEP for this project. However, the available information in Windenergy Report Germany is still of use. The trend of the annual share of power classes for wind turbines installed each year in Germany are presented in this report, see Figure 10. 11 ELFORSK Figure 10. Annual share of power classes for installed wind turbines in Germany, presented in Windenergy Report Germany [11]. Another interesting trend is how the availability of wind turbines varies over the years, which has been studied in Figure 11. Technical availability in Figure 11 is defined as: Availability = Available time ⋅100% . Nominal time (2) The Available time is the time when the turbine is functional and available for generation and Nominal time is the total reporting period. This means that the availability numbers from WMEP, which are showed in Figure 11, are calculated more or less in the same way as the availability from Vindstat [3], see 3.1.1. 12 ELFORSK Figure 11. Average technical availability for German wind turbines from the Windenergy Report Germany [11]. The availability levels on average have always been between 98 and 99 % most of the time since the start of the monitoring programme (Figure 11,). It was slightly below 97.5% in 2002. It is once again noted that these values are very (unrealistically?) high and should be analysed with caution. The availability and reliability data from the Windenergy Report Germany 2008 is further analysed in chapter 4. 3.1.4 VTT In the end of 2008, there was 142 MW of installed wind power in Finland The aim of the Finnish government is to increase to 2000 MW in 2020. Every month since 1996, Finnish wind power operators, manufacturers and third parties send in production and down time data of wind turbines to VTT. Detailed information about down time is sent manually and on a voluntary basis. VTT then compile the information and publish it in monthly and annual reports, similar to WindStats Newsletter and the Swedish database Vindstat. These reports include energy production and total down time for each turbine, while details about failures on component level are classified information and are therefore not published in detail (Stenberg [12]). The manual system for reporting details about wind turbine failures in Finland is similar to the system that was used up to 2005 in Sweden (chapter 3.1.1.) The reported down times are split up between icing, service, grid etcetera. This is further discussed in chapter 4. 3.1.5 LWK The Landwirtschaftskammer in Schleswig-Holstein has collected data from some hundred wind turbines in the Schleswig-Holstein federal state of Germany. The reliability data from LWK are categorised on turbine size and wind turbine concept. The data from 1994-2004 13 ELFORSK are analysed in-depth in a PhD thesis by Spinato [13], where turbine component reliability data were divided in three power classes; around 300 kW, around 500 kW and >1 MW. The turbines in each group were also categorised by model and technology (like direct or indirect drive, use of converter, and pitch or stall regulation). 14 ELFORSK 4 Available reliability data and data quality 4.1 Overall information about wind power reliability The quality and usefulness of the information about wind turbine components in the databases (chapter 3) are discussed in this chapter. These discussions are complemented by experience from wind power operators and insurance companies. Information from individual papers and reports will also be discussed. 4.1.1 General information When addressing reliability of components, it is customary to identify three different stages of failure rates. The first stage is ‘Early failures’, or ‘Infant Mortality’, occurring in the beginning of operation. This phase is generally followed by a longer period of ‘random failures’, or “Normal Life’, with a statistically constant failure rate. Finally, the failure rate due to wear and damage accumulation (‘wear-out failures’) increases with operational age. The total life period and the individual phases are normally rather easily identified, and can be illustrated with the so-called Bathtub Curve, see Figure 12. Do wind turbine components follow this curve? Unfortunately for wind turbines, there are probably not enough data available to identify these stages (Echiavarra [10]). Figure 12. The Bathtub Curve [14]. It is of interest to define different parameters for which to group the reliability data. Ideally, it should be possible to study the reliability data as a function of each parameter. Such parameters are manufacturer, turbine type, turbine size, turbine age and also IEC wind 15 ELFORSK turbine class. This project partly aims investigating if it is possible analyse the reliability data as functions of these parameters. 4.1.2 German information from WMEP An overview of failure causes for the turbines examined in the WMEP study is illustrated in Figure 13 and presented in [11]. These figures are based on failures reported from around 1500 German turbines during 2008. The majority of failures are due to component failure or to malfunction of the turbine control systems. In 19% of the cases, the faults were caused by external influences such as storms, lightning, ice accretion or grid outages. Figure 13. Frequency of failure causes on German wind turbines, with a total of 32166 failures presented by Faulstich et al [11]. These figures are based on failures reported during 2008. The distribution of failed components of the turbines in WMEP during 2008 is shown in Figure 14. This information is divided on power classes. It is interesting to see that the number of failures in the electrical system seems to increase dramatically with turbine size. One potential reason could be larger turbines usually being newer and designed with somewhat immature technology compared to the older and smaller turbines. The larger and newer turbines probably use more electrical components, often with higher complexity. This implies that more components can fail (Spinato [13]). 16 ELFORSK Figure 14. Affected components in Germany, divided by power class, Faulstich et al [11]. These figures are based on failures reported during 2008. Figure 15 shows failure frequencies and down times (stop times) per failure for different components. It is apparent that failures on the electrical system (excluding the generator) occur frequently. On the other hand, these failures could be handled relatively quickly. This condition is likely to apply especially for larger turbines, with a higher failure rate of electrical components. It is also probably easier to find spare parts for these newer turbines, which enables quick fix. Failures occur more seldom for the generator and the drive train. However, these are larger components, and the repair time increases. The time for repair of the gearbox on a large turbine, for example, is rather low in Figure 15. It should be noted, however, that there are only a few large turbines included in the study, which may bias the results. Hence, the figures for the large turbine should be interpreted with caution. Thus there is a possibility that no serious failures, demanding time-consuming repairs or replacement, occurred during the period. This scenario could lead to a considerable underestimation of the average down time at gearbox failure. Figure 15 also indicate that larger wind turbines have a higher annual failure rate than smaller turbines. The down time is however generally much shorter than in the case of smaller turbines. According to Faulstich et al [11], this is however more likely the result of quick technical support rather than due to high reliability of the larger turbines. 17 ELFORSK Figure 15. Frequency of failures for different subassemblies and typical down time per failure for different power classes, presented in Faulstich et al [11]. Data from the around 1500 German turbines included in the WMEP from 2008 [11]. (Note: units for P in kW). Annual downtime per subassembly Annual downtime [days] P<500 kW, 500 kW <P<1000 kW, P>1000 kW ni c El ec tro El ec tri ca ls ys co te nt m ro ls ys te m Se Hy ns dr or au s li c sy st em Ya w sy st em Ro M to ec rh ha ub ni ca lb ra Ro ke to rb la de s G ea rb ox G en er St at ru or ct ur al pa rt Dr ive tra in 1,8 1,6 1,4 1,2 1 0,8 0,6 0,4 0,2 0 Subcomponent Figure 16. Total annual down time per subassembly, derived with data from Figure 15 [9]. Data from the around 1500 German turbines included in WMEP during 2008 [11]. 18 ELFORSK Figure 16 indicates that the electrical system and the electronic control system cause the longest down times. The information in Figure 16 is obtained by multiplying the failure rate with the down time from Figure 15. On this ground it could be argued that electrical components should be prioritised in terms of damage preventing measures. In contrast, the larger mechanical components with lower annual failure rate dominate for a single failure. This makes these components more sensitive to individual failures. A few additional failures could dramatically increase the total down time. This is especially true for the gearbox. This sensitivity indicates a high need for damage preventing measures. In the end the priority for damage preventing measures will be subjective. It is clear from the statistics that the type of damage preventing measure may be very different between the components. 4.1.3 German information from WindStats Data from WindStats during 1999-2008 is shown in Figure 17 to Figure 20. Today, around 20000 German turbines report to WindStats (whereof some, but not all, also report to WMEP). It is important to note that the failure classes “Entire Unit”, “Other” and “Only down hours reported” were excluded from the data in these four figures. This is done in order to compare only failures with detailed information. As discussed earlier in this report, 62% of all reported failures were reported without detail in 1999 and as much as 93% of all failures in 2008. However, assuming that failures without detailed information would not bias the data, the proposed presentation gives a clearer picture of the distribution of failure between components. It should be remembered that the data maybe somewhat misleading since such a small fraction of downs are reported with details. Only a more thorough study with more data available could confirm if the distribution is valid for the entire population. Figure 17. Total number of stops between 1999-2008, based on stops reported in some detail. Hence, failures reported under the growing subclasses “Entire Unit”, “Other” and “Only down hours reported” are excluded. Based on data from WindStats and Canter [8]. 19 ELFORSK Percent of all stops Percentage of total stops, divided on turbine components 100% 80% 60% 40% 20% 20 00 20 01 20 02 20 03 20 04 20 05 20 06 20 07 20 08 19 99 0% Year Sensors Hydraulics Elec. system Elec. controls Anamometer Yaw system Generator Gearbox Main shaft/bearing Pitch adjust. Mech. brake Rotor Figure 18. Percentage of total stops between 1999-2008, based on stops reported in some detail. Hence, failures reported under the growing subclasses “Entire Unit”, “Other” and “Only down hours reported” are excluded. Based on data from WindStats and Canter [8]. Total down time divided on turbine components Sensors Hydraulics Hours [h] Elec. system 200000 Elec. controls 150000 Anamometer Yaw system 100000 Generator 50000 Gearbox 0 Main shaft/bearing 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 Pitch adjust. Year Mech. brake Rotor Figure 19. Total number of down time between 1999-2008, based on stops reported in some detail. Hence, failures reported under the growing subclasses “Entire Unit”, “Other” and “Only down hours reported” are excluded. Based on data from WindStats and Canter [8]. 20 ELFORSK Sensors Hydraulics Elec. system 100% Elec. controls 80% Anamometer 60% Yaw system 40% Generator 20% Gearbox Main shaft/bearing 0% 19 99 20 00 20 01 20 02 20 03 20 04 20 05 20 06 20 07 20 08 Percentage of total down time Percentage of total down time, divided on turbine components Year Pitch adjust. Mech. brake Rotor Figure 20. Percentage of total down time between 1999-2008, based on stops reported in some detail. Hence, failures reported under the growing subclasses “Entire Unit”, “Other” and “Only down hours reported” are excluded. Based on data from WindStats and Canter [8]. Figure 17 and Figure 18 shows that the electrical system and electrical controls contributes significantly to the number of stops. Furthermore Figure 19 and Figure 20 show that the electrical system and the electrical controls also contribute significantly to the total down time. The generator and, above all, the gearbox contribute significantly to the total down time. These components fail comparatively seldom in comparison to the electrical system, but each failure leads to individually long down times. Rotor failures also seem to contribute to the total down time to the order of 10%. This may seem somewhat surprisingly high. 4.1.4 Finnish information from VTT The quality and continuity of the failure reports in Finland vary due to the manual reporting system. The documentation is often incomplete. The results from Stenberg [15] should hence be regarded as trends. The results should not be used for direct comparison with other statistics. A substantial amount of data comes from relatively new turbines. This means that they might suffer from failures due to immature technology. Those turbines were however not included in Stenberg’s report [15]. Some turbines also suffered from bad reporting routines, which excluded them from the report as well. In the end, a total of 72 wind turbines with a total rated power of 73 MW were examined. A total of 37 of these turbines were of size 1 MW or larger. Because of the limited number of turbines, all data are analyzed in one single group. The failure data in the Finnish report are collected during the period 1996-2008. 21 ELFORSK Total number of stops per component Rotor Brakes Pitch adjust. Gearbox Generator Yaw system Elec. controls Elec system Hydraulics Sensors Structure Heating Grid connection Other Only stop hrs reported Figure 21. Total number of stops on Finnish turbines, reported to VTT during 1996-2008. (Stenberg [15]). Total stop time per component Rotor Brakes Pitch adjust. Gearbox Generator Yaw system Elec. controls Elec system Hydraulics Sensors Structure Heating Grid connection Other Only stop hrs reported Figure 22. Total down time (stop time) for Finnish turbines reported to VTT during 19962008 and presented in Stenberg [15]. 22 ELFORSK 4.2 Detailed failure information for turbine components The following chapters deal with the reliability and failure data in view of the different components of a wind turbine. Figure 23 includes a sketch to provide an overview of the components in order to facilitate the reading of the discussion. Figure 23. Overview of components in a wind turbine. 4.2.1 Electrical system As can be seen in Figure 14 and Figure 15, the numbers of failures in the electrical systems are high, but the down time is often low. Fuses, short-circuited cables or defect components are reported to be the most frequent failures. Many of these components are relatively common, cheap and small, which make it possible to have them in stock or delivered within a short time. Echiavarra et al [10] claimed in 2007 that there are more failures in the electrical systems for synchronous generators than for induction generators. Furthermore, their data indicate that wind turbines with synchronous generators use a full power converter, which is regarded as a new component possibly representing a less mature technology. It is claimed that this leads to an increase of failures compared to the more mature technology with induction generators. Tavner et al [16], claim that the reliability of wind turbine converters is considerably worse than the reliability of converters in other industries. Due to time constraints, this argument was not further investigated deeper during this project. Spinato [13] also reports data where the number of failures in the electrical system is dominant. Even if these failures might not take long time to repair, a high number of failures can lead to long total down time. It is therefore important to have quick access to 23 ELFORSK spare parts and service personnel. It is also important to have quick access to the turbine site. The latter might be harder to fulfil at an offshore wind farm. According to Faulstich et al [18], failures of electrical subassemblies may occur at a variety of parts in different locations. The failure cause may also be different. This may make failure prediction and damage prevention more difficult. Fires in wind turbines are often caused by failures in the power electronics and short-circuit in the electrical system (Ny Teknik [17]). 4.2.2 Generator The study of Stenberg [15], of maintenance and replacement data points out failure of the generator slip rings as the most common failure mode of a generator. The shortest time for replacing a generator was 14 hours. The longest time to get the turbine in operation again after a generator failure was 1306 hours. Note that these figure include the total time from failure to fulfilled replacement. Hence purchase, administration, installation controls etc may be a substantial part of the time. Average time for a replacement was 410 hours and the replacements are almost evenly spread out over the age of the turbines. As mentioned in chapter 4.2.1, Echiavarra et al [10] have shown that induction generators are generally twice as reliable as synchronous generators. A possible reason is that the synchronous generators use full power converters. These were quite new components in wind turbines at the time. The WMEP database (chapter 3.1.3) was used as input to Echiavarra et al [10]. A total of 83% of the included turbines used an induction generator. Many of the turbines using synchronous generators in this study were of relatively new designs. According to Tavner et al [16], the reliability of wind turbine generators in general is worse than the reliability of generators in other applications. No discussions about the reason for this have been found. 4.2.3 Gearbox The gearbox is one of the components that cause the longest down time. The reason for this is of course the long time for repairing or replacing a gearbox. Also, the failure rate is far from negligible leading to considerable total down times. Ribrant and Bertling [19] focus on failures of Swedish wind power plants during 1997–2005. The gearbox is the most critical component in a wind turbine when it comes to down time per failure. Table 2, shows failed subcomponents in a gearbox for turbines with a rated power of 490 kW or more. 24 ELFORSK Table 2. Gearbox failures during 1997-2004 on Swedish wind turbines larger than 490 kW, as reported by Ribrant [19]. The number of failures caused by wear is shown in the two last columns and this cause of failure is called B1. The data in Table 2 were calculated from information given from Vindstat [1], and this data was reported manually to Vindstat. Automatic reporting routines were already in use at the time when [19] was written, but detailed information from some turbines were still reported manually. Each type of failure has a specific code assigned. The letter “I” stands for gearbox, and the subsequent number is the code indicating which part of the gearbox that failed. Table 2 also shows unspecified failures. According to Ribrant and Bertling it was possible to examine additional text added in the database of failures. This text revealed that about half of the unspecified gear failures (I-other) correspond to serious failures that resulted in a replacement of the entire gearbox. It was also revealed that most of the bearing failures also demanded a replacement of either the gearbox or the gearbox bearings. B1-failures, which can be seen in the title of the last two columns, are failures caused by wear. As can be seen in Table 2, the majority of gearbox failures are caused by wear, which mean long time damage mechanisms such as fatigue or mechanical abrasion. Stenberg [15] also reports that the gearbox, with all its sub-components, is the equipment that has caused the longest down times. There are ten gearbox replacements reported in the Finnish data, during a total operational time of 522 years. Surprisingly, the shortest time for replacing a gearbox was just 24 hours. The gearbox in this particular case was actually replaced before it actually failed, which is important information. However, no information about the detection method, CMS monitoring system, inspection etc., was given. This indicates the benefits of being able to predict failures and being able to replace the component before failure. This could save considerable time and money. The average total time for replacing a failed gearbox with a new one was 622 hours, while the longest stop lasted for 2245 hours. Of course the delivery time and other factors like availability of cranes affect the total time for replacing a gearbox. During the period of collecting information, nine gearboxes with a repair time over one month were reported. The gearbox of a conventional turbine is a source of noise often complained about. This will not be a problem with direct drive machines. Of course, the direct drive concept also eliminates the problems with long down times. However, the direct drive concept may suffer from other problems that have yet to appear with the increased number of direct drive turbines. A possible source for failure is the multi-pole generator and the full size converter 25 ELFORSK that is needed (Spinato [13]). However, Faulstich et al [22] reports that higher failure rates for these components does not automatically implicit lower availability. Despite a relative high failure rate, the annual down time seem to be low compared to turbines with gearboxes. Tavner et al [16], state that the total availability of a direct drive wind turbine is higher even though the failure rate of generators and converters is higher than the corresponding failure rate of gearboxes, generators and converters in geared wind turbines. Faulstich et al [22] suggest that the differences in failure rates for direct and indirect drive machines could be due to: – Much larger number of coils used in direct drive machines. The failure rate could perhaps also be improved by replacing the field coils by permanent magnets. – The larger diameter of the direct drive generator makes it more difficult to protect the windings from the environment, like humidity and contaminations. – Insufficient standardization of the manufacturing process, as a consequence of relatively small production series According to Tavner et al [16], gearbox technology should be regarded as a mature technology. Therefore, the authors claim that substantial improvement of the reliability of wind turbine gearboxes is unlikely in the future without radical redesign of the gearbox. This conclusion can seem to be rather pessimistic in a view of damage preventing measures. It also highlights the necessity of further research in the area of gearbox in wind turbine applications. Possible differences against other applications should be investigated. The difference compared to other technologies should be addressed. It should be of strong interest to more closely address the difference between gearboxes in wind turbine applications as compared to other applications. The difference could potentially lie in the design, in the load conditions, in the maintenance etc. The data in this study clearly indicate the bearings as the most failed parts. It remains yet to identify and distinguish the particular conditions for bearings in wind turbine applications. Such factors may be load conditions, lubrication, contact pressure, rotational speed etc. 4.2.4 Pitch regulation A total of 51 turbines in Stenberg [15] are reported to have failed. The failure occurred in the blade angle regulation. A total of 16 were stall regulated. This technology is out-of-date today. The most common failure for the pitch regulation reported to VTT is failure in the hydraulic system. Problems with the motor bearings and the measurement equipment are also reported. The total down time was of some tens of hours in average per year. An interesting observation is that increased failure frequency for the pitch regulation has been found at a site for testing equipment in cold climate. 4.2.5 Mechanical brake The mechanical brakes are worn out during normal operation of wind turbines. Adjustment and replacement of the brakes are recurrent events. These activities are not very time consuming. However, an event with a down time of around 90 hours was reported to Stenberg [15]. This event was related to the hydraulic system of the brake. Air brakes are not included in this report, since modern turbines use pitch and not stall regulation. Air brakes are only used on stall-regulated turbines. 26 ELFORSK 4.2.6 Hydraulic system Hydraulic problems are recurrent events and constitute one of the most common reasons for technical problems in a turbine (Stenberg [15]). Replacements of hydraulic pumps and tubes are common and occur in more or less all turbines. The approximated downtime for a failure in the hydraulic system is in most cases around 100 hours, but in extreme situations the downtime has been over 300 hours. 4.2.7 Yaw system Problems with the yaw system are also rather common and the most common solution is replacement of the yaw motor, see Stenberg [15]. The reason for problems is for example icing. In some cases there is a long waiting time for a new motor. The approximated downtime for a failure in the yaw system is in most cases below 20 hours, but in the worst cases the downtime has been around 45 hours. 4.2.8 Sensors and control system There are many different sensors in a turbine and problems occur often. The down time is normally around 20 hours since only a single sensor replacement is required. In cases of older turbines, the needed sensors might not be in production anymore. Hence, the down time can increase dramatically (Stenberg [15]) in these cases. Stenberg [15] further concludes that the most common failures of the control systems lead to replacement of the electronic circuits. This is easily done if new circuits are readily available. However, for some advanced failures, the down time can be extended. According to Faulstich [18], 75% of all failures of the control system are caused by hardware problems on the control unit. Software and communication problems are also rather common. 4.2.9 Rotor and structure Problems with the rotor are unusual according to Stenberg [15]. However, in WindStats the failure rate for the rotor is not negligible and stands for around 10% of the total stops and also around 10% of the total downtime for a turbine, see Figure 18. The downtime can be over 70 hours for a single failure . This holds especially if the rotor must be dismounted from the turbine. This may happen if the main shaft or bearing, or a rotor blade must be replaced. Strokes of lightning for example, can require blade replacement. Problems with the structure (tower, for example) are rare, but the down time can be approximately 100 hours, according to Stenberg [15]. Blades have come off at some recent incidents reported in media. Such failures occurred in Falkenberg in 2009 and in Norway, at Hundhammerfjell 2009. The Falkenberg failure was reportedly due to the lack of tightening of the bolts. A damage investigation report of this failure is about to be released (according to information), however still not available. Further, the complete rotor came off in an accident in Jylland, Denmark in 2009. This happened due to complete failure of the main shaft. In January 2008, a 850 kW turbine in Gotland lost one rotor blade. Media reported that the failure was also in this case due to lack of tightening of the bolts. It is yet to investigate why these bolt failures could happen. Tightening control is a rather easy operation. Preventing these dramatic types of failures will be addressed in the coming phases of the project. 27 ELFORSK Figure 24. Falkenberg rotor failure in 2009 (Ny Teknik). Figure 25. Rotor failure due to broken main shaft in Jylland 2009. Fracture surface (Ingeniøren, Danish journal) 28 ELFORSK 4.2.10 Transformers According to Stenberg [15], a component that contributes to long down times is the transformer. This fact is confirmed in He [20], in which reliability data for equipment in the distribution network were studied. No specific reasons are mentioned for transformer failures and the transformer down times are not reported explicitly either. However, a transformer that caught fire in Finland caused a stop for 1159 hours. Most transformer failures are related to breakers and disconnectors. 4.3 Experiences from operators and insurance companies Two operators, operator A and B, have contributed with their experience in communication with the project. Both operators have experience of damages on the equipment, primarily on the gearbox. One of the operators claimed that the openness with regards to problems and maintenance is currently increasing in the industry. This should lead towards increasing reliability. Due to the rapid development, the industry is still immature. It is clear that monitoring systems will be more common in the future. Alongside, the number of inspections will probably increase. Today, some insurance companies have mandatory inspections connected to the insurance. Both operators agree that there is an immense value in being able to predict failures in order to have planned replacements before failure. This is clearly supportive of the findings in 4.2.3. One of the operators is now introducing a maintenance database. So far, the database contains very limited data. A general problem is that the manufacturers are performing the maintenance during the warranty time. Thus the operators have limited insight during the early operation. However, the database is promising and in the long run serve to provide valuable information for improved maintenance. The operators interviewed have not experienced generator or rotor failures to the extent reported in the literature. The gearbox is the main cause of problems. A crane is needed for dismounting the gearbox from the turbine. Long repair times also affect the energy production and lead to lower incomes. There are also some components with reoccurring problems that cause long total down times due to the high failure frequency. The power electronic converters used for the variable speed function are such components according to Operator A. This component is rather easy to repair, even if there is a certain cost to take into consideration for repairing this component repeatedly. Generator problems with long down times are not as common as in the statistics, see chapter 3. The most common failure on a generator is, according to Operator A, related to the bearings. This problem can be fixed directly on site and without long down times. Operator B is of a similar opinion. The generator is rather reliable but dependent on maintenance programs such as exchange of slip rings. The insurance company Trygg-Hansa has provided a list of failures for the project. However, the list confirms the importance of the gearbox in the failure data. See appendix A. 4.3.1 Rotor Problems with the rotor are claimed by operator A not to be common. Most problems occur due to a manufacturing defect in the laminate. Operator B also mentions lightning strikes as a cause of rotor damage. Visual inspections of the blades are always performed at inspections, but in some cases the Eigen frequency of the blades is also measured. Blade defects can in this way be found at an early stage by noticing a change in the measured Eigen frequency. A majority of all blades are made of epoxy. Some blades are made of 29 ELFORSK carbon fibre for a reduced weight. However, blades made of carbon fibres are stiffer than epoxy blades and also conduct electricity. It is desirable with some damping in a blade and a conductive blade can easily be ruined in case of a stroke of lightning. Both these properties of a carbon fibre blade are undesirable. The risk for a blade to come off at the bolts is minimal according to both operators. The bolts are tightened during inspections. 4.3.2 Gearbox Both operators agreed that the gearbox is a component that strongly contributes to the total down time of a turbine. It is the experience that the gearboxes have a life expectancy of 6-8 years. Gearbox bearings are the most critical and life-limiting components. The high speed and the intermediate shaft bearing are critical parts of the gearbox. Failures in these parts of the gearbox can possibly be repaired at the site, in the best case without removal of the gearbox. Failures on the low speed shaft are even worse, since this type of failure demands an expensive lift. Repairing these failures offshore means even higher costs. There are also some fatigue related failures in gearbox teeth. The operator A argues that these failures are due to material imperfections, stemming from the hardening of the material at manufacturing. Operator A claims that the fact that a wind turbine gearbox is driven on the low speed side, makes it more vulnerable than gearboxes in other applications. Normally, the motor is connected to the high speed side. This statement remains to be investigated. CMS/Vibration sensors are often used on gearboxes in newer turbines for monitoring purposes. However, these detectors are hard to place on the rotating planetary gear wheels of the gearbox, which is one of the parts that suffer from the highest amount of failures. Figure 26. Sketch of a gearbox typical for wind turbines, here a one stage planetary and two spur stages. 30 ELFORSK 4.3.3 General experiences and opinions Smaller wind turbines around 15 years of age are relatively simple compared to today’s turbines of several MW. Operator A claims that these smaller turbines (around 500 kW) do not have the many problems associated with turbines manufactured around 6-7 years ago, even if they are about to be worn out after many years of operation. One reason for this could be that smaller turbines were more robustly dimensioned. Larger turbines (>2 MW) were under development some years ago. Today, these turbines have a total gear ratio of around 100, which is very high. This should be compared to older, smaller turbines with gear ratio at 30. Difficulties to handle the high gear ratio can be one participating factor in the gearbox problems. The reason for the high gear ratio for larger turbines is that the blade tip speed and the generator rotational speed (about 1500 rpm) are fairly constant irrespective of turbine size. Hence the rotational speed of the low-speed shaft is lower for turbines with large rotors, requiring a higher gear ratio to obtain the desired generator rotational speed. The manufacturers competed against each other in developing larger turbines 6-7 years ago. New models were constantly developed and produced in short series. The manufacturers did not prioritize the development and improvement of existing models. The current models have had more time to develop and mature. However, problems with the gearbox for example, are still a relatively big. An operator can handle a single replacement of the gearbox during the turbines expected life but a second or third major repair could potentially ruin the economy. The turbine manufacturer is normally responsible for the turbine service during the warranty time, and also some time after the warranty has expired. A normal time for such a service contract is 2-5 years. The operator does not have a full insight in the service activities during this time. This applies especially for the cost of the service and repair activities. Limited influence on the total cost of maintenance results (operator B). Operator A is convinced that it would be valuable to have an efficient monitoring system that could signal if components (like gearboxes) are about to fail. To replace damaged components before they fail could save considerable time and cost. Operator B regards CMS as necessary. But operator B also believes that inspection programs are important steps towards successful investment of wind power turbines. 4.4 General conclusions of available reliability data There are just a few reliability databases for wind turbine components. Almost all papers referenced in this project are based on the same databases. The databases all have severe limitations. Such limitation is the lack of detail. Failure data on component level are very rare. A substantial part of the data is on the entire unit. More detailed data mainly come from older types of turbines. It would be ideal to group reliability data on important parameters. Such parameters could be turbine manufacturer, rated power, age and load conditions (for example IEC wind class). Most of the available data are unfortunately not classified in similar groups. WMEP has grouped some of the data in turbine power class and turbine location (Coastline, Low mountains and Inland), but their amount of data is still limited. Most of the available data are also some years of age, and less information about turbines with a rated power larger than 1 MW is available. 31 ELFORSK The data from VTT show some differences compared to WMEP and WindStats. The hydraulics contributes more significantly to both the number of stops and the total down time. Moreover, the failure rate for the electrical system is lower. However, the Finnish data come from a small population of turbines, which of course affect the validity of the comparison. It is indicated from the literature that the gearbox, and in some cases also the generator, contributes most to the total down time, even if the failure rate is rather low. However, the Swedish operators that were interviewed within the project did not completely agree. Their experience is that generators contribute very little to the total down time for their turbines. The electrical system also contributes significantly to the total down time. This is due to the high failure rate. On the other hand, the electrical systems are easy to repair. Due to the easiness of replacement the electrical system failures may be regarded as less severe than failure of large mechanical components. Almost all data used in this project mainly come from onshore turbines. Offshore conditions may alter the priority. An attempt to compare the sources can be found in Table 3 below. The subassemblies with the highest failure rate and longest down time per failure are presented. Table 3. Turbine subassemblies with the highest failure rates and longest down times according to different databases. For WindStats, the first line is for German turbines, the second line for Danish turbines. [22]. According to Bertling [24], the gearbox, control system and the electric system are the three sub-systems that have the longest total down times in Sweden (named Elforsk in Table 3). There are of course useful data in the various databases studied in this project. However, improvements are clearly needed if the data should be able to provide a basis for efficient damage preventing measures. 32 ELFORSK 5 Conclusions and recommendations This report has summarised the current state of public reliability databases and their usefulness for implementing damage preventing measures. It is tempting to be somewhat pessimistic about the results. The level of detail is far from sufficient and the quality of reporting is even decreasing. This makes it impossible to make a relevant analysis of the damage dependency on parameters such as age and size, which was a stated goal of the project. These limitations must be regarded in the subsequent phases of this project. To balance these negative results, it is encouraging to note that operators and insurance companies are demanding improved insight in damage collection, maintenance and overall damage preventing measures. They all have a strong and natural interest in improved availability. Hence, an increased cooperation with these parties is a possible and realistic way forward. It is also noted that other databases are being developed today. Such examples are the EU project “ReliaWind”, the German “Offshore-WMEP” project and the Swedish VindForsk project “V-344 RAMS-database for wind turbines”. The Swedish VindForsk project is a study on how to structure a reliability database for wind turbines. A report will be published during 2010. A short list with suggestions for an improved reliability database is presented below. – Incentives and means for operators/owners/service people to report to a reliability database should be considered. – The reporting routines should be automatic and standardized. That is, the information structure and terminology should be standardized. – Reliability data should be reported and presented on a detailed component level and not on a general level. – It should preferably be possible to split the reliability data for each component into more detailed subsystems. For example, a gearbox could be divided into several subcomponents like gears, bearings, gears and shafts. – It should be considered to utilize a standardized product breakdown structure such as RDS-PP[26]. – Component reliability data should be possible to divide into turbine type and size, technical concept like synchronous and asynchronous generators, manufacturing year, external environmental conditions, IEC wind turbine class, failure cause etcetera. For example, there are many different types of climate in Sweden and the loads on a turbine can vary substantially with different climates. This means that reliability data for one type of turbine might vary depending on where the turbine is located. It is noted that these suggestions agree well with those presented by Besnard [23] in another VindForsk project. 33 ELFORSK During this project, a simple version of how a wind turbine could be split up in different components was made. This sketch for a database is shown in APPENDIX B. The proposed structure aims at connecting the failure to a proposed damage preventing measure and may be integrated in a database with a more general purpose. At a further stage the database terminology should be adjusted to follow standards for product breakdown structures in order to be more compatible with other databases. Such a standard could be RDS-PP by VGB[26]. It is also strongly recommended that the future work on damage preventing measures is not only based on failure statistics. Even if the available statistics were considerably better, this would not suffice. It is strongly believed the physical conditions for wind turbines should be investigated more thoroughly. The understanding of the impact of the load conditions should be increased. Very little is known about the relation between failures and load conditions. The current data gives little information on this important issue. Future studies should focus on this relation. Moreover it should be interesting to study the connection between failure and maintenance actions. It is temping to believe that some of the failures could be avoided by simply following the maintenance instructions. Damages on wind turbines occur due to damage mechanisms that are generally very well known. There should be no question about that. The difference in the conditions for component failure between the wind power industry and other industries should not be large. Of course different industries have different traditions when it comes to maintenance, inspection and condition monitoring. Comparing experience of damage preventing measures from other industries, knowledge about the nature of the damage mechanism and current practice in the wind industry will be an important tool in the evaluation of different damage preventing measures. This will be done the following phases of this project. 34 ELFORSK 6 References [1] Driftuppföljning vindkraft, available at: www.vindstat.nu [2] Interview, Nils-Erik Carlstedt, VPC, March 2010 [3] N-E Carlstedt, Vattenfall Power Consultant AB, Driftuppföljning av Vindkraftverk, Årsrapport 2009 [4] E-mail, Nils-EriK Carlstedt, VPC, March-May 2010 [5] WindStats Newsletter web site, available at: www.windstats.com [6] E-mail, Jochen Keiler, Betreiber-Datenbasis, March-April 2010 [7] WindStats Newsletter, Vol. 22, No. 4, Autumn 2009, ISSN 0903-5648 [8] Data from Bill Canter, Editor at WindStats Newsletter, January 2010 [9] E-mail, Stefan Faulstich, Fraunhofer Institute for Wind Energy and Energy Systems Technology (IWES), March 2010 [10] E. Echiavarra et al, Delft University of Technology and B. Hahn ISET, How Has Reliability Of Technology Developed Through Time?, Paper for the European Wind Energy Conference in Milan, Italy, May 2007 [11] S. Faulstich et al, Windenergy Report Germany 2008, Institut für Solare Energieversorgungstechnik (ISET), Kassel, Germany. Report available for order at www.windmonitor.de [12] E-mail, Anders Stenberg, VTT, April 2010 [13] F. Spinato, The Reliability of Wind Turbines, PhD Thesis, Energy Group, Durham University, England, December 2008 [14] Illustration of the Bathtub Curve, available http://www.weibull.com/hotwire/issue21/hottopics21.htm, 2010-07-06 [15] A. Stenberg, Analys av vindkraftsstatistik i Finland, universitetet Tekniska Högskolan, Esbo, 2010-02-05 [16] P. J. Tavner et al, Durham university and G. J. W. van Bussel et al, Delft university of Technology, Reliability of Different Wind Power Concepts with Relevance to Offshore Application, Paper for the European Wind Energy Conference in Brussels, Belgium, April 2008 [17] Article in Ny teknik, published 2010-04-22, available at: http://www.nyteknik.se/nyheter/energi_miljo/vindkraft/article766440.ece 2010-0526 [18] S. Faulstich, P. Lyding, B. Hahn, IWES, Kassel, Germany, Electrical subassemblies of wind turbines – a substantial risk for the availability, European Wind Energy Conference, Warsaw, Poland, April 2010 35 Master Thesis at: Aalto- ELFORSK [19] J. Ribrant and L. Bertling, Survey of Failures in Wind Power Systems With Focus on Swedish Wind Power Plants During 1997–2005, IEEE Transaction on energy conversion, Vol. 22, No. 1, March 2007 [20] Y. He, Study and Analysis of Distribution Equipment Reliability Data – Datastudier och analys av tillförlitlighetsdata på komponentnivå för eldistributionsnätet, Elforsk report 10:33, March 2010 [21] S. Faulstich and B. Hahn, ISET, Comparison of different wind turbine concepts due to their effect on reliability, UpWind, Deliverable WP 7.3.2, 2009-02-27 [22] S. Faulstich, B. Hahn and P. Lyding, IWES, Kassel, Germany, P. Tavner, Energy Group, Durham University, Reliability of offshore turbines – identifying risks by onshore experience, European Offshore Wind, Stockholm, Sweden, September 2009 [23] F. Besnard, Reliability studies of wind power systems and RAMS databases – Stateof-the-art, presentation at Vattenfall Stockholm, April 2010 [24] L. Bertling, et al, Förstudie om tillförlitlighetsbaserat underhåll för vindkraftssystem – Fokus på metoder för tillståndskontroll, Elforsk rapport 06:39, May 2006 [25] European Standard EN 13306:2001, Maintenance terminology [26] VGB PowerTech e.V., www.vgb.org 36 ELFORSK Appendix A. Data provided by Trygg Hansa. Skademån Märke Typ Tillvår Skada 0205 0205 0206 0208 0210 0210 0211 0211 0212 0303 0303 0303 0307 Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas Vestas V80- 2MW V80- 2MW V80- 2MW V80- 2MW V80- 2MW V80- 2MW V42-600KW V80- 2MW V80- 2MW V80- 2MW V80- 2MW V80- 2MW V44-600Kw 02 02 02 02 02 02 95 02 02 02 02 02 96 0308 Wind World Vestas Vestas Wind World Vestas Wind World Vestas 600Kw 98 V80- 2MW V47-660 kW 500Kw 02 00 96 Entreprenadskada. Påsegling. Skada på tornet Entreprenadskada. Påsegling. Skada på tornet Entreprenadskada 36 KV sjökabel Entreprenadskada. Påsegling. Skada på tornet Entreprenadskada. Påsegling. Skada på tornet Stormskada under entreprenadtid. Växellådshaveri. Hansenlåda Entreprenadskada. Påsegling. Skada på tornet Stormskada under entreprenadtid. Åskskada under entreprenadtid. Entreprenadskada Entreprenadskada Elektronikenhet(RCC styrning rotorström)sönderbränd Växellådshaveri. HSS lager. Märken från åsknedslag Åskskada på vinge under entreprenadtid. Växellådshaveri. Lagerskador. Slitage Generatorlager skurit med följdskador på axel V80- 2MW 600Kw 02 98 Skada på vinge underentreprenadtid Generatorlager havererat 3967 225KW V42-600KW W-3700 500kw 3700 500kW V52 V52 850Kw 250Kw 92 95 95 Växellådshaveri.Drev släppt, orsakat en onormal utmattningsspricka Växellådshaveri. Hansenlåda Växellådshaveri. Metallbit mellan kuggar. 96 Växellådshaveri. Lagerhaveri. 03 03 96 600Kw 98 Skador på kommunikationsmodul. Generatorhaveri Brand i maskinrummet. Totalskadat maskinrum. Primärt lagerhaveri? Växellådshaveri. Onormalt slitage lager? V47 V44-600 V47 98 98 98 Växellådshaveri Flenderlåda. Växellådshaveri. Växellådshaveri Hansenlåda 0308 0403 0405 0407 0503 0503 0503 0610 0701 0703 0703 0703 0703 0704 0704 0704 Vestas Wind World Wind World Vestas Vestas Wind World Wind World Vestas Vestas Vestas 37 ELFORSK 0704 0705 0705 0706 0706 0707 0708 0708 0708 0710 0711 0711 0711 0712 0712 0712 0712 0712 0712 0801 0801 0801 0801 0802 0802 0802 0803 0804 0804 0806 0806 0808 0810 0810 0810 Nordic Wind World Wind World Vestas Vestas Vestas Windworld Wind World Vestas Vestas Vestas Vestas Neg Micon Vestas Vestas Vestas Vestas Vestas Vestas Wind World Wind World Windworld Windworld Wind World Wind World Micon Vestas Wind World Wind World Nordic Windworld Wind World Vestas Vestas Vestas 1000 500 nr 2 02 96 600kW 98 V44 600kW V52 850Kw V52 500 600Kw 96 03 03 95 98 Fel i hydrauliksystemet för vridningen av verket Växellådshaveri. Innerringen på lager spruckit. Följdskador i växellådan Åsknedslag skadat integralmotor. Ny typ+omformare pga inga reservd Växellådshaveri Elutrustning skadad Generatorhaveri. Lagerskador. Generatorhaveri Kortslutning Omlindn stator Växellådshaveri pga felaktig olja V39 V42 600kW V42 600kW V90 750Kw 95 96 96 07 00 Skada på Pitch-ackumulator RCC skadad av elfenomen Lager växellåda Skiipack i VCS konvertern. Garantiskada Växellådshaveri. Lagerskada. V47 V47 V47 V47 V47 V52 600Kw 98 98 98 98 98 03 98 500 96 Växellådshaveri Hansenlåda. Växellådshaveri Hansenlåda. Växellådshaveri Hansenlåda. Växellådshaveri Hansenlåda. Växellådshaveri Hansenlåda. Generatorhaveri Kortslutning Växellådshaveri. Felaktig PT-100 givare orsakat varmgång i lager Generatorskada W-3700 95 W-3700 600 95 99 Lager växellåda. Lådan nyrenoverad precis innan skadan. Garanti? Åska orsakat skada på vinge Skadeanmälan tillbakadragen W-4200 600 97 Generatorskada. Lager skurit 900 V44 600 250 01 99 97 Skada på transformator pga storm Byte "Thermos" effektenhet Kortslutning generator 600Kw 98 Växellådshaveri. 1000 500 250 02 95 97 Kommunikationsutrustning skadade pga åska Generatorhaveri pga kortslutning Växellåda V44-600 V44 V42 97 98 Växellådsskada Kontaktfel RCC-enhet har slutat att fungera 38 ELFORSK 0810 0811 0811 0811 0811 0811 0812 0902 0903 0904 0906 0906 0906 0908 0909 0911 1001 1001 1003 Wind World Vestas Vestas Vestas Vestas Vestas Vestas Wind World Vestas Nordic Nordic Wind World Vestas Bonus Vestas Vestas Vestas Wind World Vestas 150 91 Klaff går inte in V52 V39 V52 V52- 850 kw V44 02 93 02 02 97 V47 600 01 98 Läckage trafo Åsknedslag styrutrustning Pump till växellåda havererat Ljusbåge i transformatorn Lager i kardan har skurit. Kulor har ramlat ur och har antänt isolering Växellådshaveri Wire gått av. Utmattning V52 1000 1000 250 03 02 02 96 Fel i generatorn. Garanti? Åsknedslag hydraulikcylinder i vinge Gummidämpare gått av Åsknedslag i vingspets V90 08 600 V47 V90 V44-600 3700-500 98 99 08 99 95 V44 600kW 96 Koppling mellan växellåda o generator havererat= Garanti Blixtnedslag Överslag i brytare Brandskada kopparskenor generator. Garanti Lager skadat i växellådan. Fel i värmare till växellådsoljan. Felaktig leverans från början Låda 07 RCC skadad av elfenomen 39 ELFORSK Appendix B. Suggestion for a database structure. The database should enable linking of the component to a proposed damage preventing measure. Suitable for simple excel implementation. The structure also includes an initial attempt to link with RDS designations. Figure B1. Turbine Overview. RDS AAG MDA Component Date Damage mechanism (fatigue, wear, corrosion etc) Root Cause Consequence Load Type Turbine age Turbine Size Proposed action (inspection, monitoring, replacement etc) Medium voltage distribution >1kV to (30)35 kV Rotor system MDA10 Rotor blades MDA 11 Rotor blade A MDA 11 MQ001 Blade bolts etc. MDA 11 MQ001 Blade bolts etc. Falkenberg 2009 Gotland 2008 Fatigue Fatigue Untightened bolts Untightened 40 Roto blade came off Roto blade came off 850 kW Conv. Tightening Inspection Conv. Tightening ELFORSK bolts MDA 12 MDA 13 MDA20 MDA20 UL001 MDC MDC1x GL001 MDC1x UP001 Rotor blade B Rotor blade C Hub Cast body of hub (hub bolts) Blade adjustment Pitch drive Blade bearing MDC10 Pitch system MDC10 UP001 Pitch bearing MDK Drive train MDK10 Rotor shaft MDK10 UP001 MDK10 UQ001 Rotor bearing Clamping set main shafts MDK20 Gear MDK20xx yyy Gear box housing Main gear (gear supports, screws, bearing, shaft) MDK20 TL001 MDK20 TL001 xxx MDK20 TL001 xxx MDK20 TL001 xxx MDK20 TL001 xxx MDK30 MDK30 QQN001 Gear box teeth Gear box shafts Gear box bearings Gear box bolting Brake system Brake hydraulic system MDK30 xxx Disc brake MDK40 Couplings MDK51 MDK51 EQ001 Main flow gear oil system Gear oil cooler 41 Inspection ELFORSK MDK51 BP001 MDL MDL10 MDL10 BG010 MDL10 GL00x MDL10 TL01 MDL10 TL01 OP01 MDL20 MDY MDY10 MDY10 BS01 MDY10 KF001 Gear oil pressure cooling system Yaw gear box Azimuth drive system Wind direction(Wi nd vane) Azimuth drive Azimuth live ring Azimuth bearing Azimuth brake system Control and protection equipment Electrical control system Anemometer CMS control MK Generator system MKA Generator MKA10 Generator MKA10 yyy MKA10 yyy MKA10 yyy MKA10 yyy MKJ MSA MST MUD UMD UMD10 Generator stator winding Generator rotor winding Generator shaft bearings Generator shaft Generator air cooling Generator transmissio n Generator transforme r incl. Cooling Machinery enclosue Structures WTG Tower foundation 42 ELFORSK UMD 20 UMD20 EA 001 UMD20 UB001 UMD20 UM2xx Tower Construction Lightning Cable carrier system Flanged connection ring xx (HVbolts, nuts) 43 ELFORSK 44
© Copyright 2026 Paperzz