Item 14.1.2 Attachment 2 BRIDGES RENEWAL Victor Harbor CC Projected Capital Renewal Works Program - Bridges_S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 BRG 4 - Waitpinga Road RE. Replace guard rail to standard 2 BRG 4 - Waitpinga Road RE. Seal shoulders and widen pavement $20 3 BRG 5 - Waitpinga Road RE. Seal shoulders $10 4 BRG 11 - Nottle Hill Road RE. Seal shoulders $7 5 BRG 6 - Waitpinga Road RE. Seal shoulders $9 $7 6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals 1 BRG 4 - Waitpinga Road RE. Repair cracked & spalled posts / rails 2 3 4 5 6 7 8 9 10 2018 Defect Repairs 1 $53 $25 2 3 4 5 6 7 8 9 10 2018 Total $25 ($000) Year Item 2019 Description Estimate Network Renewals 1 BRG 5 - Waitpinga Road RE. Repair cracked & spalled bridge railing / posts $40 2 3 4 5 6 7 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals 1 2 3 4 5 6 7 $40 Estimate 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $0 ($000) Year Item 2021 Description Estimate Network Renewals 1 2 3 4 5 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2021 Total 2022 Network Renewals 1 2 $0 3 4 5 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $0 ($000) Year Item 2023 Description Estimate Network Renewals 1 BRG 15 - Keen Road RE. Replace guard railing to standards $25 2 BRG 16 - Kirk Road RE. Replace guard railing to standards $20 3 BRG 17 - Back Valley Road RE. Replace guard railing to standards $20 4 5 6 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 $65 Network Renewals 1 Bridge Allowance - Upgrades - Railing $180 2 3 4 5 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $180 ($000) Year Item 2025 Description Estimate Network Renewals 1 Bridge Allowance - Upgrades - Railing 2 3 4 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 $120 6 7 8 9 10 2025 Total 2026 Network Renewals 1 Bridge Allowance - Bitumen Seal Approach Shoulders and Decking $120 $125 2 3 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $125 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Bridges_S2_V2 ($000) Year Item Description Estimate 2017 1 BRG 4 - Waitpinga Road RE. Seal shoulders and widen pavement $5 2 BRG 5 - Waitpinga Road RE. Seal Shoulders $6 3 BRG 11 - Nottle Hill Road RE. Seal Shoulders $3 4 BRG 6 - Waitpinga Road RE. Seal Shoulders $9 5 6 7 8 9 10 2017 Total $23 ($000) Year Item 2018 1 Description Estimate 2 3 4 5 6 7 8 9 10 2018 Total $0 ($000) Year Item 2019 1 Description Estimate 2 3 4 5 6 7 8 9 10 2019 Total $0 ($000) Year Item 2020 1 Description Estimate 2 3 4 5 6 7 8 9 10 2020 Total $0 ($000) Year Item 2021 1 Description Estimate 2 3 4 5 6 7 8 9 10 2021 Total $0 ($000) Year Item 2022 1 Description Estimate 2 3 4 5 6 7 8 9 10 2022 Total $0 ($000) Year Item 2023 1 Description Estimate 2 3 4 5 6 7 8 9 10 2023 Total $0 ($000) Year Item 2024 1 Description Estimate 2 3 4 5 6 7 8 9 10 2024 Total $0 ($000) Year Item 2025 1 Description Estimate 2 3 4 5 6 7 8 9 10 2025 Total $0 ($000) Year Item 2026 1 Description Estimate 2 3 4 5 6 7 8 9 10 2026 Total $0 BUILDINGS RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Buildings_S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 Soldiers Memorial Reserve - Toilets - New Construction (MER Brian Doman) 2 Town Hall - Balustrade - External Stairs (DCCS Kate Jessep) $54 $6 3 Horse Tram - Causeway Office - Stables - Air-conditioning - Hot Water Service (DPRS Graham Pathuis) $2 4 Recreation Centre - Lighting Stadium 1 and 2 (DCCS Kate Jessep) 5 Recreation Centre - General Purpose Room - Floor Replacement and Upgrade (DCCS Kate Jessep) 6 Recreation Centre - Change room Floor Replacement (DCCS Kate Jessep) 7 Recreation Centre - Stadium One Blackboard Replacement (DCCS Kate Jessep) $40 $100 $10 $8 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals 1 Yacht Club - Replace Roller Shutter, Clubroom Bar (DCCS Kate Jessep) 2 Whale Centre Toilet Upgrade (DPRS Graham Pathuis) 3 4 5 6 7 8 9 10 2018 $220 Defect Repairs $5 $25 1 2 3 4 5 6 7 8 9 10 2018 Total $30 ($000) Year Item 2019 Description Estimate Network Renewals 1 Horse Tram - Causeway Office / Stables - Amenities Improvements (DPRS Graham Pathuis) $10 2 Library - Major Refurbishment - Stage 1 (DCCS Kate Jessep) $50 3 4 5 6 Visitor Information Centre - Floor Coverings - Carpet Replacement (DPRS Graham Pathuis) Visitor Information Centre - Shop / Office - Internal Refurbishment / Reconfiguration (DPRS Graham Pathuis) Town Hall - Performing Arts and Culture Centre – Stage 1, Tender Design Services Town Hall & Old Library (DCCS Kate Jessep) Whale Centre Security System including standard swipe card and smoke detectors (DCCS Kate Jessep) 7 Renewal Works - Condition Ratings 4 & 5 8 Visitor Information Security System including standard swipe card and smoke detectors (DCCS Kate Jessep) 9 Recreation Centre - Kiosk/Cafeteria - Design (DCCS Kate Jessep) $25 $30 $5 $9 $15 $8 $10 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals 1 Civic Centre - Café Kitchen - Kitchen Replacement (DCCS Kate Jessep) $162 Estimate $7 2 Town Hall - Performing Arts and Culture Centre - Stage 2, Detailed Design Services Town Hall & Old Library (DCCS Kate Jessep) $25 3 Library - Major Refurbishment - Stage 2 (DCCS Kate Jessep) $50 4 Renewal Works - Condition Ratings 4 & 5 $15 5 Horse Tram Granite Island Terminal (DPRS Graham Pathuis) $50 6 Recreation Centre - Kiosk / Cafeteria - Construction (DCCS Kate Jessep) $40 7 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $187 ($000) Year Item 2021 Description Estimate Network Renewals 1 Yacht Club - Roof Replacement (DCCS Kate Jessep) 2 Town Hall - Performing Arts and Culture Centre - Stage 1 - Construction (DCCS Kate Jessep) 3 Whale Centre - Refurbishment of Kitchen (DPRS Graham Pathuis) $10 4 Town Hall - Performing Arts Centre Security System including standard swipe card and smoke detectors, (to be done within Stage 1 construction) (DCCS Kate Jessep) $15 5 Renewal Works - Condition Ratings 4 & 5 $15 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 $50 $750 8 9 10 2021 Total 2022 Network Renewals $840 1 Town Hall - Performing Arts and Cultural Centre - Stage 2 - Construction (DCCS Kate Jessep) 2 Yacht Club - Replace Eaves - Fascia and Gutter (Clubroom) (DCCS Kate Jessep) $20 3 Visitor Information Centre - Replace Air-Conditioner (DPRS Graham Pathuis) $15 4 Renewal Works - Condition Ratings 4 & 5 $15 $750 5 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $800 ($000) Year Item 2023 Description Estimate Network Renewals 1 Library - External Wall Treatment (DCCS Kate Jessep) $40 2 VH Football Club - Replace Windows (DCCS Kate Jessep) $20 3 Visitor Information Centre - Kitchen - Refurbishment (DPRS Graham Pathuis) $10 4 Renewal Works - Condition Ratings 4 & 5 $15 5 6 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 Network Renewals 1 $85 Renewal Works - Condition Ratings 4 & 5 $40 2 3 4 5 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $40 ($000) Year Item 2025 Description Estimate Network Renewals 1 Yacht Club - Refurnish Kitchen (DCCS Kate Jessep) $18 2 VH Oval Canteen - Replace Internal Ceiling (DCCS Kate Jessep) $10 3 Renewal Works - Condition Ratings 4 & 5 $40 4 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total 2026 Network Renewals 1 Renewal Works - Condition Ratings 4 & 5 $68 $40 2 3 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $40 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Buildings_S2_V2 ($000) Year Item Description Estimate 2017 1 Soldiers Memorial Reserve - Toilets - New Construction (MER Brian Doman) 2 Horse Tram - Causeway Office - Stables - Air-conditioning - Hot Water Service (DPRS Graham Pathuis) $4 3 Depot Security System Enhancements (Swipe cards, electric gate) to upgraded security system in FY2015/16 (DCCS Kate Jessep) $35 $81 4 5 6 7 8 9 10 2017 Total $120 ($000) Year Item Description Estimate 2018 1 Whale Centre - Installation of Air- Conditioning (DPRS Graham Pathuis) 2 Whale Centre Toilet Upgrade (DPRS Graham Pathuis) 3 Whale Centre - Lift (DPRS Graham Pathuis) $110 Total $235 $100 $25 4 5 6 7 8 9 10 2018 ($000) Year Item 2019 1 Horse Tram - Causeway Office / Stables - Amenities Improvements (DPRS Graham Pathuis) 2 Victor Harbor Oval - Public Toilets - Construction (MER Brian Doman) 3 Whale Centre Security System including standard swipe card and smoke detectors (DCCS Kate Jessep) 4 Library - Major Refurbishment - Stage 1 (DCCS Kate Jessep) 5 Visitor Information Security System including Standard Swipe Card & Smoke Detectors (DCCS Kate Jessep) 6 7 Description Estimate $10 $145 $9 $50 $8 8 9 10 2019 Total $222 ($000) Year Item Description Estimate 2020 1 Civic Centre - Entrance and Customer Service Air-conditioning Design (DCCS Kate Jessep) 2 Civic Centre - Café Kitchen - Kitchen Replacement (DCCS Kate Jessep) 3 Bridge Tce, Toilets - Construction (MER Brian Doman) 4 Town Hall - Performing Arts and Culture Centre - Detailed Design for Town Hall & Old Library (DCCS Kate Jessep) $50 5 Horse Tram Barn Security System including standard swipe card and smoke detectors (DCCS Kate Jessep) $15 6 Recreation Centre Security System including standard swipe card and smoke detectors (DCCS Kate Jessep) $130 7 Library - Major Refurbishment - Stage 2 (DCCS Kate Jessep) $50 8 Recreation Centre - Kiosk/Cafeteria - Construction (DCCS Kate Jessep) $80 $30 $7 $140 9 10 2020 Total $502 ($000) Year Item Description Estimate 2021 1 Civic Centre - Entrance and Customer Service Air-conditioning Construct (DCCS Kate Jessep) 2 Civic Centre - Additional Solar Panels (DPRS Graham Pathuis) 3 Town Hall - Performing Arts and Culture Centre - Stage 1 - Construction (DCCS Kate Jessep) $750 4 Security System Upgrade to Performing Arts Centre (to be done during construction) (DCCS Kate Jessep) $50 $180 $70 5 6 7 8 9 10 2021 Total $1,050 ($000) Year Item 2022 1 Kleinigs Hill, Toilets - Construction (MER Brian Doman) $150 2 Town Hall - Performing Arts and Culture Centre - Stage 2 - Construction (DCCS Kate Jessep) $750 3 Description Estimate 4 5 6 7 8 9 10 2022 Total $900 ($000) Year Item 2023 1 Description Estimate 2 3 4 5 6 7 8 9 10 2023 Total $0 ($000) Year Item 2024 1 Description Estimate 2 3 4 5 6 7 8 9 10 2024 Total $0 ($000) Year Item 2025 1 Whale Centre - Amenities - Staff and Public Amenity Improvements (DPRS Graham Pathuis) 2 Franklin Parade / Whalers Rd, Toilets - New Construction (MER Brian Doman) 3 4 Description Estimate $10 $150 5 6 7 8 9 10 2025 Total $160 ($000) Year Item 2026 1 Description Estimate Causeway Toilets - Refurbishment (MER Brian Doman) $160 Total $160 2 3 4 5 6 7 8 9 10 2026 FOOTPATHS RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Footpaths_S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 Townhall Walkway - Paving & Stormwater Improvements - Construction 2 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 $8 $50 3 4 5 6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals $58 1 Bike Strategy Ref# 1.9 - VH Bowling Club - Widen Existing 1.8m path to 3.5m, protect from sand drift - (Brian Doman) Comment: 140m x 2.5m @$80/m2 $30k $15 2 Bike Strategy - Ref# 1.12 - Railway Crossing Hindmarsh River (Brian Doman) Comment: Plan and Cost $10k // Bike Strategy - Ref# 1.11 - Yacht Club to Hindmarsh River - new alignment through Bridge Tce Reserve (Brian Doman) Comment: Plan and Cost Only $5k $10 3 4 5 6 7 8 9 Bike Strategy Ref# 5.12 - Armstrong at Ewen Tce - Median Refuge (Brian Doman) Comment: Plan & Cost Bike Strategy Ref# 6.3 - Mill Rd - New 2.5m Wide Path (Brian Doman) Comment: Plan & Cost $2 $1 10 2018 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2018 Total $28 ($000) Year Item 2019 Description Estimate Network Renewals 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 $15 2 Peace Ave - High Street to Carlyle Street (length about 55m) $6k Bike Strategy Ref# 6.7 - Menton Rd, (Ocean Rd to Goolwa Port Elliot Rd) 2.5m wide shared pathway, northern side $240k 3 Bike Strategy Ref# 1.11 - Yacht Club To Hindmarsh River - 3.5m Wide Path, Seaward of Bridge Tce - (Brian Doman) 0 $45 4 Bike Strategy Ref# 7.1 - Bluff Jetty Rd - Crushed Stone Path Traversable by Bikes from the end of Bikeway to the Bikeway to the Bluff Ring Rd (Brian Doman) $40k Bike Strategy Ref# 5.12 - Armstrong at Ewen Tce - Median Refuge (Brian Doman) $10k Bike Strategy Ref# 6.3 - Mill Rd - New 2.5m Wide Path (Brian Doman) $20k $35 $146 5 6 7 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total $241 2020 Network Renewals Estimate 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 $350 2 Bike Strategy Ref# 2.5 - Bay Road - Permanent Bike Lanes - (Brian Doman) $39 3 Bike Strategy Ref# 6.5 - Waterport Rd, Strawberry Hill Rd to Ocean Rd - 2.5m Wide Shared Use Pathway on Southern Side - (Brian Doman) $94 4 Bike Strategy - Ref# 1.12 - Railway Crossing Hindmarsh River - (Brian Doman) $6 5 6 7 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $489 ($000) Year Item 2021 Description Estimate Network Renewals 1 2 3 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 Bike Strategy Ref# 1.5 - Adjacent to Franklin Parade - Bitumen Resurface Existing Pathway & Widen Where Possibile to 3.5m - (Brian Doman) Bike Strategy Ref# 5.13 - Adelaide Rd, North of Strawberry Hill Rd - Medium Refuge & Shift 60kph Sign North of this - (Brian Doman) 4 5 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 $70 $160 $40 6 7 8 9 10 2021 Total 2022 Network Renewals $270 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 $100 2 Bike Strategy Ref# 1.5 - Adjacent to Franklin Parade - Bitumen Resurface Existing Pathway & Widen Where Possible to 3.5m - (Brian Doman) $200 3 Bike Strategy Ref# 5.14 - Crozier Rd at Lindsay - Place Median Refuge - (Brian Doman) $15 4 Bike Strategy Ref# 5.15 - Seaview Rd at Carlyle - Place Median Refuge - (Brian Doman) $15 5 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $330 ($000) Year Item 2023 Description Estimate Network Renewals 1 2 3 4 5 6 7 8 9 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 Bike Strategy Ref# 1.7 - Willis St to Causeway - 3.5m Shared Pathway, Adjacent to Fence - (Brian Doman) Bike Strategy Ref# 3.7 - Kullaroo Rd, Adjacent to High School - 3m Wide Shared Pathway - (Brian Doman) $100 $87 $4 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 Network Renewals $191 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 2 Bike Strategy Ref# 3.2.1 - Kent Reserve - Provide 3.5m Wide Shared Pathway - (Brian Doman) $170 $46 3 4 5 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $216 ($000) Year Item 2025 Description Estimate Network Renewals 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 2 Bike Strategy - (Brian Doman) 3 $200 $40 4 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total 2026 Network Renewals $240 1 Footpaths Asset Register, Mydata - Condition Assessments 4 and 5 $200 2 Bike Strategy - (Brian Doman) $130 3 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $330 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Footpaths_S2_V2 ($000) Year Item 2017 1 C/F-VIC Centre to Causeway (REPLAS Con) & Townhall Walkway / Drainage $57 2 Mentone Rd - from Port Elliot Rd to Sutherland Ave (length about 160m) $17 3 Mentone Rd - from Sutherland Ave to Ocean Rd (length about 1,055m) $111 4 Sinclair Street - from McDonald Street to Mentone Road (length about 140m) 5 Sutherland Ave - Mentone Road to Ocean Road (length about 940m) 6 First Ave - from Port Elliot Road to Olivers Parade (length about 260m) $27 7 Alexander Street - from dead end to Rupara Ave (length about 90m) $10 8 Bike Strategy Ref# 1.7b - Causeway to Boat Ramp - Block Paving 90mx2.5m = 225m2 (Brian Doman) $20 9 Harborview Tce - from Bay Road to Malen Ave (length about 150m) $17 10 Malen Ave - from Harbourview Tce to Kent Drive (length about 90m) $7 2017 Description Total Estimate $15 $100 $381 ($000) Year Item 2018 1 Cudmore Road - from Tom Thumb Grove to Hindmarsh Road (length about 295m) $26 2 Adara Ave - from Dinan Road to Hindmarsh Road (length about 385m) $35 3 Wattle Drive - from Pearsons Drive to Dinan Road (length about 190m) $17 4 Dinan Rd - full length through dead end to Laxton Street (length about 185m) $16 5 Laxton Street - from Coleman St to Dinan Road (length about 100m) 6 Bike Strategy Ref# 1.9 - VH Bowling Club - Widen Existing 1.8m path to 3.5m, protect from sand drift - (Brian Doman) Comment: 140m x 2.5m @$80/m2 $30k 7 Description Estimate $9 $15 8 Kingsford Street - Oval Rd to Granite St (length about 360m, includes both sides) Bike Strategy - Ref# 1.12 - Railway Crossing Hindmarsh River (Brian Doman) Comment: Plan and Cost $10k // Bike Strategy - Ref# 1.11 - Yacht Club to Hindmarsh River - new alignment through Bridge Tce Reserve (Brian Doman) Comment: Plan and Cost Only $5k 9 Bike Strategy Ref# 5.12 - Armstrong at Ewen Tce - Median Refuge (Brian Doman) Comment: Plan & Cost $2 10 Bike Strategy Ref# 6.3 - Mill Rd - New 2.5m Wide Path (Brian Doman) Comment: Plan & Cost $1 2018 Total $34 $5 $160 ($000) Year Item 2019 1 Bond Ave - Full Length (length about 250m) Description Estimate $22 2 Pine Ave - footpath north of Field Ave to Hindmarsh Rd (length about 560m) $53 3 Renown Ave - footpath north of Field Ave to Hindmarsh Rd (length about 570m) $53 4 Brand Ave - from Renown Ave to Pine Ave (length about 100m) $9 5 Broadway - full length (length about 102m) $9 6 High Street - full length (length about 112m) $10 7 Riverview Rd - full length (length about 310m) $27 8 Peace Ave - High Street to Carlyle Street (length about 55m) $6k Bike Strategy Ref# 6.7 - Menton Rd, (Ocean Rd to Goolwa Port Elliot Rd) 2.5m wide shared pathway, northern side $240k $98 9 Bike Strategy Ref# 1.11 - Yacht Club To Hindmarsh River - 3.5m Wide Path, Seaward of Bridge Tce - (Brian Doman) 0 $45 10 2019 Bike Strategy Ref# 7.1 - Bluff Jetty Rd - Crushed Stone Path Traversable by Bikes from the end of Bikeway to the Bikeway to the Bluff Ring Rd (Brian Doman) $40k Bike Strategy Ref# 5.12 - Armstrong at Ewen Tce - Median Refuge (Brian Doman) $10k Bike Strategy Ref# 6.3 - Mill Rd - New 2.5m Wide Path (Brian Doman) $20k Total $35 $361 ($000) Year Item Description Estimate 2020 1 Bridge Tce - near Cornhill Rd to Bridge Court (length about 565m) $51 2 Bridge Tce - Bridge Court to Hindmarsh Road Railway Bridge (length about 220m) $19 3 Caterbury Road - from Jenkins Ave to Norfolk Ave (length about 1,455m) 4 Bike Strategy Ref# 2.5 - Bay Road - Permanent Bike Lanes - (Brian Doman) $36 5 Bike Strategy Ref# 6.5 - Waterport Rd, Strawberry Hill Rd to Ocean Rd - 2.5m Wide Shared Use Pathway on Southern Side - (Brian Doman) $62 6 Bike Strategy - Ref# 1.12 - Railway Crossing Hindmarsh River - (Brian Doman) $131 $6 7 8 9 10 2020 Total $305 ($000) Year Item Description Estimate 2021 1 Harvey Ave - full length to existing footpath at dead end (length about 144m) $13 2 Swain Road - full length (length about 300m) $27 3 Kullaroo Road / Oval Park Tce - full length (length about 462m) $41 4 Kent Drive - fill in footpath gap, south of Bay Rd (length about 55m) 5 Broderick Tce - from George Main Rd to Phillip Ave (length about 285m) $26 6 Phillip Ave - from Broderick Tce to Bay Village Entrance (length about 145m) $13 7 Bike Strategy Ref# 1.5 - Adjacent to Franklin Parade - Bitumen Resurface Existing Pathway & Widen Where Possible to 3.5m - (Brian Doman) 8 Bike Strategy Ref# 5.13 - Adelaide Rd, North of Strawberry Hill Rd - Medium Refuge & Shift 60kph Sign North of this - (Brian Doman) $6 $160 $10 9 10 2021 Total $296 ($000) Year Item Description Estimate 2022 1 Maude Street - from Inman Valley Rd to past Enterprise Ave (length about 425m) $39 2 Bacchus Rd - track from Bacchus Road to Inman Valley Rd (length about 140m) $12 3 Prime Boulevard - from North of Wishart Crescent to Rymill Ave (length about 400m) $38 4 Poltong Crescent - from Mill Rd to End (length about 410m) $37 5 6 7 Bike Strategy Ref# 1.5 - Adjacent to Franklin Parade - Bitumen Resurface Existing Pathway & Widen Where Possible to 3.5m - (Brian Doman) Bike Strategy Ref# 5.14 - Crozier Rd at Lindsay - Place Median Refuge - (Brian Doman) Bike Strategy Ref# 5.15 - Seaview Rd at Carlyle - Place Median Refuge - (Brian Doman) $160 $5 $5 8 9 10 2022 Total $296 ($000) Year Item Description Estimate 2023 1 Mill Rd - from Tabernacle Rd to short of Poltong Crescent (length about 600m) $57 2 Bay Road - from Tabernacle Rd to past Crosby Court (length about 390m) $35 3 Charles Street - from Ainsile Roberts Drive to Franklin Parade (length about 155m) $14 4 Nicolaus Baudin Drive - from Tabernacle Rd to Bartel Boulevard (length about 805m) 5 Bike Strategy Ref# 1.7 - Willis St to Causeway - 3.5m Shared Pathway, Adjacent to Fence - (Brian Doman) 6 Bike Strategy Ref# 3.7 - Kullaroo Rd, Adjacent to High School - 3m Wide Shared Pathway - (Brian Doman) $180 $57 $2 7 8 9 10 2023 Total $345 ($000) Year Item Description Estimate 2024 1 Tabernacle Rd - north of Cutter Circuit to Matthew Flinders Drive (length about 175m) $15 2 Tabernacle Rd - from Bay Rd to Mill Rd (length about 125m) $14 3 Tabernacle Rd - from Bay Rd to Ena Reid Reserve (Kingfisher Court) (length about 180m) $18 4 Wood Street - from Encounter Tce to Franklin Parade (length about 115m) $10 5 Bike Strategy Ref# 3.2.1 - Kent Reserve - Provide 3.5m Wide Shared Pathway - (Brian Doman) $20 Total $77 6 7 8 9 10 2024 ($000) Year Item Description Estimate 2025 1 Ridgeway St - from Russell St to Franklin Parade (length about 235m) $21 2 Whalers Rd - from Mollien Ave to Franklin Parade (length about 555m) $53 3 Giles St - from Fell St to Tabernacle Rd (length about 390m) $35 4 Petrel Ave - from Whalers Rd to Fell St (length about 345m) $31 5 Franklin Parade - from Jagger Rd into Whalers Inn Car Park (length about 75m) $9 6 Jagger Rd - from Investigator Crescent to Franklin Parade (length about 170m) $16 7 Bike Strategy - (Brian Doman) $20 8 9 10 2025 Total $185 ($000) Year Item 2026 1 Description Estimate Bike Strategy - (Brian Doman) $40 Total $40 2 3 4 5 6 7 8 9 10 2026 KERB CHANNEL, CAR PARKS, TRAFFIC CONROL DEVICES RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Kerb Channel, Car Parks_S2_V2 ($000) Year Item Description Estimate 1 Bluff Boat Ramp Car Park Extension - Construction $390 2 Kerb & Channel Replacement Program (as per condition assessments) $120 3 Traffic Management / Treatments - General Areas 4 Kullaroo Rd - High School - Traffic and Pedestrian Improvements - Construction 2017 Network Renewals $40 $220 5 6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals $770 1 Kerb & Channel Replacement Program (as per condition assessments) $100 2 New Guard Railing - Waitpinga Rd $155 3 Waitpinga Rd/Battye Rd Intersection - Construction $545 4 5 6 7 8 9 10 2018 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2018 Total $800 ($000) Year Item 2019 Description Estimate Network Renewals 1 Yacht Club Car Park - Design $25 2 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $35 3 New Guard Railing for High Risk - Major Culverts 4 Kerb & Channel Replacement Program (as per condition assessments) $150 $70 5 6 7 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals $280 Estimate 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $60 2 Encounter Bikeway Lighting adjacent Franklin Parade $15 3 New Guard Railing for High Risk - Major Culverts 4 Kerb & Channel Replacement Program (as per condition assessments) 5 6 $50 $120 7 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $245 ($000) Year Item 2021 Description Estimate Network Renewals 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $90 2 New Guard Railing for High Risk - Major Culverts $80 3 Crozier/Acraman/Lindsay - Treatment Design $15 4 Kerb & Channel Replacement Program (as per condition assessments) $110 5 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2021 Total 2022 Network Renewals $295 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study 2 New Guard Railing for High Risk - Major Culverts 3 Yacht Club Car Park - Construction $500 4 Kerb & Channel Replacement Program (as per condition assessments) $130 $100 $40 5 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $770 ($000) Year Item 2023 Description Estimate Network Renewals 1 Kerb & Channel Replacement Program (as per condition assessments) $130 2 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $110 3 New Guard Railing for High Risk - Major Culverts $40 4 Crozier/Acraman/Lindsay - Treatment - Construct Implement $35 5 6 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 Network Renewals $315 1 Kerb & Channel Replacement Program (as per condition assessments) $210 2 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $140 3 New Guard Railing for High Risk - Major Culverts $100 4 5 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $450 ($000) Year Item 2025 Description Estimate Network Renewals 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $160 2 New Guard Railing for High Risk - Major Culverts $120 3 Kerb & Channel Replacement Program (as per condition assessments) $210 4 New Guard Railing for High Risk - Major Culverts $120 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total 2026 Network Renewals $610 1 Kerb & Channel Replacement Program (as per condition assessments) $210 2 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $140 3 New Guard Railing for High Risk - Major Culverts $120 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $470 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Kerb Channel, Car Parks_S2_V2 ($000) Year Item Description Estimate 2017 1 Bluff Boat Ramp Car Park Extension - Construction $200 2 Traffic Management / Treatments - General Areas $40 3 New Guard Railing for High Risk - Major Culverts $50 4 Kullaroo Rd - High School - Traffic and Pedestrian Improvements - Construction $220 Total $510 5 6 7 8 9 10 2017 ($000) Year Item 2018 1 Description Estimate Waitpinga Rd/Battye Rd Intersection - Construction $136 Total $136 2 3 4 5 6 7 8 9 10 2018 ($000) Year Item 2019 1 Yacht Club Car Park - Design $25 2 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $35 3 4 5 6 7 8 9 Description Estimate 10 2019 Total $60 ($000) Year 2020 Item Description Estimate 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $20 2 Encounter Bikeway Lighting adjacent Franklin Parade $65 Total $85 3 4 5 6 7 8 9 10 2020 ($000) Year Item 2021 1 Description Estimate 2 3 Crozier/Acraman/Lindsay - Treatment Design $15 Total $15 4 5 6 7 8 9 10 2021 ($000) Year Item 2022 1 Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $20 2 Yacht Club Car Park - Construction $50 3 4 5 6 7 8 9 10 Description Estimate 2022 Total $70 ($000) Year Item 2023 1 Description Estimate Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $30 Total $30 2 3 4 5 6 7 8 9 10 2023 ($000) Year Item 2024 1 Description Estimate Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $40 Total $40 2 3 4 5 6 7 8 9 10 2024 ($000) Year Item 2025 1 Description Estimate 2 3 4 5 6 7 8 9 10 2025 Total $0 ($000) Year Item 2026 1 Description Estimate Traffic Management Treatments - General Areas - Outcomes/Resolutions from 2016 Traffic Study $20 Total $20 2 3 4 5 6 7 8 9 10 2026 OPEN SPACE RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Open Space _S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 Irrigation for Reserves - Cliff Thorpe $10k / Eric Ashby $7k / Brain Spilsbury $8k 2 Reserve Furniture Replacements $30 $8 3 Street Furniture Replacements $15 4 Beach & Reserve Access Points $20 5 Cemetery Development, Finnis Rd $9 6 Walking Trails $6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals $88 1 GT Fischer Reserve Playground & Equipment Replacement 2 Street Furniture Replacement Program $15 3 Reserve Furniture Replacement Program $25 4 Irrigation - Alf Siegert and Causeway $30k - Irrigation, GT Fischer Reserve $35k $20 5 Cemetery Development, Finnis Rd $10 6 7 8 9 10 2018 Defect Repairs 1 $176 2 3 4 5 6 7 8 9 10 2018 Total $246 ($000) Year Item 2019 Description Estimate Network Renewals 1 Open Space Structures $10 2 Court Development - Foreshore Courts - Drainage and Surfacing / Foreshore Courts, Fencing $25k $87 3 Reserve Furniture Replacements $25 4 Street Furniture Replacements $13 5 Playgrounds $30 6 Beach and Reserve Access Points $20 7 Walking Trails - Morgan Park $10 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals $195 Estimate 1 Playgrounds - Young Reserve and Blockers Reserve $40 2 Reserve Furniture Replacements $30 3 Street Furniture Replacements $15 4 Beach and Reserve Access Points $25 5 Cemetery Development, Finnis Rd $10 6 Irrigation - Bridge Tce Reserve $20 7 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $140 ($000) Year Item 2021 Description Estimate Network Renewals 1 Reserve Development - Kent Reserve $5 2 Open Space Structures $5 3 Irrigation Renewal - Grosvenor Gardens - Barker Reserve $30 4 Playground Renewal - Young Reserve - Blocker Reserves $25 5 Reserve Development - Kent Reserve 6 Reserve Furniture Replacements $30 7 Street Furniture Replacements $15 8 Beach and Reserve Access Points $25 9 Walking Trails $10 10 Cemetery Development, Finnis Rd $10 2021 $156 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2021 Total 2022 Network Renewals 1 Reserve Development $311 $10 2 Irrigation Renewal - Kent Reserve (Water Re-Use) $105 3 Playground Upgrades $30 4 Reserve Development $55 5 Reserve Furniture Replacements $30 6 Street Furniture Replacements $15 7 Beach and Reserve Access Points $10 8 Cemetery Development, Finnis Rd $5 9 Walking Trails $10 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $270 ($000) Year Item 2023 Description Estimate Network Renewals 1 Irrigation Upgrades $25 2 Playground Upgrades $30 3 Reserve Development $80 4 Reserve Furniture Replacements $30 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $30 7 Walking Trails $10 8 Open Space Structures $15 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 Network Renewals $235 1 Reserve Development $60 2 Irrigation Upgrades $40 3 Playground Upgrades $52 4 Reserve Furniture Replacements $45 5 Street Furniture Replacements $25 6 Beach and Reserve Access Points $25 7 Walking Trails $15 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $262 ($000) Year Item 2025 Description Estimate Network Renewals 1 Open Space Structures $10 2 Irrigation Upgrades $25 3 Playground Upgrades $35 4 Reserve Development $96 5 Reserve Furniture Replacements $40 6 Street Furniture Replacements $20 7 Beach and Reserve Access Points $25 8 Walking Trails $40 9 Open Space Structures $15 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total 2026 Network Renewals $306 1 Reserve Development $60 2 Irrigation Upgrades $20 3 Playground Upgrades $35 4 Reserve Development $30 5 Reserve Furniture Replacements $40 6 Street Furniture Replacements $25 7 Beach and Reserve Access Points $30 8 Walking Trails $20 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $260 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Open Space _S2_V2 ($000) Year Item Description Estimate 2017 1 Irrigation Water Reuse - Complete Soldiers Memorial Gardens $20 2 Irrigation for Reserves - Cliff Thorpe $10k / Eric Ashby $7k / Brian Spilsbury $8k $17 3 Brandwood Reserve - Stage 2 FINAL $40 4 Reserve Furniture Replacements $20 5 Street Furniture Replacements $30 6 Beach and Reserve Access Points $25 7 Cemetery Development, Finnis Rd $51 8 9 10 2017 Total $203 ($000) Year Item Description Estimate 2018 1 Irrigation - Alf Siegert and Causeway $30k - Irrigation, GT Fischer Reserve $35k 2 GT Fischer Reserve Playground & Equipment Replacement 3 Reserve Furniture Replacement Program $25 4 Street Furniture Replacement Program $15 5 Beach and Reserve Access Points $75 6 Cemetery Development, Finnis Rd $40 7 Railway Turntable Project (DPRS Graham Pathuis) 100% funded by council $462 Total $926 $45 $264 8 9 10 2018 ($000) Year Item 2019 1 Reserve Furniture Replacements Description Estimate $25 2 Street Furniture Replacements $13 3 Beach and Reserve Access Points $55 4 Cemetery Development, Finnis Rd $40 5 Walking Trails - Morgan Park $40 6 Open Space Structures $10 7 Playgrounds $30 8 Court Development - Foreshore Courts - Drainage and Surfacing $58 9 10 2019 Total $271 ($000) Year Item Description Estimate 2020 1 Playgrounds - Young Reserve and Blockers Reserve $20 2 Reserve Furniture Replacements $30 3 Street Furniture Replacements $15 4 Beach and Reserve Access Points $50 5 Cemetery Development, Finnis Rd $20 6 Irrigation - Bridge Tce Reserve $20 7 Walking Trails - Bluff Reserve $20 8 9 10 2020 Total $175 ($000) Year Item Description Estimate 2021 1 Irrigation Renewal - Grosvenor Gardens - Barker Reserve $30 2 Playground Renewal - Young Reserve - Blocker Reserves $40 3 Reserve Development - Kent Reserve $39 4 Reserve Furniture Replacements $30 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $25 7 Cemetery Development, Finnis Rd $20 8 Walking Trails $50 9 Open Space Structures $15 10 2021 Total $264 ($000) Year Item Description Estimate 2022 1 Irrigation Renewal - Kent Reserve (Water Re-Use) $45 2 Playground Upgrades $30 3 Reserve Development $55 4 Reserve Furniture Replacements $30 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $40 7 Cemetery Development, Finnis Rd $15 8 Walking Trails $50 9 10 2022 Total $280 ($000) Year Item Description Estimate 2023 1 Irrigation Upgrades $25 2 Playground Upgrades $30 3 Reserve Development $40 4 Reserve Furniture Replacements $30 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $20 7 Walking Trails $50 8 Open Space Structures $5 9 10 2023 Total $215 ($000) Year Item 2024 1 Irrigation Upgrades Description Estimate $20 2 Playground Upgrades $13 3 Reserve Development $60 4 Reserve Furniture Replacements $20 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $25 7 Walking Trails $45 8 9 10 2024 Total $198 ($000) Year Item Description Estimate 2025 1 Irrigation Upgrades $25 2 Playground Upgrades $30 3 Reserve Development $14 4 Reserve Furniture Replacements $40 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $25 7 Walking Trails $20 8 Open Space Structures $5 9 10 2025 Total $174 ($000) Year Item 2026 1 Description Irrigation Upgrades Estimate $30 2 Playground Upgrades $35 3 Reserve Development $30 4 Reserve Furniture Replacements $40 5 Street Furniture Replacements $15 6 Beach and Reserve Access Points $20 7 Walking Trails $40 8 9 10 2026 Total $210 ROADS RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Roads_S2_V2 ($000) Year Item 2017 1 2 3 4 5 6 7 8 9 10 2017 Description Network Renewals Resheeting Unsealed Roads Bitumen Reseals Greenhillls Road, Construction (Greenhills Bridge to Canterbury) Waitpinga Road - Range Rd to End of The Straight - Stage 1 Estimate $140 $300 $463 $100 Main Street Precinct Master Plan: Part Stage 1 - Ocean/Coral Intersection & Stage 2-North and South Nodes, Construction - 50% Grant Funding Received $442 Ocean Road - Construction Stage 2 - Ch480 to about Ch890 Traffic Management Treatments Matthews St - Bitumen Seal Wattlebury Rd - Finalise Design $191 $70 $6 $22 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 1 2 Network Renewals Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works $140 $125 3 The Parkway (Riverview to Field) - Construction $300 4 Ocean Road - Construction - Stage 3 FINAL - about Ch890 to End Goolwa/Port Elliot Rd, (subject to SLRP Grant Funding) $190 5 Mainstreet Precinct Master Plan - Stage 2, Complete Construction (WIP from 2016/17), (subject to 50% grant funding) $227 6 7 Passat Street, Design Wattlebury Road, Construction/Bitumen Seal $20 $153 8 Mainstreet Precinct Master Plan - Stage 3, Start Design & Documentation (project 100% funded by council) $154 9 10 Waitpinga Road - The Straight - Stage 2 (subject to SLRP Grant Funding) $1,734 $60 2018 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2018 Total $1,369 ($000) Year Item 2019 Description Estimate 1 Network Renewals Pine Avenue, Construction (Hindmarsh to Riverview) Stage 1 $310 2 3 4 Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works Ridge Avenue, Construction (Battye to Clair) $140 $300 $212 5 Mainstreet Precinct Master Plan - Stage 3 - Start Construction (subject to 50% Grant Funding) $194 6 7 Ridge Avenue, Construction (Battye to Clair) Mainstreet Precinct Master Plan - Stage 4 - Start Design & Documentation (project 100% funded by council) $348 $46 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals Pine Avenue, Construction(Hindmarsh to Warland) Stage 2 FINAL Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works 1 2 3 4 Mainstreet Precinct Master Plan - Stage 3 - Complete Construction (subject to 50% Grant Funding) $1,550 Estimate $192 $150 $200 $213 5 Mainstreet Precinct Master Plan - Stage 4 - Start Construction (subject to 50% Grant Funding) $54 6 Traffic Management Treatments $20 7 8 Passat Street, Construction Lincoln Road - Lincoln Rd Change of Seal to End - Length about 230m - Design Mainstreet Precinct Master Plan - Stage 5 - Start Design & Documentation (project 100% funded by council) 9 $250 $15 $120 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $1,214 ($000) Year Item 2021 Description Estimate Network Renewals 1 2 Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works 3 Mainstreet Precinct Master Plan - Stage 4 - Complete Construction (subject to 50% Grant Funding) 4 Mainstreet Precinct Master Plan - Stage 5 - Start Construction (subject to 50% Grant Funding) 5 6 Sturt Street, Design (Burke to Oval Road) Traffic Management Treatments 7 8 Lincoln Road - Lincoln Rd Change of Seal to End - Length about 230m - Construction Valley View Rd - Waggon Rd to End - distance about 286m - Design Mainstreet Precinct Master Plan - Stage 6 - Start Design & Documentation (project 100% funded by council) 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 8 9 10 $150 $470 $72 $300 $35 $20 $110 $20 $114 2021 Total 2022 Network Renewals Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works 1 2 $1,291 $150 $384 3 Mainstreet Precinct Master Plan - Stage 5 - Complete Construction (subject to 50% Grant Funding) $300 4 Mainstreet Precinct Master Plan - Stage 6 - Start Construction (subject to 50% Grant Funding) $309 5 6 7 8 9 Sturt Street, Construction (Burke to Oval Rd) Day Road, Design Valley View Rd - Waggon Rd to End - distance about 286m - Construction River Road, Design Mainstreet Precinct Master Plan - Stage 7 - Start Design & Documentation (project 100% funded by council) $295 $35 $150 $20 $64 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $1,707 ($000) Year Item 2023 1 2 Description Network Renewals Resheeting Unsealed Roads Bitumen Reseals / Asphaltic Works Estimate $150 $570 3 Mainstreet Precinct Master Plan - Stage 6 - Complete Construction (subject to 50% Grant Funding) $309 4 Mainstreet Precinct Master Plan - Stage 7 - Start Construction (subject to 50% Grant Funding) $202 Day Road - Construction and Bitumen Seal $650 5 6 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2023 Total 2024 Network Renewals Resheeting Unsealed Roads Bitumen Reseals 1 2 3 4 5 6 7 8 $1,881 $150 $550 Mainstreet Precinct Master Plan - Stage 7 - Complete Construction (subject to 50% Grant Funding) Traffic Management Treatments Hart Avenue - Battye Rd to Lot 1 - distance about 125m - Design River Road - Baudin Rd to Canterbury Rd - distance about 225m - Design $202 $20 $30 $20 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $972 ($000) Year Item 2025 1 2 3 4 5 6 7 8 9 Description Network Renewals Resheeting Unsealed Roads Bitumen Reseals Traffic Management Treatments River Road - Baudin Rd to Canterbury Rd - distance about 225m - Construction & Bitumen Seal Estimate $150 $550 $20 $216 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total $936 2026 Network Renewals Resheeting Unsealed Roads Bitumen Reseals Traffic Management Treatments $170 $550 $20 Hart Avenue - Battye Rd to Lot 1 - distance about 125m - Construction & Bitumen Seal $110 1 2 3 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $850 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Roads_S2_V2 Year 2017 Item 1 2 3 4 5 6 7 8 9 Description Greenhillls Road - Construction (Greenhills Bridge to Canterbury) Ocean Road - Construction - Stage 2 - Ch480 to about Ch890 Matthews St - Bitumen Seal Wattlebury Rd - Finalise Design Traffic Management Treatments ($000) Estimate $198 $128 $7 $13 $70 Main Street Precinct Master Plan: Part Stage 1 - Ocean/Coral Intersection & Stage 2North and South Nodes - Complete Construction - 50% Grant Funding Received $189 Total $605 10 2017 Year Item 2018 1 2 3 Ridge Avenue, Design Only (Battye to Clair) Traffic Management Treatments Passat Street, Design 4 5 6 Ocean Road - Construction - Stage 3, FINAL - about Ch890 to End Goolwa/Port Elliot Road, (subject to SLRP Grant Funding) Wattlebury Road, Construction/Bitumen Seal Waitpinga Road - The Straight - Stage 2 (subject to SLRP Grant Funding) $47 $102 $60 7 8 Mainstreet Precinct Master Plan - Stage 3, Start Design & Documentation (project 100% funded by council) Bitumen Reseals / Asphaltic Works $66 $125 9 Mainstreet Precinct Master Plan - Stage 2, Complete Construction (WIP from 2016/17), (subject to 50% grant funding) $515 10 The Parkway (Riverview to Field) - Construction 2018 Year 2019 Description ($000) Estimate Total Item 1 2 3 Description Ridge Avenue, Construction (Battye to Clair) Traffic Management Treatments Pine Avenue, Construction (Hindmarsh to Riverview) Stage 1 5 Waitpinga Road - Range Rd to End of The Straight Stage 2, project subject to SLRP 66% Grant Funding Mainstreet Precinct Master Plan - Stage 4 - Start Design & Documentation (project 100% funded by council) 6 Mainstreet Precinct Master Plan - Stage 3 - Start Construction (subject to 50% Grant Funding) 4 $40 $20 $20 $21 $1,016 ($000) Estimate $141 $35 $135 $400 $70 $453 7 8 9 10 2019 Year 2020 Total Item 1 2 3 4 Description Traffic Management Treatments Passat Street, Construction Lincoln Road - Lincoln Rd Change of Seal to End - Length about 230m - Design Pine Avenue, Construction(Hindmarsh to Warland) Stage 2 FINAL ($000) Estimate $15 $250 $15 $193 5 Ring Road Bridge Approaches $120 6 7 Waitpinga Road - Range Rd to End of The Straight - Stage 4 FINAL (project subject to SLRP 66% Grant Funding) Bitumen Reseals / Asphaltic Works $300 $200 8 Mainstreet Precinct Master Plan - Stage 5 - Start Design & Documentation (project 100% funded by council) $179 9 Mainstreet Precinct Master Plan - Stage 3 - Complete Construction (subject to 50% Grant Funding) $499 10 2020 Year 2021 $1,234 Item 1 2 3 4 Mainstreet Precinct Master Plan - Stage 4 - Start Construction (subject to 50% Grant Funding) Total Description Sturt Street, Design (Burke to Oval Road) $125 $1,896 ($000) Estimate $35 5 Traffic Management Treatments Lincoln Road - Lincoln Rd Change of Seal to End - Length about 230m - Construction Valley View Rd - Waggon Rd to End - distance about 286m - Design Mainstreet Precinct Master Plan - Stage 6 - Start Design & Documentation (project 100% funded by council) $15 $110 $15 6 Mainstreet Precinct Master Plan - Stage 4 - Complete Construction (subject to 50% Grant Funding) $107 7 Mainstreet Precinct Master Plan - Stage 5 - Start Construction (subject to 50% Grant Funding) $700 $172 8 9 10 2021 Year 2022 Total Item 1 2 Description Sturt Street, Construction (Burke to Oval Rd) Day Road, Design $1,154 ($000) Estimate $295 $35 3 Traffic Management Treatments $35 4 5 6 Valley View Rd - Waggon Rd to End - distance about 286m - Construction River Road, Design Bitumen Reseals / Asphaltic Works $45 $20 $96 7 Mainstreet Precinct Master Plan - Stage 7 - Start Design & Documentation (project 100% funded by council) $150 8 Mainstreet Precinct Master Plan - Stage 5 - Complete Construction (subject to 50% Grant Funding) $700 9 Mainstreet Precinct Master Plan - Stage 6 - Start Construction (subject to 50% Grant Funding) $721 10 2022 Total $2,097 Year Item Description 2023 1 2 3 Day Road - Construction and Bitumen Seal Traffic Management Treatments Mainstreet Precinct Master Plan - Stage 6 - Complete Construction (subject to 50% Grant Funding) 4 Mainstreet Precinct Master Plan - Stage 7 - Start Construction (subject to 50% Grant Funding) ($000) Estimate $300 $40 $721 $470 5 6 7 8 9 10 2023 Year 2024 Total Item 1 2 3 4 5 6 7 8 $1,531 Description Traffic Management Treatments Hart Avenue - Battye Rd to Lot 1 - distance about 125m - Design River Road - Baudin Rd to Canterbury Rd - distance about 225m - Design ($000) Estimate $20 $15 $20 Mainstreet Precinct Master Plan - Stage 7 - Complete Construction (subject to 50% Grant Funding) $470 Total $525 9 10 2024 ($000) Year Item Description Estimate 2025 1 2 3 4 5 6 7 Traffic Management Treatments $20 River Road - Baudin Rd to Canterbury Rd - distance about 225m - Construction & Bitumen Seal $144 Total $164 8 9 10 2025 Year 2026 Item 1 2 3 4 Description Traffic Management Treatments Hart Avenue - Battye Rd to Lot 1 - distance about 125m - Construction & Bitumen Seal ($000) Estimate $29 $110 5 6 7 8 9 10 2026 Total $139 STORMWATER RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Stormwater _S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades $70 $8 3 Bacchus Wetland Upgrade/Construction. Design Completed, Review of Design & Costs $7 4 Lamont Court - Stormwater Drainage Construction $141 5 Yandra Tce (Ocean Outfall up to Brandwood Reserve Construction - Stage 1 of 2 $255 6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals 1 Inlet Program, Construction 2 Yandra Tce (Brandwood Reserve to Mentone) Construction - Stage 2 FINAL 3 Cakebread Rd - Service Depthing - Design Only 4 Coastal Stormwater Outlet Upgrades 5 Field Ave / Brand / Pine Av - Construction 6 7 8 9 10 2018 Defect Repairs 1 $481 $35 $310 $16 $5 $122 2 3 4 5 6 7 8 9 10 2018 Total $488 ($000) Year Item 2019 Description Estimate Network Renewals 1 Inlet Program, Construction $30 2 Coastal Stormwater Outlet Upgrades $15 3 Acraman Street (Hill St - Hinkler St) Construction 4 Petrel Ave, Construction Stage 1 of 2 $1,040 $50 5 6 7 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades 3 Bacchus Wetland Upgrade, Construction 4 Higgins Street, Design 5 Cakebread Rd - Construction, including downstream upgrades 6 7 $1,135 Estimate $40 $8 $1,248 $55 $300 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $1,651 ($000) Year Item 2021 Description Estimate Network Renewals 1 Inlet Program Construction 2 Coastal Stormwater Outlet Upgrades 3 Seaview Road / Hindmarsh Road Construction 4 Yilki Common Reserve - Design $25 $5 $800 $25 5 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2021 Total 2022 Network Renewals $855 1 Coastal Stormwater Outlet Upgrades $5 2 Inlet Program Construction $5 3 Lamont Court Levee, Construction $328 4 Churchill Road (Crozier - Inman River) Design $20 5 Flood Mitigation, Beachfront Caravan Park, Design $30 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $388 ($000) Year Item 2023 Description Estimate Network Renewals 1 Coastal Stormwater Outlet Upgrades 2 Inlet Program Construction 3 Churchill Road (Crozier - Inman River) Construction 4 Haugs Dam Upgrade, Design $40 5 Fell Street - Upgrade, Design $20 6 Flood Mitigation - Beachfront Caravan Park, Construction 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 10 $6 $35 $140 $440 2023 Total 2024 $681 Network Renewals 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades 3 Haugs Dam Upgrade, Construction 4 Sweetman Avenue, Construction 5 Fell Street, Construction $25 $8 $256 $29 $105 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $423 ($000) Year Item 2025 Description Estimate Network Renewals 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades $5 3 Canterbury (Dene - Crozier) Design $30 4 Kullaroo Road (Flood Protection Levee) Design $30 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 $35 6 7 8 9 10 2025 Total 2026 Network Renewals 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades 3 Canterbury (Dene - Crozier) Construction 4 Kullaroo Road (Flood Protection Levee) Construction $100 $40 $2 $44 $130 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $216 NEW/UPGRADES Victor Harbor CC Projected Capital Upgrade/New Works Program - Stormwater _S2_V2 ($000) Year Item Description Estimate 2017 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades 3 Petrel Ave, Design for Kerb & Channel / Underground Stormwater 4 Lamont Court - Stormwater Drainage Construction 5 Yandra Tce (Ocean Outfall up to Brandwood Reserve) Construction - Stage 1 of 2 $80 6 Field Ave / Brand / Pine Av - Design $20 $35 $6 $60 $159 7 8 9 10 2017 Total $360 ($000) Year Item Description Estimate 2018 1 Field Ave / Brand / Pine Av - Construction 2 Inlet Program, Construction 3 Coastal Stormwater Outlet Upgrades 4 Railway Terrace - Warland Reserve to Large Tree - Underground Stormwater (Design Only) 5 Yandra Tce (Brandwood Reserve to Mentone) Construction - Stage 2 FINAL 6 Tabernacle Rd - Bay Rd to Matthews Flinders Drive - Design Only $49 7 Cakebread Rd - Service Depthing - Design Only $15 $488 $30 $5 $40 $310 8 9 10 2018 Total $937 ($000) Year Item 2019 1 Acraman Street (Hill St - Hinkler St) Construction 2 Inlet Program, Construction $30 3 Seaview Road / Hindmarsh Road Design $75 4 Coastal Stormwater Outlet Upgrades $15 5 Petrel Ave, Construction Stage 1 of 2 $450 6 Railway Terrace - Warland Reserve to Large Tree - Underground Stormwater (Construction) $370 7 Tabernacle Rd - Bay Rd to Matthews Flinders Drive - (Construction) $880 8 9 Description Estimate $260 10 2019 Total $2,080 ($000) Year Item Description Estimate 2020 1 Bacchus Wetland Upgrade, Construction 2 Inlet Program, Construction 3 Coastal Stormwater Outlet Upgrades $8 4 Petrel Ave, Construction Stage 2 of 2 $600 5 Higgins Street, Design 6 Cakebread Rd - Construction, including downstream upgrades $252 $30 $15 $300 7 8 9 10 2020 Total $1,205 ($000) Year Item Description Estimate 2021 1 Inlet Program, Construction $25 2 Higgins Street Construction $40 3 Lamont Court Levee, Design $60 4 Coastal Stormwater Outlet Upgrades $20 5 Seaview Road / Hindmarsh Road Construction 6 Yilki Common Reserve - Design $200 $25 7 8 9 10 2021 Total $370 ($000) Year Item Description Estimate 2022 1 Lamont Court Levee, Construction $82 2 Churchill Road (Crozier - Inman River) Design $20 3 Flood Mitigation, Beachfront Caravan Park, Design $30 4 Coastal Stormwater Outlet Upgrades $15 5 Inlet Construction Program 6 Yilki Common Reserve - Construction $375 Total $592 $70 7 8 9 10 2022 ($000) Year Item Description Estimate 2023 1 Churchill Road (Crozier - Inman River) Construction 2 Flood Mitigation - Beachfront Caravan Park, Construction 3 Haugs Dam Upgrade, Design $40 4 Fell Street - Upgrade, Design $20 5 Sweetman Avenue, Design $25 6 Coastal Stormwater Outlet Upgrades 7 Inlet Construction Program $34 $110 $6 $35 8 9 10 2023 Total $270 ($000) Year Item Description Estimate 2024 1 Inlet Program, Construction $25 2 Haugs Dam Upgrade, Construction $64 3 Fell Street, Construction $105 4 Sweetman Avenue, Construction $116 5 Coastal Stormwater Outlet Upgrades $16 6 7 8 9 10 2024 Total $326 ($000) Year Item Description Estimate 2025 1 Inlet Program, Construction 2 Coastal Stormwater Outlet Upgrades $5 3 Canterbury (Dene - Crozier) Design $30 4 Kullaroo Road (Flood Protection Levee) Design $30 $35 5 6 7 8 9 10 2025 Total $100 ($000) Year Item Description Estimate 2026 1 Canterbury (Dene - Crozier) Construction 2 Inlet Program, Construction 3 Kullaroo Road (Flood Protection Levee) Construction $130 Total $346 $176 $40 4 5 6 7 8 9 10 2026 OTHER INFRASTRUCTURE RENEWALS Victor Harbor CC Projected Capital Renewal Works Program - Other Infrastructure_S2_V2 ($000) Year Item 2017 Description Estimate Network Renewals 1 Replacement of Encounter Lakes Gates $165 2 3 4 5 6 7 8 9 10 2017 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2017 Total 2018 Network Renewals 1 Replace Horse Tram Track Sleepers (DPRS Graham Pathius) 2 Tram Refurbishment 3 4 5 6 7 8 9 10 2018 Defect Repairs 1 $165 $60 $200 2 3 4 5 6 7 8 9 10 2018 Total $260 ($000) Year Item 2019 Description Estimate Network Renewals 1 Replace Horse Tram Track Sleepers (DPRS Graham Pathius) $60 2 3 4 5 6 7 8 9 10 2019 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2019 Total 2020 Network Renewals $60 Estimate 1 Replacement of Tram Line - Penguin Centre to Granite and Terminus (DPRS Graham Pathuis) $80 2 Replace Horse Tram Track Sleepers (DPRS Graham Pathius) $60 3 4 5 6 7 8 9 10 2020 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2020 Total $140 ($000) Year Item 2021 Description Estimate Network Renewals 1 Replace Horse Tram Track Sleepers (DPRS Graham Pathius) $60 2 3 4 5 6 7 8 9 10 2021 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2021 Total 2022 Network Renewals 1 Franklin Parade - Sea Wall - Stage 1 - Height 2.65m AHD $60 $100 2 3 4 5 6 7 8 9 10 2022 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2022 Total $100 ($000) Year Item 2023 Description Estimate Network Renewals 1 Franklin Parade - Sea Wall - Stage 2 - Height 2.65m AHD 2 3 4 5 6 7 8 9 10 2023 Defect Repairs 1 2 3 4 5 6 7 8 9 $100 10 2023 Total 2024 Network Renewals $100 1 Tram Line Replacement - Granite Island Loop and Points (DPRS Graham Pathuis) $130 2 Franklin Parade - Sea Wall - Stage 3 - Height 2.65m AHD $100 3 4 5 6 7 8 9 10 2024 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2024 Total $230 ($000) Year Item 2025 Description Estimate Network Renewals 1 Franklin Parade - Sea Wall - Stage 4 - Height 2.65m AHD $100 2 Esplanade - Sea Wall - Stage 1 - Height 2.65m AHD $100 3 4 5 6 7 8 9 10 2025 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2025 Total 2026 Network Renewals 1 Esplanade - Sea Wall - Stage 2 - Height 2.65m AHD $200 $100 2 3 4 5 6 7 8 9 10 2026 Defect Repairs 1 2 3 4 5 6 7 8 9 10 2026 Total $100 NEW/UPGRADE Victor Harbor CC Projected Capital Upgrade/New Works Program - Other Infrastructure_S2_V2 ($000) Year Item 2017 1 Description Estimate Beach Erosion - Placement of Concrete Blocks - King Street $47 Total $47 2 3 4 5 6 7 8 9 10 2017 ($000) Year Item Description Estimate 2018 1 Bluff Boat Ramp Holding Area - Located Off Breakwater - Final Extension (Subject to SABFAC 50% Grant Funding) $38 2 RV Dump Point $40 Total $78 3 4 5 6 7 8 9 10 2018 ($000) Year Item 2019 1 2 3 4 5 6 7 8 9 10 Description Estimate 2019 Total $0 ($000) Year Item 2020 1 Description Estimate Replacement of Tram Line - Penguin Centre to Granite and Terminus (DPRS Graham Pathuis) $20 Total $20 2 3 4 5 6 7 8 9 10 2020 ($000) Year Item 2021 1 Description Estimate 2 3 4 5 6 7 8 9 10 2021 Total $0 ($000) Year Item 2022 1 Description Estimate Franklin Parade - Sea Wall - Stage 1 - Height 2.65m AHD $400 Total $400 2 3 4 5 6 7 8 9 10 2022 ($000) Year Item 2023 1 Description Estimate Franklin Parade - Sea Wall - Stage 2 - Height 2.65m AHD $400 Total $400 2 3 4 5 6 7 8 9 10 2023 ($000) Year Item 2024 1 Description Estimate Franklin Parade - Sea Wall - Stage 3 - Height 2.65m AHD $400 Total $400 2 3 4 5 6 7 8 9 10 2024 ($000) Year Item Description Estimate 2025 1 Franklin Parade - Sea Wall - Stage 4 - Height 2.65m AHD $400 2 Esplanade - Sea Wall - Stage 1 - Height 2.65m AHD $400 Total $800 3 4 5 6 7 8 9 10 2025 ($000) Year Item 2026 1 Description Estimate Esplanade - Sea Wall - Stage 2 - Height 2.65m AHD $400 Total $400 2 3 4 5 6 7 8 9 10 2026
© Copyright 2026 Paperzz