Photos at least 1 up to 3 project/survey specific to completely fill the white box, DO NOT CHANGE SIZE OF WHITE BOX KOOLAN ISLAND IRON ORE MINE AND PORT FACILITY Conceptual Closure Plan ecologia ENVIRONMENT Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Document Status Rev Author No. Final K. Bleby R. Mason Reviewer/s Date V Ee Nov 05 Approved for Issue Name Distributed To Dudley EPA Kingsnorth Date Nov 05 © ecologia Environment (2005). Reproduction of this report in whole or in part by electronic, or mechanical means including photocopying, recording or by any information storage and retrieval system, in any language, is strictly prohibited without the express approval of Aztec Resources Limited and/or ecologia Environment. Restrictions on Use This report has been prepared specifically for Aztec Resources Limited. Neither the report nor its contents may be referred to or quoted in any statement, study, report, application, prospectus, loan, or other agreement document, without the express approval of Aztec Resources Limited and/or ecologia Environment. ecologia Environment 76 Thomas Street WEST PERTH WA 6005 Phone 08 9322 1944 Fax 08 9322 1599 Email [email protected] Page i ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan CONTENTS SUMMARY 5 1.0 6 1.1 1.2 1.3 1.4 INTRODUCTION PREVIOUS OPERATIONS ........................................................................................................................7 CURRENT OPERATIONS .........................................................................................................................8 PLANNED OPERATIONS .........................................................................................................................8 PROJECT CLOSURE PLAN SCOPE ..........................................................................................................9 2.0 PROJECT CLOSURE OBJECTIVES 14 3.0 LEGAL OBLIGATIONS 15 3.1 3.2 4.0 4.1 4.2 5.0 5.1 5.2 6.0 6.1 6.2 7.0 7.1 7.2 8.0 8.1 8.2 8.3 9.0 9.1 9.1.1 9.1.2 9.1.3 9.2 9.2.1 9.2.2 9.2.3 9.3 9.3.1 9.3.2 9.3.3 9.4 9.4.1 9.4.2 9.4.3 9.5 9.5.1 9.5.2 9.5.3 LEGISLATION .......................................................................................................................................15 GUIDELINES AND CODES OF PRACTISE ..............................................................................................16 COMPLETION CRITERIA 17 OBJECTIVE...........................................................................................................................................17 PROPOSED COMPLETION CRITERIA ...................................................................................................17 CONTAMINATED SITES 19 OBJECTIVE...........................................................................................................................................19 CONTAMINATED SITES INVESTIGATION AND MANAGEMENT............................................................19 DECOMMISSIONING 21 OBJECTIVE...........................................................................................................................................21 REMOVAL OF INFRASTRUCTURE ........................................................................................................21 DEVELOPMENT OF FINAL LANDFORMS 23 OBJECTIVE...........................................................................................................................................23 SHAPING OF LANDFORMS....................................................................................................................23 REHABILITATION STRATEGIES 25 OBJECTIVES .........................................................................................................................................25 REHABILITATION ................................................................................................................................25 MONITORING OF REHABILITATION ....................................................................................................26 PROPOSED CLOSURE STRATEGIES 27 MINE PITS ............................................................................................................................................27 CLOSURE OBJECTIVE .............................................................................................................................27 CLOSURE STRATEGY ...............................................................................................................................27 COMPLETION CRITERIA ..........................................................................................................................28 SEAWALL .............................................................................................................................................30 CLOSURE OBJECTIVE ............................................................................................................................30 CLOSURE STRATEGY .............................................................................................................................30 COMPLETION CRITERIA.........................................................................................................................30 WASTE ROCK MANAGEMENT .............................................................................................................30 CLOSURE OBJECTIVE .............................................................................................................................31 CLOSURE STRATEGY ...............................................................................................................................31 COMPLETION CRITERIA ..........................................................................................................................32 BORROW PITS ......................................................................................................................................32 OBJECTIVES ...........................................................................................................................................32 CLOSURE STRATEGY ...............................................................................................................................32 COMPLETION CRITERIA ..........................................................................................................................32 DEWATERING ......................................................................................................................................33 OBJECTIVES ...........................................................................................................................................33 CLOSURE STRATEGY ...............................................................................................................................33 COMPLETION CRITERIA ..........................................................................................................................33 Page ii ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.6 9.6.1 9.6.2 9.6.3 9.7 9.7.1 9.7.2 9.7.3 9.8 9.8.1 9.8.2 9.8.3 9.9 9.9.1 9.9.2 9.9.3 9.10 9.10.1 9.10.2 9.10.3 9.11 9.11.1 9.11.2 9.11.3 9.12 9.12.1 9.12.2 9.12.3 9.13 9.13.1 9.13.2 9.13.3 9.14 9.14.1 9.14.2 9.14.3 9.15 9.15.1 9.15.2 9.15.3 10.0 10.1 10.2 11.0 11.1 11.2 12.0 12.1 12.2 14.0 HAUL ROADS, ROM PAD, STOCKPILE AND ORE PROCESSING .........................................................34 OBJECTIVE ............................................................................................................................................34 CLOSURE STRATEGY ...............................................................................................................................34 COMPLETION CRITERIA ..........................................................................................................................34 JETTY AND SHIP LOADER ....................................................................................................................34 OBJECTIVE ............................................................................................................................................35 CLOSURE STRATEGY ...............................................................................................................................35 COMPLETION CRITERIA ..........................................................................................................................35 POWER STATION .................................................................................................................................35 OBJECTIVE ............................................................................................................................................35 CLOSURE STRATEGY ...............................................................................................................................35 COMPLETION CRITERIA ..........................................................................................................................36 FUEL AND BULK STORAGE FACILITIES ..............................................................................................36 OBJECTIVE ............................................................................................................................................36 CLOSURE STRATEGY ...............................................................................................................................36 COMPLETION CRITERIA ..........................................................................................................................36 WORKSHOPS ........................................................................................................................................37 OBJECTIVE ............................................................................................................................................37 CLOSURE STRATEGY ...............................................................................................................................37 COMPLETION CRITERIA ..........................................................................................................................37 EXPLOSIVE STORAGE ..........................................................................................................................38 OBJECTIVE ............................................................................................................................................38 CLOSURE STRATEGY ...............................................................................................................................38 COMPLETION CRITERIA ..........................................................................................................................38 LANDFILL.............................................................................................................................................38 OBJECTIVE ............................................................................................................................................39 CLOSURE STRATEGY ...............................................................................................................................39 COMPLETION CRITERIA ..........................................................................................................................39 BIOREMEDIATION FACILITY ...............................................................................................................40 OBJECTIVES ...........................................................................................................................................40 CLOSURE STRATEGY ...............................................................................................................................40 COMPLETION CRITERIA ..........................................................................................................................40 ACCOMMODATION ..............................................................................................................................41 OBJECTIVES ...........................................................................................................................................41 CLOSURE STRATEGY ...............................................................................................................................41 COMPLETION CRITERIA ..........................................................................................................................41 ADMINISTRATION OFFICES .................................................................................................................42 OBJECTIVE ............................................................................................................................................42 CLOSURE STRATEGY ...............................................................................................................................42 COMPLETION CRITERIA ..........................................................................................................................42 PUBLIC ACCESS AND SAFETY ASPECTS 43 OBJECTIVES .........................................................................................................................................43 STRATEGY............................................................................................................................................43 RECORDS MANAGEMENT AND REPORTING SCHEDULES 44 OBJECTIVE...........................................................................................................................................44 STRATEGY............................................................................................................................................44 MONITORING 45 OBJECTIVES .........................................................................................................................................45 STRATEGY............................................................................................................................................45 SUMMARY OF MANAGEMENT ACTIONS REFERENCES 47 55 Page iii ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan FIGURES 1.1A 1.1B 1.2 1.3 9.1 PROPOSAL STUDY REGION .................................................................................................................11 PROJECT LOCATION............................................................................................................................11 BHP MINING OPERATIONS AT ARBITRATION COVE PRIOR TO 1993 (TOP FOUR PHOTOS) AND A VIEW OF ARBITRATION COVE AT PRESENT (JULY 2004) ...................................................................12 PROPOSED OPERATIONS ON KOOLAN ISLAND ....................................................................................13 LAYOUT ON KOOLAN ISLAND .............................................................................................................29 TABLES 1.1 14.1 SUMMARY OF KEY CHARACTERISTICS ASSOCIATED WITH THE PROPOSAL.....................................10 SUMMARY OF MANAGEMENT ACTIONS..............................................................................................47 Page iv ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan SUMMARY Site closure, either at the end of the mine life or running concurrently with mining activities is a critical component of mine management and is important in regard to public perception of mining activities. In accordance with the Mine Closure Policy (Minerals Council of Australia, 2000) the primary objective for mine closure is “to leave the site in a condition which is safe, stable and limits further environmental impacts so that mining tenements can be relinquished for alternative land use.” Aztec Resources Ltd (Aztec) are proposing to re-establish an iron ore mine on Koolan Island. BHP mined iron ore on Koolan Island between 1965 and 1993. On May 30 2003, the Minister for State Development granted Aztec authorisation to explore for iron ore on Koolan Island. Aztec sought and obtained environmental approval under a Notice of Intent (NOI) to commence exploration activities on the island in February 2004. Feasibility studies to investigate the viability of a mining and processing operation have commenced. These include environmental baseline surveys of the island, the results of which will be used to develop environmental management plans for the project. Aztec aims to complete feasibility studies and commence construction in early 2006. It is envisaged that production will begin by the early 2007, at a rate of 2-4 million tonnes per annum with a strip ratio of 6:1, and life in excess of nine years. A conceptual closure plan is to be submitted as part of the documentation for environmental approval. By developing a closure plan as part of the planning stages of the project Aztec can demonstrate that the site can be closed in a manner acceptable to regulators and post-mining land users. Planning for mine closure seeks to address the social, environmental, financial and safety aspects of mine closure. The aim is to prevent or minimise long-term environmental impacts and to create a self-sustaining natural ecosystem or alternate land use based on an agreed set of objectives (ANZMEC, 2000). In undertaking mine closure activities at Koolan Island, Aztec will fulfil the following objectives: • Protect public safety; • Minimise environmental and socio-economic impacts; • Meet legislative requirements; • Enable all stakeholders to have their interests considered during the mine closure process; • Re-establish self-sustaining ecosystems compatible with post-mining land use requirements; • Establish stable landforms that are sympathetic with the regional landforms and geotechnically stable; • Develop completion criteria to enable relinquishment to occur; • Undertake monitoring until agreed completion criteria are achieved; • Fulfil commitments in the Closure Plan; and • Release the operator from further liability. Page 5 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 1.0 INTRODUCTION Koolan Island is one of the many islands comprising the Buccaneer Archipelago off the Kimberley Coast. It is located 130 km north east of Derby at the northern end of the Yampi Peninsula. It is separated from the mainland by a 1 km wide channel. The waters surrounding Koolan Island are a proposed marine conservation reserve under the CALM Act (CALM, 1994). Koolan Island is one of three islands hosting the Yampi Sound iron ore deposits (Figure 1.1a & 1.1b). Aztec Resources Ltd (Aztec) are proposing to re-establish an iron ore mine on Koolan Island. BHP mined iron ore on Koolan Island between 1965 and 1993. During this period approximately 68 million tonnes of high-grade haematite ore was extracted from five pits, crushed and shipped from a wharf facility. Decommissioning of the mine in 1993 included the removal (some in situ burial) of infrastructure associated with BHP operations, rehabilitation of cleared areas by moon scaping, and the construction of a channel to allow seawater flooding of the Main pit. On May 30 2003, the Minister for State Development granted Aztec the authorisation to explore for iron ore on Koolan Island under exploration licence 04/1266. Aztec sought and obtained environmental approval under a Notice of Intent (NOI) to commence exploration activities on the island in February 2004. Subsequent to the initial NOI approval, two amendments have been submitted and approved to increase the scope of the exploration activities. Aztec aims to complete feasibility studies by mid 2005 and commence construction in early 2006. It is envisaged that production will commence by the early 2007, at a mining rate of 2-4 million tonnes of ore per annum with a strip ratio of 6:1, and life of more than nine years. This Conceptual Closure Plan is to be submitted as part of the documentation for environmental approval. As mining is a transient land use it is important that closure and rehabilitation strategies are incorporated into all aspects of the mine development from initial mine planning and through the life of the mine. By developing a closure plan as part of the planning stages of the project Aztec can demonstrate that the site can be closed in a manner acceptable to regulators and post-mining land users. In this document the term closure is based in the ANZMEC/MCA (2000) definition and includes decommissioning and rehabilitation and culminates in tenement relinquishment. The aim of this closure plan is to provide a strategic planning framework for the closure of Aztec’s Iron Ore Project by: • Identifying those aspects relating to decommissioning and closure which may impact on the environment, health and safety and developing management strategies to be implemented as part of the project’s design and construction to minimise this impact; • Identifying closure costs to establish a financial provision; • Providing a basis for consultation with regulators and identified stakeholders regarding the post-mining land uses of the project area and the development of agreed completion criteria; Page 6 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Identifying those aspects relating to closure that will require determination and/or input by appropriate regulatory agencies relating to completion criteria and the relinquishment of Aztec’s mineral leases on Koolan Island; and • Providing details of the management strategies to be implemented by Aztec to the appropriate regulatory agencies as part of project approvals. Throughout the life of the project the closure plan will be reviewed to consider changes in site conditions, operations, technology and community expectations. 1.1 Previous Operations William Dampier, in 1688, was the first European to discover the Buccaneer Archipelago. Early pearling fleets frequently stopped at the islands of the Yampi Sound to pick up ballast from the beaches and coves. It was eventually discovered that the ballast was in fact ironstone and the earliest attempts to develop these reserves was in 1907 when the first leases were granted. Eventually, after changing hands several times, the leases became the property of BHP. Through the 1940s, mining companies moved in on the rich deposit, and by 1963, BHP had established substantial mining operations on both Cockatoo and Koolan Islands. From 1965 to 1993, BHP extracted approximately 68 million tonnes of high-grade iron ore from five pits on Koolan Island - Main, Mullet, Eastern, Barramundi and Acacia. During mine operations BHP maintained infrastructure consisting of: • Haul roads and access roads; • Airstrip; • Accommodation village; • Workshops and bulk storage facilities; • Mobile plant; • Power Station; • Primary crushing and screening plant; • Shiploading and wharf facilities; • Bulk fuel storage facilities; • Administration offices; and • A series of water bores. A layout of the mine infrastructure is illustrated in Figure 1.2. As part of mining operations BHP reclaimed the area east of Arbitration Cove (Lower Mangrove Inlet) with waste rock. Waste rock dumps were also placed around each of the pits. BHP operated three domestic tips and four industrial tips on the island. There are no known records of the materials that were placed in the tips, management techniques, or the longevity of each waste disposal area. Page 7 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan BHP closed the mine in 1993, which consisted of decommissioning and disassembly of all fixed and mobile plant including the wharf facilities, some burial of infrastructure, rehabilitation of cleared areas by moon scaping, and the construction of a channel to allow seawater flooding of the Main pit. Apart from known domestic and industrial tips sites, the exact locations of other burial pits, and the materials buried as part of decommissioning is unknown. The footprint of BHP activities was contained within the southern part of the island with the northern shore line and the western and north-eastern ends of the island remained undisturbed (Figure 1.2). 1.2 Current Operations Aztec commenced exploration drilling in February 2004 targeting the five ore bodies already mined by BHP. To date, approval has been granted by DoIR and DoE for the clearing of 37.2 ha (76.5 % in previously disturbed areas) for access roads, drill pads, minor landfill and an exploration accommodation camp. 1.3 Planned Operations Aztec is planning to commence production by the early 2007, at a mining rate of 2-4 million tonnes of ore per annum with a strip ratio of 6:1. At this rate it is planned to have a mine life of more than nine years (Table 1.1). Although previously mined by BHP, there is no existing infrastructure on Koolan Island to support a mining operation. As such, the scope of the Koolan Island Iron Ore project includes: • Construction and establishment of complete mine infrastructure; • Mining of three main ore bodies; • Dewatering of the main pit; • Partial infill of Arbitration cove for expansion of the main pit; • Waste rock management; • Primary crushing and dry screening of ore; • Stockpiling and Shiploading; • Construction of shiploading facility; • Maintenance of mine operations; • Maintenance of an accommodation village; • Management of environmental impacts; • Rehabilitation and Decommissioning; and • Relinquishment of mining tenements. Page 8 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 1.4 Project Closure Plan Scope This plan only covers Aztec mining lease areas disturbed by Aztec’s exploration and mining operations, as shown in Figure 1.3. The Closure Plan excludes: • All areas outside Aztec’s current mining leases; • Areas within Aztec’s mining leases that have not been disturbed by Aztec’s operations; and • The airstrip, located to the north of the mine area, which is used by the public. Page 9 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Table 1.1 Summary of Key Characteristics associated with the Proposal Component Key Aspect Description Mining Location of Mine Koolan Island – 130 km NW of Derby in the Buccaneer Archipelago 3 main deposits: Main Pit, North Pit and East Pit Main Pit: 17.4 Mt resource Mullet Pit: 6.3 Mt resource Eastern Pit: 5.4 Mt resource Main Pit: Current 80m Final 165m below sea level Mullet Pit: Current 50m Final 80 below ground level Eastern Pit: Current 60m Final 115 m below ground level Generally > 100 m below ground level High grade hematite (61-68%) Commence construction early 2006 Commence production in early 2007 2 – 4 million tonne per year (Year 1 – 2 Mt, Year 2 - 2.5 Mt, Year 3 – 8 - 4 Mt and Year 9 - 0.6 Mt) 9 Years + Ore Deposits Depth of mine pits Depth of water table Ore Type Proposed Project Schedule Ore Mining Rate Project Life Span Approximate Year of Decommissioning Stockpile of ROM material Waste Dump Capacity and Area Strip Ratio (waste : ore) Amount of land disturbance Dewatering of Main Pit Construction of Sea Wall Dewatering Ore Processing Primary Crushing and Screening Ship loading Ship loading Infrastructure Project access Power Source Water Source Workshops Equipment Fuel Consumption Ore Handling Port Facility Accommodation General Work force Solid Waste Bulk Transport of material Page 10 2015 Capacity: 100,000 Tonne; Area: 10 ha 3 Capacity: 124 Mm ; Area: 280 ha Approximated at 6:1 540 ha (45% previously disturbed) 300 m wall across Arbitration Cove, 75 m wide at the base, 15 m high Initial Dewatering: Approximately 7 Mm3 of sea water at 300 l/s Maintenance: Ongoing rate of 50-150 l/s Turbid water will be placed in sedimentation pond prior to discharge into ocean 2 stage dry crushing and screening plant to produce fines and lump product. Product will be stockpiled near the ship loader for direct loading Inter-island: Aircraft Intra-island: Haul and access roads Power : Diesel fuelled 2 MW power station Generators: 5 x 0.5 kVa generators Fresh water will be extracted from three existing bores, 75 kL/day potable water Heavy and light equipment maintenance workshops Conventional heavy and light mobile equipment Approx 10.6 ML/year Ore will be transferred from the stockpiles to the ship loader via a conveyor system A ship loader and jetty will be re-established to enable ship loading Single persons village 200 persons, with fluctuations during peak periods; fly in, fly out Maximum of 300 tonnes per year Via Barge from Derby / Broome, or coastal shipping ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Figure 1.1a Figure 1.1b Proposal Study Region. Project Location (inset box – see Figure 1.1a). Page 11 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan BHP mining operations at Arbitration Cove prior to 1993. BHP ship loading wharf facilities at Arbitration Cove prior to 1993. Recent photograph of Arbitration Cove taken in July 2004. Figure 1.2 BHP Mining Operations at Arbitration Cove prior to 1993 (top four photos) and a view of Arbitration Cove at present (July 2004). Page 12 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Figure 1.3 Proposed operations on Koolan Island. Page 13 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 2.0 PROJECT CLOSURE OBJECTIVES Planning for mine closure seeks to address the social, environmental, financial and safety aspects of mine closure. The aim is to prevent or minimise long-term environmental impacts and to create a self-sustaining natural ecosystem or alternate land use based on an agreed set of objectives (ANZMEC/MCA, 2000). In undertaking mine closure activities at Koolan Island, Aztec will fulfil the following objectives: • Protect public safety; • Minimise environmental and socio-economic impacts; • Meet legislative requirements; • Enable all stakeholders to have their interests considered during the mine closure process; • Re-establish self-sustaining ecosystems compatible with post-mining land use requirements; • Establish stable landforms that are sympathetic with the regional landforms and geotechnically stable; • Develop completion criteria to enable relinquishment to occur; • Undertake monitoring until agreed completion criteria are achieved; • Fulfil commitments in the Closure Plan; and • Release the operator from further liability. Decommissioning and rehabilitation will be undertaken progressively, where practicable, throughout the life of the mine and will involve: • Determining appropriate post-mining land uses for disturbed areas; • Determining if any infrastructure such as the wharf and jetty can be utilised by another party; • Removing or burying any infrastructure not to be utilised by another party; • Removal and treatment of contamination; • Establishing final landforms and drainage paths; and • Rehabilitating areas that have been disturbed by Aztecs operations. Page 14 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 3.0 LEGAL OBLIGATIONS To ensure the closure of Aztec’s Iron Ore Project meets all legal requirements a review was undertaken to identify legislation and guidelines applicable to mine closure. As part of the review of the Closure Plan during the project life, legislation and other requirements will be reviewed to identify any new requirements. 3.1 Legislation West Australian legislation as such does not specifically deal with or refer to mine closure. However, Section 84 of the Mining Act 1978 does allow the Minister for Mines to impose mine closure conditions at his/her discretion on mines administered under this Act. The following legislation was deemed relevant to mine closure and have been taken into account when developing this Conceptual Closure Plan. • Aboriginal Heritage Act, 1972 • Conservation and Land Management Act, 1984 • Contaminated Sites Act, 2003 • Environment Protection and Biodiversity Act, 1999 • Environmental Protection Act, 1986 part IV & V • Heritage of Western Australia Act, 1990 • Mines Regulation Act, 1946 • Mines Safety and Inspection Act, 1994 • Mines Safety and Inspection Regulations, 1995 • Mining Act, 1978 • Rights in Water and Irrigation Act, 1914 • Soil and Land Conservation Act, 1945 • Waterways Conservation Act, 1976 • Western Australia Marine Act, 1981 • Wildlife Conservation Act, 1950 Page 15 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 3.2 Guidelines and Codes of Practise The Guidelines and Codes of Practice outlined below were used in the preparation of this document: • ANZMEC/MCA (2000), Strategic Framework for Mine Closure. Australian and New Zealand Minerals and Energy Council and Minerals Council of Australia. Canberra, ACT. • Australian Mining Industry Council (1989), Mine Rehabilitation Handbook. • Chamber of Minerals and Energy of Western Australia Inc (November 1999) Mine Closure Guidelines for Minerals Operation in Western Australia. • Department of Environment (1996), Code of Practice for Country Landfills. • Department of Minerals and Energy (1997) Safety Bund Walls around abandoned Open Pit Mines. Department of Mines & Energy, WA. • Department of Minerals and Energy (1998) Geotechnical Considerations in Open Pit Mines Draft. Department of Mines & Energy, WA. • Department of Minerals and Energy (1996), Guidelines for Mining in Arid Environments. Department of Mines & Energy, WA. • Minerals Council of Australia (February 2000) Code for Environmental Management. Page 16 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 4.0 COMPLETION CRITERIA Completion criteria are an agreed set of environmental indicators, which upon being met, will demonstrate successful rehabilitation of a site and hence are inextricably linked to the monitoring programme (ANZMEC/MCA, 2000). Rehabilitation can be considered successful when the site can be managed for its designated land use without any greater management inputs than other land in the area being used for a similar purpose (EPA, 1995). 4.1 • 4.2 Objective To establish a set of indicators which will demonstrate the successful completion of the closure process and facilitate the release of the mining operator from further environmental obligations. Proposed Completion Criteria The project proposed completion criteria have been developed taking into consideration the following factors: • Public health and safety; • Regulatory requirements; • Aztec’s Environmental Policy; • Geotechnical stability of final landforms; • Sustainability of revegetated areas; • Expectations of stakeholders; and • Post-closure land use objectives. The proposed completion criteria, detailed more fully in Section 9 (Proposed Closure Strategies), are summarised below: • Post-closure land use objectives have been established and agreed by the appropriate regulatory agencies; • Mining-related infrastructure not required by a post-closure land user has been removed or buried; • Contaminated areas have been remediated to levels that are acceptable to the DoE and other stakeholders; • Post mining landforms are geotechnically stable and respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; • Final landforms are compatible with the adjacent landscape; Page 17 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Runoff from surface waters within and running off the site have similar quality to runoff from undisturbed sites; • Self-perpetuating and resilient locally native vegetative cover has been established on disturbed areas; • The local marine environment displays similar floral, faunal and benthic habitat diversity, health and water quality as other nearby marine ecosystems; • Identified aboriginal heritage sites have not been disturbed; • No new outbreaks of weeds or pest have occurred due to Aztec’s operations; • No adverse significant impacts to flora or fauna have occurred due to Aztec’s operations; • Relevant legislative requirements and ministerial commitments have been met; • Agreed monitoring programs are implemented; • As part of relinquishment all required records and reports have been submitted to the appropriate regulatory agencies; and • There are no unsafe areas where the general public could gain inadvertent access. Completion criteria should ultimately stem from consultation between the proponent and stakeholders. This communication should be ongoing and open, providing for a mutually agreeable set of criteria against which the success of the closure and rehabilitation program can be measured. Aztec will consult with all stakeholders and interested parties throughout the life of the project to develop agreed completion criteria. Page 18 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 5.0 CONTAMINATED SITES 5.1 Objective • Develop a process with the DoE for the management of any areas identified as contaminated by BHP’s previous activities; and • Undertake a contaminated site assessment as per the DoE guidelines prior to Aztec commencing mining operations on Koolan Island, and again as part of the decommissioning and closure process. 5.2 Contaminated Sites Investigation and Management Under the Contaminated Sites Act 2003 a site is considered to be contaminated if it has a substance present at above background concentrations that presents, or has the potential to present, a risk of harm to human health, the environment or any environmental value. Aztec was required by the DoE to identify potential environmental contamination issues resulting from historic mining of Koolan Island, which through the proposed mining activities could impact upon future mining and the environment. In response, Aztec commissioned URS Australia Pty Ltd (URS) to conduct a Phase 1 and Phase 2 environmental site assessment in November and December 2004 (URS, 2005). The Phase 2 investigations were a baseline study to enable Aztec to understand the potential environmental liabilities associated with future mining on Koolan Island. The main potential contamination issues from former mining activities at Koolan Island are: • Domestic and industrial landfill disposals; • Workshop activities; • Fuel and waste oil distribution and storage; • Buried machinery; and • Former township support systems and infrastructure. The investigations indicated that the primary potential sources of contamination present on Koolan Island are petroleum hydrocarbons and asbestos. The proposed mining activities may be undertaken in areas where potential contamination has been identified, such as petroleum hydrocarbons in the Main Pit. Extensions to the Mullet Pit are not expected to result in an environmental or human health based issue. Where Aztec disturbs areas of identified contamination they will remediate these areas as per the DoE guidelines. The potential exists for contamination to occur during the life of the project due to the handling and storage of hydrocarbons and chemicals. This potential will be minimised by ensuring hazardous materials, such as hydrocarbons and chemicals, are stored in contained areas and spills are cleaned up immediately. Page 19 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan A Contaminated Sites Assessment process will be undertaken as per the DoE Contaminated Sites Guidelines, before decommissioning of infrastructure occurs and will incorporate the following: • Investigation: determine the nature and extent of any soil and/or groundwater contamination; • Assessment: evaluate the risks of any identified contamination to human health or the environment; • Action Plan: develop and document an operations plan and implementation schedule which addresses all necessary activities including disposal of contaminated material, monitoring and criteria for completion; • Consultation: discuss all aspects of the program and obtain agreement from DoE (as the responsible regulatory agency), together with other agencies as appropriate; • Implementation: undertake all aspects of the program in compliance with the documented plan and any relevant standards such as AS 4482.1 – 1997 related to the sampling and investigation of contaminated soils; • Validation: undertake monitoring and/or testing, using appropriate, recognised methods, to demonstrate reduction of contamination to an acceptable levels using an independent consultant; and • Closure: Obtain regulatory signoff that the remediation process has been effective and the site is no longer contaminated. Page 20 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 6.0 DECOMMISSIONING 6.1 Objective • Remove or dispose of infrastructure, not to be utilised by another party, associated with Aztec’s iron ore project; and • Dispose all waste material appropriately. 6.2 Removal of Infrastructure During the decommissioning phase of the project all infrastructure that cannot be used by another party will be removed, including concrete footings, and the disturbed areas rehabilitated. This could include the removal of: • Crushing and screening plant, and processing buildings; • Fuel and Bulk Storage Facilities and associated pipe work; • Workshops; • Ship loader (including conveyors, conveyor structures and on-shore and offshore footings) and jetty (including deck, substructures, piles and dolphins); • Dewatering equipment; • Power Station; • Explosives magazine; • Offices and accommodation village; and • Support infrastructure such as water pipelines, redundant structures at the airstrip and recreational facilities. The dismantling of infrastructure will generate scrap and waste materials that will be disposed in the following manner: • Steel will be stored until the mine is decommissioned and shipped off the island for recycling; • Inert material that is not reusable (such as concrete, building rubble) will be buried in the landfill site; • Hazardous materials, such as asbestos, will be disposed of in accordance with appropriate governing regulations; and Page 21 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Left over fuel, oils and chemicals will be removed from site and returned to the supplier. Waste oils, fuels and chemicals will be removed from site and disposed of at an appropriate waste facility, recycled or reused where possible. Page 22 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 7.0 DEVELOPMENT OF FINAL LANDFORMS 7.1 Objective • Post mining landforms are geotechnically stable and respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; • Landforms are compatible with the adjacent landscape; and • Runoff from surface waters within and running off the site have similar quality to runoff from undisturbed sites. 7.2 Shaping of Landforms A major cause of serious erosion on newly created landforms is the lack of adequate drainage control. It is essential to design and construct drainage control measures that will handle the expected rainfall events (DME, 2001). The DME recommends that sloped landforms be covered with topsoil and then deep ripped to a minimum of 1 m on contour. It is essential that rip lines are surveyed to ensure that they are horizontal for the entire length. Ripping on contour minimises the amount of water flow along the line encouraging infiltration of water and minimise erosion. To ensure final landforms are geotechnically stable, not prone to ersoion and able to be successfully rehabiliated the DoIR recommends slopes of no greater than 20 ° with benches every 7–10 m of vertical height. A slope of 20 ° is the maximum that machinery can safely work on. However, soil characteristics, rainfall, drainage and topography are all contributing factors that have to be taken into account in determining the optimal slope angle and slope length. Reshaping of landforms aims to produce slopes with angles, lengths and shapes compatible with the surrounding landscape, suitable for the proposed land use and not prone to an unacceptable rate of erosion. On finalisation of the project, the following landforms will require earth works reshaping: • Waste Dumps; • Borrow Pits; • Haul roads; and • Seawall. Due to the mining schedule, Aztec will only backfill pits where it is economic to do so. Page 23 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Reshaping of landforms will be undertaken to: • Prepare landforms and disturbed areas to acceptable standards prior to the implementation of revegetation procedures; • Ensure post mining landforms are geotechnically stable and respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; • Minimise long-term visual impact by creating landforms which are compatible with the adjacent landscape; • Reinstate, where practicable, natural drainage patterns; • Ensure runoff from surface waters within and running off the site have similar quality to runoff from undisturbed sites; and • Batter free-standing slopes to an angle of 20 º or less, or to slopes consistent with the surrounding landforms. Page 24 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 8.0 REHABILITATION STRATEGIES 8.1 Objectives • Where feasible areas disturbed by Aztec’s operation will be rehabilitated; • Species native to Koolan Island will only be used in the rehabilitation; and • Rehabilitation will be undertaken as soon as practicable to facilitate fauna habitat restoration. 8.2 Rehabilitation Climate is an important consideration in relation to revegetation procedures. Plant growth in the Kimberley is closely tied to seasonal fluctuations; the majority of growth occurs in the wet season as warm temperatures combined with moist soil conditions encourage proliferation of plants. In certain instances plants will naturally recolonise areas of exposed soils, however, these areas do not necessarily resemble natural ecosystems, comprising principally grasses and herbs. In order to successfully bind the soil and facilitate development of permanent vegetation, planting of shrubs and trees is required in addition to natural revegetation. The most suitable time for seeding or planting is during the ‘build-up’ to the wet season, or following the first substantial rains, as this allows for a period of several months during which plants can become established prior to the dry season with its concomitant loss of soil moisture. This is particularly the case for perennial species. The use of topsoil as a growing medium is important for successful rehabilitation. During the life of the mine any area to be disturbed will have the topsoil stripped and stockpiled, and vegetation debris, logs and leaf litter will be retained for reuse during rehabilitation. Rehabilitation will consist of: • Where available, topsoil will be utilised to provide a foundation into which native vegetation will be planted and/or seeded. Topsoil will be applied at a minimum of 100 mm to: • Accommodate root systems; • Provide water holding capacity to attenuate moisture from rainfall and to sustain vegetation through dry periods; • Allow for long term erosive losses; and • Prevent desiccation. • Vegetation debris, logs and leaf litter from the clearing of areas will be spread over rehabilitated areas to provide fauna habitat; • Ripping on contour is required to relieve compaction and improve water infiltration. Deep ripping to a depth of 1 m will be undertaken where the soil or waste material is of low permeability. In areas where the soil or waste material is of high permeability Page 25 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan cultivation on contour will be undertaken. On steep slopes this may require terracing or benching. All ripping, terracing or benching will be surveyed to ensure that they are on contour; • Direct seeding and/or planting will be undertaken to encourage vegetation growth to stablilise surfaces and aid the integration of landforms into the surrounding landscape. Seeding and/or planting will be undertaken prior to the wet season as soon as possible after earthworks using seed and plants native to Koolan Island; • Where necessary, fertilizer will be applied to offset the loss of nutrients and soil microbiota associated with loss of topsoil; and • Rehabilitation and closure procedures will include measures to address specific habitat types of listed fauna. 8.3 Monitoring of Rehabilitation • Rehabilitation monitoring will be carried out until revegetation meets the designated completion criteria and is signed off by the DoIR. In response to monitoring results, infill planting and weed control will be implemented as necessary; • A visual inspection of rehabilitated areas will be carried out following rain to ensure that any potential erosion issues are identified early and can be repaired before they become severe; • Photographic monitoring will be undertaken. This will consist of establishing fixed photographic points (adequately marked with a long lasting item such as metal star picket) and taking photographs from each of these points, usually in four directions (north, south, east and west); • Quantitative assessment of the progress of revegetation will be undertaken. Replicate monitoring quadrats (20 m x 20 m) will be established and total plant species richness and plant cover index will be recorded; and • Reporting procedures will be established to ensure that results of all trials and actions are properly recorded, referenced, and available for other personnel and for long-term reference. Page 26 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.0 PROPOSED CLOSURE STRATEGIES Before decommissioning occurs, a risk assessment will be undertaken to identify risk to environment, health and safety. A document decommissioning strategy will be developed to ensure that risks are managed to an acceptable level. 9.1 Mine Pits Aztec intends to reopen and expand on the previously mined ore bodies to access remnant ore reserves. All five previous mined pits will be reopened and amalgamated into three active pits. They are the Main Pit (Main Pit), Mullet Pit (Mullet and Acacia Pits) and Eastern Pit (Eastern and Barramundi Pits) (Figure 9.1). The Main Pit will be expanded to the south by approximately 17 ha and extended on the east and west ends by 22 ha. The Mullet Pit will amalgamate both Mullet and Acacia Pits, and will have an estimated surface area of 55 ha. The Eastern Pit will amalgamate Eastern and Barramundi Pits, with extensions of the pits towards Ellis Fjord. The final formation will have a surface area of approximately 63 ha. Where practicable and economically feasible the mining regime will be designed to include backfilling of mined-out pits. The decision to flood the Main Pit on closure will be made at a future date after consultation with relevant agencies including CALM and DoE approximately 2 years before closure. Prior to implementation of this plan the matter will be reviewed with all relevant stakeholders in order to identify the most appropriate action. 9.1.1 Closure Objective • Ensure pit void and walls are structurally stable; and • Ensure public safety by restricting access to remaining pits. 9.1.2 Closure Strategy Stability of Pit Walls Geotechnical investigations will be undertaken to determine the optimum final landform of the mine pit walls to ensure stability of the landform. Safety Bunds In order to minimise inadvertent public access to abandoned open pits: • An abandonment bund wall will be constructed around the perimeter of open pit voids greater than 5 m in depth; • The bund wall will be constructed outside the area designated as being susceptible to wall collapse; and Page 27 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • The location and design of the abandonment bund will be in accordance with procedures detailed in “Safety Bund Walls around Abandoned Open Pit Mines” (DME, 1997). Rehabilitation There is evidence of natural revegetation on some areas of the pit walls, including growth of trees and shrubs, which indicates that plant regrowth is possible. On completion of mining, final rehabilitation of the pit walls around the active mining area will be undertaken. • Where required, additional earthworks will be undertaken on those areas of the pit walls that are safely accessible to improve long term structural stability and facilitate revegetation; and • Hand seeding will be undertaken where access is available to improve long term stability, particularly in the erosion prone haematite-poor grey band material. 9.1.3 Completion Criteria • Pit voids and walls are assessed by a suitably qualified engineer and determined to be structurally stable; and • Safety bunds comply with the procedures detailed in “Safety Bund Walls around Abandoned Open Pit Mines” (DME, 1997). Page 28 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Figure 9.1 Layout of Koolan Island. Page 29 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.2 Seawall To facilitate the expansion and reactivation of the Main Pit, and to maintain dry working conditions a seawall extending approximately 300 m across the mouth of Arbitration Cove will need to be constructed. It will be keyed through existing waste dumps on the abutments and into sound bedrock, where it intersects the margin of the cove. The seawall will reach an approximate height of 15 m to minimise overtopping and damage to the sea wall during storm events. The width of the sea wall at foundation level will be approximately 75 m, with an upstream slope of 1(v):2.5(h) and downstream slope of 1(v):2(h). At its crest the width of the sea wall will be 10 m. 9.2.1 • 9.2.2 • 9.2.3 • 9.3 Closure Objective At the time of writing this Closure Plan it is intended that the seawall will be breached to reinstate the natural tidal movement of the area. The topic will be reviewed prior to implementation of the plan. Closure Strategy The breaching of the seawall will be designed to minimise the impact to coastal habitats and allow for re-establishment of marine biota on disturbed areas. Completion Criteria Marine biota have re-established in the area of the seawall to a similar density and diversity as that existing prior to construction of the seawall. Waste Rock Management Overburden materials comprising low grade ore and un-mineralised rock will be generated as part of the mining process. Due to the geology of the area, ore and waste rock materials consist predominantly of sandstone and conglomerates, and do not pose physiochemical impacts to the environment, hence there are no acid rock drainage issues. Waste rock will be disposed in waste dumps located adjacent to the existing pits or within extensions of previously disturbed areas (Figure 9.1). Four main areas have been delineated for waste rock placement: • Main Dump (west): The existing waste dumps to the northwest of the Main Pit run into a series of gullies that drain to the north of the island. It has a capacity of 41.3 Mm3; • Mullet Dump: The area between the Main Pit and North Pit has been previously disturbed to accommodate waste dumps and low grade stockpiles. The road from the Main Pit to the North Satellite Pit runs along a ridge between two gullies that are enclosed by either existing pits or waste dumps. It has a capacity of 2.9 Mm3 of waste rock; Page 30 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Eastern Dump: The largest of the dumps is East Dump B to the north of the East Pit. It has a capacity of 40.9 Mm3 and is the extension of two dumps created during previous mining activities and the backfilling of two gullies to 150 m ASL; and • Main Dump (east): The dump to the south of the East Pit includes access roads to the crushing and stockpiling areas. These new access roads are required as the East Pit and pushback for the Main Pit are likely to remove existing access. This dump has a capacity of 15.7 Mm3, fills a number of small gullies to 160 m ASL and partially buries an existing waste dump. All waste dumps will be designed to a flat crest and will be no higher than the general terrain. The area on top of the dump will be designed to accommodate additional waste material to create long term landform slopes. Sedimentation ponds will be established downstream of waste dumps to collect run off from the slopes during waste dump construction, and allow sediment fall out / evaporation. Low grade material will be stored separately to waste rock to enable possible reclaiming for processing at a later stage of the mine life. These materials will be preferentially stored nearest to the ROM crusher for ease of access. The area of disturbance caused by the conceptual waste dumps is 281 ha of which a large proportion was previously disturbed and rehabilitated (31.6 %). Specific waste dump locations for each pit will be determined as part of feasibility studies. Waste dumps are often the most visible landforms remaining following open pit mining. Control of erosion on waste dump slopes is also an important consideration. During the engineering phase of the proposal, investigations will be conducted into the volume of saline waste rock material that will be produced, the appropriate placement of the waste rock and the type of contamination and methods required to prevent contamination of groundwater 9.3.1 Closure Objective • To ensure that the profile of the waste rock dump final structure is safe, stable, blends into the surrounding landscape and not prone to erosion; • The waste rock and slope gradients will be capable of withstanding the intense rainfall events of the wet season; and • To ensure sufficient cover of vegetation will be established to minimise erosion resulting from the impact of severe rains on dry soils. 9.3.2 Closure Strategy Waste dumps will require extensive earthworks and subsequent seeding and revegetation to ensure they are stable and blend into the surrounding landscape. • Waste dumps will be designed to ensure that the profile of the final structure is safe, stable and not prone to erosion; • Dumps will be designed so after rehabilitation they blend into the surrounding landscape; Page 31 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Adequate drainage control will be implemented to ensure that erosion does not occur; • Outslopes will be designed at less than 20o as required for geotechnical stability, or will be consistent with surrounding landforms; • A major cause of erosion on newly created landforms is the lack of adequate drainage control. Drainage control measures will be designed and constructed to handle expected rainfall of the area; • Dump surface will be covered with clean fill and if available soil to a minimum depth of 100 mm; • Both the tops and the side of the waste dump will be contour ripped to encourage infiltration of rainfall; and • 9.3.3 Waste dumps will be seeded or planted with local species. Completion Criteria • Waste dump slopes are below 20 o; • Waste dumps are assessed by a suitably qualified engineer and determined to be structurally stable; • Rehabilitated waste dumps respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; and • Vegetation cover is self-sustaining. 9.4 Borrow Pits 9.4.1 Objectives • To ensure the profile of borrow pits final structure is safe, stable, blends into the surrounding landscape and not prone to erosion; and • A sufficient cover of vegetation is established to minimise erosion resulting from the impact of severe rains on dry soils. 9.4.2 Closure Strategy Borrow pits will be progressively rehabilitated as soon as possible following pit closure. The sides of the pits will be battered to a maximum slope of 20 o. If required, diversion drains and upslope windrows, will be utilised to divert surface water flow from entering the pit causing ponding and erosion. Pits will be rehabilitated as per the strategy detailed in Section 8. 9.4.3 • Completion Criteria Borrow pit slopes are below 20 o; Page 32 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Borrow pits are assessed by a suitably qualified engineer and determined to be structurally stable; • Once rehabilitated borrow pits respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; and • Vegetation cover is self-sustaining. 9.5 Dewatering The Main Pit will require dewatering in two stages; initial bulk displacement of sea water, and ongoing dewatering to maintain dry work conditions in the pit floor. Ongoing dewatering will largely result from dewatering bores combined with some pumping from in pit sumps. Infrastructure required for initial dewatering of sea-water will consist of: • Offshore dewatering discharge poly pipe(s) installed below the annual low water mark, anchored and floated to facilitate discharge of water; • Poly pipe rising mains installed up the side of the pit wall; • Floating pontoons with suspended electric submersible pumps; • Centrally located and secondarily contained diesel powered generators to provide power to the pumps; • Booster stations will be available to provide extra power as pressure head increases with decrease in pit water level; and • A settling dam established adjacent to the Main Pit. When the water level of the Main Pit is such that turbidity is being generated from pit floor disturbance, the water will be directed to the settling dam prior to discharge into the ocean. It is not anticipated that dewatering of the other pits will be required. 9.5.1 Objectives • All infrastructure associated with dewatering is removed; and • Impact on the marine environment from dewatering operations is minimised. 9.5.2 Closure Strategy All infrastructure associated with dewatering will be removed and disposed of as per Section 4. 9.5.3 Completion Criteria • All infrastructure removed and disposed of appropriately; and • Monitoring of marine environment within Arbitration Cove shows no significant impacts when compared to baseline study data. Page 33 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.6 Haul Roads, ROM Pad, Stockpile and Ore Processing Ore and waste rock will be transported by haul trucks to designated areas via haul roads. Ore will be deposited onto ROM pads and fed into a crusher hopper by front end loaders. A flat area, previously a waste dump at the base of the proposed access road is a potential area for the ROM pad and stockpile. Initial designs suggest sufficient room exists for 500,000 tonne ROM stockpiles. A two stage dry crushing and screening plant and stacker will be installed east of the Main Pit to produce 2-3 Mtpa of a predominantly fines product. Pre and post processing ore stockpiles will be established on existing flat ground. It is anticipated that shipping requirements will dictate the size of product stockpiles with a nominal 250 kt stockpile for the fines product and 100 kt stockpile for a potential lump product being available at the commencement of ship-loading. Product will be stockpiled in 8 – 10 m high stockpiles. At this height, the area available in the stockpile yard has an approximate holding capacity of 100,000 m3 of product. The total area available to be disturbed to accommodate the pre and post crusher stockpiles along with the ore handling plant and associated workshops, offices and infrastructure is 25 ha. 9.6.1 Objective • All infrastructure associated with haulage and ROM ore storage is removed; and • Disturbed areas are reshaped to blend into the landscape, and rehabilitated. 9.6.2 Closure Strategy All infrastructure associated with ore processing will be removed as per Section 6. Haul roads, ROM pad and stockpile and other disturbed area will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.6.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Once rehabilitated disturbed areas associated with ore processing respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; and • Vegetation cover is self-sustaining. 9.7 Jetty and Ship Loader Steel fabricated jetty supported by steel piles driven into or anchored on the sea floor. A travelling ship loader will run on rails along the jetty. Page 34 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.7.1 Objective • If not required by another party, all infrastructure associated with ship loading will be removed; • Disturbed areas are reshaped to blend into the landscape and rehabilitated; and • Disturbed marine areas recolonised by marine flora and fauna. 9.7.2 Closure Strategy All infrastructure associated with the jetty and ship loader, including any structures in the ocean will be removed as per Section 6, if not required by another party. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. Marine areas will be left to naturally recolonise. 9.7.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Rehabilitated areas associated with ship loader respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; • Vegetation cover is self-sustaining; and • Marine biota have re-established in the area of the ship loader to a similar density and diversity as that existed prior to construction. 9.8 Power Station A 2 MW diesel fuelled power station will be established near the crushing plant to supply electricity to the ore processing plant and shiploading facility. The power station will consist of four to six, 0.5 kVA gensets. 9.8.1 Objective • All infrastructure associated with the power station is removed; • The area is investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and rehabilitated. 9.8.2 Closure Strategy All infrastructure associated with the power station will be removed as per Section 6. Once the infrastructure is removed a contaminated site assessment will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Page 35 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.8.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Area not classed as a ‘contaminated site’ as per the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. 9.9 Fuel and Bulk Storage Facilities Distillate will be required for heavy and light vehicle use and for power generation. Fuel storage facilities will be located at the Mobile Plant Workshop and Ore Processing Plant. A bulk storage facility adjacent to the workshop area will be established for the contained storage of hydrocarbons and chemical materials. To prevent contamination of ground and water from the storage of fuel, hydrocarbons and chemical the Fuel and Bulk Storage Facilities will be fully contained and designed and maintained according to statutory standards. 9.9.1 Objective • All infrastructure associated with fuel and bulk storage facilities is removed; • Storage areas are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and rehabilitated. 9.9.2 Closure Strategy All infrastructure associated with fuel and bulk storage facilities will be removed as per Section 6. Once the infrastructure is removed a contaminated site assessment will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.9.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Storage areas not classed as a ‘contaminated site’ as per the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. Page 36 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.10 Workshops Workshop facilities will be established for the repair and maintenance of mine equipment. These facilities will include: • Haul truck and mining equipment maintenance bays; • Light vehicle workshop; • Lubrication area; • Welding and boiler making area; • Wash-down bays; • Tyre store; and • Offices. To prevent the contamination of ground and water from the use and storage of oils and chemicals workshop catchment areas will be contained and kept separate from storm water interaction. Waste water from the workshop area will be treated by an oily waste water separator unit prior to reuse for dust suppression, or licensed and monitored discharged into the environment. 9.10.1 Objective • All infrastructure associated with the workshops is removed; • Workshop areas and the wash-down bay are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. 9.10.2 Closure Strategy All infrastructure associated with workshops will be removed as per Section 6. Once the infrastructure is removed a contaminated site assessment will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.10.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Workshop areas and the wash-down bay are not classed as a ‘contaminated site’ as per the DoE the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. Page 37 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.11 Explosive Storage Explosive magazines will be required for the storage of both wet and dry condition explosives, component ingredients, and the initiation systems. Magazines will be licensed and contained to ensure there is no contamination of ground or water due to the storage of explosives. 9.11.1 Objective • All infrastructure associated with explosives storage is removed; • Explosive storage areas are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. 9.11.2 Closure Strategy All infrastructure associated with explosive storage will be removed as per Section 6. Once the infrastructure is removed a contaminated site assessment will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.11.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Explosive storage areas are not classed as a ‘contaminated site’ as per the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. 9.12 Landfill A minor rural landfill will be established to manage the disposal of putrescible and inert wastes. The landfill will be located in an area that poses minimal impact on surface and ground water, and to reduce the potential for pollution. The location will be determined during feasibility studies. While in operation the following will be undertaken to ensure the landfill site impacts are managed: • Only inert, general and putrescible waste will be disposed of in the landfill. hazardous material will be disposed of according to government guidelines; • The landfill will be sited and designed to prevent surface water from draining into the landfill. Diversion drainage structures will be used to divert stormwater flows away from the landfill area; Page 38 All ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Surface water and groundwater monitoring will be undertaken if deemed to be necessary to determine any impacts to water quality. If changes in water quality are identified the DoE will be notified and an action plan developed; • Adequate separation distance will be maintained between the base of the landfill and the water table. The DoE Code of Practice for Country Landfills (DoE, 1996) recommends a minimum separation distance from the base of the landfill to the highest seasonal groundwater level is 2 m for clay soils and 3 m for sandy soils; and • To facilitate consolidation of the landfill to minimise subsidence, waste material will be compacted in layers not exceeding 500 mm thickness. Each time waste is disposed into the landfill it will be covered by a depth of soil no less than 230 mm and compacted. Not only will this facilitate consolidation of the waste material but ensure other impacts such as fire, pests and odour are minimised. 9.12.1 Objective • All infrastructure associated with the landfill is removed; • The site is compacted and stable; • Landfill site is investigated to determine if any contamination of soil and groundwater present and if so remediation strategies are developed and agreed with the DoE; • Landfill site is capped by a cover of low permeable material to a depth of 300 mm; and • Landfill area is reshaped to blend into the landscape and manage drainage and rehabilitated. 9.12.2 Closure Strategy The main issues associated with the closure of the landfill site area are; • Ground or surface water contamination due to the release of leachate from the site; and • Stability of the landfill area as subsidence occurs. All infrastructure associated with landfill site will be removed as per Section 6. Once the infrastructure is removed a contaminated site assessment will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. DoE Karratha has advised that there is not a requirement to undertake testing for landfill gases. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.12.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Landfill area is not classed as a ‘contaminated site’ as per the DoE the Contaminated Sites Act 2003; Page 39 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Landfill area is assessed by a suitably qualified engineer and determined to be structurally stable; • Landfill site is capped by a cover of low permeable material to a depth of 300 mm; and • Vegetation cover is self-sustaining. 9.13 Bioremediation Facility If required a small licensed bioremediation facility will be established for the management of contaminated soil and biodegradable absorbent materials (peat and paper). The facility will be constructed and managed as per the DoE guideline Bioremediation of Hydrocarbon Contaminated Soils in Western Australia (2004). The facility will be located in an area that poses minimal impact on surface and ground water, and to reduce the potential for pollution. It will be constructed with a base layer of impermeable clay materials, and maintained in accordance with license conditions. 9.13.1 Objectives • All infrastructure associated with the Bioremediation Facility is removed; • Bioremediation Facility is investigated to determine if any contamination of soil, and if required groundwater, is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and rehabilitated. 9.13.2 Closure Strategy Closure of the bioremediation landfarm will not be undertaken until all areas where contamination may occur have been investigated and remediated to agreed levels with the DoE. On completion of bioremediation, the remediated soil will be removed and utilised in rehabilitation of disturbed areas. Sampling of the natural ground surface beneath the bioremediation facility will be undertaken to determine if any contamination is present. Groundwater monitoring may be required if impacted material has leached into underlying soils and the potential exists for groundwater contamination. Once the bioremediation landfarm area has been investigated and any contamination remediated, infrastructure associated with the bioremediation landfarm will be removed as per Section 6 and the area reshaped to ensure they blend into the surrounding landscape and to control rainfall runoff. Areas will then be rehabilitated as per Section 8. 9.13.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Bioremediation Facility area is not classed as a ‘contaminated site’ as per the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. Page 40 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.14 Accommodation The accommodation village will be a nominally 200 person facility located at the site of the previous town in the north east of the island, and will include the following facilities: • Single person en-suite rooms; • Laundry modules; • Kitchen and dry mess; • Administration office; • First aid facility; • Wet mess; and • TV room. Sewerage and grey water management facilities will be as approved by the Shire of Derby and West Kimberly, and will comprise of a series of leach drains. 9.14.1 Objectives • If not required by another party, all infrastructure associated with the accommodation facility will be removed; • Areas were sewerage and grey water were managed will be investigated to determine if any contamination of soil and if required groundwater, is present and if so remediation strategies are developed and agreed with the DoE; and • Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. 9.14.2 Closure Strategy All infrastructure associated with accommodation facility will be removed as per Section 6, if not required by another party. Once the infrastructure is removed a contaminated site assessment in the areas where sewerage and grey water were managed will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.14.3 Completion Criteria • All infrastructure removed and disposed of appropriately; • Accommodation area is not classed as a ‘contaminated site’ as per the Contaminated Sites Act 2003; and • Vegetation cover is self-sustaining. Page 41 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 9.15 Administration Offices Administration offices will be established at each of the main work areas. Offices will comprise of office work space, ablutions, tea rooms and other general office facilities. Sewerage and grey water management facilities will be as approved by the Shire of Derby and West Kimberly, and will comprise of a series of leach drains. 9.15.1 Objective • If not required by another party, all infrastructure associated with the administration offices will be removed; and • Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. 9.15.2 Closure Strategy All infrastructure associated with administration offices will be removed as per Section 6, if not required by another party. There will be no storage or use of chemicals within the office areas and hence the site will not need to be investigated for contamination. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated as per Section 8. 9.15.3 Completion Criteria • All infrastructure removed and disposed of appropriately; and • Vegetation cover is self-sustaining. Page 42 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 10.0 PUBLIC ACCESS AND SAFETY ASPECTS 10.1 Objectives • To ensure that disturbed areas are left stable and free of infrastructure and waste; and • To restrict access to areas that cannot be made safe through rehabilitative techniques. 10.2 Strategy Public access and safety is an important issue at any mine site, particularly where there are potential safety issues in the form of open pits and steep cliff faces. Though there are no public facilities on Koolan Island. The public can assess the island by boat. Aztec considers it essential that public access to the old mining areas is restricted and the sites rendered as safe as possible. The following measures will be implemented: • Signs clearly stating the risk to public safety and prohibiting unauthorised public access will be erected around the site, particularly in areas near open pits; • On cessation of mining all roads leading to open pits will be closed; and • Safety bunds will be constructed to minimise the potential risk to the public safety of inadvertent access to abandoned open pits as per the DoIR procedures detailed in “Safety Bund Walls around Abandoned Open Pit Mines” (DoIR, 1997). Page 43 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 11.0 RECORDS MANAGEMENT AND REPORTING SCHEDULES 11.1 • 11.2 Objective To provide clear, detailed and comprehensive information on all aspects of the mines operating and closure history. Strategy The retention of mine records is important because they provide: • A history of past developments; • Information for incorporation into state and national natural resource data bases; and • The potential to improve future land use planning and/or site redevelopment (ANZMEC/MCA, 2000). The following measures are proposed or ongoing: • Records of the history of the site following closure will be preserved to facilitate future land use planning; • Reporting procedures will be established to ensure that results of all trials and actions including remediation works and monitoring of revegetation are properly recorded, referenced, and available for other personnel and for long-term reference; • Prior to relinquishment or surrender of tenure, records of the site development will be submitted to the Responsible Authority; and • The types of records required by the Responsible Authority will include the following: • Geological records, including drilling data; • Plans and surveys of surface facilities; • Mining and production records; • Locations, quantities and qualities of waste dumps;, • Location, quantities and types of waste disposed in the landfill; • Engineering reports regarding the stability of final landforms; • Site specific surveys or studies; and • Mine Closure Plan. Page 44 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 12.0 MONITORING 12.1 • • 12.2 Objectives To provide feedback on: • Final landform stability; • Marine environment recolonisation and water quality; • Surface and groundwater quality; • Public safety issues; • Rehabilitation and revegetation programs; and To identify potential and actual impacts in order that remedial work can be implemented. Strategy The implementation of a monitoring programme is crucial in recording the success or otherwise of the completion criteria, as well as validating agreed criteria for relinquishment (Chamber of Minerals and Energy, 1999). Monitoring will address the following areas: • Biological (flora and fauna); • Marine environment; • Surface and groundwater; • Public safety; and • Landform stability. Post-closure monitoring programs will be developed in consultation with appropriate regulatory agencies. Suggested monitoring programs are: • Annual assessment of rehabilitated areas to monitor the re-establishment of vegetation on all areas disturbed by mining activities i.e. waste dumps, stockpiles, infrastructure area, haul and access roads etc.; • Annual assessment of surface and groundwater quality to ensure water quality in disturbed areas is similar to that in undisturbed areas; • Once off assessment of the stability of final landforms by a suitable qualified engineer. Monitoring will then be undertaken as per the stability assessment recommendations; • Annual assessment of rehabilitated coastal habitats to monitor the re-establishment of marine biota and water quality in areas disturbed by the seawall and ship loader; Page 45 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan • Assessment of identified aboriginal heritage site on closure of the site to ensure they have not been disturbed; • Assessment of weeds and pests on closure of the site to identify if any new outbreaks have occurred due to Aztec’s operations; • Assessment of flora and fauna on closure of the site to identify if any impacts have occurred due to Aztec’s operations; and • Monitoring of all safety bunds, fencing and signage on an annual basis to ensure all public safety aspects are adequately addressed. Monitoring will identify the need for remedial work at an early stage. Monitoring plans will be developed in consultation with the appropriate regulatory agency and will include agreed actions should monitoring identify issues that could lead to agreed completion criteria not being met. Monitoring will be undertaken by Aztec until the agreed completion criteria have been met. Page 46 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan 14.0 SUMMARY OF MANAGEMENT ACTIONS Table 14.1 Summary of Management Actions Aspect Consultation Legal Obligations Completion Criteria Contaminated Sites Management Actions Relevant Section(s) Enable all stakeholders to have their interests considered during the mine closure process The aim of the closure plan is to provide a strategic framework for the closure of Aztec’s Iron Ore Project by providing a basis for consultation with regulators and identified stakeholders regarding the post-mining land uses of the project area and the development of agreed completion criteria. 1.0 Ensure that the closure of Aztec’s Iron Ore Project meets all legal. As part of the review of the Mine Closure Plan during the project life legislation and other requirements will be reviewed to identify any new requirements. Establish a set of indicators which will demonstrate the successful completion of the closure process and facilitate the release of the mining operator from further environmental obligations Aztec will consult with all stakeholders and interested parties throughout the life of the project to develop agreed completion criteria. A process is developed with the DoE for the management of any areas identified as contaminated by BHP’s previous activities. To ensure that the site is not classed as contaminated due to Aztec’s operation, investigations will be undertaken as part of the closure to determine whether contamination exists. A Contaminated Sites Assessment process will be undertaken as per the DoE Contaminated Sites Guidelines which incorporates the following: No areas disturbed by Aztec to be classed as a contaminated site as per the Contaminated Sites Act 2003. • Investigation: determine the nature and extent of any soil and/or groundwater contamination; • Assessment: evaluate the risks of any identified contamination to human health or the environment; • Action Plan: develop and document an operations plan and implementation schedule which addresses all necessary activities including disposal of contaminated material, monitoring and criteria for completion; • Consultation: discuss all aspects of the program and obtain agreement from DEP (as the responsible regulatory agency), together with other agencies as appropriate; • Implementation: undertake all aspects of the program in compliance with the documented plan and any relevant standards such as AS 4482.1 – 1997 related to the sampling and investigation of contaminated soils; • Validation: undertake monitoring and/or testing, using appropriate, recognised methods, to demonstrate reduction of contamination to an acceptable levels using an independent consultant; and • Closure: Obtain regulatory signoff that the remediation process has been effective and the site is no longer contaminated. Objective(s) Page 47 3.0 4.0 5.0 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Decommissioning Development of Final Landforms Objective(s) Remove or dispose of infrastructure associated with Aztec’s Iron Ore Project; and During the decommissioning phase of the project all infrastructure that cannot be used by another land user will be removed, including concrete footings, and the disturbed areas rehabilitated. Dispose of waste material appropriately. The dismantling of infrastructure will generate scrap and waste materials that will be disposed in the following manner: • Steel will be stored until the mine is decommissioned and shipped off the island for recycling; • Inert material that is not reusable (such as concrete, building rubble) will be buried in the landfill site; • Hazardous materials, such as asbestos, will be removed from the island and disposed of in accordance with appropriate governing regulations; and • Left over fuel, oils and chemicals will be removed from site and returned to the supplier. Waste oils, fuels and chemical will be removed from site and disposed of at a appropriate waste facility or reused where possible. Post mining landforms are geotechnically stable and respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types. Reshaping of landforms will be undertaken to: • Prepare landforms and disturbed areas to acceptable standards prior to the implementation of revegetation procedures; Landforms are compatible with the adjacent landscape. • Ensure post mining landforms are geotechnically stable and respond to erosion agents in a similar manner to naturally occurring landforms composed of similar rock types; • Minimise long-term visual impact by creating landforms which are compatible with the adjacent landscape; • Reinstate, where practicable, natural drainage patterns; • Ensure runoff from surface waters within and running off the site have similar quality to runoff from undisturbed sites; and • Batter free-standing slopes to an angle of 20 º or less, or to slopes consistent with surrounding landforms. Runoff from surface waters within and running off the site have similar quality to runoff from undisturbed sites. Rehabilitation Management Actions All area disturbed by Aztec’s operation will be rehabilitated. Relevant Section(s) 6.0 7.0 Rehabilitation will consist of: • Where available, topsoil will be utilised to provide a foundation into which native vegetation will be planted and/or seeded. Topsoil will be applied at a minimum of 100mm; • Vegetation debris, logs and leaf litter from the clearing of areas will be spread over rehabilitated areas to provide fauna habitat; • Ripping on contour is required to relieve compaction and improve water infiltration. Deep ripping to a depth of Species native to Koolan Island will only be used in the rehabilitation. 8.0 Rehabilitation will be undertaken as soon as practicable to facilitate fauna habitat restoration. Page 48 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Objective(s) Management Actions Relevant Section(s) 1m will be undertaken where the soil or waste material is of low permeability. In areas where the soil or waste material is of high permeability cultivation on contour will be undertaken. On steep slopes this may require terracing or benching. All ripping, terracing or benching will be surveyed to ensure that they are on contour; Mine Pits Ensure the pit void and walls are structurally stable. Ensure public safety by restricting access to the remaining pit • Direct seeding and/or planting will be undertaken to encourage vegetation growth to stabilise surfaces and aid the integration of landforms into the surrounding landscape. Seeding and/or planting will be undertaken prior to the wet season as soon as possible after earthworks using seed and plants native to Koolan Island; • Where necessary, fertilizer will be applied to offset the loss of nutrients and soil microbiota associated with loss of topsoil; and • Rehabilitation and closure procedures will include measures to address specific habitat types of listed fauna. Geotechnical investigations will be undertaken to determine the optimum final landform of the mine pit walls to ensure stability of the landform. • An abandonment bund wall will be constructed around the perimeter of open pit voids greater than 5m in depth; • The bund wall will be constructed outside the area designated as being susceptible to wall collapse; and • The location and design of the abandonment bund will be in accordance with procedures detailed in Safety Bund Walls around Abandoned Open Pit Mines. 9.1 Where required, additional earthworks will be undertaken on those areas of the pit walls that are safely accessible to improve long term structural stability and facilitate revegetation. Hand seeding will be undertaken where access is available to improve long term stability, particularly in the erosion prone haematite-poor grey band material. Seawall Waste Dumps To breach the seawall to below the low water level to reinstate the natural tidal movement of the area. The breaching of the seawall will be designed to minimise the impact to coastal habitats and allow for re-establishment of marine biota on disturbed areas. This strategy will be reviewed with stakeholders and the Responsible Authority prior to closure. To ensure that the profile of the waste rock dump final structure is safe, stable, blends into the surrounding landscape and not prone to erosion. The waste dumps will require extensive earthworks and subsequent seeding and revegetation to ensure they are stable and blend into the surrounding landscaped. • The waste rock and slope gradients will be capable of withstanding the intense rainfall events of the wet season. A sufficient cover of vegetation will be established to minimise erosion resulting from the impact of severe Waste Dumps will be designed to ensure that the profile of the final structure is safe, stable and not prone to erosion; • Dumps will be designed so that after rehabilitation they blend into the surrounding landscape; • Adequate drainage control will be implemented to ensure that erosion does not occur; Page 49 9.2 9.3 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Objective(s) rains on dry soils. Borrow Pits The profile of borrow pits final structure is safe, stable, blends into the surrounding landscape and not prone to erosion. Management Actions • Outslopes will be designed at less than 20o or lower if required for geotechnical reasons; • The dump surface will be a concave slope which are more stable and are less prone to erosion; • The tops of the waste dumps will be designed to contain run-off so as not to cause erosion on the sides of the dumps; • Dump surface will be covered with 4 m of clean fill and if available, topsoil to a depth of 100m; • Both the tops and the side of the waste dump will be contour ripped to encourage infiltration of rainfall; and • Waste dumps will be seeded or planted with local species. Borrow pits will be progressively rehabilitated as soon as possible following pit closure. The sides of the pits will be battered to a maximum slope of 20 °. If required, diversion drains and upslope windrows, will be utilized to divert surface water flow from entering the pit causing ponding and erosion. Pits will be rehabilitation as per the strategy detailed in Section 8. Relevant Section(s) 9.4 A sufficient cover of vegetation will be established to minimise erosion resulting from the impact of severe rains on dry soils. Dewatering All infrastructure associated with dewatering is removed. All infrastructure associated with dewatering will be removed and disposed of appropriately. 9.5 Impact on the marine environment from dewatering operations is minimised. Haulage & Ore handling If not required by another part, all infrastructure associated with haulage and ore handling is removed. Disturbed areas are reshaped to blend into the landscape, manage drainage and rehabilitated. Ship Loader If not required by another party, all infrastructure associated with ship loading is removed. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. All infrastructure associated with haul roads and ore handing will be removed. Haul roads, ROM pad, stockpile and other disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. 9.6 All infrastructure associated with the ship loader, including any structures in the ocean will be removed. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. 9.7 Marine areas will be left to naturally recolonise. Disturbed marine areas recolonised by marine flora and fauna. Page 50 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Power Station Objective(s) All infrastructure associated with the power station is removed. The area is investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. Management Actions Relevant Section(s) All infrastructure associated with power station will be removed. Once the infrastructure is remove an investigation for contamination will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. 9.8 Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Fuel & Bulk Storage Facilities All infrastructure associated with fuel and bulk storage facilities is removed. Storage areas are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. All infrastructure associated with fuel and bulk storage facilities will be removed. Once the infrastructure is remove an investigation for contamination will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. 9.9 Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Workshops All infrastructure associated with the workshops is removed. Workshop areas and the wash-down bay are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. All infrastructure associated with workshops will be removed. Once the infrastructure is remove an investigation for contamination will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. 9.10 Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Explosive Storage All infrastructure associated with the explosive storage is removed. Explosive storage areas are investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. All infrastructure associated with explosive storage will be removed. Once the infrastructure is remove an investigation for contamination will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. 9.11 Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Landfill All infrastructure associated with the landfill is All infrastructure associated with landfill site will be removed. Page 51 9.12 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Objective(s) removed. The site is compacted and stable. Landfill site is investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. Management Actions Relevant Section(s) Once the infrastructure is remove an investigation for contamination will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. DoE Karratha has advised that there is not a requirement to undertake testing for landfill gases. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. Landfill site is capped by a cover of low permeable material to a depth of 300mm. Landfill area is reshaped to blend into the landscape and manage drainage and rehabilitated. Bioremediation Facility Accommodation All infrastructure associated with the Bioremediation Facility is removed. Closure of the bioremediation landfarm will not be undertaken until all areas were contamination may occur have been investigated and remediated to agreed levels with the DoE. Bioremediation Facility is investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. On completion of bioremediation, the remediated soil will be removed and utilised in rehabilitation of disturbed area. Sampling of the natural ground surface beneath the bioremediation facility will be undertaken to determine if any contamination is present. Groundwater monitoring may be required if impacted material has leached into underlying soils and the potential exists for groundwater contamination. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Once the bioremediation landfarm area has been investigated and any contamination remediated, infrastructure associated with bioremediation landfarm will be removed and the area reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. If not required by another party, all infrastructure associated with the accommodation facility will be removed. All infrastructure associated with accommodation facility will be removed, if not required by another party. Areas were sewerage and grey water were managed will be investigated to determine if any contamination is present and if so remediation strategies are developed and agreed with the DoE. 9.13 Once the infrastructure is remove an investigation for contamination in the areas where sewerage and grey water were managed will be undertaken. If soil or water contamination is identified a remediation plan will be developed and agreed with the DoE. Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. 9.14 Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. Administration Offices If not required by another party, all infrastructure associated with the administration offices will be removed. Disturbed areas are reshaped to blend into the landscape and manage drainage and rehabilitated. All infrastructure associated with administration offices will be removed, if not required by another party. There will be no storage or use of chemicals within the office areas and hence the site will not need to be investigated for contamination. 9.15 Disturbed areas will be reshaped to ensure they blend into the surrounding landscape and to control rainfall run-off. Areas will then be rehabilitated. Page 52 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Public Access and Safety Aspects Objective(s) Management Actions To ensure that disturbed areas are left stable and free of infrastructure and waste. Signs clearly stating the risk to public safety and prohibiting unauthorised public access will be erected around the site, particularly in areas near open pits. To restrict access to areas that cannot be made safe through rehabilitative techniques. On cessation of mining all roads leading to the pits will be closed. Relevant Section(s) 10.0 Additional safety bunds will be constructed to minimise the potential risk to the public safety of inadvertent access to abandoned open pits Records Management and Reporting Schedules To provide clear, detailed and comprehensive information on all aspects of the mines operating and closure history. Records of the history of the site following closure will be preserved to facilitate future land use planning. Reporting procedures will be established to ensure that results of all trials and actions including remediation works and monitoring are properly recorded, referenced, and available for long-term reference. Prior to relinquishment or surrender of tenure, records of the site development will be submitted to the Responsible Authority. The types of records required by the Responsible Authority will include the following: Monitoring To provide feedback on • • final landform stability; marine environment recolonisation and water quality; • Geological records, including drilling data; • Plans and surveys of surface facilities; • Mining and production records; • Locations, quantities and qualities of stored waste dumps; • Location, quantities and types of waste disposed in the landfill; • Site specific surveys or studies; and • Mine Closure Plan. 11.0 The implementation of a monitoring programme is crucial in recording the success or otherwise of the completion criteria, as well as validating agreed criteria for relinquishment (Chamber of Minerals and Energy, 1999). Monitoring will address the following areas: 12.0 • Biological (flora and fauna); Page 53 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan Aspect Objective(s) Management Actions • surface and groundwater quality; • Marine environment; • public safety issues; and • Surface and groundwater; • rehabilitation and revegetation programs. • Public safety; and • Landform stability. To identify potential and actual impacts in order that remedial work can be implemented. Relevant Section(s) In summary the monitoring proposed is as follows: • Annual assessment of rehabilitated areas to monitor the re-establishment of vegetation on all areas disturbed by mining activities i.e. waste dumps, stockpiles, pit walls, infrastructure area, haul and access roads etc.; • Annual assessment of surface and groundwater quality to ensure water quality in disturbed areas is similar to that in undisturbed areas; • Once off assessment of the stability of final landforms by a suitable qualified engineer. Monitoring will then be undertaken as per the stability assessment recommendations; • Annual assessment of rehabilitated coastal habitats to monitor the re-establishment of marine biota and water quality in areas disturbed by the seawall and ship loader; • Assessment of identified aboriginal heritage site on closure of the site to ensure they have not been disturbed; • Assessment of weeds and pests on closure of the site to identify if any new outbreaks have occurred due to Aztec’s operations; • Assessment of flora and fauna on closure of the site to identify if any impacts have occurred due to Aztec’s operations; and • Monitoring of all safety bunds, fencing and signage on an annual basis to ensure that all public safety aspects are adequately addressed. Monitoring will identify the need for remedial work at an early stage. Monitoring plans will be developed in consultation with the appropriate regulatory agency and will include agreed actions should monitoring identify issues that could lead to agreed completion criteria not being met. Monitoring will be undertaken by Aztec until the agreed completion criteria have been met. Page 54 ecologia Koolan Island Iron Ore Mine and Port Facility Conceptual Closure Plan REFERENCES ANZMEC/MCA (2000). Strategic Framework for Mine Closure. Australian and New Zealand Minerals and Energy Council and Minerals Council of Australia. Canberra, ACT. Australian Mining Industry Council (1989). Mine Rehabilitation Handbook. Chamber of Minerals and Energy of Western Australia Inc (1999). Mine Closure Guidelines for Minerals Operation in Western Australia. Department of Environment (1996). Code of Practice for Country Landfills. Department of Environment (2004). Bioremediation of Hydrocarbon-Contaminated Soils in Western Australia. Contaminated Sites Management Series. Department of Minerals and Energy (1996). Guidelines for Mining in Arid Environments. Department of Mines & Energy, WA. Department of Minerals and Energy (1997). Safety Bund Walls around abandoned Open Pit Mines. Department of Minerals and Energy (1998). Geotechnical Considerations in Open Pit Mines Draft. Department of Minerals and Energy (2001). Environmental Notes on Mining - Waste Rock Dumps Issue Number 1 January 2001 Department of Industry and Resources (1997). Safety Bund Walls around Abandoned Open Pit Mines Guideline. December 1997. Environment Protection Agency (1995). Best Practice Environmental Management in Mining – Rehabilitation and Revegetation. Minerals Council of Australia (February 2000). Code for Environmental Management. URS Australia Pty Ltd. (2005). Phase 1 and Phase 2 Baseline Environmental Site Assessment – Koolan Island Iron Ore Project. Unpublished report prepared for Aztec Resources Limited. Page 55 ecologia
© Copyright 2026 Paperzz